Determination 425058
Delay in arranging overdraft facility
Summary
A farming applicant and his company complained that a three-month overdraft delay caused lost crop profits and that loan interest was overcharged. AFCA upheld part of the delay, ordered $500 non-financial loss compensation, and rejected the consequential loss and interest complaints.
The FSP was responsible only for the initial delay, and the company had not shown that delay caused quantifiable financial loss.
Issues
- Delay primary · upheld“FSP unreasonably delayed the overdraft application review by 19 business days before counter-signing”
- Incorrect fees or charges secondary · not upheld“The variable interest rate has been applied correctly to the loan”
- Misleading conduct secondary · not upheld“The 2012 and 2013 letters do not make any promises to the Company”
Subjects and remedies
small businesspay non financial loss
Related
All Financial Firm (Unknown - Credit) determinations · Find similar determinations
Text of the determination
Determination
Case No: 425058 Determination Page 1 of 6
Case number: 425058 3 March 2017
1 Overview
1.1 Dispute
This dispute is about facilities the Financial Services Provider (FSP) provided to four
borrowers. Two of the four borrowers, the Applicant and the Company, lodged this
dispute in which they claim that:
in 2014, the FSP took three months to arrange an overdraft, which meant the
Company was unable to sow its crop at the expected time, and
between February and June 2015, the FSP overcharged interest on a loan (the
loan).
In resolution to the dispute, the Applicant and Company claim compensation related
to the delay in provision of the overdraft.
The senior case analyst provided the parties with a recommendation dated 8
December 2016 on the issues in dispute. The recommendation was in favour of the
FSP. A copy of the recommendation is attached to this determination.
The Applicant (on behalf of himself and the Company) rejected the recommendation,
further submitting:
the FSP delayed arranging the overdraft and was aware of the incorrectly
registered trust before May 2014
although loss cannot be quantified, it is undoubtedly considerable
the FSP acted in a threatening manner and
the FSP did not follow through with various offers to provide products.
1.2 Issues and key findings
Were the findings of the recommendation correct?
The findings contained in the recommendation were correct and are adopted in this
determination. Further submissions provided after the recommendation have been
considered.
Do the Applicant’s further submissions change the outcome?
The submissions made after rejecting the recommendation do not change the
outcome for the reasons set out in section 2.2. They do not show any financial loss
was suffered as a result of the FSP‟s contribution to delay in relation to the overdraft
facility.
Case No: 425058 Determination Page 2 of 6
The variable interest rate has been applied correctly to the loan and it has not been
established that the FSP threatened the Applicants or made any other error.
1.3 Determination
This determination is substantially in favour of the FSP.
I agree with the senior case analyst ‟s reasons for the recommendation and the
recommended outcome.
If the Applicants accept this determination, the FSP should pay the Applicant $500
compensation for the non-financial loss he suffered. No compensation is payable to
the Company.
Case No: 425058 Determination Page 3 of 6
2 Reasons for determination
2.1 Were the findings in the recommendation correct?
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
recommendation. I am satisfied that the documentation I have relied on has been
provided to both parties.
I am satisfied that the senior case analyst ‟s recommendation contains an accurate
summary of the dispute, the issues to be determined, any applicable paragraphs of
the Terms of Reference and any relevant law.
2.2 Do the Applicant’s further submissions change the outcome ?
The FSP identified the trust issue on 29 April 2014
The recommendation found that the FSP was responsible for some delay in providing
the overdraft but that the Applicants also contributed to the delay because the
relevant trust was incorrectly registered.
The recommendation concluded that:
the Company had signed the overdraft application on 22 May 2014
the FSP unreasonably waited until 18 June 2014 (i.e. 27 days later) to co-sign
the application
the FSP consequently unreasonably delayed until 25 June 2014 identifying that
the trust was incorrectly registered (the “trust issue”) .
the FSP asked the Company to resolve the trust issue on 26 June 2014
the Company did not do so until 5 August 2014 (i.e. 40 days later), and
the delay in setting up the overdraft was therefore held to be in part the FSP‟s
responsibility and in larger part the Applicant‟s responsi bility.
The Applicant has now drawn FOS‟s attention to correspondence showing that the
FSP became aware of the trust issue as early as 29 April 2014, i.e. 58 days before its
26 June 2014 request that the Company resolve the issue.
The trust issue did not impact on the financial arrangements at that time
On 29 April 2014, when the FSP became aware of the trust issue, it considered
whether that impacted on its financial relationship as of that date. The FSP‟s internal
emails dated 30 April 2014, show that it concluded the trust issue did not impact on
its relationship with the Company at that time:
Credit Analyst‟s email, 9:22 AM:
“ We have two options:
1) Given that no Letter of Offer will be issued and the [existing] debt will most likely be
paid out in full soon, We can proceed as is […]
Case No: 425058 Determination Page 4 of 6
2) We can put the remaining debt in the name of the Company only ”
Manager‟s email, 10:52 AM:
“can we proceed on the basis of option 1.”
