Cash settlement amount for home damage claim

FirmFinancial Firm (Unknown - Insurer)
Decided2017-02-07
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$50,000
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant's home was damaged by ground movement and leaking stormwater pipes. The FSP was entitled to cash settle but its offer of about $30,000 was not fair, and AFCA determined a $50,000 settlement.

The FSP may elect to cash settle under the policy, but the settlement must be fair and include all repair items and additional benefits such as temporary accommodation and debris removal.

Issues

Subjects and remedies

pay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 430588 Determination Page 1 of 9 Case number: 430588 20 January 2017 1 Overview 1.1 Dispute The applicant lodged a claim in 2011 with the financial services provider (FSP) for damage to his home, which he believed could be due to storm activity. After initially denying liability, the FSP accepted the applicant’s claim on 2 October 2012 and agreed to carry out the necessary repairs subject to the applicant repairing the stormwater pipes. Those repairs were completed by May 2014. After allowing suitable period for the soil to dry out, the FSP obtained a scope of works for the relevant repair work as well as quotations for those repairs. A dispute has arisen as to the scope of works and estimated cost of repairs. Whilst the FSP has offered to cash settle the applicant’s claim on the basis of the most competitive quote obtained, the applicant would prefer the FSP to authorise the repairs rather than cash settle the claim. 1.2 Issues and key findings Is the FSP entitled to cash settle the claim? The FSP may elect to repair, replace or compensate an insured the amount it would cost to repair or replace. As the FSP could not guarantee the repairs due to unrelated ongoing ground movement it has elected to cash settle the claim. I accept that the FSP is entitled to cash settle the applicant’s claim . Is the FSP’s offer of cash settlement fair in all the circumstan ces? I am not satisfied the FSP’s offer to cash settle the applicant’s claim is fair in all the circumstances. The offer does not cover all items to be repaired or the additional benefits under the policy such as temporary accommodation and removal of debris. Considering the various quotations and allowing for the additional benefits, I determine a cash settlement of $50,000 fair in all the circumstances. 1.3 Determination This determination is in favour of the applicant. The FSP is to pay the applicant the sum of $50,000 in settlement of the applicant’s claim for the damage sustained in accordance with the terms of the policy. Case No: 430588 Determination Page 2 of 9 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the information exchanged. This determination follows consideration of all of the information exchanged and is based on what is fair in all the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice including codes of practice and prior determinations where applicable. 2.1 Is the FSP entitled to offer to cash settle the applicant’s claim? The FSP is entitled to cash settle the applicant’s claim The policy clearly provides that the FSP can choose the method by which it settles claims. The FSP can decide whether to repair the home, replace the damaged portion of the home, or compensate the applicant for the amount it would have cost the FSP for repair or replacement. The discretion as to how to settle the claim must be exercised reasonably and consistent with the principles of utmost good faith. The FSP’s policy provides a lifetime guarantee on repairs which does not operate where a claim is cash settled. Effectively, in cash settling a claim the FSP transfers the risk that may arise during any repair process to an insured. Any offer to cash settle the claim should in my view take into account the risk as well as additional benefits that may be available under a policy such as temporary accommodation, architectural fee and removal of rubbish. There are many reasons why an FSP may choose to cash settle a claim. In the current dispute, the FSP has noted its repairers are unable to guarantee the work due to ongoing ground movement w hich is not related to the applicant’s claim. I have set out particulars of the relevant engineering findings in section 3.2 of this determination. I do not propose repeating the engineering findings in this section of the determination. I accept after considering the evidence from the various engineers and leak detection specialist who inspected the property that it is difficult to accept that the damage from the leaking pipe the left back of the home was responsible for all of the observed damage. Whilst the FSP has accepted liability for the repair of the applicant’s property caused by movement to the property, it has done so more as an act of good faith given its decision in October 2012 rather than based on the further engineering reports obtained. I accept in these circumstances that as there is likely to be ongoing