Text of the determination
Determination
Case No: 425484 Determination Page 1 of 9
Case number: 425484 15 February 2017
1 Overview
1.1 Dispute
The Applicants obtained a commercial loan for $2,850,000 (Loan) from the FSP to
construct 15 townhouses in three stages (project). The project is now complete and
the Loan repaid. This dispute is about whether:
the FSP acted irresponsibly when it approved the Loan
unreasonably delayed its advance of the Loan
misled the Applicants about the amount available under the Loan, and the Loan
conditions
mismanaged drawdowns on the Loan.
The Case Manager provided the parties with a Recommendation on the issues in
dispute. The Recommendation was partly in favour of the Applicants and a copy is
attached to this Determination. The Applicants rejected the Recommendation saying
FOS ought to have concluded the FSP acted irresponsibly given its calculation
errors; they should be refunded the Loan establishment fee ; and FOS made errors
with its assessment of GST paid on the project. The FSP accepted the
Recommendation.
1.2 Issues and key findings
Were the findings of the Recommendation correct?
The findings contained in the Recommendation were correct and are adopted in this
Determination, except for:
the amount of GST paid on the construction which is dealt with in section 2.4
below; and
the Recommendation identified a number of errors such that it is my view that
half of the establishment fee should be refunded.
Did the FSP act responsibly when it approved the Loan?
The Applicants’ post -Recommendation submissions have been considered but do
not change the outcome reached on this aspect of the Recommendation. T he FSP’s
decision to approve the Loan was reasonable in the circumstances including in
particular that there were sufficient funds from the sale of the stage one units to
repay the Loan and fund the project.
Case No: 425484 Determination Page 2 of 9
What is the Applicants’ loss a rising from being misled about the retentions?
The Applicants have not provided any new information which alters the conclusion
reached in the Recommendation that they could not have obtained better loan terms
if not misled about the retentions. The compensation awarded in the
Recommendation for the Applicants’ loss associated with paying the builder the
balance of the progress payments retained by the FSP was appropriate. (The
calculation of this compensation has been updated in this Determination).
What is the Applicants’ loss arising from the FSP’s GST error?
Regardless of the amount the Applicants paid in GST on the construction, they have
not shown they suffered a lo ss as a result of the FSP’s failure to manage their GST
funding requirements. This is because they borrowed the funds to meet their GST
requirements at a better rate than the FSP could have offered them under its
overdraft facility, had it accommodated this short-term funding requirement.
Does the Applicants’ claim that the FSP deleted an entry in its notes have a
bearing on the issues in dispute?
The Applicants have not established the FSP deleted an entry regarding
“maladministration in lending” from its internal notes. This issue has no bearing on
the conclusions as to responsible lending reached by FOS nor the outcome of the
dispute.
Can FOS consider a defamation claim by a director of one of the Applicants?
FOS cannot consider defamation claims as these are more appropriately heard by a
court which can take evidence under oath as to the effect of the defamatory
statement on the claimant’s reputation. Further, in the circumstances of this dispute,
the Applicant’s director did not receive a financial service from the FSP and is not a
party to this dispute. This also prevents FOS from considering his claim.
Can FOS consider the third party business’ claim?
FOS cannot consider a claim for loss from a third party to a dispute. L’s business is a
third party to the dispute and did not receive a financial service from the FSP.
What is an appropriate outcome to this dispute?
Having regard to the FSP’s overall poor management of the Loan, it is appropriate
that it:
apologise to the Applicants
refund 50% of the Loan establishment fee being $9,350.23 plus simple interest
calculated at $0.57 per day from 30 January 2017 up to the date of payment.
1.3 Determination
This Determination is partly in favour of the Applicants.
Case No: 425484 Determination Page 3 of 9
I agree with the Case M anager’s reasons for the Recommendation and the
recommended outcome.
Within 14 days of the Applicants’ acceptance of this Determination, the FSP is to pay
the Applicants the following compensation by crediting to an account they nominate:
for the Applicants’ accountancy costs incurred in dealing with the FSP’s errors
related to retentions, GST and management of the draw downs on the Loan,
$4,059 (including GST)
for additional interest incurred on funds borrowed to pay retention amounts to
the builder, $7,120.55 plus simple interest calculated at $0.57 per day from 30
January 2017 up to the date of payment
for the FSP’s poor management of the Loan, a 50% refund of the Loan
establishment fee being $9,350.23 plus simple interest calculated at $0.57 per
day from 30 January 2017 up to the date of payment.
Therefore the total compensation payable to the Applicants calculated up to 30
January 2017 was $20,529.78.
Case No: 425484 Determination Page 4 of 9
2 Reasons for Determination
2.1 Were the findings in the Recommendation correct?
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
Recommendation. I am satisfied that the documentation I have relied on has been
provided to both parties.
I am satisfied that the Case M anager’s Recommendation contains an accurate
summary of the dispute, the issues to be determined, any applicable paragraphs of
the Terms of Reference and any relevant law.
2.2 Did the FSP act responsibly when it approved the Loan?
The Applicants maintain the FSP acted irresponsibly
The Applicants rejected the findings in the Recommendation on the bases that:
FOS’s conclusion that the FSP acted responsibly when approving the Loan was
incorrect because the FSP did not “follow the law when it approved the Loan”.
FOS, the FSP and the Applicants’ accountant each reached different
conclusions about the amount of the shortfall in funds to complete the project at
the Loan approval stage. Each party should come up with the same figure if
they follow the “loan ratios”. Their accountant’s estimate of the shortfall at Loan
approval is $244,000.
The FSP wrongly criticised them for not kno wing the FSP’s “80/20 rule” when it
failed to apply this rule itself. The Applicants refer to their understanding that the
FSP would fund up to 80% of the value of the construction project with a 20%
contribution from them. The FSP broke this rule when it incorrectly assessed
the funds to complete the project.
The FSP did not admit or tell them about its error in the Loan calculations and
instead provided other reasons such as their having insufficient equity to settle
on the first five units. It attempted to “cover up” and lie about its error in
calculations and its irresponsible lending. In particular, the FSP changed the
terms of the Loan after approval in order to withhold funds from them and cover
its risk caused by its error in calculations.
The FSP should refund its Loan establishment fee of about $17,000 because it
failed to accurately calculate the Loan and acted irresponsibly.
The Applicants ’ response to the Recommendation does not change the
outcome
The Applicants’ re sponse does not alter the conclusion reached in the
Recommendation that the FSP ’s decision to approve the Loan was reasonable in the
circumstances. This is because:
They do not dispute they had sufficient funds to complete the project and repay
the Loan, which is what occurred.
Case No: 425484 Determination Page 5 of 9
They have not provided any calculations or other information to show how the
Case Manager’s calculation of the shortfall in funds to complete the project was
wrong.
They had committed to completing the project before seeking finance approval
from the FSP. They have not established, with supporting material, what
alternative loan they could have obtained on better terms, for stage one only or
for the entire project.
They say the FSP changed the Loan terms after approval to cover its risk
caused by the error in its calculations. This is not relevant to whether the
decision to lend was irresponsible when it was made.
The Recommendation addressed and correctly calculated compensation for the
Applicants’ loss arising from the FSP’s decision to require retentions contrary to
the Loan agreement. Further detail about this is set out in section 2.3 below.
The Recommendation appropriately determined that, despite the FSP’s errors,
the Applicants did not suffer any loss from its:
o decisions to withhold $200,000 from the amount paid to the vendor from the
first drawn down. The Applicants would always have incurred interest on this
existing debt.
o failure to manage their GST funding requirements. Further detail about this
issue is set out below in section 2.4.
