Text of the determination
Determination
Case No: 425621 Determination Page 1 of 11
Case number: 425621 22 December 2016
1 Overview
1.1 Dispute
The applicant lodged a claim under her home insurance policy with the financial
services provider (FSP) after her home was damaged during severe storms in April
2015.
The FSP accepted the applicant’s claim and offered to cash settle her for the
estimated cost of repairing the damage to her home, based on a quotation provided
by its builder. The FSP also paid the applicant an allowance for temporary
accommodation during the repair period.
The applicant says the cash settlement offered by the FSP is not sufficient to restore
all of the damage to her property caused by the storm. She seeks payment of the full
sum insured ($318,000) so the property can be demolished and rebuilt, and
considers the FSP should be required to undertake the necessary works.
The applicant also seeks payment of additional benefits for temporary
accommodation, together with compensation for stress and inconvenience suffered
during the claims process.
1.2 Issues and key findings
Is the FSP entitled to cash settle the claim?
The FSP acted reasonably in offering to cash settle the claim, given the pre-existing
condition of the property and the partially completed repairs.
Is the FSP required to increase the settlement for building repairs?
The cash settlement should be increased by an additional amount of $10,315.06 to
ensure that the applicant has sufficient funds to carry out the necessary repairs to the
property.
Is the applicant entitled to additional accommodation benefits?
Given the protracted repair period and the applicant’s actions in continuing to reside
at the property under trying circumstances, the FSP is required to pay the applicant
additional accommodation benefits (reflecting the costs it would have incurred had
the applicant chosen to move into alternative accommodation).
Case No: 425621 Determination Page 2 of 11
Is the applicant entitled to compensation?
The applicant is entitled to reimbursement fees incurred in obtaining her building
consultant’s report, but is not otherwise entitled to compensation.
1.3 Determination
This determination is partly in favour of the applicant.
The FSP is required to pay the applicant the following amounts in full and final
settlement of her claim:
$113,465.70 for the costs of repairing the damage to her property caused by the
storm in April 2015 (to the extent the cash settlement amount of building repairs
has not previously been paid); and
$18,800, less the total amount of temporary accommodation benefits paid under
the claim to date.
The FSP is to pay interest on the outstanding settlement amount as set out in section
2.3 below.
The FSP is to reimburse the applicant for costs incurred in obtaining a report from
her building consultant, subject to provision of an appropriate invoice.
Case No: 425621 Determination Page 3 of 11
2 Reasons for determination
2.1 Is the FSP entitled to cash settle the claim?
Policy sets out how claims will be settled
Under the terms of the policy, the FSP may settle a claim for damage to the
applicant’s home by:
arranging for its contractors to repair the damage, so as to restore the property
to the condition it was in before the damage occurred; or
paying the applicant the cost (to the FSP) of doing so.
It is clear from the terms of the policy that the FSP has the discretion to decide which
settlement method to adopt.
FSP is entitled to cash settle claim
The storm in April 2015 resulted in rainwater run-off coursing down the sloping site at
the applicant’s property, inundating the rear section of her home. During the storm,
the drains at the property became blocked, causing raw sewerage to discharge into
the property through the bathroom fixtures.
The FSP elected to cash settle the app licant’s claim after its assessor (BH) advised
that the property was in poor condition prior to the storm and had a number of
outstanding maintenance issues.
The available information establishes that there was pre-existing damage and
partially completed repairs to the property at the time of the storm in April 2015.
The applicant had lodged a prior claim under the policy following a n earlier storm in
November 2014. At the time, the FSP accepted liability for internal water damage to
various rooms at the property and cash settled the applicant for the estimated cost of
the repairs.
However, the FSP declined cover for repairs to the roof, which required replacing due
to extensive corrosion and deterioration over a prolonged period. The FSP’s builder
also noted pre-existing termite damage to the walls of the enclosed verandah and the
timber decking.