ground movement that the FSP is entitled to elect to cash settle the applicant’s claim rather than complete the repairs. Case No: 430588 Determination Page 3 of 9 2.2 Is the FSP’s offer to cash settle the applicant’s claim fair in all the circumstances? FSP agreed to pay for the repair of the home Although the FSP may not be liable for all the damage to the home given the engineering findings, it has agreed to pay for the repairs to the home. The FSP did so in acknowledgement of the possible contribution of the leaking pipe to the damage to the home. Quotation for repair of the home The FSP obtained several scopes of works for the repairs to home, the most recent by engineer WPB. The FSP also obtained quotations for the repairs outlined in the scope of works. Builder JPF provided a quotation of $29,977.09, while builder JLG quoted $50,853.99. The applicant also obtained a quotation from ACB for $37,600. None of the quotations provide an allowance for other benefits payable under the policy such as:  temporary accommodation if the home is unlivable  removal of debris The FSP’s offer to cash settle the claim for $29,997.09 is based on the quotation from JPF. That quotation does not include a quote for the footings and stumps which had heaved, does not allow for the complete removal of the bathroom floor and tiles or the likely required repairs following the relevelling of the property. I do not accept that JPF’s quotation is adequate to allow the applicant to repair the damage to the property as agreed. In my view, the quotations obtained from the applicant’s builder ACB and from the FSP’s builder JLG are more appropriate quotations on which to base a cash settlement. In my view, it is fair to take an average of the quotations from ACB and JLG which gives a figure of $44,226.54. Allowing for the likelihood of temporary accommodation and rubbish removal and the transfer of the risks associated with the repairs, I am satisfied that a fair figure to cash settle the claim is $50,000. Case No: 430588 Determination Page 4 of 9 3 Supporting information 3.1 Policy provisions Product Disclosure Statement – preparation date 20 Feb 2008 ‘ Home insurance – What IS covered Escape of liquid from the following.  Any water main or fixed pipe, gutter or guttering, fixed tank or drain. … Temporary accommodation Following loss or damage insured by this policy, if we are satisfied your home is unliveable, we will pay any additional costs you incur for similar accommodation until you are able to live in your home. The amount we pay you will be based on the market’s weekly rental value of your home…. Maximum benefit - Up to 20% of the sum insured as shown on your certificate … General exclusions applicable to your policy …  Structural defects or faulty workmanship, settling, shrinkage or expansion.  The action of the sea, erosion, landslide, subsidence or tsunami. … Paying your claim How we pay a claim for your home Where we pay a claim for your home, we will choose to do one of the following: • repair your home, • replace the damaged portion of your home, • compensate you the amount it would have cost us for repair or replacement. …’ 3.2 Reports referenced Record Key points FSP’s leak detection specialist (AL) Report 9 Jan 2012  CCTV inspection of storm water line failed due to breaks, misaligned joins and blockages, all in the VIC clay sections of line.  Due to blockages and line appearing to drop away at rear of house, could not get through to easement point.  Entire storm water line to be completely renewed. Case No: 430588 Determination Page 5 of 9 FSP’s engineer (C) Report 22 Feb 2012  Older dwelling – no doubt it has suffered from past differential foundation movement – evident from previous patching and permanent distortions to various door and window frames  Restumping occurred approx. 7 yrs. ago.  Inherent foundation movement will continue to occur, given original perimeter strip footing most likely under - sized and shallow founded.  Past leaking of below ground stormwater pipe system possibly contributed to recent movements and damage.  Recommend re port from plumber FSP’s engineer (C) Report 1 May 2012  AL has completed plumbing investigations report.  Domestic water supply pipe systems all holding pressure – no leaks.  CCTV inspection of sewer and stormwater pipelines showed all clear and no signs of faults or leakages  Leaking pipework can be eliminated as possible cause of recent movement and damage.  Damage reported by applicant to older earthenware pipe join located away from main dwelling. Highly unlikely this pipe dislocation contributed to current and ongoing movement/damage.  Current movement and damage are most likely an extension of all previous foundation movements – which are expected to continue until improvements made to general site drainage issues and shallow foundation support. FSP’s engi neer (C) Report 17 Sep 2012  Since issue of 1 May report, a plumbing report by AL (from Jan 2012) was provided. This predates April 2012 AL report upon which 1 May report was based.  