Storm-related water and mould damage claim declined in part and roof settlement disputed
Text of the determination
Determination
Case No: 428475 Determination Page 1 of 14
Case number: 428475 11 January 2017
1 Overview
1.1 Dispute
The applicant lodged a claim on his home insurance policy in relation to mould and
water damage to his property which he claims is as a result of a storm in July/August
2014.
The FSP accepted the claim for water damage to the ensuite floor and cash settled
the applicant for the cost of repairing that damage.
The FSP declined the claim for the remaining damage on the basis that it is was not
caused by an insured event. The FSP relies on policy exclusions relating to structural
defects and damage caused by mould.
1.2 Issues and key findings
Is the FSP’s offer to settle the claim reasonable?
The FSP’s offer to settle the claim is not reasonable as the applicant has established
parts of the roof were damaged in storm events in August 2014 which in turn allowed
water to enter the home causing water and mould damage for which the applicant
has not been compensated.
On the material provided, the FSP has not established on the balance of probabilities
the storm damage was caused when water entered the home because of a structural
defect, faulty design or faulty workmanship when the home was constructed in the
1970’s.
Further, as the FSP has not established the defects were present when the building
was constructed, section 46 of the Insurance Contracts Act is not relevant. Moreover,
the FSP has not established the applicant was or should have been aware of the
defects identified by the FSP’s engineer when the policy commenced. This is
because the said defects and are not identified in the applicant’s pre -purchase report.
Further, the material provided establishes the water ingress and mould damage o nly
occurred after the policy commenced.
The FSP policy exclusion relating to gradual deterioration is not applicable because
this policy exclusion refers to accidental damage to valuable items and is not relevant
to the policy response concerning the app licant’s claim.
The material establishes the proximate cause of the mould damage is water which
has entered the home as a result of a storm. Therefore, the policy exclusion
regarding mildew and mould does not apply as the claimed damage does not arise
from mould but rather, the mould resulted from an insured event.
Case No: 428475 Determination Page 2 of 14
Is the applicant entitled to alternative accommodation costs?
The applicant is entitled to alternative accommodation costs as the material provided
establishes alternative accommodation was necessary because of health issues
caused by the mould.
Is the applicant entitled to compensation?
The applicant is entitled to compensation as the reports from the applicant’s
plumbers and the flood restoration expert were useful in understanding the dispute
and the experts assisted the applicant to establish his claim.
Further, the material establishes the FSP’s conduct has contributed to the time taken
to resolve the matter and has interfered with the applicant’s expectation of enjoyment
or peace of mind.
1.3 Determination
This determination is substantially in favour of the applicant.
Upon acceptance of this determination by the applicant, within 7 days, the FSP is to
pay to the applicant:
$4,500 as contribution to the costs of re -stumping
statutory interest on the said sum from the date of payment of the re-stumping by
the applicant until the date of settlement by the FSP
$1,500 compensation
the cost of replacing stumps damaged as a result of the defective waterproof
membrane and pay statutory interest on the said sum from the date of payment
by the applicant until the date of settlement.
Upon provision of proof of the cost of expert reports, the FSP is to reimburse the
applicant for the cost of the said reports and pay statutory interest on the said sums
from the date of payment for the reports until date of settlement.
Within 14 days of acceptance of this determination, the FSP is to arrange a scope of
works and assess the cost of repairs for which it is liable (as set out in the
determination) and cash settle the applicant. The cash settlement is to take into
account $4,500 contribution to re-stumping costs and $14,623.63 already paid.
The FSP is to pay statutory interest on the said cash settlement from the date of
payment by the applicant for repairs to the date of settlement.
Within 14 days of acceptance of this determination, the FSP is also to commence to
assess the applicant’s claim for alternate accommodation pursuant to the policy
terms and conditions. Statutory interest is also to be paid for alternate
accommodat ion costs from the date of the applicant’s expenditure on alternate
accommodation until settlement.
Case No: 428475 Determination Page 3 of 14
2 Reasons for determination
2.1 Is the FSP’s offer to settle the claim reasonable?
Applicant must establish a prima facie claim
The applicant must establish on the balance of probabilities he has suffered a loss
caused by an event to which the policy responds. This is known as a prima facie
claim.
In the applicant’s claim form, the applicant said the roof was damaged in storms in
July/August 2014 which allowed water to penetrate into the home over a period of
approximately six months.
In answer to a specific question as to how rain or water came into the home, the
applicant said in the claim form:
“Storm damage to box guttering has caused opening.”