Following its assessment of the applicant’s claim for damage caused by the
November 2014 storm, the FSP advised the applicant that, in order for cover to be
renewed, she would need to undertake the repairs to the roof, the verandah and the
deck.
When the FSP’s assessor (BH) inspected the property following the subsequent
storm in April 2015, he confirmed that the repairs to the verandah and deck had been
partially completed and the roof repairs were due to commence the following week.
BH recommended that these repairs be put on hold until the second claim had been
finalised.
In circumstances where there were outstanding maintenance repairs to the property
at the time of the storm in April 2015, the panel considers the FSP acted reasonably
Case No: 425621 Determination Page 4 of 11
in deciding to cash settle the claim. The nature of the pre-existing issues with the
prop erty meant that the FSP’s builders were unlikely to be able to guarantee the
claim-related works.
While the approach taken by the FSP is consistent with the terms of the policy, it left
the applicant with the responsibility of arranging building repairs herself, in somewhat
challenging circumstances.
The applicant was living alone in a relatively isolated, rural area and experienced
significant stress as a result of the damage to her home caused by the storm, which
exacerbated a pre-existing psychological condition.
In these circumstances, the FSP was obliged to ensure that the cash settlement
amount paid for building repairs was sufficient to allow the applicant to engage a
builder directly to complete the necessary repairs.
2.2 Is the FSP required to increase the settlement for building repairs?
Applicant says cash settlement offer underestimates repairs required
The cash settlement amount of $100,903.17 initially offered by the FSP in January
2016 included an amount of $92,503.17 for the repair of the damage to the
applicant’s home caused by the storm in April 2015.
This amount was determined based on quotations provided by the FSP’s builder
(DW) based on a scope of works prepared by the FSP’s assessor (BH) following the
storm. DW quoted an amount of $9,128 for the strip out and deodorising of the
damaged sections of the building and an amount of $83,375.17 for the reinstatement
of the damaged areas.
The FSP had previously paid an additional amount of $17,600 to the applicant’s
representative (SK), to remove damaged contents items and undertake initial
sanitising of the property to enable the repairs to commence. This amount was paid
to SK at the applicant’s request, although it is unclear to what extent he actually
carried out the relevant works.
The applicant disputed the FSP’s cash settlement offer for the building repairs, on the
basis that it did not fully provide for the cost of repairing all of the damage caused by
the storm in April 2015.
Among other things, the applicant says that additional damage to the property has
occurred after it was inspected by the FSP’s contractors, due to the ongoing effects
of the inundation experienced during the storm.
The applicant has provided a copy of a report and scope of works prepared by her
building consultant (DL), which outlines additional damage to various parts of the
property which are not included in the scope of works approved by the FSP. DL
estimated the total cost of the repairs set out in his scope of works at $138,477.10
(including the strip out of the damaged building materials).
Following review of DL’s scope of works, the FSP agreed to increase the cash
settlement amount for the building repairs to $103,150.64.
Case No: 425621 Determination Page 5 of 11
This increased cash settlement offer for the building repairs was based on the
amount quoted by DL for the repair of the damage for which the FSP had accepted
liability (including damage to the rear entry which had been omitted from the FSP’s
scope of works).
However, the FSP says it is not liable for the remainder of the damage to the building
outlined in DL’s report, on the basis that this damage pre -existed the storm in April
2015 and/or has been separately addressed under the applicant’s contents claim .
Approved scope of works for building repairs is generally appropriate
As outlined above, the cash settlement amount for the building repairs was based on
quotations provided by the FSP’s builder (DW) based on a scope of works prepared
by the FSP’s assessor (BH).
Having reviewed the available information, the panel is satisfied that BH’s sco pe of
works generally provides an accurate assessment of the damage to the property
caused by the storm in April 2015 and a breakdown of the works required to repair
that damage.
The repairs included in the scope of works are generally consistent with the claim-
related damage to the property, as identified in the reports provided and photographs
taken during BH’s initial inspection of the property in May 2015 (and his subsequent
reinspection in August 2015).
