Summary

The trustee of an SMSF said the FSP unreasonably delayed a sell order by about 4.5 minutes, causing a loss of $28,750 as the share price fell. AFCA found the delay resulted from a reasonable internal order review consistent with the client agreement and market obligations.

The FSP's pre-set review filters and market integrity obligations justified the delay, and clause 19(a) of the general conditions excludes liability for lost opportunity.

Issues

Subjects and remedies

smsfno remedy

Related

All Financial Firm (Unknown) determinations · Find similar determinations

Text of the determination

Determination Case No: 427359 Determination Page 1 of 6 Case number: 427359 23 September 2016 1 Overview 1.1 Dispute The applicant is a trustee of a self-managed superannuation fund (SMSF) and has an online share trading account with the financial services provider (FSP). The FSP is an ASX trading participant online stockbroker, operating an automated order processing system. This dispute concerns an order placed by the applicant to sell 250,000 AHF shares at $0.58 on 30 December 2015 at 12:43:32pm. The order was delayed by the FSP prior to the order being released to the market. The applicant claims the FSP unreasonably delayed placing the order by 4.5 minutes leading to a loss of $28,750 as the share price started to fall. The FSP says there was a necessary delay caused by a review of the order by its automated processing system, acted in accordance with the client agreement and its market integrity obligations . The case manager provided the parties with a recommendation on the issues in dispute. A copy of the recommendation is attached to this determination. The recommendation was in favour of the FSP. 1.2 Issues and key findings Were the findings of the recommendation correct? The findings contained in the recommendation were correct and are adopted in this determination . Further submissions provided after the recommendation have been considered. Did the FSP act in accordance with the client agreement and its legal obligations to the client and the market? The FSP met the terms and conditions of the agreement between the parties. It is reasonable to expect that would the FSP’s automated processing system would select some orders for review, as a result of the trade volume in AHF on the day the applicant placed the order. Did the FSP’s conduct cause an unreasonable delay releasing the order to market? The FSP did not cause an unreasonable delay releasing the order to market. In my view, any delay was the necessary consequence of the review. The pre-set filters in the FSP’s automatic auto processing system selected the order for review consistent Case No: 427359 Determination Page 2 of 6 with the terms and conditions of the client agreement and the FSP’s market integrity obligations. Is the FSP responsible for losses named by the applicant from the delay? The delay was caused by the FSP’s review of the applicant’s sell instruction. This was consistent with the client agreement and its legal obligations. The FSP is not responsible for any losses incurred from the delay in the order being placed. 1.3 Determination This determination is in favour of the FSP. Case No: 427359 Determination Page 3 of 6 2 Reasons for determination 2.1 Were the findings in the recommendation correct? I am satisfied that the case manager’s recommendation contains an accurate summary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. I am of the view that the recommendation’s findings were correct. I make the following further comments on matters raised by the parties in their post recommendation, for the sake of completeness. 2.2 Did the FSP act in accordance with the client agreement and its legal obligations? A review of orders in certain circumstances is common place A review of orders is common in the industry and constitutes good industry practice. The order was selected by the FSP’s pre -set filters in the automatic auto processing system. The order was referred for the reviews:  first for order value limit non warrant, and  then for large order value exception The order was referred to the work bench for manual review. Upon completion of the review it was released to the market without future delay. All up, the review process took 3 minutes and 56 seconds. The FSP met the terms and conditions of the client agreement in doing so The FSP refers to and relies on page 9, Clause 19a of its terms and conditions which provides that whilst all reasonable attempts to enter instructions to buy and sell securities will be made as quickly as possible, delays may be experienced for a range of reasons. I am satisfied that as a market participant, the FSP had an obligation to ensure all orders placed through its trading platform met regulatory and internal guidelines. These guidelines are in place to protect the integrity of the market and to prevent market manipulations. Ensuring compliance with these guidelines can potentially result in delays in reviewing orders, especially when there is an unusual increase in the volume of orders being placed in the market, as was the case in this instance. The FSP provided records including order history with time stamps, reports of filters and setting rules and demonstrated a clear understanding of its market integrity rule obligations. The evidence indicates that AHF shares experienced a significant increase in trade volume on the day of