The FSP’s policy covers loss or damage caused by specific events. Relevantly, the
FSP will cover damage caused by storm, flood, rainwater, hail or wind.
Applicant relies on various expert reports
The applicant relies on a flood restoration company (F). F was engaged by the
applicant because of visible mould in the property in certain identified areas:
F inspected the inside of the house and formed the view there was a ceiling or gutter
issue. It is not clear if F climbed on the roof but photographs were pr ovided and F’s
commentary noted various moisture issues with the roof, gutter and downpipe.
F concluded the roof and gutter issues had contributed to mould in the spare back
room, walk in robe, the bathroom ceiling in the master bedroom bathroom and the
garage and subfloor.
In a summary report, F said a storm in August 2014 caused the roof and gutter
damage to the property.
In February 2015, the applicant engaged a roofer, B. B provided a quote to repair the
roof in the amount of $39,820. B also wrote a roof report on 25 February 2015 in
which he said:
“Having inspected the roof at (insured property) there is substantial storm damage to
the property.
It is my belief that throughout the investigation of the roof that these issues where
caused from the recent storm in late 2014 and early 2015.
Damage:
- Over flowing of rain water in box gutter.
- Unstable roof sheets that need urgent attention.
- Quad gutters barely hanging onto timber fascia.
- Galvanised nails that are not suitable fixing for roof.
- Mould on the plaster ceilings due to leaking roof.”
Case No: 428475 Determination Page 4 of 14
In September 2015, the applicant also provided an undated report from A plumbing.
A plumbing noted:
the damaged downpipe on the east side of the house was leaking
the box gutter was level and without fall to the rain head
the box gutter was warped and water damage was seen
the observed water damage was likely due to the box gutter overflowing from
excessive water and damaging supporting structure
the valley gutters were satisfactory but were leaking due to extreme wind and
rain
In March 2010, the applicant purchased the property and obtained a prepurchase
building inspection report. An external appraisal took place. The appraisal does not
identify any structural defect, faulty design or faulty workmanship when the building
was constructed. (According to the FSP’s engineer, the building was constructed
sometime in the 1970’s).
In March 2010, the following was observed and reported on regarding the roof:
some rot was appearing in the timber barge boards and will require protecting
as for the colour bond corrugated iron roof, roof sheets were nailed down over
existing and were lifting in areas and should be replaced with screws
the roof appears to be in good condition over addition - possibility of leaks low
the possibility of the roof leaking over the colourbond corrugated iron roofing over
the carport was low
Applicant has established parts of the roof were storm damaged
Having considered the material provided by the applicant, I am satisfied on the
balance of probabilities the applicant has established parts of the roof were damaged
in storm events in August 2014 which in turn allowed water to enter the home
causing mould damage. I am satisfied the applicant has established a prima facie
claim.
FSP must establish policy exclusions
Once so established, the onus shifts to the FSP to prove on the balance of
probabilities an exclusion applies if it seeks to deny or limit its liability for the loss. In
the context of this policy, the FSP must establish the storm damage was caused
when water entered the home because of a structural defect, faulty design or faulty
workmanship when the home was constructed in the 1970’s.
FSP relies on engineer’s opinion
The FSP’s engineer i nspected and photographed the property on 2 April 2015. The
photographs taken by the engineer show the damage claimed by the applicant
including:
mould to the ceiling lining of the carport beneath the box gutter
the box gutter above the carport was holding water
mould and water damage to the rear west wall of the carport
mould spots on the ceiling of the bathroom
Case No: 428475 Determination Page 5 of 14
mould staining to the ceiling of the walk in wardrobe
mould staining to eaves adjacent to the southern bedroom and wardrobe
water staining to the roof framing at the downstream end of the valley gutter over
the walk in wardrobe and previous attempts to prevent water ingress with sealant
water damage to the floor from defective waterproof membrane in the ensuite
the subfloor ground surface was generally wet
The engineer made the following observations and findings:
no evidence of storm related damage to the box gutter or other roof plumbing
above the carport
as the box gutter was holding water, it had been installed with inadequate slope
the slab level of the carport was below the level of the external ground and there
was inadequate drainage in this site
after inspection of the roof above the bathroom, he saw no issues with roof
plumbing or storm created openings and concluded the mould was caused by
elevated humidity levels in the bathroom
there was no evidence of storm related damage to the roof cladding or plumbing
above the walk in wardrobe
he observed the mould coincided with the location of the downstream end of the
valley gutter
he concluded the mould was caused by defective installation of the eaves gutter
and valley gutter
the staining to the floor joists and bearers in the ensuite floor was consistent wi th
escape of water from a defective water proof membrane of the shower base
In November 2015, the FSP’s engineer reviewed the reports from the applicant’s
plumber A. Essentially, the engineer reiterated his findings:
he agrees the mould damage to the ceiling lining of the carport is due to the
overflow of the box gutter but says this is because of poor installation not
because the overflow has caused warping of the structure
he agrees there is mould damage to the ceiling lining of the wardrobe but says
this is due to the inadequate discharge of the valley gutter
the valley gutters require rectification
otherwise the roof cladding does not need to be replaced
FSP has not established identified structural defects were present when the
home was constructed
The FSP’s engineer agrees there is water ingress and mould damage as claimed by
the applicant. Although the FSP’s engineer identifies the reasons for the water
ingress (poor installation of the box gutter, inadequate discharge of the valley gutters,
inadequate drainage in the area of the carport and issues with the carport slab), the
FSP’s engineer does not say water entered the building because of structural defects
when the building was constructed. Therefore, the FSP has not established the
identified structural defects were there when the building was constructed.
