Determination 425594
Poor management of water damage claim and undue delay in repairs
Summary
The applicant's strata water damage claim had been running for over 15 months with repairs still incomplete and poor service from the insurer's appointed consultants. AFCA found the claim management unreasonable and ordered $1,000 non-financial compensation.
Under section 9.3(b)(i) of the Terms of Reference, an unusual degree of physical inconvenience, undue delay and interference with peace of mind justify non-financial compensation even without a breach of utmost good faith.
Issues
- Poor claim handling primary · upheld
“the FSP's overall management of the claim has resulted in an unusual degree or extent of physical inconvenience”
- Third-party or outsourcing failure secondary · upheld
“the conduct of the FSP's appointed consultants are reasonable i.e. a lack of contact, failure to meet timelines”
Subjects and remedies
home or building damagepay non financial loss
Text of the determination
Determination
Case No: 425594 Determination Page 1 of 3
Case number: 425594 1 July 2016
1 Overview
1.1 Dispute
The Applicant is a member of an Owner’s Corporation (the insured) which held a
Residential Strata Insurance Policy (the policy) underwritten by the Financial
Services Provider (FSP). The policy was arranged via the FSP authorised
representatives and distributors. For the sake of brevity the underwriter and its
representatives will be referred to as the FSP for the purpose of this determination.
A claim was lodged upon the policy on 18 March 2015 where the Applicant was
seeking cover for water damage to her home (building) which occurred on or about
10 January 2015. The FSP accepted the claim and authorised repairs to its
appointed consultants under the claim.
The Applicant remains dissatisfied with the level of service provided by the FSP and
its overall management of the claim. The Applicant is seeking compensation for non-
financial loss from the FSP under the claim as well as finalisation of the authorised
repairs.
1.2 Issues and key findings
Is the Applicant entitled to non-financial compensation under the claim?
The available evidence does not reasonably establish a failure by the FSP to act with
the utmost good faith in managing the Applicant’s claim. However, I am satisfied the
FSP’s management of the claim through its appointed representatives has been less
than ideal.
I am satisfied the FSP’s overall management of the claim has resulted in an unusual
degree or extent of physical i nconvenience, time taken to resolve the situation and
interference with the Applicants of peace of mind. Accordingly, in line with Section
9.3 of the Service’s Terms of Reference, the FSP is arrange payment of $1,000 to
the Applicant by way of non-financial compensation.
1.3 Determination
This determination is in favour of the Applicant.
In line with section 9.3 b) (i) of the Service’s Terms of Reference (ToR), the FSP is to
arrange payment of $1,000 to the Applicant by way of non-financial compensation.
Case No: 425594 Determination Page 2 of 3
2 Reasons for determination
2.1 Is the Applicant entitled to non-financial compensation?
The FSP is to pay the Applicant $1,000 by way of non-financial compensation
I have considered all of the information made available by the parties. I note the
claim subject of this determination was lodged on 18 March 2015 for water damage
to the insured property. I am satisfied that although there was a fair amount of water
damage at the insured property however it was not a significant amount. It is
concerning to see the repairs as at 28 June 2016 still remained incomplete and
outstanding.
The Applicant in bringing this dispute to FOS has expressed great dissatisfaction with
the level or service received under the claim. It is clear the claim has been ongoing
for over 15 months, which considering the degree water damage and associated
scope of repairs, I accept is quite unreasonable.
I accept the concerns raised by the Applicant regarding the conduct of the FSP’s
appointed consultants are reasonable i.e. a lack of contact, failure to meet timelines
agreed upon and general failure to provide an acceptable level of service to her. It is
not in dispute arising from the water damage a nd subsequent delay in addressing the
water damage has resulted in mould infestation the rectification was also then
included under the claim.
The FSP acknowledges that the level of service provided to the Applicant in terms of
the repairs and time frames was not ideal. However, the FSP maintains it has at all
times kept up efforts to address the Applicant’s concerns and has at all time acted
with the utmost good faith in managing the claim.
The FSP also states some of the delays were due to the Applicant not allowing its
appointed representatives access to the insured building. I accept this to be accurate
however the evidence suggests such refusal on the part of the Applicant commenced
some four to five months into the claim and due to a breakdown in trus t.
I accept this may have resulted in some contribution to the delays in managing the
claim. However, it was only a minor contributing factor and further the reason for her
reluctance and lack of trust in the FSP’s claim management was not without
reasonable cause.
The TOR allow for an award of compensation for non-financial loss up to a maximum
award of $3,000. Such an award is subject to consideration as to whether there has
occurred an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the Applicant’s expectation of enjoyment or
peace of mind.
Having considered all of the information I am not satisfied it has been established
that the FSP’s conduct and management of the Applicant’s claim can re asonably be
considered a breach of utmost good faith. I accept the FSP from its point of view did
make genuine efforts to acknowledge and resolve the Applicant’s concerns under the
claim. However, this does not absolve the FSP of its commitments under the policy
Case No: 425594 Determination Page 3 of 3
and from providing an acceptable level of service in line with acceptable industry
expectations as well.
It is clear that there has been a clear failure to live up to acceptable service levels
and which has quite clearly interfered with the Applicant’s peace of mind, resulted in
physical inconvenience and there has occurred an undue delay in finalising the
repairs authorised under the claim.
In line with section 9.3 b) (i) of the FOS ToR, I determine the FSP is to arrange
payment of $1,000 to the Applicant by way of non-financial compensation under the
claim.
3 Supporting information
TOR 9.3
9.3 Other compensation
...
b) Subject to paragraph 9.3c) and paragraph 9.7, FOS may decide that the
Financial Services Provider Compensate the Applicant for non-financial
loss but only where:
(i) An unusual degree or extent of physical inconvenience, time
taken to resolve the situation or interference with the Applicant’s
expectation of enjoyment or peace of mind has occurred; or
(ii) In t he case of a Dispute pertaining to an individual’s privacy rights
– injury has occurred to the Applicant’s feelings or humiliation has
been suffered by the Applicant.
The maximum amount of compensation for non-financial loss will be
$3,000 per claim made i n the Dispute. …