2.3 What is the Applicants’ loss as a result of being misled about
retentions?
The compensation awarded in the Recommendation was appropriate
The Applicants say it was not possible for them to provide FOS with the requested
proof that they could have found an alternative loan without the requirement for
retentions in January 2015. They offered to provide the opinion of their broker to that
effect, but have not done so. In these circumstances, the Applicants have not
provided any new information which alters the conclusion reached in the
Recommendation.
I agree with the Case Manager’s conclusion that the Applicants have not provided
information to establish that they could have obtained finance from another lender on
better terms if they had not been misled about the FSP’s Loan terms.
In any event, the outcome in the Recommendation was to compensate the
Applicants for the additional interest expense they incurred to pay the builder the
retention amounts. If the FSP had not required retentions, the Applicants would have
incurred interest on the extra Loan drawings to pay the builder the full progress
payments.
The compensation awarded effectively puts them in position they would have been in
had they borrowed the funds for retentions at the FSP’s rates rather than at the
higher rates at which they obtained the funds. In the circumstances, this adequately
compensates the Applicants for their loss arising from the FSP’s decision to impose
retentions when this was not agreed under the Loan contract.
Case No: 425484 Determination Page 6 of 9
As set out in section 2.6 of the Recommendation, the amount of interest the FSP is to
compensate the Applicants as at 16 June 2016 was $6,990.59 plus simple interest
on that amount at an annual interest rate of 3% ($0.57 per day) until date of payment.
Calculated to 30 January 2017, the FSP is to compensate the Applicants in the
amount of $7,120.55 (228 days x $0.57 = $129.96 + $6,990.59).
2.4 What is the Applicants’ loss arising from the FSP’s GST error?
The Applicants have not established they suffered a loss
The Applicants rejected the findings in the Recommendation saying that the Case
Manager incorrectly concluded that GST paid on the construction was not as high as
$194,823. They say this is incorrect because the information they provided shows the
total GST paid on the project was $219,000, of which $194,000 was specifically for
construction.
Based on the two building contracts, the total cost of construction was $1,935,818
plus GST at 10%, being $193,581.80. The Case Manager was incorrect in
concluding that the GST paid on the construction was not as high as $194,823, as
the correct figure was close to that amount. However, the Applicants were entitled to
progressively claim a refund on GST paid on the construction from the Australian Tax
Office (ATO) and so this was a short term funding requirement.
Further, this does not change the finding reached in the Recommendation that the
Applicants did not suffer a loss on funds borrowed to pay GST. The Applicants claim
their loss was comprised of all interest paid on $194,823 which they borrowed to fund
GST. However this is not appropriate because the Applicants would always have had
this interest-bearing liability. Irrespective of whether the FSP had approved the Loan,
the Applicants required the funding for construction costs, including GST. They
obtained finance through a related entity at a better rate than the FSP could have
offered and therefore suffered no financial loss.
2.5 Does the Applicants’ claim the FSP deleted an entry in its notes
have a bearing on the dispute outcome?
The alleged deleted file note has no bearing on the outcome of this dispute
The Applicants say the FSP admitted in internal notes its maladministration in lending
associated with the advance of the Loan, and subsequently deleted this entry in its
notes. They refer to a note made by an FSP employee on 19 January 2016 saying
“ #added issue of maladministration in lending identified ”. This note made in the
course of management of the Applicants’ dispute does not comprise an admission of
maladministration in lending but simply identifies this as an issue in dispute.
The Applicants allege the FSP deleted the entry from the document and that this was
a breach of law. In accordance with our usual procedures, FOS had exchanged this
document (including the “maladministration in lending” entry) with the Applicants on
30 March 2016 as a Word document in the same format as provided by the FSP. On
14 April 2016, the Applicants provided by email to FOS two versions of the document
Case No: 425484 Determination Page 7 of 9
which they allege show the initial “maladministration in lending” entry in one (a PDF)
and not in the other (an internet explorer document). It is not clear how the
Applicants obtained another version of the document.
There is no information to indicate that the FSP deleted the “maladministratio n in
lending” entry in the notes, and in any event, it consented to its complaint notes being
exchanged with the Applicants in their entirety. FOS has dealt with the issue of
irresponsible lending (or maladministration in lending) in this Determination and
neither the FSP’s complaint notes in general nor the disputed “maladministration in
lending” entry has any bearing on the conclusions reached.
2.6 Can FOS consider a defamation claim by a director of one of the
Applicants?
FOS cannot consider a defamation claim
The Applicants say:
the FSP defamed the Applicant’s director (L) by saying that he had shifted
assets in his banking accounts in circumstances where this is incorrect
the Case Manager failed to mention this issue in the Recommendation.
FOS is unable to consider claims of defamation. We are not able to award
compensation for loss of reputation or a general claim that a financial services
provider has defamed an applicant. This is because we do not have the power to
take evidence under oath, and any compensation for defamation would depend on
evidence given on oath regarding the effect of the financial services provider’s action
on the Applicant’s reputation. For this reason, we consider that a court is a more
appropriate place to consider a claim for loss of reputation.
Further, L is not a party to this dispute which has been lodged by the Applicant
companies. We therefore cannot consider his personal claim against the FSP.
2.7 Can FOS consider the third party business’ claim?
FOS cannot consider a third part y’s’ claim
The Applicants say the FSP’s conduct in disbursing the progress payments
negatively impacted the other business of L, the director of one of the Applicant
companies, because he was reimbursed only some of the money the FSP promised.
The Case Manager determined that the Applicants did receive from the Loan funds a
reimbursement of payments made to the builder before the Loan was advanced. This
issue was addressed in section 2.4 of the Recommendation. The Applicants have not
made any new submissions which alter the conclusions reached.
In any event , FOS cannot consider a claim for loss from a third party to a dispute. L’s
business is a third party to the dispute and did not receive a financial service from the
FSP. Accordingly, FOS is unable to consider its claim for loss against the FSP.
Case No: 425484 Determination Page 8 of 9
2.8 What is an appropriate outcome to this dispute?
The FSP is required to apologise to the Applicants
It is appropriate that the FSP apologise to the Applicants for its overall poor
administration of the Loan facility and in particular the issues they experienced with
regard to retentions and GST funding. The wording to be used in the apology is set
out in section 3.1 below.
The FSP is required to refund 50% of the Loan establishment fee
It is appropriate that the FSP refund 50% of its Loan establishment and security
processing fee of $17,750 paid on 20 April 2015. In reaching this conclusion, regard
was had to the following:
the FSP’s poor administration of the Loan , in particular in relation to those
matters identified in section 2.8 of the Recommendation, and the difficulties the
Applicants experienced with managing the Loan and project as a result of this.
the FSP is entitled to a 50% portion of this fee given that the Applicants
received and benefited from the Loan.
The FSP is required to refund $8,875 to the Applicants plus simple interest on that
amount at an annual interest rate of 3% ($0.73 per day) from 20 April 2015 until date
of payment. Calculated to 30 January 2017, the FSP is to compensate the
Applicants in the amount of $9,350.23 (651 days x $0.73 = $475.23 + $8,875).
Case No: 425484 Determination Page 9 of 9
3 Supporting information
3.1 FSP apology to the Applicants
We acknowledge your complaint regarding our approval, and management, of your
Loan account ending in 3440.
