Home / Financial Firm (Unknown - Credit) / Determination 425842

Determination 425842

Final construction progress payment released before works were complete

FirmFinancial Firm (Unknown - Credit)
Decided2016-07-22
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The FSP released the final progress payment to the builder on a construction loan although the building works were incomplete, after representing it would confirm completion. AFCA found the FSP misrepresented its position but the applicant did not rely on it to her detriment and the loss was caused by the builder, so nothing was ordered.

A misleading representation requires proof that the applicant relied on it to her detriment, and the loss was more likely caused by the builder's failure to complete the works.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 425842 Determination Page 1 of 6 Case number: 425842 22 July 2016 1 Overview 1.1 Dispute The applicant entered a fixed price contract with a builder to construct a new home. To complete the construction work the financial services provider (FSP) granted the applicant a construction loan. The applicant says the FSP should not have made the final progress payment to the builder under the construction loan. 1.2 Issues and key findings Did the FSP incorrectly make the final progress payment? The FSP represented to the applicant that if would confirm the building works were complete prior to making the final progress payment. The building works were incomplete when the FSP released the final progress payment to the builder. What compensation is payable to the applicant? While the FSP misrepresented its position to the applicant, it has not been shown the applicant acted on the misrepresentation to her detriment. The loss claimed by the applicant was more likely caused by the builder and not the FSP. No compensation is payable. 1.3 Determination This determination is in favour of the FSP. Case No: 425842 Determination Page 2 of 6 2 Reasons for determination 2.1 Did the FSP incorrectly make the final progress payment? The applicant agreed to make progress payments In May 2014, the applicant entered a fixed price contract with a builder to construct a new home for $259,240. The builder agreed to comple te the work for an agreed fixed amount. The building contract included a progress payment schedule setting out the cost for the six stages of the construction as set out in section 3.2 below. The final three stages were paid with the funds from the construction loan including the final payment of $40,230 on 7 October 2015. The applicant disputes the final progress payment The applicant says the final payment should not have been paid by the FSP as the builder had not completed construction to the practical completion stage. The FSP says prior to releasing the final progress payment to the builder it:  arranged for an independent valuation agent to conduct a progress payment inspection of the construction works to determine whether the works had been completed in accordance with the building contract  received a tax invoice from the builder outlining the stage completed consistent with the progress payment schedule, and  received the a pplicant’s written authorisation to release the final progress payment to the builder. The FSP made the final four progress payments as set out in section 3.2. Prior to the final progress payment an inspection of the works was undertaken Prior to the final progress payment by the FSP, its independent valuer attended the security property to conduct an inspection of the work. The valuation dated 2 October 2015 records that at that time the practical completion stage had not been reached and full payment was not recommended, with painting still to be completed. In his report to the FSP the valuer:  noted there were no ceiling fans and basic fixtures in the original valuation  noted that it had not sight ed the ‘Final Certificate’, and  recommended withholding $3,000 until works were completed. Prior to the final progress payment and in line with the FSP’s policy, an inspection of security property and the works was undertaken before the final progress payment was made to the builder. The applicant authorised the final builder ’ s invoice Prio r to the final progress payment and in line with the FSP’s policy, t he applicant: Case No: 425842 Determination Page 3 of 6  provided a signed letter to the FSP advising that the (outstanding) painting would be completed on 6 October 2015, and  signed off on the builder ’ s invoice in relation to the final progress payment. Following receipt of this signed invoice, the FSP paid the final progress payment to the builder. The applicant says that she signed the final progress invoice without conducting her own inspection of the construction because she believed it was appropriate for her to also rely on the expertise of the FSP’s independent valuer. The FSP does not owe the applicant a duty to act in her interests The FSP, including its agent the independent valuer, does not have a ‘fiduciary’ duty or responsibility to the applicant to act solely in her interest and make judgments on her behalf. This means that the FSP was not obliged to share the valuation report or advise the a pplicant as to when or if she should sign the builder’s tax invoice and authorise the final progress payment. The applicant has responsibility to protect her own interest in this regard. Generally, when a financial services provider obtains a valuation, it does so for its own benefit as mortgagee of the property on which the house is being constructed, as the construction will form part of its security for the loan. If the applicant had doubts about signing the invoice or required an independent assessment or advice, she should have sought independent advice prior to signing the authorisation. It was therefore not appropriate for the applicant to rely on the expertise of the FSP or its valuer that the building works were complete. The FSP misrepresented that it would confirm all works were finished The documents provided by the FSP