Home / Financial Firm (Unknown - Insurer) / Determination 428509

Determination 428509

Extent of cash settlement for water-damaged parquetry flooring

FirmFinancial Firm (Unknown - Insurer)
Decided2017-01-20
ProductGeneral Insurance · Strata
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A pipe leak damaged parquetry flooring in the applicant's unit. The FSP accepted the claim but offered to cash settle only the damaged area, and AFCA ordered cash settlement of flooring in the whole bedroom, re-sanding and resealing across the unit, and related clean-up and accommodation costs.

Because the original parquetry is no longer available and replacement may not match, the policy's matching and reinstatement terms require the FSP to consider the aesthetics of the replacement flooring, so the cash settlement extends beyond the damaged square metre.

Issues

Subjects and remedies

home or building damagepay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 428509 Determination Page 1 of 5 Case number: 428509 19 December 2016 1 Overview 1.1 Dispute This matter involves a claim by the applicant under a Residential Strata Insurance Policy, held with the financial service provider (FSP), following damage to the applicant’s home. The FSP has accepted the applicant’s claim but a dispute has arisen as to the extent of the FSP’s obligation s under the terms and conditions of the policy. 1.2 Issues and key findings What is the exten t of the FSP’s obligations under the terms and conditions of the policy? The FSP is to cash settle the reasonable costs associated with replacing the parquetry floor in the bedroom where the damage occurred. 1.3 Determination This determination is partially in favour of the applicant. The FSP is to cash settle the applicant the cost to replace the parquetry flooring in the whole of the bedroom in which the damage occurred. The FSP is to cash settle the applicant the reasonable cost to re-sand the parquetry flooring throughout the entire unit, which includes the sills around windows and the cost to reseal the floor through the entire unit. Finally, the FSP is to cash settle the applicant the reasonable clean-up costs and the reasonable costs associated with temporary accommodation, removal/storage/return of the unit’s contents, during the period it would take to complete all this work. The FSP is to obtain an up-to date quotation to complete this work and to cash settle the applicant on the basis of this quotation. As it will be an up-to date quotation, no interest is payable. Case No: 428509 Determination Page 2 of 5 2 Reasons for determination This determination has been the subject of a Recommendation issued by the Service on 30 June 2016. It was the case manager’s recommendation that the FSP was requir ed to replace or pay the cost to replace the entire flooring of the home. The FSP has disputed the recommendation. I have carefully considered all of the material provided both before and after the recommendation, in the preparation of this Determination. This determination follows consideration of all of the information exchanged and is based on what is fair in the circumstances, having regard to the relevant legal principals, terms of the policy, good industry practice and where applicable, prior determinations. 2.1 What is the extent of the FSP’s obligations under the terms and conditions of the policy? Coverage of the policy The coverage provided by the Residential Strata Insurance Policy is detailed within the Product Disclosure Statement (PDS). The PDS details: WHAT YOU ARE COVERED FOR This Section is an Accidental, Physical Loss or Destruction Contract of Insurance between You and Us. We will cover Your Insured Property for any Damage occurring during the Period of Insurance not excluded by this Section. … The PDS also details how the FSP is required to pay a claim: HOW WE PAY CLAIMS 1. REINSTATEMENT AND REPLACEMENT a. Building(s) When Damage not excluded by this Section occurs to Your Building(s), We will pay the reasonable and necessary cost of rebuilding Your Building(s) or repairing the Damaged portions to the same condition as when they were new. We decide which one We will do. If We pay the cost of rebuilding Your Building(s), You can rebuild on another site. You can do this provided the amount We pay is not increased. Where Your Building(s) have any architectural features and/or structural materials possessing an ornamental, historical or heritage character, or for which the original materials are not available, We will rebuild or restore Your Building(s) to an equivalent appearance and capacity, using the original design and nearest equivalent materials. Case No: 428509 Determination Page 3 of 5 … 7. MATERIALS We will try to match any material used to repair or replace Your Insured Property with the original materials. If We cannot, We will use the nearest equivalent available to the original materials. 8. UNDAMAGED PROPERTY We will not pay any costs for replacing, repairing, altering or modifying any undamaged Insured Property or undamaged sections of Your Insured Property. The coverage provided by the policy is also subject to exclusions which are detailed within the PDS: EXCLUSIONS We will not cover Your Insured Property for Damage arising from or caused by: … 4. Consequential loss other than provided for under the Policy. … Circumstances of the loss and damage The exchanged material confirms that the unit ’ s parquetry flooring was damaged as a result of pipe leak on 11 April 2015. The FSP has accepted the applicant’s claim but seeks to meet its liability under the policy by way of a cash settlement representing the cost to repair the damaged area. The FSP maintains that the policy provisions mean it is not required to replace or repair any undamaged section of the parquetry floor. At this point it is worth noting that the FSP accepts that it is required to meet the fair and reasonable costs associated with temporary accommodation, removal/storage/return of the unit’s contents, during the floor repairs. The FSP says that it is unable to estimate the extent of these costs until the repairs are actually undertaken. Further, the FSP is unable to quantify any clean-up costs until the repairs have been undertaken. Upon acceptance of this determination by the applicant, the FSP should assess the period that is reasonably necessary for repairs and clean up to be completed and assess the costs associated. Matching new for old The exchanged material includes a quotation for repairs which includes the notation: ‘New parquetry may not match colour due to organic variation and the age of the existing floors.’ Case No: 428509 Determination Page 4 of 5 Further, within the Notice of Response the FSP has confirmed: ‘The Member acknowledges that it is not in dispute that the repairers are suggesting that the replacement material will not match the current flooring …’ The exchanged material confirms that the area damaged by the water leak is approximately 1 square metre. The information exchanged confirms that the parquetry flooring within the unit covers an area of approximately 74 square metres. The one square metre of damaged area is at the entrance to the bedroom. The FSP says that the applicant is endeavouring to claim the cost to replace the entire flooring in order to provide a uniform aesthetic in relation to the materials which must be used for the water damaged area. The FSP maintains that it is not obliged to meet the cost to replace the entire floor as the policy is clear in stating that when the original materials are no longer available it is entitled to use the nearest equivalent. Significantly the policy also provides that the FSP is not require to pay any costs for replacing any undamaged section of the property. The FSP says that in order to trigger coverage under the policy, the insured property in question must sustain ‘physical loss or destruction’ and the physica l loss or destruction is limited to approximately one square metre of the parquetry floor. The FSP points out that in addition to repairing and replacement of the damage of one square metre of damaged parquetry floor, the quotations provided include a re- sanding of the entire parquetry floor, not just the one square metre of damaged floor. Further, the FSP relies upon the commentary from its assessor to the effect that the assessor: ‘… did observe at the time of our inspection the flooring throughout the unit is generally in a poor state of repair and has extensive wear and tear and damage from general use.’ As stated the FSP maintains that its obligation does not extend beyond replacing or repairing the damaged area and damage is the physical loss or destruction, as detailed within the PDS: DEFINITIONS … Damage Means any Accidental physical loss or destruction. Damaged has a corresponding meaning. Consideration of the policy provisions The policy requires the FSP to meet the reasonable and necessary costs of rebuilding or repairing the damaged portions of the building to the same condition as when they were new, subject to a limitation that the FSP will not pay any costs for Case No: 428509 Determination Page 5 of 5 replacing, repairing, altering or modifying any undamaged insured property or undamaged sections of the insured property. The policy requires the FSP to try to match any material used to repair or replace the insured property with the original materials and if it cannot the FSP will use the nearest equivalent available to the original materials. The exchanged material confirms that the original materials are no longer available and the new parquetry flooring which would replace the damaged floor may not match in colour, with the current flooring. A consideration of the aesthetics of the new parquetry flooring for the one square metre damaged area, is relevant to the question of the FSP’s obligations under the terms and conditions of the policy. Having reviewed all of the exchanged material, including the photographs of the damaged floor, I consider it fair in all the circumstances that the FSP cash settle the applicant the cost to replace the flooring in the whole of the bedroom in which the damage occurred. In addition, the FSP is required to cash settle the applicant the reasonable cost to re- sand the parquetry flooring through the entire unit which includes the sills around windows and to reseal the entire floor. The FSP should also cash settle the applicant the reasonable clean-up costs and the reasonable costs associated with temporary accommodation, removal/storage/return of the unit’s contents, during the period it would take to repair. The parties are to work together to establish a reasonable period that this work would require. Other matters The applicant has said that partial repair of the floor will devalue the property. In this regard I note that the policy provisions (detailed above) exclude coverage in respect to consequential loss. I accept that any potential devaluation (if it occurs) would be consequential to the repairs and thus excluded from coverage under the policy. The applicant has said that the FSP’s treatment of him has been discriminatory and unreasonable and he believes that it would not have happened to other customers. Having reviewed all of the exchanged material I am not satisfied that there is any evidence to support the applicant’s allegations in this regard and I accept the case manager’s commentary to the effect that the FSP is entitle d to consider each claim on its merits, its individual facts and circumstances.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.