In the circumstances, I am not satisfied the FSP has established on the balance of
probabilities it is entitled to decline the claim for the water and mould damage in the
home and carport as identified by F.
Case No: 428475 Determination Page 6 of 14
Material does not establish the applicant was aware of identified structural
defects before policy commenced
The FSP argued the damage predated the inception date of the policy. The policy
commenced on 15 January 2014. Submissions were made in relation to section 46 of
the Insurance Contracts Act.
However, although a contract of insurance can limit or exclude liability in relation to a
defect where it existed before the contract was entered into, an insurer cannot rel y on
such a provision, where, at the time the contract was entered into, the insured was
not aware of, and a reasonable person in the circumstances of the insured could not
be expected to be aware of, the defect.
The FSP has not established the defects we re present when the building was
constructed. Therefore, section 46 is not applicable. However, even if the section
was applicable, the FSP has not established the applicant was or should have been
aware of the defects identified by the engineer when the policy commenced in
January 2014. This is because the said defects and are not identified in the pre-
purchase report. Further, the material provided establishes the water ingress and
mould damage only occurred after the policy commenced.
Various causes of damage to timber stumps
The applicant also claims water damage to timber stumps.
The applicant’s plumber B does not address this issue.
The applicant’s plumber A refers to sub floor water from a storm damage d pipe and
water residue from the last year stormy few months. A says storm damage has
caused moisture issues in the subfloor joist, stumps and studs.
The issue was also addressed by F who noted the subfloor was slightly moist. F cites
the opinion of the plumber who said the down pipe was supposed to run off the
ground but has in fact ran into the subfloor. Apparently this was rectified, but, F says
the subfloor timber was damaged. F provided a photograph which is annotated
noting mould on the subfloor and stumps. F says both plumbing work was done and
some stumps were replaced.
The FSP denied the claim for the stumps. Relying on its engineer’s report, and
reports obtained by the applicant in 2010, the FSP said this damage was caused by
poor site and subfloor drainage conditions, discharge from a drainage field of a septic
tank system, discharge from defective stormwater plumbing (which had previously
been repaired) and escape of water due to a defective waterproof membrane to the
tiled base of the shower enclosure.
The FSP’s engineer noted the subfloor ground surface was generally damp. He
observed evidence of erosion and water scour consistent with surface water flow
through the sub floor.
Of the stumps which were visible, the FSP’s engineer agreed there was varying
degrees of water damage with some stumps suffering significant decay.
Case No: 428475 Determination Page 7 of 14
The engineer also said the pre-purchase report indicated issues were present prior to
the purchase of the property. The engineer agreed the elevated soil moisture would
have accelerated decay of timber stumps throughout the subfloor area.
The applicant contends the septic irrigation hoses pump out the treated product into
the garden beds at the back of the property rather than into the subfloor area. This is
not specifically rebutted by the engineer. Rather, the engineer refers to the other
reasons for the moisture under the house.
In a second report, the applicant’s plumber, A, reviewed the FSP’s reports and
reiterated findings he had made in his first report. Regarding the cause of moisture
under the house, he said:
“The report from (the FSP’s engineer) mentioned the septic tank and the fall of the
land. I found this assumption to false due to no smell from the water and the fall of the
land would not equate to the damage and amount of water under the house. Due to
rain at the time, it was observed that a damaged down pipe on the east side of the
house was leaking (sic)”
The FSP’s engineer reviewed the plumber’s report. He noted this further defect,
namely the leaking downpipe to the east side of the house. However, he said this did
not contribute to decay of the timber stumps as the stumps at the east side of the
building had been replaced with concrete stumps during previous renovations.
