Determination 428509
Extent of cash settlement for water-damaged parquetry flooring
Summary
A pipe leak damaged parquetry flooring in the applicant's unit. The FSP accepted the claim but offered to cash settle only the damaged area, and AFCA ordered cash settlement of flooring in the whole bedroom, re-sanding and resealing across the unit, and related clean-up and accommodation costs.
Because the original parquetry is no longer available and replacement may not match, the policy's matching and reinstatement terms require the FSP to consider the aesthetics of the replacement flooring, so the cash settlement extends beyond the damaged square metre.
Subjects and remedies
home or building damagepay claim
Text of the determination
Determination
Case No: 428509 Determination Page 1 of 5
Case number: 428509 19 December 2016
1 Overview
1.1 Dispute
This matter involves a claim by the applicant under a Residential Strata Insurance
Policy, held with the financial service provider (FSP), following damage to the
applicant’s home.
The FSP has accepted the applicant’s claim but a dispute has arisen as to the extent
of the FSP’s obligation s under the terms and conditions of the policy.
1.2 Issues and key findings
What is the exten t of the FSP’s obligations under the terms and conditions of
the policy?
The FSP is to cash settle the reasonable costs associated with replacing the
parquetry floor in the bedroom where the damage occurred.
1.3 Determination
This determination is partially in favour of the applicant.
The FSP is to cash settle the applicant the cost to replace the parquetry flooring in
the whole of the bedroom in which the damage occurred.
The FSP is to cash settle the applicant the reasonable cost to re-sand the parquetry
flooring throughout the entire unit, which includes the sills around windows and the
cost to reseal the floor through the entire unit.
Finally, the FSP is to cash settle the applicant the reasonable clean-up costs and the
reasonable costs associated with temporary accommodation, removal/storage/return
of the unit’s contents, during the period it would take to complete all this work.
The FSP is to obtain an up-to date quotation to complete this work and to cash settle
the applicant on the basis of this quotation. As it will be an up-to date quotation, no
interest is payable.
Case No: 428509 Determination Page 2 of 5
2 Reasons for determination
This determination has been the subject of a Recommendation issued by the Service
on 30 June 2016.
It was the case manager’s recommendation that the FSP was requir ed to replace or
pay the cost to replace the entire flooring of the home.
The FSP has disputed the recommendation.
I have carefully considered all of the material provided both before and after the
recommendation, in the preparation of this Determination.
This determination follows consideration of all of the information exchanged and is
based on what is fair in the circumstances, having regard to the relevant legal
principals, terms of the policy, good industry practice and where applicable, prior
determinations.
2.1 What is the extent of the FSP’s obligations under the terms and
conditions of the policy?
Coverage of the policy
The coverage provided by the Residential Strata Insurance Policy is detailed within
the Product Disclosure Statement (PDS).
The PDS details:
WHAT YOU ARE COVERED FOR
This Section is an Accidental, Physical Loss or Destruction Contract of Insurance
between You and Us.
We will cover Your Insured Property for any Damage occurring during the Period of
Insurance not excluded by this Section.
…
The PDS also details how the FSP is required to pay a claim:
HOW WE PAY CLAIMS
1. REINSTATEMENT AND REPLACEMENT
a. Building(s)
When Damage not excluded by this Section occurs to Your Building(s), We will pay the
reasonable and necessary cost of rebuilding Your Building(s) or repairing the Damaged
portions to the same condition as when they were new. We decide which one We will
do. If We pay the cost of rebuilding Your Building(s), You can rebuild on another site.
You can do this provided the amount We pay is not increased.
Where Your Building(s) have any architectural features and/or structural materials
possessing an ornamental, historical or heritage character, or for which the original
materials are not available, We will rebuild or restore Your Building(s) to an equivalent
appearance and capacity, using the original design and nearest equivalent materials.
Case No: 428509 Determination Page 3 of 5
…
7. MATERIALS
We will try to match any material used to repair or replace Your Insured Property
with the original materials. If We cannot, We will use the nearest equivalent
available to the original materials.
8. UNDAMAGED PROPERTY
We will not pay any costs for replacing, repairing, altering or modifying any
undamaged Insured Property or undamaged sections of Your Insured Property.
The coverage provided by the policy is also subject to exclusions which are detailed
within the PDS:
EXCLUSIONS
We will not cover Your Insured Property for Damage arising from or caused by:
…
4. Consequential loss other than provided for under the Policy.
…
Circumstances of the loss and damage
The exchanged material confirms that the unit ’ s parquetry flooring was damaged as a
result of pipe leak on 11 April 2015.
The FSP has accepted the applicant’s claim but seeks to meet its liability under the
policy by way of a cash settlement representing the cost to repair the damaged area.