We understand that, as a result of our poor service and management of the Loan,
you experienced considerable difficulties and confusion in managing the funding for
your construction project. We appreciate this caused you significant inconvenience,
with additional time spent seeking explanations about management and conditions of
the Loan. You were required to make alternative arrangements with third parties such
as your vendor, your builder for retentions, and for GST funding because of our
errors. We regret the frustration you felt in your dealings with us and that your
banking experience was well below satisfactory.
Please accept our apology for the very poor experience you had as a result of our
inadequate management of the Loan.
3.2 A new claim has now been resolved.
On 31 January 2017, the Applicants’ directors lodged a new dispute number 468791
with FOS related to the events the subject of this dispute. This dispute was resolved
by agreement on 9 February 2017 and need not be considered by FOS any further.
Recommendation
Case No: 425484 Recommendation Page 1 of 21
Case number: 425484 30 November 2016
4 Overview
4.1 Dispute
The Applicants obtained a commercial loan for $2,850,000 (Loan) from the FSP to
construct 15 townhouses in three stages (project). The project is now complete and
the Loan repaid. This dispute is about whether:
the FSP acted irresponsibly when it approved the Loan
unreasonably delayed its advance of the Loan
misled the Applicants about the amount available under the Loan, and the Loan
conditions
mismanaged drawdowns on the Loan.
4.2 Issues and key findings
Did the FSP act responsibly when it approved the Loan?
The FSP incorrectly calculated the funds available to complete the project by about
$163,000. However, the Applicants had capacity to complete the project and repay
the Loan from the proceeds of sale of the townhouses. The FSP’s decision to
approve the Loan was not irresponsible in the circumstances.
Did the FSP unreasonably delay its approval and advance of the Loan funds?
The FSP did not unreasonably delay its approval of the Loan. The Applicants were
not entitled to the Loan funds until they had received the unconditional offer of
finance. The FSP did not unreasonably delay its advance of the Loan because it was
just seven days between acceptance of the Loan offer and the first draw down. Even
if there was a delay in the Loan approval, the Applicants did not rely on this to their
detriment because they were already committed to completing the project before they
sought finance from the FSP.
Did the FSP mislead the Applicants that it would fund the entire project?
The FSP did not tell the Applicants it would fund the entire project. The FSP agreed
to lend the Applicants $2,850,000. They were aware that the FSP was not funding
the entire project because the FSP told them this in February 2015, and their
development budget of $3,271,000 exceeded the Loan.
Did the FSP mislead the Applicants about reimbursement of their payments to
the builder?
The FSP did not mislead the Applicants because it reimbursed them for their
contributions to construction costs paid before the Loan was advanced.
Case No: 425484 Recommendation Page 2 of 21
Did the FSP mislead the Applicants it would refinance the $600,000 loan at the
initial drawdown of the Loan?
The FSP mislead the Applicants it would refinance the $600,000 vendor loan from
the first drawdown. It refinanced $400,000 of the vendor loan from the initial
drawdown in April 2015 and the remaining $200,000 in August 2015. The Applicants
did not rely on this misrepresentation to their detriment. Even if not misled, they
would still have paid interest on the remaining vendor debt of $200,000 at the
applicable annual i nterest rate of 10%.
Did the FSP make an error when it withheld retentions from the builder?
The FSP was not entitled under the Loan contract to withhold retentions. As a matter
of fairness, the FSP should compensate the Applicants for their additional interest
expense incurred on the funds borrowed to pay the builder the gap between the full
progress claim amounts and the retention funds withheld by the FSP. This comprises
the difference between the interest paid on funds borrowed to pay the builder
ret entions and the interest they would have paid to the FSP had it paid the builder’s
progress claims without retention. FOS calculated the compensation payable as
$7,085.78 plus simple interest calculated at $0.57 per day from 30 November 2016
up to the date of payment.
Did the FSP mislead the Applicants about funding for GST?
The FSP failed to adequately manage the Applicants’ GST funding requirements. If it
had done so, it would likely have offered them an overdraft facility to fund GST (in
accordance with good industry practice). The FSP’s annual interest rate on small
business overdrafts was 16%. The Applicants paid less interest on funds they
borrowed to fund the GST (10.57%) and have therefore not suffered a loss.
Did the FSP mismanage drawdowns on the Loan?
The Applicants raised various claims about alleged errors and mismanagement of
drawdowns on the Loan. These claims relate to the Applicants’ e mployees’, directors’
and purchaser s’ stress and inconvenience in dealing with such errors. As those
parties did not receive a financial service from the FSP, FOS cannot under its Terms
of Reference award compensation to them. FOS cannot award compensation for
non-financial loss to the Applicant companies.
The FSP is to compensate the Applicants for their reaso nable accountancy costs
incurred in in dealing with errors related to retentions, GST and management of the
draw downs on the Loan of $4,059.
Is the FSP liable for interest the Applicants incurred on additional borrowed
funds?
The Applicants say they borrowed significant additional money for the project and the
FSP ought to reimburse their related interest expenses. This claim is not made out
because:
the available information shows the FSP appropriately paid the claimed civil
works costs, authority fees and consultant fees in accordance with the QS
reports
Case No: 425484 Recommendation Page 3 of 21
the Applicants spent more than the budgeted amount on the project
the Applicants were responsible for costs which were not included in the Loan
amount (such as overruns, marketing and other project costs). The FSP is not
liable for interest incurred on those funds.
4.3 Recommendation
This Recommendation is partly in favour of the Applicants.
Within 14 days of all parties’ acceptance of this Recommendation, the FSP is to pay
the Applicants the following compensation into an account nominated by them:
for the Applicants’ accountancy costs incurred in dealing with errors related to
retentions, GST and management of the draw downs on the Loan, $4,059
(including GST)
for additional interest incurred on funds borrowed to pay retention amounts to
the builder , $ 7,085.78 plus simple interest calculated at $0.57 per day from 30
November 2016 up to the date of payment.
Therefore the total compensation payable to the Applicants calculated up to 30
November 2016 was $11,144.78.
Case No: 425484 Recommendation Page 4 of 21
5 Reasons for Recommendation
5.1 Did the FSP act responsibly when it approved the Loan?
The law and Code of Banking Practice (CBP) set the lending standard
At law and under the CBP, a financial services provider has obligations to exercise
the care and skill of a diligent and prudent lender in assessing whether a customer
has the ability to repay a loan. Generally, as part of a loan assessment process, a
financial services provider should:
request documentation to support the loan application
make further enquiries where there are obvious inconsistencies in the
information
ensure there is sufficient information and supporting documentation provided
that shows capacity to service the loan.
The Applicants say the FSP failed to appropriately assess the Loan
The Applicants say the FSP acted irresponsibly because after it had approved the
Loan and the parties had signed the Loan contract, it told them they had insufficient
equity to complete the project.
The FSP’s internal email correspondence dated 16 Ap ril 2015 shows that:
it was aware, before the Loan was approved, of a deficit of about $142,000
between the expected drawdowns under the Loan and the costs to complete
stage one of project
after Loan approval, it became apparent that the deficit was about $265,000.
The FSP incorrectly calculated the funds available to complete the project
Based on FOS’s assessment of the available material, the FSP erroneously
overstated the funds available to complete the project by $324,000.
The FSP’s “Funds Position” determined that the Applicant required $3,375,233 to
complete the project and the funds available to the Applicant were $3,535,835. The
FSP calculated surplus available cash or savings at $160,602 (that is, $3,535,835
less $3,375 ,233). Details of the FSP’s Funds Position are set out in section 3.1
below.