to the applicant included a Construction Home Loan Fact Sheet and Contract Building Loans – Notes to Customers. In both documents the FSP states that when a final progress payment is requested on completion of a construction, the FSP will arrange a final property inspection to ‘confirm that all works’ have been completed. Importantly, the confirmation referred to in the FSP documents is that the FSP satisfies itself, as the mortgagee, that all works have been completed. The confirmation is not an assurance upon which the applicant can rely. The valuer ’s report obtained by the FSP for the applicant’s property did not contain confirmation that all works had been completed. Instead it recommended a withholding of $3,000 to allow completion to be undertaken. It follows that the FSP proceeded with the final payment without first confirming for its own purposes that all works were finished. In making the final progress payment the FSP therefore misrepresented to the applicant that it was satisfied that the works were finished. Case No: 425842 Determination Page 4 of 6 The building works were incomplete The applicant has provided a property inspection report dated 26 April 2016 prepared by an independent property inspector. The inspection was conducted to identify defects and safety hazards associated with the property and compare its overall condition to industry best practices for a similar new building. The applicant’s property report lists a number of major and minor defects and concludes that the building has incomplete work, is well below industry standards in many areas with the site and internal areas unfit for the purpose of habitation and unsafe. There is no information to show that the builder supplied the applicant with all the council approval documents including the final certification documents, water proofing and warranty documents at settlement. The applicant says she was not provided with a certificate of occupancy. The a pplicant’s report shows the building works were incomplete when the FSP released the final progress payment to the builder. 2.2 What compensation is payable to the applicant? The applicant did not act in reliance on the FSP’s misrepresentation Where an applicant has been misled by the conduct of a financial services provider, FOS will assess how much worse off they are as a result of relying on the misrepresentation. The remedy for misleading conduct is not to make the misrepresentation come true. It is not clear that the applicant relied upon the FSP’s misrepresentation that it had confirmed that the building works were complete, for the following reasons:  as set out above the FSP ’s representation was t hat it would satisfy itself (not the applicant) that completion had occurred  the FSP’s Contract Building Loans – Notes for Customers made it clear that it was the obligation of the applicant to obtain an occupancy certificate at completion  the applicant provided a signed letter to the FSP advising that the painting would be completed on 6 October 2015, and  the applicant signed off on the builder’s final invoice authorising payment. Further the payment of the final process amount allowed the applicant to move into and live in the property despite the defects identified. I acknowledge that the FSP’s payment of the final progress amount meant that t he applicant lost commercial leverage she had against the builder to continue to negotiate to complete the unfinished work. This, however, needs to be balanced against the benefit to the applicant of moving into the property. Regard must also be had to the fact that the applicant authorised the payment and moved in to the property without receiving an occupancy certificate. Case No: 425842 Determination Page 5 of 6 On the information available it has not been shown that the applicant acted in reliance on the FSP’s misrepresentation to her detriment. The FSP’s conduct did not cause the applicant loss The applicant ’s claimed financial loss has arisen as a consequence of the builder failing to complete the building works in accordance with the building contract after the final progress payment was made. There is no information to show to what extent the applicant and builder agreed to variations to the building contract or to what stage these works were completed. The applicant has the right and is taking steps to pursue completion of the building through the builder, his insurer and the Queensland Building and Constructions Commission. As a result, some or all the defects and safety hazards identified in the inspection report will likely be rectified in the future. I am unable to conclude any loss has arisen as a consequence of the FSP’s error rather than the builder’s actions . Case No: 425842 Determination Page 6 of 6 3 Supporting information 3.1 Decision basis and process This dispute has been the subject of a preliminary view in favour of the applicant, which was not accepted by the applicant. I have considered all the material submitted by the parties, both before and after the preliminary view was issued, in order to reach my decision. I am satisfied that the material I relied upon in reaching my findings has been exchanged between the parties. I have considered what is fair in all the circumstances, having regard to legal principles, applicable industry codes or guidance as to practice, good industry practice and previous relevant decisions of FOS or its predecessors (though I am not bound by these). 3.2 Progress payments Stage % Amoun t Date paid Invoice 1 Deposit 5 $12,977 Paid by Applicant before Construction Loan granted INV1047 5% deposit 2 Base 30 $77,862 Paid by Applicant before Construction Loan granted INV1048 1Base 30% construction contract 3 Frame 15 $38,931 Paid 14/01/15 INV - 0052 15% Enclosed Draw 4 Enclosed 20 $51,908 Paid 05/03/15 INV - 0037 20% progress payment 5 Fixing 15 $38,931 Paid 22/04/15 INV - 0068 15% Draw for Fixing stage 6 Practical completion 15 $38,931 Paid $40,230 07/10/ 15 INV - 0068 15% Draw for Final Stage 100% $259,540

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.