Although the FSP refers to certain reports obtained by the applicant in 2010, they are
not provided. The only 2010 report provided is the pre-purchase building inspection
report. The report noted re-stumping would be required in some areas.
The report notes no access was possible to the under floor space although it was
noted the concrete stumps were in good condition from a visual inspection. But it was
also noted the state of some floors indicated, as there was some slope to the
external walls, external stumps were rotting. The report strongly recommended
access be gained to all inaccessible areas and said:
“The condition of the timber stumps will vary from good to fair due to the amoun t of rot
caused from moisture that has been around them over the years. Access will need to
be gained to evaluate all timber stumps, usually the condition of internal stumps are
better than external due to external being exposed to weather.”
The FSP’s poli cy provides cover for loss or damage if liquid escapes from a fixed
pipe and/or if there is storm damage.
Having considered the material provided by the applicant’s plumber, I am satisfied
there is water and mould damage to timber stumps under the house caused by a
leaking down pipe (which has since been repaired) and water run-off after storms.
The FSP’s policy states if water entered under the house because of a structural
defect or faulty design when the building was constructed, the FSP does not have to
pay for storm damage.
The FSP identified four reasons for the damage to the stumps:
poor site and subfloor drainage conditions
discharge from a drainage field of a septic tank system
Case No: 428475 Determination Page 8 of 14
discharge from defective stormwater plumbing (which had previously been
repaired)
escape of water due to a defective waterproof membrane to the tiled base of the
shower enclosure
The FSP contends reports obtained by the applicant at about the time of purchase,
indicated the stormwater system was not properly connected, the soil was saturated,
there was poor drainage at the property, and there were plumbing defects.
However, these reports have not been provided by the FSP.
FSP agreed to indemnify the applicant for damage caused by defective
waterproof membrane
The FSP agreed to indemnify the applicant in relation to damage caused by the
defective waterproof membrane. The FSP’s engineer identified at least six stumps in
the immediate vicinity of the shower.
In the circumstances, the FSP is to indemnify the applicant in re lation to any stumps
damaged as a result of the defective waterproof membrane.
As for discharge from the septic tank system, the FSP’s engineer has not rebutted
the applicant’s contention the discharge goes to garden beds and not under the
house. Further, the FSP’s engineer has not rebutted the plumber’s opinion about the
smell from water in the relevant place. In these circumstances, on the information
provided, I am not satisfied the FSP has established on the balance of probabilities
the stumps were damaged because of discharge from the septic tank system.
The FSP also denied the claim for damage to the stumps because of poor site and
subfloor drainage conditions. However, in view of the plumber’s opinion that the fall
the land would not equate to the damage and water under the house, I am not
satisfied the FSP has established on the balance of probabilities the stumps were
damaged because of this reason.
As for the leaking down pipe, as the applicant has not rebutted the engineer’s
contention the pipe is not responsible as the pipe was on the east side of the house
where stumps were replaced with concrete stumps during previous renovations, I am
not satisfied on the balance of probabilities this leaking down pipe is any longer
responsible for the present damage to the stumps under the house.
The FSP also submits when the policy commenced on 15 January 2014 a
reasonable person in the circumstances of the applicant could have been expected
to been aware of the issues and the state of the timber stumps. In the absence of the
reports referred to by the FSP, I am not satisfied the applicant knew about the four
issues identified by the FSP’s engineer.
However, in view of the pre-purchase building inspection report, I am satisfied, before
the policy commenced, the applicant knew the condition of the timber stumps would
vary due to the amount of rot already caused by moisture.
The material establishes some of the timber stumps referred to in the pre-purchase
building inspection report have been replaced by the applicant.
Case No: 428475 Determination Page 9 of 14
The material also establishes a variety of causes for the damage to the timber
stumps some of which have not been established by the FSP. The applicant has
provided a cost breakdown from F which includes a quote of $9,000 to re-stump.
The FSP is to indemnify the applicant in relation to any stumps damaged as a result
of the defective waterproof membrane under the shower
Fair in all the circumstances the FSP pay the applicant $4,500 for re -stumping
Having considered all the material provided and for the reasons stated, I consider it is
fair in all the circumstances the FSP pay to the applicant a further $4,500 as
contribution to the cost to re-stump the subfloor stumps.