There is no independent information to support the applicant’s position that the FSP
should cash settle her for the full sum of insured of $318,000 on the basis that the
house needs to be demolished and rebuilt. The applicant’s own building consultant
(DL) has confirmed that the claim-related damage can be effectively repaired.
Having carefully reviewed the alternative scope of works prepared by the applicant’s
builder (DL), the panel considers that it includes a number of items for which the FSP
is not liable.
In particular, the panel notes that DL appears to have attributed all of the cracking
and movement damage at the property (including uneven flooring) to the effects of
water inundating the property during the storm in April 2015.
DL’s conclusions were in part based on the assumption that the flo ors were level
prior to the storm, given the brick piers under the property had been replaced several
years earlier.
However, the applicant has acknowledged that the floors were not level and there
was pre-existing cracking damage to the walls at the time of the storm (although she
says the unevenness and the cracking has worsened significantly since that time).
The pho tographs taken by the FSP’s assessor in May 2015 (shortly after the storm)
indicate that the cracking was pre-existing, given the debris contained within the
cracks. It is quite possible that (as suggested by BH), the unevenness of the floors
reflects the fact that they were not properly re-levelled when the new piers were
installed.
Case No: 425621 Determination Page 6 of 11
Accordingly, the panel considers that the FSP is not liable for all of the additional
cracking and movement damage included in DL’s scope of works, as not all of this
damage was caused by the storm in April 2015.
DL’s scope of works and quotation also provide for the replacement of damaged
items such as carpets and electrical appliances which do not form part of the insured
building for the purposes of the policy. The FSP has ad vised that these items were
included in the amount of $28,950 paid to the applicant in settlement of her contents
claim.
For the reasons outlined above, the panel is satisfied that the FSP’s approved scope
of works is generally appropriate to address the d amage to the applicant’s property
caused by the storm in April 2015.
The panel is also satisfied that the quotations for the cost of the necessary repairs
are generally consistent. In this regard, the panel notes that:
after adjustment for items of damage in respect of which liability is disputed, the
total repair cost as estimated by the applicant’s building consultant (DL) is not
dissimilar to the quotations provided by the two builders engaged by the FSP;
and
in making its revised settlement offer, the FSP has effectively agreed to base
the settlement amount on DL’s pricing, after excluding the disputed items.
Cash settlement should be increased by 10% to allow for extra repair costs
For the reasons outlined above, the panel considers that the FSP has generally
acted reasonably in determining the cash settlement amount for the building repairs.
However, the panel considers that the cash settlement amount should be increased,
in order to allow for any additional damage to the applicant’s property which w as not
apparent at the time of the FSP’s most recent inspection and/or to provide for
reasonable variations during the repair process.
When he inspected the property following the storm, the FSP’s engineer (DW)
confirmed that the brick piers were susceptible to differential movement (particularly
in the context of severe storm events). DW observed scouring of the soil under the
sub-floor caused by the flow of water during the storm and noted that minor
differential movement had most likely occurred.
Further, DW recommended that internal repairs to the property be delayed for a
period of up to nine months in order to allow sufficient time for the foundation soils to
dry out and any ongoing differential movement to cease.
While there was pre-existing movement damage to the property prior to the storm, in
light of DW’s advice, it is likely that additional movement occurred over subsequent
months, as advised by the applicant.
After the applicant raised concerns about additional damage, the FSP was provided
with an opportunity to reinspect the property in mid-2016 but declined to do so. A
further inspection by the FSP at this time might have assisted in determining the
existence and extent of any further damage.
Case No: 425621 Determination Page 7 of 11
In addition, the panel considers that an increase in the settlement amount is
appropriate in the circumstances, given that:
the quotations provided do not appear to include any provisional allowance (or
“buffer”) to take into account any variations to the scope which may be required
as a result of further damage which may become apparent during the course of
the repairs; and
the applicant has advised on a number of occasions that further water entry to
the property has occurred during the course of the claim. The panel accepts
that this additional damage was most likely due to the pre-existing deteriorated
condition of the roof, for which the FSP is not liable. However, the panel also
notes that the applicant relied on the advice of the FSP’s assessor in May 2015
not to progress the roof repairs until the current claim had been settled.