the applicant’s order. The price and volume of shares traded increased significantly leading up to and on 30 December 2015. It was reasonable to expect that orders such as the applicant’s would have been selected by the FSP’s automated order processing system for review as a result. Case No: 427359 Determination Page 4 of 6 2.3 Did the FSP’s conduct cause an unreasonable delay releasing the order to the market? The applicant continues to claim that the FSP was responsible for an unreasonable delay of 4.5 minutes in releasing the order to market. The order history presented by the FSP, which I accept, shows that the first and second order reviews needed to have been completed within 14 seconds and then released to the market within another 4 seconds (of 12:43.50pm) in order to participate in sales at 0.58 cents. I am satisfied that it is not reasonable to expect that these referrals, reviews and release procedures would have been conducted within that timeframe. In all, the order history illustrates that the two reviews conducted prior to the order being released to market took approximately 3 minutes and 56 seconds from the time the order was placed by the applicant. I am satisfied on the basis of this evidence that the FSP’s referrals, reviews and then release of the order to the market was necessary and did not cause an unreasonable delay. Is the FSP responsible for losses named by the applicant from the delay? Whilst there was sufficient buy and demand to complete the order to sell 250,000 AHF shares at the time the applicant placed the order on the FSP’s platform, it was not reasonable to expect that the FSP would be able to refer, review and release the order in the relevant period of 18 seconds. By that time, the price had fallen below 0.58 cents and never recovered. I am satisfied that the FSP was entitled to take steps to check the bona fides of any order or instruction before action on that order of instructions took place. This is set out in the terms and conditions between the applicant and the FSP which also incorporates, amongst other things, the general conditions of trading rules. These rules clearly state that the applicant’s instructions to trade are not completed until the FSP accepts it. In this instance I am satisfied the FSP has demonstrated that the delay for the acceptance of the applicant’s sell order was reasonably based and due to its internal review processes. In accordance with Clause 19a of the general conditions of trade therefore, the FSP is not liable for the applicant’s loss. Case No: 427359 Determination Page 5 of 6 3 Supporting information 3.1 The FOS process This dispute has been the subject of a recommendation in favour of the FSP, which was not accepted by the applicant. I have considered all of the material submitted by the parties, both before and after the recommendation was issued, in order to reach my decision. I am satisfied that the material I have relied upon in reaching my findings has been exchanged by the parties. I have decided this dispute on the basis it was fair in all the circumstances, having regard to legal principles, applicable industry codes and guidance about good practice, and previous relevant decisions at FOS or its predecessors, (though I am not bound by these). 3.2 Other issues raised by the applicant The applicant has raised additional concerns about the conduct of the FSP which I address here for the sake of completeness. In my view, these matters are not relevant to the determination of this dispute. Did the FSP’s designated trading representatives act outside the FSP’s terms and conditions (T and C’s)? In my view the FSP’s DTR’s, as authorised persons, acted within the requirements of the ASX market integrity rules 2010. They also acted within the FSP’s terms and conditions in relation to the review of the orders. The successful execution of two other orders by the applicant does not mean the FSP breached its obligations I am satisfied that the order in dispute was not unreasonably delayed, notwithstanding that the applicant was successful in completing other sales at 12:44 (sold 30,000) and 12:47 (sold 100,000). The FSP’s failure to publicly disclose threshold amounts for a review I accept that the FSP’s references to value and volume threshold , without being too specific, was necessary to ensure that sensitive commercial information contained within the FSP’s interna l procedures was not disclosed. Case No: 427359 Determination Page 6 of 6 The relevant issue to be determined in this matter was whether the review was conducted in accordance with the FSP’s internal procedures , its market obligations and consistent with its terms and conditions, not the threshold amount that might trigger a review. Recommendation Case No: 427359 Recommendation Page 1 of 4 Case number: 427359 29 April 2016 4 Overview 4.1 Dispute The applicant has a share trading account with the financial services provider (FSP). On 30 December 2015, the applicant placed a good for day trade to sell 250,000 units of AHF at $0.580 via the FSP’s online trading platform. The FSP delayed the acceptance of the applicant’s order and by the time it was accepted, the price of AHF fell below $0.580. The applicant sold the AHF units later that day at a lower price. The applicant considers that the delay was unreasonable. He is seeking $28,750, plus costs, in compensation. 