The FSP’s assessment of the Funds Position was erroneous in that it:
included 100% of the building contract price ($1,936,000) when the Applicants
had already paid $141,716 to the builder. Therefore the funds required were
overstated.
included $465,756 in funds available to complete that had already been
expended by the Applicants. Therefore the source of funds available were
overstated.
Case No: 425484 Recommendation Page 5 of 21
The development project funds already expended by the Applicants was for civil
works, consultant fees and authority fees and charges totalling $342,040, as noted in
the Quantity Surveyor’s (QS) pre -funding report. 1
The available material leads FOS to the conclusion that the FSP’s approval of the
Loan for $2,850,000 resulted in a potential funding shortfall of $163,398 as follows:
Description Calculation
Funds required to complete $3, 233,517 ($3,375,233 - $141,716 ) 2
Source of funds available $3,070,000 ($3,535,835 - $465,756) 3
Short fall in funding $(163,398)
The difference of $324,000 between the FSP’s surplus of $160,602 and the actual
shortfall of ($163,398) was due to the FSP’s erroneous inclusion of $324,000 in funds
available to complete the project when those funds had already been expended by
the Applicants.
The FSP’s decision to approve the Loan was not irresponsible
On the basis of the FOS assessment, there was a $163,000 deficit in current
available funds to complete the project when the FSP assessed the Loan in April
2015. Neverth eless, the FSP’s decision to approve the Loan was reasonable having
regard to the following factors:
within three months of the Loan appro val, the Applicants expected to receive
net sale proceeds of at least $1,030,000 from the sale of the first five units (as
noted in the FSP’s decision notes dated 17 March 2015). These were additional
funds available for debt reduction or future project costs not included in the
FSP’s Funds Position calculation
the FSP’s budget included a contingency of $193,000
the FSP was aware of a possible shortfall in total funding for the project but this
would only arise in a worst case scenario, for example, if there were major cost
overruns or the pre-sale of units did not settle for stage one of the construction
the FSP considered its position and potential exposure and was willing to
proceed with approval signed off at the appropriate higher delegated approval
level
the Applicants were aware that the FSP was not funding the entire project cost
given that their Development Budget was at least $3,271,000 and the Loan was
for $2,850,000
the Applicants had capacity to repay the Loan because the value of pre-sold
units before the Loan approval exceeded 120% of the debt. 12 out of 15 units
had been sold for a combined value of $3,840,000 and the Loan amount was
$2,850,000.
1 The FSP apparently transposed the numbers as $3 24 ,000 instead of $3 42 ,000 as quoted in the QS
report.
2 Funds already paid to builder
3 Project development funds already expended by Applicant
Case No: 425484 Recommendation Page 6 of 21
Overall, and despite the apparent funding deficit, the Applicants had capacity to
complete the project and repay the Loan and therefore the FSP’s decision to approve
it was not irresponsible.
5.2 Did the FSP unreasonably delay its approval and advance of the
Loan funds?
The FSP did not unreasonably delay the Loan approval or advance of funds
The Applicants say the FSP delayed approval and advance of the Loan. They
expected the FSP to grant approval by about 18 March 2015 but the first draw down
was not made until 21 April 2015. A timeline of the Loan application process is set
out in section 3.2 below.
The FSP appropriately progressed its consideration of the Loan application from the
point it received all application information from the Applicants on 24 February 2015.
Whilst it took the FSP about one week from receipt of the QS report to approve the
Loan and a further two weeks to issue the Loan offer, this is not unreasonable given
the circumstances. This was a construction loan involving two companies which were
entering into the Loan as trustees for two separate trusts. Therefore, it is reasonable
for the FSP to take some time to check and prepare its security documentation.
The FSP was not obliged to advance any funds to the Applicants until:
it made its offer,
the offer was accepted, and
the Applicants had complied with all pre conditions to funding stated in the offer.
The FSP made the Loan offer on 2 April 2015. Both Applicants had not signed the
Loan offer until 14 April 2015. The FSP made the first payment on 21 April 2015.
Therefore, the time between acceptance of the Loan offer and the first draw down
was seven days. In the circumstances, this was not an unreasonable delay.
The Appli cants’ claim for loss is not established
Even if the FSP did delay its Loan approval and advance, the Applicants’ have not
established their claim for loss.
The Applicants say that as a result of the alleged delay, they borrowed funds from
alternative sources at higher interest rates in order to start construction before the
first draw down under the Loan. This claim for loss is not established because:
the FSP did not unreasonably delay advance of the Loan funds after completion
of the preconditions to funding
the Applicants commenced the project well before making the Loan application
and therefore were already committed to meeting its cost. They contracted to
purchase the land and pre-sold units before approaching the FSP for finance in
late January 2015. They say their purchasers wanted them to commence
construction as soon as possible. Their decision to start construction with their
own funds was not based on the FSP’s promise to approve the Loan and permit
drawdowns, but rather on their commitment to their purchasers to complete the
project
even if, as alleged, the FSP promised the Loan would be advanced within a
certain timeframe, the Applicants did not change their position in reliance on
Case No: 425484 Recommendation Page 7 of 21
that. They were already contractually committed to their purchasers to complete
the project whether the FSP approved the Loan or not.
5.3 Did the FSP mislead the Applicants that it would fund the entire
project?
The Applicants say the FSP let them believe it would fund the entire project
The Applicants say:
they initially wanted funding for stage one of the construction only (5 units)
their broker suggested they consider applying for funding for the whole
development (15 units)
“D”, a Director of one Applicant company, told “A”, an employee of the FSP, in
their first meeting that they:
o only wanted funding for all 15 units if the FSP could 100% fund the
project
o he would use his own funds to start construction as long as he would
be fully reimbursed by the FSP from the Loan funds
o A told D that he would be fully reimbursed his contributions from the
first Loan draw if he kept records of payments to the builder
subsequent to that meeting, the Applicants provided A with their development
budget. They requested to borrow $3,271,014 to complete the project
in an emai l on 9 February 2015, A told the Applicants’ broker that the FSP could
lend them a maximum of between $2,775,000 to $2,800,000, including a 5%
contingency and interest capitalisation
A asked D if the Applicants could cover the short fall between their requested
$3,271,014 and the $2,850,000 the FSP was prepared to lend. D said the
Applicants could cover the short fall because:
o the FSP was going to fully reimburse all the funds he proposed to contribute
to the construction before the Loan approval
o the first five unit sales would settle and reduce the debt or be available for
stages two and three of the construction
after they signed the Loan offer, the FSP told them:
o they had insufficient equity in the project to complete it
o it proposed to withhold $200,000 from the $600,000 allocated to payout the
first mortgagee over the property
o it had withheld about $170,000 from the money that D paid upfront for the
construction instead of reimbursing it as A had promised
o it would not fund the deposit or the GST component of the construction.
t he FSP’s conduct caused them huge cash flow problems because they were
forced to contribute further funds to the project.
The FSP did not tell the Applicants that it would fully fund the project
The FSP did not mislead the Applicants that it would fully fund the project. This is
because:
Case No: 425484 Recommendation Page 8 of 21
based on the Applicants’ own submissions and recollections, they were aware
there was a shortfall between their funding requirements ($3,271,014) and the
amount the FSP was prepared to lend ($2,850,00 0). The FSP’s employee, A,
communicated this to the Applicants on 9 February 2015
even if the Applicants expected to be reimbursed their pre -Loan approval
contributions to construction costs, that amount was about $305,000. They
would still have been required to pay the remainder of the shortfall between the
total funding requirements of $3,271,014 and the FSP Loan of $2,850,000.