Having regard to the matters outlined above, the panel considers it fair in all the
circumstances that the FSP’s cash settlement offer of $103,150.64 be increased by
10% (ie $10,315.06).
2.3 Is the applicant entitled to additional accommodation costs?
Policy provides for payment of certain accommodation costs
The applicant’s policy provides for payment of reasonable temporary accommodation
costs where she is unable to live in her home due to damage resulting from an
insured event.
The policy also provides for the payment of related costs, including:
utility connection costs at the applicant’s temporary residence;
relocation of the applicant’s contents to and from her temporary residence; and
temporary accommodation for her pets in a commercial boarding establishment.
Under the policy, temporary accommodation costs are payable for the time it takes to
repair the applicant’s property to a liveable condition. However, the total benefits
payable are capped at 20% of the building sum insured and a maximum of 52 weeks.
The policy provides a separate benefit for the costs of storing undamaged contents
which cannot be kept at the insured property, until such time as they are above to be
returned. The maximum amount payable under this benefit is 5% of the contents sum
insured.
Applicant seeks payment of additional temporary accommodation costs
Based on the information provided, it appears that the FSP paid the applicant
temporary accommodation benefits for a period of approximately seven months
between May 2015 and December 2015.
When the applicant was initially advised to vacate the property for health reasons,
the FSP offered to arrange temporary accommodation. However, the applicant did
not want to leave the property, due to concern about the welfare of her elderly pets.
The FSP initially funded the cost of a rented caravan ($800 per month) so the
applicant could remain at the property. However, due to issues erecting temporary
Case No: 425621 Determination Page 8 of 11
fencing for her pets, the applicant moved into the garage instead, after it was
modified by her representative (SK).
The FSP subsequently paid the applicant temporary accommodation benefits of
$1,400 per month ($350 per week), based on the estimated rental cost of an
equivalent property (even though the applicant continued to live in her garage during
this period).
The FSP’s cash settlement offer includes an amount of $ 7,000, being 20 weeks of
additional temporary accommodation costs at the rate of $350 per week. The period
of 20 weeks was determined based on an estimated repair period of 16 weeks, plus
an additional 4 weeks to enable the applicant to locate an appropriate rental property.
The applicant seeks payment of additional temporary accommodation benefits. She
says she has incurred significant additional costs in order to make her garage
habitable (including electricity connection and ongoing usage charges). The applicant
says she has also incurred storage costs for her undamaged contents items.
FSP is required to increase settlement for accommodation costs
As outlined above, the FSP’s engineer (DW) advised that the repairs to the
applicant’s property should be delayed by up to nine months, in order to allow
sufficient time for the soil to dry out.
The available information suggests that the property would not have been inhabitable
during that period, due to the nature and extent of the damage resulting from the
inundation and sewerage backflow during the storm.
On this basis, and taking into account the estimated time to comple te the repairs, the
applicant’s property would have been uninhabitable for the maximum period of 12
months for which benefits are payable under the policy (regardless of any delays
experienced during the claim process).
Accordingly, under the terms of the policy, the applicant would have been entitled to
payment of reasonable temporary accommodation costs for herself and her six pets
(four dogs and two cats) during this period, as well as the costs of storing her
undamaged contents items.
The panel acknowledges that the actual costs incurred by the applicant are
significantly less than the amount to which she would have been entitled, as she has
chosen to live in her garage at the property rather than move into alternative
accommodation.
However, the panel also recognises that the applicant has suffered significant
inconvenience as a result. Among other things, she has continued to use the dirty
and damaged shower and bathroom in the main residence, which remains subject to
ongoing sewerage discharge issues.
