Home / Financial Firm (Unknown - Insurer) / Determination 430594

Determination 430594

Claim declined for subsidence damage; cost of underpinning repairs

FirmFinancial Firm (Unknown - Insurer)
Decided2016-11-25
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$9,500
SourceAFCA PDF

Summary

The applicant sought reimbursement of just over $9,500 for underpinning works after cracks reappeared, blaming the FSP's 2010 repairs. AFCA found the damage was caused by excluded subsidence and the repairs were not shown to be defective, so nothing is payable.

The applicant bears the onus of establishing a covered loss, and subsidence is excluded while defective repairs were not established on the evidence.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 430594 Determination Page 1 of 5 Case number: 430594 25 November 2016 1 Overview 1.1 Dispute The applicant held a home building insurance policy (the policy) with the financial services provider (FSP). The policy provides cover for loss or damage arising from the listed insured events subject to the limitations and exclusions specified within the policy. The applicant maintains the building damage subject of this dispute arises from repairs completed by the FSP under a claim lodged in April 2009. The FSP disputes the applicant’s position and maintains the building damage is the result of subsidence and earth movement which is clearly excluded from cover under the policy. 1.2 Issues and key findings Is the current damage covered under the policy? The applicant has not been successful in establishing on the balance of probabilities the damage noted in March 2014 is due to an event covered under the policy. Rather, the available information establishes on balance the cause for the damage is clearly excluded from cover. Has the applicant established the damage is due to defective repairs? The available information does not establish the repairs authorised by the FSP under the claim in 2010 were defective. Also, the available evidence does not establish on balance the current damage is due to or related to the original repairs completed under the claim. 1.3 Determination This Determination is in favour of the FSP. The available information does not establish on balance the damage claimed is due to defective and/or inadequate repairs completed by the FSP. Further, the applicant has not established on balance the damage claimed is due to an event covered under the policy. Case No: 430594 Determination Page 2 of 5 2 Reasons for Determination 2.1 Is the cause for the current damage covered under the policy? The current damage is not due to circumstances covered under the policy I have considered the available information and am satisfied the applicant’s policy is a listed events contract of insurance. Therefore, cover under the policy extends to loss or damage caused by one of listed insured events provided in Product Disclosure Statement (PDS) subject to the policy exclusions. The policy can extend to provide cover for accidental damage. However, only if the policyholder elects to be included this extended cover upon the policy as an optional cover. The applicant’s policy does not include the optional cover for accidental damage. Having considered the available information, I am satisfied it is not the applicant’s position that a new insured event has occurred resulting in the current damage claimed. There is an absence of any compelling evidence to support such a view and more so no reference or evidence from the applicant to support the occurrence of a new event. The applicant strongly maintains the current damage arises from defective and/or inadequate repairs authorised by the FSP under the claim in 2010. The applicant in maintaining this view relies upon the evidence from consultants ‘BM’ (builder) and ‘DP’ (engineer). The FSP strongly refute s the applicant’s assertion in this regard it maintains the current damage is the result of differential settlement of the buildings footings due to seasonal changes in the moisture content of the foundation soils. The FSP relies upon the advice from engin eers ‘HE’ and builders ‘PP’. The issue as to whether the applicant has been successful in establishing on balance the repairs authorised by the FSP were defective or inadequate will be further discussed below. On the available information, I am not satisfied it has on balance been reasonably established by the applicant that the current damage is due to an event covered under the policy. Further, the policy clearly excludes from cover loss or damage to the insured building arising from subsidence (earth movement). 2.2 Has the applicant established the damage is due to defective repairs? The current damage is not due to the original repairs authorised by the FSP I have considered all the available information and am satisfied on balance it establishes the following:  a leaking water pipe was discovered by the applicant in the sub-floor area of the insured building in or around October 2008, which was repaired Case No: 430594 Determination Page 3 of 5  water which had leaked from this pipe did effect the moisture content of the foundations soils which have been classed as Quaternary Basaltic Clay and considered highly reactive (Class H)  a claim was lodged in April 2009 seeking cover for damage to the insured building noted as cracking of the external brickwork as well as internal plaster walls and ceilings  the applicant appointed builder BM to undertake an assessment of the damage who attended and submitted a report in May 2009  BM noted substantial damage and subsidence to the front section and recommended repair by way of foundation underpinning  the FSP appointed engineers HE to assess the cause and extent of the damage and which was completed in June 2009  HE confirmed the extent of damage and formed the view it was consistent which having occurred due to a combination of differential movement of the footings over time and the more recent leaking water pipe incident  HE noted considerable amount of weathering to the edges of the cracking consistent with having occurred over an extended period as well as fresh additional cracking consistent with the water leak incident  it was decided to allow a period of nine months to monitor the foundation soils and movement