5.4 Did the FSP mislead the Applicants about reimbursement of their
payments to the builder?
The FSP reimbursed the Applicants’ payments to the builder
The FSP did not mislead the Applicants because it reimbursed them for their
payments to the builder before the Loan approval. This is shown in the following
table:
Date Amounts paid by
Applicants to
builder
Loan draw
down
Amount pai d to
builder/third
party
Amounts
remaining for
Applicants
6/02/2015 $35,542.50 (deposit)
3/3/3015 $100,000 (claim 1)
4/3/2015 $20,346.19 (claim 1)
2 –
14/04/ 2015
$150,000 (part payment
of claim 2)
Sub total $305,888.69
Loan contract signed 14 April 2015
21/04/ 2015 $555,247 $24,071.33 to
builder
$400,000 to V
$131,176
05/06/ 2015 $332,663.85 $106,188.63 to
builder
$226,475.22
Sub total $357,651
The above information is based on the builder’s Customer Ledger of payments
received, the FSP’s bill facility draw down letters, and statements for account number
ending #9815 into which the Loan funds were paid.
As set out in section 2.2 above, the FSP is not required to reimburse any interest
incurred on the construction funds paid before the Loan approval and drawdowns.
The Applicants’ decision to start construction with their own funds was not based on
a promise from the FSP to approve the Loan but rather, to meet their commitment to
the purchasers to complete the project on time.
Case No: 425484 Recommendation Page 9 of 21
5.5 Did the FSP mislead the Applicants that it would refinance $600,000
at the initial drawdown of the Loan?
The FSP misled the Applicants it would refinance $600,000 at the initial
drawdown
The FSP told the Applicants that it would refinance their existing $600,000 vendor
loan with “V” from the initial draw down of the Loan. Following the Applicants’
acceptance of the offer, the FSP ascertained that, for stage one of the project, the
costs to complete were higher than the available loan funds. This was contrary to the
FSP’s policy requirements. To deal with this, the parties made arrangements to:
vary the payment to V by paying it $400,000, only, from the initial draw down
and paying the remaining $200,000 at settlement of the sale of the first five
units
accept a position outside of the usual cost-to-complete requirements for stage
one only.
As a result, after paying it $400,000 from the first drawdown under the Loan, the
Applicants continued to pay interest to V on the remaining $200,000 debt at an
annual interest rate of 10%.
Applicants must show they could have avoided their loss if not misled
When FOS assesses a claim for loss arising from misleading conduct, we assess
what the customer could have done differently had they not been misled such that
they would now be in a better position. If the Applicants could not have done anything
differently to improve their position, they have not suffered a loss arising from the
misleading conduct.
The FSP is not required to compensate the Applicants for interest paid to V
The Applicants claim a loss of $6,665 for interest paid to V from May to August 2015
(comprising four monthly interest instalments of $1,666). It would not be appropriate
to compensate the Applicants all interest paid on the $200,000 as they would have
paid interest on that existing debt even had the FSP refinanced the entire V debt as
planned.
The Applicants say that if they had not been misled about the conditions of the Loan,
they would have sought finance of only about $950,000 to develop and build stage
one of the project. They say they could then have repaid the $950,000 loan from the
proceeds of sale of stage one and re-drawn further funds for stages two and three.
This sc enario could not, however, have involved the FSP refinancing the Applicants’
$600,000 loan with V. There would have been insufficient funds from a $950,000
loan to pay for construction and also refinance the V loan. The building costs of stage
one of the project were $710,000 inclusive of GST. The Applicants say they also
required about $150,000 for “council contributions”.
The Applicants say, in the alternative, they could have repaid the V loan at the end of
the project rather than the start. However, as part of its security arrangements, the
FSP always required the V loan to be repaid with the first Loan draw down, and so
the FSP would not have consented to such a proposal.
Based on the above information, even if the FSP had not misled the Applicants, they
would likely have retained the V loan and paid interest on it at the contractual rate.
Case No: 425484 Recommendation Page 10 of 21
Accordingly, despite the FSP’s misrepresentation, the Applicants are not in a worse
position with regard to their interest expense on their existing debt to V. The FSP is
therefore not required to compensate the Applicants in relation to this aspect of their
claim.
5.6 Did the FSP make an error when it withheld retentions from the
builder?
The Loan contract did not provide for retentions to be withheld by the FSP
The FSP intended to include a retention clause as a condition of the Loan. It failed to
provide appropriately for this in the Loan contract. The following information supports
this conclusion:
the Loan contract says retention monies specified in the building contract will be
deducted from the progress payments unless the FSP has accepted a third
party performance bond instead of retentions
clause 11.8 of the building contract for stage one expressly excludes retentions.
Instead, the builder was required to hold a n insurance policy to cover the cost of
rectifications or defects
the FSP had not accepted the builder’s insurance policy or any third party
performance bond instead of retentions
nevertheless, the FSP had no contractual right to withhold retentions as none
were specified in the building contract
the FSP’s employee “A” admits i n an email dated 14 April 2015 that she failed
to explain the FSP’s retention policy to the Applicants before their acceptance of
the Loan offer
the FSP also failed to identify until after the Applicants accepted the Loan offer
that the building contract did not include a retention clause in the terms it
expected.
The Applicants’ claim they could have obtained a better loan is not established
The Applicants say that if they knew the FSP would require retentions, they would
have gone to a different financial services provider that did not require retentions.
However, despite FOS requests, they have not provided information to show that an
alternative lender was willing and able to provide the required finance on terms that
did not require retentions. They say that the existing first mortgagee (V) would have
lent them the funds but have not provided any material for FOS to verify that was the
case.
In the alternative, the Applicants say they could have just borrowed $950,000 from
the FSP for stage one, however, this would not have overcome the FSP’s
requirement for retentions.
Even if the Applicants had not been misled about the FSP’s requirement for
retentions, they have not shown they could have obtained an alternative loan in the
same amount which would not have required retentions.
The FSP is to compensate the Applicants for interest paid on retention funds
The FSP was not entitled under the Loan contract to withhold retentions. As a matter
of fairness, the FSP ought to compensate the Applicants for their additional interest
Case No: 425484 Recommendation Page 11 of 21
expense on funds borrowed to pay the builder the gap between each progress claim
and the retention amount withheld by the FSP. The additional interest comprises, the
difference between the interest the Applicants paid on funds they borrowed to pay
the builder retentions, and the interest they would have paid to the FSP on those
amounts. This conclusion was reached having regard to the following factors:
the FSP did not have a contractual right to withhold retention funds
the FSP’s decision to do so was unfair in the circumstances. Retention is
designed to protect the customer’s interests where rectifications for any defects
i n the building are required. The Applicants were satisfied with the builder’s
insurance policy for that purpose
the FSP had not adequately disclosed or explained its retention policy to the
Applicants before they signed the Loan offer
there was a risk to all parties that the builder would not continue construction
work if they did not receive full payment of each progress claim
the Applicants were under time and financial pressure to proceed with the Loan,
having commenced construction and completed a three month application
process with the FSP
the FSP obtained the Applicants’ and builder’s reluctant consent to the
retentions via email in April 2015. Details of this are set out in section 3.3 below.
However there is no information to show it formalised this as a signed variation
to the Loan contract. The builder and Applicants expressed concerns about the
retention arrangement repeatedly throughout the construction
in the circumstances, the Applicants had little option but to pay the builder the
retention money to keep the construction going
the Applicants say that as a result of the FSP’s conduct, they were
unexpectedly forced to borrow funds from alternative sources at a high interest
rate. Against this, the Applicants had a contractual obligation to pay the builder
the full progress claims (independent of their loan arrangements with the FSP).