By continuing to live at the property during this period, the applicant has effectively
mitigated the need for the FSP to incur temporary accommodation costs to the full
extent for which it would otherwise have been liable.
Case No: 425621 Determination Page 9 of 11
In light of this, the panel considers it is fair in all the circumstances that the FSP be
required to pay the applicant the amount of $18,800 (being 52 weeks of temporary
accommodation benefits at the rate of $350 per week), less the total amount of
temporary accommodation costs paid under the claim to date.
Given the amount to be paid for temporary accommodation, the panel does not
consider that any additional award in respect of storage costs is justified (noting that
the quotation provided by the applicant’s builder (DL) includes an allowance for the
removal and storage of contents items).
FSP is required to pay interest on settlement amount
It is unclear whether the FSP has paid the applicant the undisputed portion of the
cash settlement amount for building repairs and temporary accommodation and, if
so, when this was paid.
While it appears the applicant initially rejected the FSP’s settlement offer, it is also
unclear whether the FSP advised her that she could accept the undisputed amount
without prejudicing the ultimate outcome of her dispute.
In these circumstances, the panel considers the FSP should be required to pay
interest on the whole of the outstanding settlement amount at the rate calculated in
accordance with section 57 of the Insurance Contracts Act 1984 (Cth), from 2 March
2016 until the payment date.
2.4 Is the applicant entitled to compensation?
Applicant is entitled to reimbursement of professional costs
Under paragraph 9.4 of the FOS Terms of Reference, FOS may require a financial
services provider to contribute to legal costs incurred by an applicant in the course of
their dispute.
The applicant is entitled to reimbursement of fees paid to her building consultant (DL)
for his report dated 19 September 2016, subject to providing an invoice evidencing
the costs incurred.
The report prepared by DL was of assistance to the panel in establishing the extent
of any additional damage to the property which had occurred following the most
recent inspection by the FSP’s assessor. The FSP had previously declined the
opportunity to arrange for an independent expert to provide an updated assessment
of the damage to the property.
Applicant is not otherwise entitled to compensation
Under paragraph 9.3(b) of the Terms of Reference, FOS may award compensation
for non-financial loss (capped at $3,000) where an applicant has suffered an unusual
degree or extent of physical inconvenience, time taken to resolve the situation or
interference with their expectation of enjoyment or peace of mind.
The panel acknowledges that it has a taken a significant period of time to resolve the
applicant’s claim. Further, the claim process has been difficult for the applicant, in
Case No: 425621 Determination Page 10 of 11
part because the usual stress and inconvenience associated with an insurance claim
has been exacerbated by her personal circumstances and the FSP’s decision to cash
settle rather than undertake repairs.
However, having carefully reviewed the claim history, the panel is satisfied that the
FSP managed the claim reasonably overall.
The claim process was complicated by factors including the pre-existing damage to
the property (and the partially completed repairs) and the applicant’s desire to remain
at the property during the repair period, as well as the involvement of her previous
representative (who the applicant now believes has withheld funds paid for her
benefit).
To the extent that the issues experienced during the claim process were attributable
to the conduct of the FSP and its contractors, the panel is satisfied that the applicant
has been adequately compensated by the payment of additional temporary
accommodation costs as outlined above.
Accordingly, the circumstances are not such as to justify the award of compensation.
Case No: 425621 Determination Page 11 of 11
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS recommendation. Due to the nature
of the dispute, it has been referred directly to a panel for determination, in line with
the Operational Guidelines to the FOS Terms of Reference. The panel consists of an
Ombudsman and two representatives with consumer and insurance experience.
The panel has decided this case based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous Financial Ombudsman Service (FOS) decisions (which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
The panel has reviewed and considered all of the material provided by the parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, the panel has restricted its commentary to those issues that it
considers directly relevant to the outcome only.
During the course of this dispute, the applicant has been represented by a consumer
advocate. For the purposes of this determination, submissions made by the
applicant’s advocate have been treated as if they had been made by the applicant
herself.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.