Jan 2012 report from AL identified numerous cracked and misaligned joints i n older clay stormwater pipe, which would be leaking. A partial blockage to drain from debris build up also noted.  Given differing reports from AL, matter referred back to JM, the proprietor of AL for further review and clarification.  New AL report (Sep 20 12) noted issues with pipe breakages and misalignments – similar to Jan 2012 report.  Using Sep 2012 AL report plus sewer and stormwater pipe diagram from relevant authorities, confirmed that: o an easement runs down southern side of property, and contains st ormwater barrel drain o 6 downpipes and 1 surface grate in front of garage connect to stormwater drainage.  Foundation movement and damage to main dwelling structure in front South/Eastern corner region & cracking to front veranda not regarded as due to any leaking storm water drainage – instead regarded as being due to founding soil movement issues from external drainage inadequacies (this is after considering lay of land, general movements, cracking patt erns, and leaking storm water pipeline locations)  Possible that cracked & misaligned leaking clay stormwater Case No: 430588 Determination Page 6 of 9 pipework (surrounding North and West sides of dwelling) contributed to other fresher movements and damage occurring throughout remaining areas of b uilding  Significant rainfall over 2 - 3 years increased amount of leakage water from pipes, and affected shrink/swell movements of foundations  After applicant rectifies all stormwater pipe leaks (and it is recommended that all clay piping be replaced), a minimum 6 months drying out required before repairs to building considered. FSP engineer (F) Report 11 Feb 2015  Old clay underground stormwater pipework now replaced with aboveground PVC piping.  All existing sewer pipework in good serviceable condition.  Internal cracking has become progressively worse since re - stumping 10 years ago.  Foundation soil expected to be highly reactive clay.  Floor levels show 2 distinct general patterns of movement to floor  Pronounced pattern of settlement around location of mai n central hallway walls: o attributed to consolidation settlement and long term shrinkage drying of reactive clay foundation soils o also consistent with re - stumping & expected ongoing differential movements of foundation soils (highly likely restumping may no t have achieved site - specific founding depths) o consistent with info from applicant that cracking to internal plasterwork is ongoing and worsened since restumping. o agree with C opinion that cracking to overall building caused by ongoing differential movemen ts to reactive clay founding soils o do not agree with C about cracking to internal plasterwork – which is considered to related to leaking of pipework but due to factors listed above o leaking pipework located external to footprint of enclosing building envelope and therefore it is not physically possible for leaking to cause or contribute to damage to internal plasterwork.  Discernable (but minor) general pattern of movement of floor toward south - western corner of building o coincides with cracking to exter nal brickwork o storm water leakage may have contributed to cracking damage to misaligned brickwork at this location to return corner walls only. o appears previous leaking storm water adjacent to south - western corner caused localised external foundation soils to swell and leading to inward rotation of strip footing and supported brick wall.  F disagrees with C re: cause of remainder of observed external wall brickwork cracking – F considers this damage due to differential movements of foundation soils/footing, and not due to Case No: 430588 Determination Page 7 of 9 leaking storm water pipes.  Differential footing movements are as a result of one or more of the following factors: o Long - term/ongoing foundation soil moisture content variations from seasonal changes o drought conditions 1997 - 2010 & then retur n to normal rainfall o very dry/hot conditions in summer of 2012/13 and 2013/14 o tree roots drying (minor) o poor site drainage (particularly at affected front of dwelling) o site not being adequately maintained o previously poorly maintained storm water drainage s ystem.  Photos and floor level plan attached. Applicant’s engineer (AC) Report 10 Oct 2015  Evidence shows restumping of home in 1993.  Floor uneven – the fall observed most towards left back corner of home.  Stormwater damage observed during 2008 concreting work.  Damage stormwater at left back of home fixed in 2014.  2008 - 2014 water was ponding under subfloor – during heavy rain a thick layer of water would flow towards road (applicant photos show this)  Subfloor soil layers must have been affected by water p onding for many years. The members like stumps must have started sinking at left back of home, causing differential settling  Although soil reactivity, soil movement, drought and tree roots contribute to differential settling of a house, in this case the in fluence of these factors to this home’s differential settling is considered negligible.  