The Applicants also would have incurred interest on the retention funds draw on
the Loan had they not been withheld by the FSP.
Based on the builder’s Customer Ledg er document provided by the Applicants for the
period 1 July 2014 to 16 February 2016, the Applicants made payments totalling
$115,099.56 to the builder for retentions. The following table shows the payments
made and the source of those payments.
Date Amou nts paid by
Applicants to builder
for retention from FSP
account ending in 9815
Source of funds paid
into account ending in
9815
Interest rate applicable
to borrowed funds
29/05/ 2015 $15,000 $15,000 from “L’s” account
ending in 0250
10.57% pursuant to an
intercompany loan
agreement bet ween L and
Applicant company S.
29/05/ 2015 $15,304.09 $15,304.09 from “O” unknown
1/09/2015 $12,000 from “O” unknown
15/10/ 2015 $15,000 from “L’s” account 10.57% pursuant to an
Case No: 425484 Recommendation Page 12 of 21
ending in 0250 intercompany loan
agreeme nt bet ween L and
Applicant company S.
15/10/ 2015 $20,000 from “S’s” LOC
account
4.59% pursuant to S’s Line
of Credit account held with
another financial services
provider.
19/10/ 2015 $47,815.17
17/11/ 2015 $40,000 from “L’s” account
ending in 0250
10.57% pursuant to an
intercompany loan
agreement bet ween L and
Applicant company S.
18/11/ 2015 $36,980.36
Total $115,099.56 $117,304.09
The Applicants claimed a refund of interest paid up to August 2016. FOS’s
calculation of loss is for the period between when the retention funds were paid to the
builder and the date the Applicants received funds from the sale of units, being 16
June 2016. This is because it is reasonable to expect the Applicants to mitigate their
loss by immediately applying the net sale proceeds from the sale of their units to
repay their project- related debts. Based on an email from the FSP’s “LC” to the
Applicants’ accountant on 31 August 2016:
the Loan was fully repaid from sale proceeds on 15 June 2016
the Applicants received further sale proceeds of:
o $290,482 on 3 June 2016
o $103,063.32 on 16 June 2016
o $281,950 on 27 June 2016
o $288,517 on 23 August 2016.
On that basis, the Applicant had sufficient available funds to repay their retention
related debts by 16 June 2016.
FOS has calculated the interest the Applicants paid on funds borrowed to pay for
retentions at $8,835.99. Had the FSP not withheld the retentions from the builder,
the Applicants would have incurred an interest cost of $1,845.40 payable to the FSP.
FOS’s interest calculations are set out in section 3.4 below.
Therefore the amount of interest the FSP is to compensate the Applicants as at 16
June 2016 is $6,990.59 ($8,835.99 less $1,845.40) plus simple interest on that
amount at an annual interest rate of 3% ($0.57 per day) until date of payment.
Calculated to 30 November 2016, the FSP is to compensate the Applicants in the
amount of $7,085.78 (167 days x $0.57 = $95.19 + $6,990.59).
The FSP is not required to reimburse the Applicants for insurance costs
Th e Applicants claim as part of their loss associated with the FSP’s required
retentions the cost of the builder’s insurance policy for defects. This was supposed
to be in place instead of retentions.
Case No: 425484 Recommendation Page 13 of 21
The FSP is not required to compensate the Applicants for the cost of that insurance
because:
they will be compensated for their interest expenses arising from the FSP’s
decision to impose retentions as set out above
they agreed to the building contract (which included the builder’s insurance for
defects) before they approached the FSP for finance. They would therefore
have incurred this cost irrespective of the FSP’s requirement for retentions.
5.7 Did the FSP mislead the Applicants about funding for GST?
The FSP did not adequately manage the Applicants’ GST fundin g requirements
The Loan contract does not specify who was to fund the GST payments to the
builder.
Generally, when dealing with construction finance of this kind, it is good industry
practice for a financial services provider to discuss with its customer the source of
funding for GST. Where the customer cannot fund GST from its own resources, a
financial services provider may offer to fund the GST separately with, for example, an
overdraft facility. This is because the funding requirement is short term pending a
rebate from the ATO.
In this case, the FSP’s Funds Position document shows that it accounted for GST.
However, no separate facility to fund GST was agreed between the parties.
Based on correspondence between the parties during the course of construction,
there was confusion about who was responsible for paying the GST. This shows the
FSP did not adequately discuss or understand the Applicants’ GST funding
requirements before approving the Loan. This was poor banking practice and a
contributing facto r to the Applicants’:
confusion about what costs could be met from Loan funds
cash flow difficulties during the project.
However, on the other hand, the Applicants were aware that they would have a GST
liability for the construction and were ultimately responsible for ensuring they had
sufficient funding in place to meet this cost like all other costs.
The Applicants have not suffered a financial loss on funds borrowed for GST
The Applicants say they paid the GST mainly by borrowing $194,823 from a related
entity (L) at an annual interest rate of 10.57%. However, the GST paid on the
construction was not as high as $194,823, so the alleged borrowed funds may have
been used for both GST and other purposes.
Had the FSP appropriately identified the Applicants’ GST funding requirements, it is
reasonable to conclude that in accordance with common industry practice, it would
likely have provided a separate overdraft facility for this purpose. The Applicants
would then have paid interest on that facility. The FSP says its small business
overdraft interest rate applicable in April 2015 was 16%. On that basis, the Applicants
would have paid a higher interest rate on a separate FSP facility for GST than what
they say they paid L, that is, 10.57%. As such, the Applicants have not established
they suffered a financial loss as a result of the FSP’s failure to adequately manage
their GST funding requirements.
Case No: 425484 Recommendation Page 14 of 21
The FSP is not required to compensate the Applicants for ATO interest paid
Based on the Applicants’ running ledger of GST payments, the ATO charged total
interest of $2,167 on the Applicants’ unpaid GST from 28 September 2015 to 24
September 2016. It is not appropriate for the FSP to compensate the Applicants for
interest paid to the ATO because:
the Applicants had an obligation to mitigate any loss resulting from lack of
appropriate funding for their GST liability
the FSP had already clarified, in its letter dated 3 August 2015, that the GST
must be met from the Applican ts’ own funds (and not from the Loan)
the ATO commenced charging interest in September 2015, after settlement on
the sales of the stage one units, from which the Applicants had sufficient funds
they could have applied to the ATO
the FSP is not responsible for the Applicants’ decision to use their available
funds for purposes other than their ATO liability.
5.8 Did the FSP mismanage drawdowns on the Loan?
The Applicants say the FSP mismanaged drawdowns on the Loan
The Applicants raised the following alleged erro rs with drawdowns on the Loan:
The FSP paid GST twice on the builder’s claim for $95,569.78. The builder
received $106,188.63 for this claim on 5 June 2015.
However, the FSP’s employee “C” said in an email dated 21 July 2015 to the
builder that progress payment three was for $96,535.12 (excluding GST). The
FSP paid the builder $106,188.63 including GST of $9,535.12 on 5 June 2015.
The builder’s Customer Ledger shows $ 1 06,188.63 was received on 5 June
2015, bringing the balance of the ledger to $0. Therefore the Applicants’ claim
that the FSP paid GST twice is not established. Whilst the FSP’s decision to
pay GST was inconsistent with its usual practice not to pay the GS T
component, the Applicants have not shown how this caused them financial loss.