The Company did not apply for the overdraft until 22 May 2014
It is only after the Company asked for the existing debt to be extended (in the form of
an overdraft application) that the trust issue became a matter the Company needed
to address. Given the overdraft was applied for on 22 May 2014, the delay in
assessing the application commenced after that time. Even if the FSP had raised the
trust issue within a reasonable period on or after 22 May 2014, given the Company
took 40 days to resolve the issue, the FSP‟s contribution to the delay is not
significantly increased from that set out in the recommendation.
The delay by the FSP in informing the Company the trust issue needed to be
resolved was addressed in the recommendation. The case analyst awarded non-
financial loss compensation of $500 to be paid to the Applicants in respective of
stress and inconvenience caused. The Company is a business and cannot suffer
stress or inconvenience; it is therefore not entitled to compensation on the same
basis.
Despite the information set out above, I consider that $500 compensation for non-
financial loss is appropriate in the circumstances.
The Company has not shown the delay caused any consequential loss
The recommendation found the Company had not provided sufficient information to
support its claim that it suffered a consequential loss relating to the unreasonable
delay caused by the FSP. In response, Mr S (a party engaged by the Applicant to
communicate on his behalf with FOS) wrote:
“… there can be no doubt that the loss between crops sown at the optimum time or at a
later date is considerable. [ … The Applicant] has provided rainfall records which show
that had the crop been sown in May a reasonable return would have been received.
What further proof would be required or indeed be possible?”
The claim therefore rests on the possibility of having sown a crop in May 2014.
However the Company did not apply for the overdraft until 22 May 2014. Allowing a
reasonable period for consideration of the application, resolution of the trust issue,
and providing the Company with access to the new facility, it is highly unlikely that
sowing would have commenced in May of that year. As indicated above, the larger
portion of the delay in opening the account is attributable to the Company by the time
it took to deal with the trust issue, and a smaller delay is attributable to the FSP.
In any case, no figures have been provided to FOS that would allow it to compare the
rainfall records to any information about the intended sowing of crops, such as
acreage, cost of seed, and cost of sowing. This means that the Company has not
been able to demonstrate loss in consequence of the FSP‟s contribution to the delay.
Case No: 425058 Determination Page 5 of 6
The FSP did not threaten the Applicant
Mr S refers to the FSP‟s letter of 24 January 2014, the relevant section s of which
have been included at section 3.1. Mr S wrote:
“…the demand of a response within 14 days… is a little heavy handed even if it is in
within legal requirements. To demand that action and then threaten Farm Debt
Mediation is not in the spirit of the FDM legislation… As a result of this letter the B ank
received some $826,000.00 by May of the same year.”
I note that the letter advises the borrowers that they have not provided necessary
information and grants a further period for the borrowers to do so, seeking a
“proposal for the repayment”. No elemen t of the letter appears to be a threat,
particularly the statement of the FSP‟s rights to engage mediation to resolve a debt
dispute. It is unreasonable to expect that a person reading the letter would have
assumed foreclosure to be imminent.
The letter requests the borrowers provide information to allow the FSP to assess the
borrowers‟ request, or to refinance the debt by the end of February 2014 , or
otherwise to enter into a mediation process . This request cannot be said to have
compelled the Company to sell its land and provide a lump sum of $826,000.00 in
May 2014.
The 2012 and 2013 letters do not make any promises to the Company
The Applicant has referred to documentation provided to him and to the Company in
2012 and 2013. He says that the letters pro vide promises of a seasonal overdraft and
offers of help.
The letters referred to are generic letters issued to customers of the previous
financial services provider of the Applicants, to announce that its assets had been
acquired by the FSP. The letters included a brochure outlining the sorts of products
the FSP can provide. The documents are not offers of these products or guarantees
that the products will be provided to its customers.
The FSP correctly applied interest to the loan
Based on the available information, for the reasons set out in the recommendation
the FSP correctly applied the variable interest rate to the loan, inclusive of both the
62 base point reduction and the subsequent 12 base point reduction.
Other matters do not relate to the provision of financial services
The Applicant has requested the FSP explain how much it paid the previous financial
services provider to purchase the loan book in so far as it made up of the Company‟s
facilities. This is unrelated to the financial services provided to him or the Company
by the FSP. These matters were fully addressed in the recommendation and are
therefore not considered in this determination.
Case No: 425058 Determination Page 6 of 6
3 Supporting information
3.1 Relevant paragraphs from the F SP’s letter dated 24 January 2014
“Dear [Borrowers],
Please be advised that you have not provided [the FSP] with the information required
to complete the review [of your facilities] and assess your request, consequently, the
review remains incomplete and request for increase has been declined.