AC has found substantial reasons to say the home’s differential settling started from left back corner, resulting in cracking in wall.  Remediated above - ground stormwate r pipework has stopped ponding of water under subfloor, which was observed to be reasonably dry  AC disagrees with finding in 11 Feb 2015 report from F regarding contribution of trees and soil reactivity to differential movement to home.  AC believes that b roken stormwater pipe in left back corner caused ponding in subfloor at this location, and layers of soil lost load bearing ability due to long term absorption of extra moisture. (strength of soil comes from friction between soil particles – when pore wate r is present in pores/voids of soil, pore water pressure pushes particles apart and reduces load bearing capacity of soil.)  Most of the major external and internal defects/damage observed around home started with differential settling of home.  Estimated cost of repairs to observed/photographed damage - $37,600.  Photos attached. Case No: 430588 Determination Page 8 of 9 FSP’s engineer (WPB) Report 5 May 2016  Home in fair to poor condition for its age. Moderate to severe cracks to brick veneer on all sides of home (particularly front and rear walls).  Movement between brickwork and window frames, and in roof guttering at south re - entrant corner of home.  Concrete slab at front of home severely cracked, and settled in area (applicant advises settled portion of slab is extension constructed after t he smaller, unsettled portion at front door).  3 moderate cracks observed in pavement at rear – not structurally significant and likely shrinkage cracks.  Front and back doors jam on closing – misalignment apparent in front door with gap formed in upper corn er  Inside home, noticeable drops and high points in floor level – likely caused by differential movement of stumps.  Slight to moderate cracks in various areas of home – incl eastern corner of bedroom 1;NE and SW sides of bedroom 2; between doorframes in la undry; above door and window frames in kitchen; on south wall of dining room; on majority of walls in lounge; in hallway.  Patterning of racking widespread and not isolated to one area.  Built - in wardrobe of bedroom 1 has separated and leaning out from wall  Some wall tiles in bathroom cracked, splashback tiles in kitchen separated along grout line.  WPB’s opinion that home has experience differential ground movement over an extended period of time  Given severity of damage, plausible that damage has been made w orse by previous or current pipe leaks and wetting of subfloor.  Recommend leak testing be done on all pipework (stormwater, water and sewer pipes), and rectify any leaks or blockages found  Allow ground moisture levels underneath home to stabilise prior to remedial works (4 - 6 months recommended), then reassess soil conditions and damage.  Photos and Scope of Works for repairs attached. FSP’s builder (JLG) Quotation 23 May 2016  Total cost of repairs based on WPB scope of works $47,042 FSP’s builder (JPF) Quotation 17 May 2016  Total cost of repairs based on WPB scope of works $27,300 FSP engineer (WPB) Memo 1 June 2016  Response to questions from applicant (though FSP): o Damage to all walls included in May 2016 report, incl western wall. Assumed that lean wo uld stabilise once ground moisture levels normalise (so no make - safe required). Included as part Case No: 430588 Determination Page 9 of 9 of repairs to re - entrant southern corner. o Confirm a small section of floating timber floorboards near bathroom uneven and creaked – from stumps settling below. Packing of stumps (included in SOW in May 2016 report should address this) o Damage to vinyl flooring to kitchen observed but not included in May 2016 report o Slight bow in hallway/laundry plaster wall should have been included as part of repairs noted in May 2016 report – although expected that re - levelling or stumps will address this. o Cannot comment on deflections of wall studs (non - invasive inspection only). Deflection only observed to plaster wall, and should be repaired as part of scope of works. Recommend builder inspect wall studs once plaster is removed to confirm. o No roof report perform due to workplace health and safety. Cannot comme nt on any damaged roof beams. FSP’s plumber (SP) Inspection reports 12 & 17 May 2016  Pressure test at 350Kpa of hot and cold water pipes - No pressure loss over 15 mins  CCTV inspections of property’s below ground sewer drainage – found all drainage in ser viceable condition – no defects detected.  Approx 30m of 90mm below ground and suspended stormwater drainage pipes servicing property. Storm water inspections were carried out via subfloor area – images show no leaks. FSP’s builder (JLG) Revised quotation 22 Jul 2016  Total cost of repairs based on WPB scope of works (including allowance for items noted in WPB’s 1 Jun memo) $50,853.99 FSP’s builder (JPF) Revised Quotation 19 Jul 2016  Total cost of repairs based on WPB scope of works (including changes in 1 Jun memo) $29,977.09