In June 2015, the FSP paid the Applicants’ suppliers without referencing invoice
numbers and the Applicants received calls from the suppliers querying whether
they had made the payment.
Whilst this was an inconvenience, the Applicants have not shown that this
caused them a financial loss.
The FSP gave the Applicants conflicting information about whether they could
lodge a claim for civil works for stages two and three. For example, on 4 May
2015, the FSP told them it would fund only construction-related items. On 5 May
2015, the FSP told them civil works for stages two and three could be claimed
as there was allowance for this in the QS report.
Again, this caused confusion and unnecessary stress for the Applicants’
directors, however, they have not shown how this caused them financial loss.
Case No: 425484 Recommendation Page 15 of 21
Regarding the last draw for stage one of the construction, they say:
o there was a discrepancy in the amount of $289 between the builder’s record
of retentions held and the FSP and QS’s records
o it took four weeks for the FSP to process the draw
o the FSP deposited payment into a wrong account and it took two to three
days to track the money
o this delayed settlement on sales of the units by four weeks which affected
the Applicants’ purchas ers as they had to refinance every three months.
FOS cannot award fo r third parties’ non -financial loss
The above claims in truth relate to the Applicants’ employees’, directors’ and
purchasers’ stress and inconvenience in dealing with alleged FSP errors. None of
those parties received a financial service from the FSP and as such, FOS cannot
award them compensation for non-financial loss. The financial service was provided
to the Applicant companies which are unable to make a claim for non-financial loss.
The directors of the Applicant companies cannot make a claim for personal loss
because the entity lodging the dispute is the company. So, we cannot consider a
claim by directors of a company for inconvenience, distress or anxiety caused by the
FSP’s conduct with respect to the company’s accounts.
The FSP is to pay the Appli cants’ accountant fees relating to the Loan
The Applicants claim that as a result of the FSP’s errors in managing the Loan, they
incurred accountancy fees totalling $8,854.55 to:
1. reconcile the available Loan funds and the project costs
2. represent them and compile information for this FOS dispute and their claim for
loss.
FOS’s processes are designed so that applicants can bring disputes to FOS without
requiring legal or other professional assistance. So if an Applicant chooses to be
represented by a paid representative, this will usually be at their own cost.
In some limited cases, we may require a financial services provider to reimburse the
reasonable fees charged by a n Applicant’s legal or other professional adviser. When
we assess this issue, we will take into account the complexity of the dispute and
whether the dispute raised issues that reasonably required the Applicant to obtain
expert advice. Unless exceptional circumstances apply, FOS will not require the
financial services provider to contribute more than $3,000 to these costs.
Having regard to the issues the Applicants experienced with retentions, GST and
management of the Loan account, it is appropriate for the FSP to compensate the
Applicants for their reasonable accountancy costs in reconciling the Loan funds and
drawdowns and the project costs.
Further, FOS considers that there are e xceptional circumstances in this case such
that the FSP should compensate the Applicants more than $3,000 for their costs.
This is because the App licants’ accountant was required to undertake complex
financial calculations when assisting them with this dispute. Had the FSP not made
Case No: 425484 Recommendation Page 16 of 21
errors in its treatment of retentions and GST, and had it been more transparent in its
management of draw-downs under the Loan, the Applicants would not likely have
required such professional assistance. It is appropriate for the FSP to compensate
the Applicants for their accountant’s time in completing calculations of loss related to
these aspects of the dispute.
Details of the accounting work undertaken for which the FSP is to compensate the
Applicants are set out in section 3.5 below. The total amount the accountant charged
for this work is $4,059.
FOS has excluded the accountant’s time charged for:
general correspondence, discussions or work that did not require expert
accounting advice
general non-dispute related accounting work and work setting up loan
agreements with V (invoice dated 10 December 2015)
work related to an issue with deposit money for one of the unit sales which does
not form part of this dispute (invoices dated 15 and 30 September 2016).
T he FSP is not required to compensate for the directors’ time
The Applicants claim compensation for their directors’ time in dealing with the
dispute. FOS does not awa rd compensation for an applicant’s time spent pursuing a
dispute or rectifying an FSP’s error and so it is not appropriate to compensate the
Applicants as requested.
5.9 Is the FSP liable for interest the Applicants incurred on additional
borrowed funds?
The Applicants claim interest expenses on additional borrowed funds
The Applicants say they had to unexpectedly borrow significant funds to meet the
difference between the total project cost and the funds advanced under the Loan, in
particular for retention and GST funding. The retention and GST funding issues have
been dealt with above.
In that regard, the Applicants’ claim for loss comprises:
interest paid on $32,241 borrowed on a director’s credit card
interest on a loan of $4,300 from a company director to one of the Applicant
companies
interest paid on a further loan of $200,000 advanced by V to the Applicants in
December 2015
interest paid on further funds borrowed under S Applicant Company’s Line of
Credit with another lender, and
interest paid on intercompany loans totaling $194,823 from L to the Applicants.
The FSP is not required to compensate the Applicants
Based on the available material, the Applicants have not established the FSP is liable
for their interest expenses on additional funds borrowed for the project (other than as
already set out in this Recommendation). This is because:
the FSP did not promise to fund the entire project cost
Case No: 425484 Recommendation Page 17 of 21
the FSP was not obliged under the Loan contract to funds costs outside of the
QS budget for construction, civil works, authority and consultant fees (and
capitalised interest)
the Applicants spent more on the project than budgeted. Further details about
this are set out below.
The FSP paid progress claims as requested
Based on my review of the QS reports 1 - 12 and the FSP’s Progress Payments
worksheet, the FSP funded the following project costs (excluding construction costs):
Developer and QS
budget for total cost
QS pre - funding budget
for costs to complete
Actual funds advanced
under the Loan
Civil works $318,802 $111,818 $136,142
Cons ultant
fees
$104,711 $81,074 $20,474
Authority
fees
$424,144 $370,164 $375,611
Totals $847,657 $563,056 $532,227
The above table shows the FSP funded about $30,000 ($563,056 - $532,227) less
than the amount allocated in the QS budget to meet the cost of civil works, consultant
fees and authority fees combined.
Whilst there was variance between the budget and actual funds advanced for
development costs, the payment of such costs was dependant on the Applicants
submitting claims to the FSP. The FSP correctly paid the amounts approved in
accordance with the QS assessments, with one reasonable exception.
The QS’s assessment five shows the Applicants lodged a claim for civil works of
$70,257.76 which the QS categorised as “overruns on various civil works
components”. The FSP’s Progress Pa yment table shows that the FSP did not pay
this amount. It was not required to do so because the Loan contract specified that
any cost over runs were to be met by the Applicants.
The Applicants spent more than budgeted on the project
Based on the available information, the Applicants spent more on the project costs
than budgeted and claimed for under the Loan.
For example, the Applicants spent more than their budgeted amount on consultant
fees. In their spending summary provided to FOS on 29 September 2016, the
Applicants claim to have spent a total of $174,519 on consultant fees. The budget for
total consultant fees was $104,711. Further, the Applicants lodged claims with the
FSP of only $20,474 for consultant fees.
Case No: 425484 Recommendation Page 18 of 21
6 Supporting information
6.1 FSP’s Funds Position
Based on the FSP’s Funds Position document, the FSP assessed the Applicants’
funding requirements as follows:
Description Amount
Land/ vendor purchase $600,000
Builder (excluding GST) $1,935,818
Authority fees $370,180
Interest capitalised $90,000
Civil works $111,818
Cons ultant fees $23,836
GST $50,000
10% contingency $193,581
Total: $3,375,233
The FSP assessed the Applicants’ funds available to meet the development costs as
follows:
Description Amount
Loan funds $2,850,000
Costs paid before the Loan
approval comprised of:
$141,716 to the builder
$324,040 for customers
contribution to date
$465,756
Cash/savings $220,079
Total: $3,535,835
The FSP therefore calculated surplus available cash or savings was $160,602
($3,535,835 - $3,375,233).