The FSP maintains that the policy provisions mean it is not required to replace or
repair any undamaged section of the parquetry floor.
At this point it is worth noting that the FSP accepts that it is required to meet the fair
and reasonable costs associated with temporary accommodation,
removal/storage/return of the unit’s contents, during the floor repairs.
The FSP says that it is unable to estimate the extent of these costs until the repairs
are actually undertaken. Further, the FSP is unable to quantify any clean-up costs
until the repairs have been undertaken.
Upon acceptance of this determination by the applicant, the FSP should assess the
period that is reasonably necessary for repairs and clean up to be completed and
assess the costs associated.
Matching new for old
The exchanged material includes a quotation for repairs which includes the notation:
‘New parquetry may not match colour due to organic variation and the age of the
existing floors.’
Case No: 428509 Determination Page 4 of 5
Further, within the Notice of Response the FSP has confirmed:
‘The Member acknowledges that it is not in dispute that the repairers are suggesting
that the replacement material will not match the current flooring …’
The exchanged material confirms that the area damaged by the water leak is
approximately 1 square metre.
The information exchanged confirms that the parquetry flooring within the unit covers
an area of approximately 74 square metres.
The one square metre of damaged area is at the entrance to the bedroom.
The FSP says that the applicant is endeavouring to claim the cost to replace the
entire flooring in order to provide a uniform aesthetic in relation to the materials which
must be used for the water damaged area.
The FSP maintains that it is not obliged to meet the cost to replace the entire floor as
the policy is clear in stating that when the original materials are no longer available it
is entitled to use the nearest equivalent. Significantly the policy also provides that the
FSP is not require to pay any costs for replacing any undamaged section of the
property.
The FSP says that in order to trigger coverage under the policy, the insured property
in question must sustain ‘physical loss or destruction’ and the physica l loss or
destruction is limited to approximately one square metre of the parquetry floor.
The FSP points out that in addition to repairing and replacement of the damage of
one square metre of damaged parquetry floor, the quotations provided include a re-
sanding of the entire parquetry floor, not just the one square metre of damaged floor.
Further, the FSP relies upon the commentary from its assessor to the effect that the
assessor:
‘… did observe at the time of our inspection the flooring throughout the unit is generally
in a poor state of repair and has extensive wear and tear and damage from general
use.’
As stated the FSP maintains that its obligation does not extend beyond replacing or
repairing the damaged area and damage is the physical loss or destruction, as
detailed within the PDS:
DEFINITIONS
…
Damage
Means any Accidental physical loss or destruction. Damaged has a corresponding meaning.
Consideration of the policy provisions
The policy requires the FSP to meet the reasonable and necessary costs of
rebuilding or repairing the damaged portions of the building to the same condition as
when they were new, subject to a limitation that the FSP will not pay any costs for
Case No: 428509 Determination Page 5 of 5
replacing, repairing, altering or modifying any undamaged insured property or
undamaged sections of the insured property.
The policy requires the FSP to try to match any material used to repair or replace the
insured property with the original materials and if it cannot the FSP will use the
nearest equivalent available to the original materials.
The exchanged material confirms that the original materials are no longer available
and the new parquetry flooring which would replace the damaged floor may not
match in colour, with the current flooring.
A consideration of the aesthetics of the new parquetry flooring for the one square
metre damaged area, is relevant to the question of the FSP’s obligations under the
terms and conditions of the policy.
Having reviewed all of the exchanged material, including the photographs of the
damaged floor, I consider it fair in all the circumstances that the FSP cash settle the
applicant the cost to replace the flooring in the whole of the bedroom in which the
damage occurred.
In addition, the FSP is required to cash settle the applicant the reasonable cost to re-
sand the parquetry flooring through the entire unit which includes the sills around
windows and to reseal the entire floor.
The FSP should also cash settle the applicant the reasonable clean-up costs and the
reasonable costs associated with temporary accommodation, removal/storage/return
of the unit’s contents, during the period it would take to repair.
The parties are to work together to establish a reasonable period that this work would
require.
Other matters
The applicant has said that partial repair of the floor will devalue the property.
In this regard I note that the policy provisions (detailed above) exclude coverage in
respect to consequential loss.
I accept that any potential devaluation (if it occurs) would be consequential to the
repairs and thus excluded from coverage under the policy.
The applicant has said that the FSP’s treatment of him has been discriminatory and
unreasonable and he believes that it would not have happened to other customers.
Having reviewed all of the exchanged material I am not satisfied that there is any
evidence to support the applicant’s allegations in this regard and I accept the case
manager’s commentary to the effect that the FSP is entitle d to consider each claim
on its merits, its individual facts and circumstances.