whilst the effects of moisture introduced into the foundation soils from the leaking water pipe settled  HE undertook a further assessment in March 2010 and was satisfied the movement of the house had stabalised and there had not occurred any further cracking. HE declared the building was ready for repairs and recommended a scope of works not including foundation underpinning  the FSP authorised the repairs to builders PP which were completed in line with the scope of works recommended by HE  in February 2014, the applicant contacted the FSP to advise the cracks had reappeared and advised he believed this was due to the FSP not authorizing the underpinning as part of the original repairs as recommended by BM  the FSP instructed both PP and then HE to attend the insured property to assess and investigate the re-appearance of the cracks  both consultants concluded the damage was not related to the original repairs conducted in 2010 rather it had occurred because of normal seasonal changes and related impact on moisture levels in the foundation soils  the applicant on the advice of BM authorised for the underpinning to be completed based on plans made available by engineer DP and is seeking reimbursement of the cost of these works at just over $9,500. The available evidence does not establish the original repairs were inadequate Having considered the available information, as discussed above I am satisfied there has not occurred a new insured event giving rise to the reappearance of damage to the insured building. Therefore, to be covered for the cost of the subsequent repairs (underpinning) the evidence must establish on balance the FSP’s authorised repairs completed in 2010 were either defective or inadequate. The onus rests with the applicant to establish on balance the damage claimed is covered under the policy. Case No: 430594 Determination Page 4 of 5 I note the applicant’s view that the repairs completed under the claim were defective or inadequate is strongly based on the information made available by BM. I have considered the information from BM in support of his view that it is the absence of underpinning which has led to the reappearance of the current damage. Further, it is clear from BM’s evidence that he maintains this opinion on his view that the insured property had not been subject of movement damage over the estimated previous four decades prior to 2009. It is his view the damage was solely the result of the leaking water pipe and that the reappearance of the damage has nothing to do with differential settlement of the foundations. BM has not made available compelling evidence to support his view in this respect in his reports. BM has not referred at all to the issue of seasonal changes in soil moisture levels, the impact this may have, provided any evidence to support an insured event and focuses his evidence on negating HE’s decision not to recommend the underpinning. It is clear BM’s opinion is strongly based on his view that the insured building had withstood weather patterns, droughts, severe weather events and atmospheric changes for over four decades with no damage until the leaking pipe incident. However, the available evidence does not support this view as it establishes on balance there was evidence of existing and weathered cracking present before the leaking pipe incident. This damage may have been on a much smaller scale when compared to the new cracking which appeared due to the leaking pipe incident, however, it does establish the property was subject to differential foundation settlement in the past. BM strongly recommends that the underpinning should have been completed but has not provided any evidence this is a requirement under the relevant building standards. Nor has there been any evidence provided to establish that had the underpinning been completed the current damage would not have occurred. Alternatively, I find the evidence from engineers HE to be the more compelling and relevant to the matter in dispute. HE has established that underpinning does not form part of any building standard requirement rather is a matter at the discretion of an engineer. Further, HE has clearly explained in his earlier report of June 2009 as well as subsequent email dated 15 September 2016 the basis for his decision not to recommend underpinning be included in the scope of repairs. HE having completed his assessments of the insured building was satisfied there was no further movement occurring and any effects on the foundation soils due to the leaking pipe had diminished by April 2010. Also, HE maintains underpinning if completed results in stiffening of that section of the building and the possibility arises that any future movement would result in cracking to either side of the underpinned area. Also, if the underpinning was completed there was a chance this could have resulted in further damage to the internal floor tiling installed in the southern bedrooms of the house. There is an absence of compelling evidence to the contrary from the applicant or his appointed consultants in this regard. Without such evidence, I am satisfied HE, Case No: 430594 Determination Page 5 of 5 as an engineer, was suitably qualified to provide such view and it was reasonable for the FSP to authorise the repairs on HE’s recommendations. I acknowledged the applicant has made available mapping of the completed underpinning prepared by engineers DP. However, this evidence does not provide any opinion on the cause of the damage claimed, the reappearance of the cracks, the need for underpinning or any view contrary to HE’s evidence. Without evidence to establish on balance that HE’s assessment of the damage and recommended repairs was flawed or inadequate, I am not satisfied the applicant has been able to establish the current damage was the result of defective repairs. Also, as discussed above, there is no information the current damage was the result of an insured event. Rather, on balance the cracking is due to circumstances clearly excluded from cover i.e. subsidence. Therefore, on the information made available to me, I determine the FSP is not obliged to reimburse the applicant for the cost to undertake the underpinning works at the insured property.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.