6.2 Timeline of Loan application process
The Applicants say the Loan application timeline went as follows:
Date Event
22/1/2015 Initial meeting between the Applicant Company director D, his broker and the FSP to
discuss funding the project.
4/2/2015 The Applicants sent the building contract to the QS and the FSP.
Case No: 425484 Recommendation Page 19 of 21
20/2/2015 The FSP completed a property valuation.
24/02/ 2015 The FSP and the QS received all the information they requested including amounts
they had already spent on the project, the Development Budget and the Development
Approval for the three staged project.
9/03/2015 The QS pre - funding report was issued.
17/03/ 2015 The FSP approved the Loan (according to its application summary notes)
26/03/ 2015 The FSP application summary notes show it identified 10 issues to be rectified in order
to prepare security documentation of the Loan. This included some missing trust deed
information.
2/04/2015 The FSP issued the Loan offer.
The FSP’s employee “A” told the Applicants they had met all Loan conditions.
9/4/2015 D signed the Loan offer.
14/4/2015 N signed the Loan offer.
15/4/2015 The FSP contacted the Applican ts and notified them they had insufficient equity in the
project. Arrangements were made to pay the vendor $400,000 from the initial draw
down and then $200,000 upon settlement on the sale of the stage one units. The FSP
imposed retentions and confirmed it would not fund the deposit or GST.
21/4/2015 The FSP made the first draw down payment.
6.3 Emails relating to retentions
Record Content
Email from FSP to “L”,
Director of the Applicant
Company “S” dated 17 April
2015 at 9.40am
“…[FSP] preference on amendments:
Retention:
Retention is to be deducted at a rate of 10% from each progress
claim until 5% of the Contract Sum is held. 2.5% of retention to be
returned upon Practical Completion and the remaining 2.5% to be
returned after the 6 month defect liability period.
An emai l from the builder confirming this will initially suffice with
formal paperwork to be provided to the Bank prior to the next claim.”
Email from the builder to “D”
in response to the above
dated 17 April 2015 at
6.11pm
“…Pleas e be advised that I have read the requirements below and
find them acceptable to [the builder] and am happy for them to be
incorporated into the contract with formal confirmation following this
email…”
6.4 FOS’s in terest calculations on retentions
The first of the below tables shows FOS’s calculation of compound interest on funds
the Applicants borrowed to pay for retentions.
The second table shows FOS’s calculation of c ompound interest payable had the
FSP funded the retentions under the Loan.
Case No: 425484 Recommendation Page 20 of 21
The above calculations are based on:
The funds sourced from “O” borrowed at the same intercompany loan
agreement interest rate of 10.57% (in the absence of any other information as
to the rate of interest charged on those funds)
BBSY refers to the bill rates which were obtained from published Bank Bill
Swap rates together with reference to what the FSP charged on actual bill
drawings dates close to the relevant rollover dates.
6.5 Accountant fees
Date Description Amount
allowed
(including
GST)
29 June 2015 Workings on [FSP] loan, reconcile payments to invoic es.
Conversations with [P] and [D] regarding issues with loan
$594 Date
Retention
paid Total cost
Int
accrued
Interest
charged
Retention
paid
Int
accrued
Interest
charged
10.57% 4.59%
29-May-15 15,000.00 $
29-May-15 15,304.09 $ 30,304.09 $
31-May-15 30,321.64 $ 17.55 $ 17.55
30-Jun-15 30,585.06 $ 263.42 $ 263.42
31-Jul-15 30,859.63 $ 274.57 $ 274.57
31-Aug-15 31,136.67 $ 277.03 $ 277.03
1-Sep-15 12,000.00 $ 43,136.67 $ 9.02 $
30-Sep-15 43,507.95 $ 362.27 $ 371.28
15-Oct-15 15,000.00 $ 58,507.95 $ 188.99 $ 20,000.00 $
31-Oct-15 58,968.04 $ 271.09 $ 460.08 20,040.24 $ 40.24 $ 40.24 $
17-Nov-15 40,000.00 $ 98,968.04 $ 290.30 $
30-Nov-15 99,630.92 $ 372.58 $ 662.88 20,115.84 $ 75.60 $
31-Dec-15 100,525.33 $ 894.41 $ 894.41 20,194.26 $ 78.42 $
31-Jan-16 101,427.77 $ 902.44 $ 902.44 20,272.99 $ 78.72 $
29-Feb-16 102,279.57 $ 851.80 $ 851.80 20,346.92 $ 73.93 $
31-Mar-16 103,197.76 $ 918.19 $ 918.19 20,426.24 $ 79.32 $
30-Apr-16 104,094.31 $ 896.55 $ 896.55 20,503.30 $ 77.06 $
31-May-16 105,028.79 $ 934.48 $ 934.48 20,583.23 $ 79.93 $
16-Jun-16 105,515.43 $ 486.64 $ 486.64 20,624.64 $ 41.41 $
97,304.09 $ 8,211.34 $ 624.64 $
20,000.00 $ 624.64 $
117,304.09 $ Total interest cost 8,835.99 $
Date Payment
Additional loan
drawings BBSY Days Interest
29-May-15 15,000.00 $
29-May-15 15,304.09 $ 30,304.09 $ 2.15% 95 169.18 $
1-Sep-15 12,000.00 $ 42,473.27 $ 2.09% 44 106.75 $
15-Oct-15 35,000.00 $ 77,580.03 $ 2.075% 33 145.54 $
17-Nov-15 40,000.00 $ 117,725.57 $ 2.055% 92 609.79 $
17-Feb-16 118,335.36 $ 2.11% 90 615.67 $
17-May-16 118,951.02 $ 2.03% 30 198.47 $
16-Jun-16 117,304.09 $ 119,149.49 $
Total interest cost 1,845.40 $
Case No: 425484 Recommendation Page 21 of 21
and missing information etc. Emails to [N] and [the FSP] re
clarification. Adjust for missing items. Email reports to [D].
Email to [I] re the Line Fees.
7 March 2016 Gather data for FOS case – including exporting data from
Xero and analysing pertinent expenses. Create
spreadsheet breaking down expenses. Calculations for
losses etc.
Workings on incorrect retentions and overpayments by FSP
$792 (partial
payment of
invoi c e)
19 August 2016 Draft email to [the FSP]
Check data provided from [the FSP] and Bill notes as to
whet her Financials could be settled without full spreadsheet
from [the FSP]. Conversations/Emails with [N]
$264 (partial
payment of
invoic e)
22 August 201 6 Draft emails to [FSP] regarding treatment of loan etc
Phone call from [the FSP]
$165 (partial
payment of
invoic e)
30 September 2016 Prepare spreadsheet to analyse CBA loan facility
transactions, incl rollovers, draws, maturity and principal
repayments
W orkings 25/09/16 – create spreadsheet for FOS on spend
to date
Further workings on spreadsheet – categorise and
summarise findings 27/ 9/16
Final calculations to spreadsheet for FOS, calc on [FSP]
lending criteria
$1,485 (partial
payment of
invoic e)
13 October 2016 Prepare calculations and documents detailing losses $759
Total: $4,059