4.2 Issues and key findings Is the FSP responsible for the losses the applicant incurred from the delay in the order being placed? The delay was caused by the FSP’s review of the applicant’s sell instruction. This was performed due to the FSP’s internal procedures. The FSP is not responsible for the applicant’s losses for loss of opportunity arising from this delay. 4.3 Recommendation The recommendation is in favour of the FSP. Case No: 427359 Recommendation Page 2 of 4 5 Reasons for recommendation 5.1 Is the FSP responsible for the losses the applicant incurred from the delay in the order being placed? AHF’s price was $0.58 or above for a short period At the time the applicant placed the instruction to sell at 12:43:32, the price for AHF was $0.580. The price of AHF continued to be at or above $0.580 until 12:43:47. The price for AHF fell at this time and never reached or went above $0.580 again that day. There was a very short period of time, or approximately 15 seconds, for the applicant’s trade to be accepted and executed. The FSP delayed the acceptance of the applicant’s instruction to trade The FSP has internal procedures that trigger reviews of an instruction to trade. According to the FSP’s internal vetting rules, when e ither buy or sell orders that require large non- warrant orders and the order value exceeds the FSP’s set thresholds, the order gets referred internally for a review. The vetting procedures occurs automatically when an instruction to trade exceeds the threshold. Once triggered the instruction is reviewed manually by a FSP representative and determined to be accepted or rejected. There is evidence that the applicant’s instruction to trade was referred for a review due to this vetting rule. The review was triggered at 12:43:34 and the trade instructions was completed and accepted at 12:47:26. The delay occurred due to the FSP’s internal review of the applicant’s instruction to trade. By the time the instruction was accepted, the price for AHF had fallen below $0.580 and never recovered. The applicant’s instruction to trade is not completed until the FSP accepts it The FSP’s Terms and Conditions (T&C) set out the agreement between the applicant and the FSP. Within the T&C, the agreement incorporates, amongst other matters, the General Conditions of Trade and Trading Rules. Clause 16 of the General Conditions of Trade states that the FSP is not obliged to accept any application or instruction to trade nor is it obliged to provide the applicant with reasons for refusing the application or instruction to trade. Further, under clause 34 of the Trading Rules, the FSP is entitled to take steps to check the bona fides of any client, order or instruction before action on that order or instruction. The FSP is not responsib le for the applicant’s missed opportunity to sell AHF at $0.58 Clause 19(a) of the General Conditions of Trade state that the FSP will make all reasonable attempts to enter the applicant’s instructions to buy or sell securities as quickly as possible. However, should delays occur:  due to the number of participates in the market at the time; Case No: 427359 Recommendation Page 3 of 4  due to verification or authorisation processes; or  due to the delays resulting from call waiting time or the adherence to internal procedures,  the FSP will not be liable for any claims of lost opportunity. The FSP was not required to provide the applicant with reasons about why an instruction to trade was not accepted. In any event, the FSP is entitled to review an instruction to check the bona fides of the instruction. In this instance, the FSP has demonstrated that the delay for the acceptance of the applicant’s sell order was due to its internal review procedures. In accordance with clause 19(a) of the General Conditions of Trade, the FSP is not liable for the applica nt’s claimed loss. Case No: 427359 Recommendation Page 4 of 4 6 Supporting information 6.1 Relevant provisions from the T&C General conditions of trade (i) (ii) 16. We are not obliged to accept any application or instruction to trade, nor are we obliged to provide you with reasons for refusing your application or instruction to trade. If we consider it is in our reasonable interest to do so, we may decline to act on your behalf in relation to any particular dealings, without explanation or advance notice. … (iii) (iv) 19(a). You acknowledge that we will make all reasonable attempts to enter your instructions to buy or sell securities as quickly as possible. However, should delays be experienced: (v) in connection with the number of participants or persons attempting to participate in the market at a point in time; (vi) due to verification or authorisation processes; or, (vii) due to delays resulting from call waiting time or adherence to internal procedures, (viii) we will not be liable for any claims for lost opport unity. Trading rules (ix) (x) 34. We reserve the right to take such steps as we consider necessary to check the bona fides of any client, order or instruction before acting on that order or instruction. 6.2 Other issues Due to the sensitive commercial information contained within the FSP’s internal procedures, the FSP has opted not to reveal the threshold amounts that trigger a review. For the purposes of this recommendation, it is accepted that the threshold amounts were not relevant. What is relevant is that the review was conducted in accordance with the FSP’s internal procedures, which was consistent with the T&C.