I note the applicant has undertaken some repair work already. If the applicant has
paid for re-stumping, then the FSP is also to pay statutory interest on $4,500 from the
date of payment by the applicant until settlement.
Proximate cause of damage is not mould but water ingress from storm
The FSP also relies on a policy exclusion relating to gradual deterioration. However,
this policy exclusion refers to accidental damage to valuable items and is not relevant
to the policy response concerning the applicant’s claim.
The FSP relies upon another general exclusion regarding mildew and mould. It says
it is not obliged to pay the claim because the loss and damage arises from mould.
However, I am satisfied the material establishes the proximate cause of the mould
damage (that is, the dominant or effective or operative cause of the loss) is water
which has entered the home as a result of a storm. In the circumstances, I am
satisfied the exclusion does not apply as the claimed damage does not arise from
mould but rather, the mould resulted from an insured event.
Cash settlement to take into account $14,623.63 paid by FSP
The FSP accepted liability for damage to the ensuite bathroom. In May 2016, the
FSP paid to the applicant $14,623.63.
The applicant provided a quote to replace the roof in the amount of $39,820.
However, the material does not establish the entire roof is damaged.
Although the applicant’s plumber says in a second report, he recommends the
replacement of half the roof, he does not attribute this to storm damage but rather
“due to poor condition caused by the openness of the rural land.”
The policy does not respond to the cause identified and the FSP is not liable to pay
to replace half of the roof.
Having considered the material provided by the applicant’s plumbers, I am satisfied
there is storm damage to parts of the roof only as identified in the reports from the
applicant’s plumbers.
Case No: 428475 Determination Page 10 of 14
FSP to arrange scope of works, assess cost of repairs and cash settle the
claim
The applicant says he has undertaken repairs. Upon acceptance of this
determination, the FSP is to forthwith arrange a scope of works and assess the cost
of repairs for which it is liable and cash settle the applicant.
The cash settlement is to include $4,500 contribution to re -stumping costs and take
into account $14,623.63 already paid to the applicant.
The FSP is to pay statutory interest on the balance of cash settlement from the date
of payment by the applicant for repairs to the date of settlement.
In summary, repairs for which the FSP is liable include the mould remediation
identified in F’s report wh ich includes but is not limited to:
mould in the subfloor
water and mould damage to the ceiling lining of the carport
water and mould damage to the rear wall and skirting of the carport
water and mould damage in the ensuite bathroom (if not already included in the
amount paid to date)
water and mould damage to the ceiling of the walk in wardrobe and adjacent
external eaves lining
storm damage to parts of the roof identified in the reports from the applicant’s
plumbers
It remains necessary for the amount of any cash settlement to be agreed. FOS
encourages the parties to this dispute to resolve any issues which might arise
regarding repairs or the cost of repairs. However, the parties can return to FOS if
they are unable to resolve any issues arising from repairs and/or the cost of repairs.
2.2 Is the applicant entitled to the costs of alternative accommodation?
Alternative accommodation payable by FSP
After the FSP agreed to pay $14,623.63, the applicant raised the issue of alternative
accommodation costs.
The FSP has not addressed this issue.
The FSP’s policy provides cover for additional things when they relate to loss or
damage from a listed event. In view of the findings in this determination, the
additional benefit relating to alternate accommodation is payable by the FSP.
The FSP’s policy says:
“If you are unable to live in your buildings after loss or damage has occurred, we will
pay you to rent another property. We will pay an amount equal to the amount that your
buildings could have been rented out for each week if the loss or damage had not
occurred. We will also pay the costs of alternate accommodation for your pets and
additional living expenses up to $1,000. The most we will pay for these costs is 20% of
your buildings sum insured as listed on your policy schedule.
Case No: 428475 Determination Page 11 of 14
We will reduce the amount we pay you or stop paying you, if you:
are able to live in your buildings”
Alternative accommodation necessary because of health issues caused by
mould
F reports a building biologist inspected the applicant’s home on 22 January 2015 and
was confident the family health was related to mould intoxication.
F’s report describes the mould in various areas in the house and the subfloor. F said:
“The health issu e will deem it impossible for (the applicant) to live in the house with
such high count of mould and fungal hyphae in the building envelope.”
The applicant says his family vacated the home on 23 January 2015. Some time in
the middle of 2015, the applicant proceeded with various remedial works. It is not
known when the applicant returned home. No information is provided regarding the
actual costs of alternate accommodation.
The FSP is to assess and settle this aspect of the applicant’s claim pursuant to the
policy terms and conditions. Statutory interest is also to be paid from the date of the
applicant’s expenditure on alternate accommodation until settlement.
It remains necessary for the amount of any cash settlement for alternate
accommodation to be agreed. FOS encourages the parties to this dispute to resolve
any issues which might arise regarding this issue. However, the parties can return to
FOS if they are unable to resolve any issues arising from the cost of alternate
accommodation.
2.3 Is the applicant entitled to compensation?
Fair in all the circumstances professional costs for reports are paid
Paragraph 9.4 of FOS’s Terms of Reference says FOS may decide the FSP
contribute to professional costs incurred by an applicant in the course of a dispute.
Unless exceptional circumstances apply, FOS will not require the FSP to contribute
more than $3,000 to these costs.
FOS found reports from the applicant’s plumbers and F useful in the understanding
of this dispute. Further, FOS considers it is fair for the FSP to contribute to expert
professional costs which have assisted the applicant to establish his claim.
Therefore, FOS is satisfied it is fair in all the circumstances the FSP pay to the
applicant for the cost of repo rts from the plumbers and F upon provision by the
applicant of proof of the cost of reports.
Compensation is paid in certain circumstances
The Terms of Reference also allow the payment of compensation (capped at $3,000)
for non-financial loss. FOS may decide an FSP should compensate an applicant for
such loss only where there has been an unusual amount of physical inconvenience,
Case No: 428475 Determination Page 12 of 14
time taken to resolve a situation, or interference with the applicant’s expectation of
enjoyment or peace of mind.
The applicant complains about the delays in claims handling. The applicant also
describes the stress suffered by the applicant and his family as a result of the
constant upheaval and change whilst commuting between two residences.
The FSP acknowledges delays occurred in the claims handling.
Fair in all the circumstances the FSP pay $1,500 compensation
FOS considers the FSP has paid insufficient attention to the many elements and
details of this claim leading to inadequacies in offers made and contentions proffered.
I n the circumstances of this dispute, FOS considers the FSP’s conduct has
contributed to the time taken to resolve the matter and has interfered with the
applicant’s expectation of enjoyment or peace of mind.
FOS takes a conservative approach to compensation for non-financial loss.
I am satisfied it is fair in all the circumstances the FSP pay to the applicant $1,500
compensation for non-financial loss.
Case No: 428475 Determination Page 13 of 14
3 Supporting information
3.1 FOS Approach
As advised to the parties, FOS has considered it appropriate to expedite this dispute
in accordance with the Operational Guidelines to the FOS Terms of Reference, due
to the nature of the dispute. Accordingly, this dispute has not been the subject of a
FOS recommendation and has proceeded directly to determination.
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All of the material provided by the parties has been reviewed and
considered for the purposes of this determination.
This dispute has been decided on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions.
While the parties have raised numerous issues in their s ubmissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
The applicant is represented by his broker. Any references to the applicant in this
determination include references to the applicant and to the applicant’s
representative.
It is an accepted principle of general insurance law that an insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie claim. Once so
established, the onus shifts to the insurer to prove on the balance of probabilities that
an exclusion applies if it seeks to deny or limit its liability for the loss.
3.2 Relevant policy extracts
The relevant policy extracts are referred to in the determination and in the FSP’s
Notice of Response dated 2 March 2016. Both the policy document and the Notice
have been exchanged with the applicant.
3.3 Other relevant material considered and relied on
Parties’ submissions, emails and all attachments to submissions including
photographs, quotations and invoices
Correspondence between the parties
Pre-purchase inspection report dated 3 March 2010
Plumber’s reports from A (two) undated
Plumber’s report B d ated 25 February 2015
Policy schedule
Claim form dated 26 February 2015
Report, summary report and costs breakdown from F (all undated) and email
from F dated 21 April 2015
Case No: 428475 Determination Page 14 of 14
FSP’s engineer’s report 9 April 2015 and emails from the engineer dated 20
April 2015 and 20 November 2015
FSP’s assessor’s report dated 13 May 2016
3.4 Case law and proximate cause
Case law establishes:
The proximate cause of the loss is the dominant or effective or operative cause of
the loss whether or not that be the last in time or the sole cause.
If there are several causes operating contemporaneously, each must be
examined for the qualities of reality, predominance and efficiency as the active,
efficient cause that sets a relevant chain of events in action. If one cause would
have caused the harm in any case, and the other would not have done so in the
absence of the first, the first is the proximate cause.
A common sense approach is taken to determine proximate cause.