Your facilities have expired and are now due and payable…
[The FSP] now requests that within 14 days (expiring 11 th February 2014) you provide
the writer with your proposal for the repayment of your facilities for further
consideration.
Alternatively, [the FSP] will allow you 30 days (expiring .28 th February 2014) to obtain
approval for refinance from another financial institution, with terms acceptable to [the
FSP].
If you fail or are unable to comply with this request by the due dates, [the FSP]
reserves its rights to initiate Farm Debt Mediation.”
Recommendation
Case No: 425058 Recommendation Page 1 of 6
Case number: 425058 8 December 2016
4 Overview
4.1 Dispute
This dispute is about facilities the FSP provided to four borrowers. Two of the four
borrowers, the Applicant and the Company, lodged this dispute and say:
in 2014, the FSP took three months to arrange an overdraft, which meant the
Company was unable to sow its crop at the expected time, and
between February and June 2015, the FSP overcharged interest on a loan (the
loan).
The Company and the Applicant raised other issues which do not form part of this
Recommendation; those issues are outlined at section 3.2.
The Applicant claims compensation related to the delay in provision of the overdraft.
4.2 Issues and key findings
Did the FSP delay providing the overdraft and cause loss?
The Company was unable to quantify the loss it is said to have suffered due to the
delay in providing an overdraft. The information does not show the FSP was entirely
responsible for the claimed delay. As such, no compensation is payable to the
Company.
Did the FSP apply the correct interest rate to the loan?
The variable interest rate has been applied correctly to the loan, inclusive of both the
62 base point reduction and the subsequent 12 base point reduction. The correct
interest rate has been applied to the loan.
Should the FSP compensate the Applicant?
Based on the information provided, it is more likely than not the FSP only caused the
initial delay in assessing the overdraft application. The initial delay is only a portion
of the three month delay claimed by the Applicant, the FSP should compensate the
Applicant relating to that portion of delay.
4.3 Recommendation
This recommendation is substantially in favour of the FSP.
The FSP should pay the Applicant $500 compensation for the non-financial loss he
suffered.
Case No: 425058 Recommendation Page 2 of 6
5 Reasons for recommendation
5.1 Did the FSP delay providing the overdraft and cause loss?
The FSP initially delayed assessing the request for the overdraft
The Applicant has claimed the overdraft application was submitted on 19 May 2014,
but due to the FSP‟s delay, it was not provided u ntil three months later on 18 August
2014. The signed application form was signed by the borrowers on 22 May 2014, but
not counter-signed by the checking officer until 19 business days later on 18 June
2014. FOS asked the FSP the reason for this delay; the FSP responded:
“Ideally, [we] would like to have lending decisions made within 20 business days. Given
the chequered credit history with this file, which was managed by the [specific FSP]
Unit and included the condition to reduce debt through land sale which had only settled
in early May [2014], this may have impacted on the turnaround time for a Relationship
Manager to review and submit an application for additional credit.”
This delay of 19 business days before the document was reviewed was an
unreasonable one on the part of the FSP. The FSP should pay the Applicant $500
non-financial loss compensation for the stress and inconvenience associated with the
unreasonable delay.
Further delays were caused by the Company
One reason for a continuing delay on the lending decision was that the FSP identified
the Company was set up as trustee for a trust which was incorrectly registered. The
FSP says it communicated this issue to the Applicant on 26 June 2014 and did not
receive the corrected information until 40 days later on 5 August 2014. The FSP says
its solicitor reviewed the corrected information on 8 August 2014, and the revised
letter of offer was issued on 11 August 2014. The Applicant‟s representative says “I
am assured by [the Applicant] that [his] solicitor/accountant only took a day to rectify
the omissions”.
When we assess disputes, we consider available documents, the recollections of the
parties, and all relevant circumstances. We give more weight to contemporaneous
documentary information. Neither the FSP nor the Applicant have provided
information to prove their respective positions. However the FSP‟s
contemporaneous “activity log” which is set out at 3.1 of this recommendation shows
after the checking officer counter-signed the application on 18 June 2014, issues with
the Trust were identified on 25 June 2014. The issues were not resolved until 5
August 2014, when the Company‟s accountant changed the Trust name.
The Company has not provided sufficient information to support its claim
The Company claimed that due to the delay in the provision of an overdraft, it was
unable to realise profits. It provided two different estimations of the lost profits:
$13,000.00 (in correspondence dated 6 April 2016)
$183,554.00 (in correspondence dated 5 September 2016).
Case No: 425058 Recommendation Page 3 of 6
FOS asked the Company to provide evidence of these consequential loss claims.
The information provided was primarily composed of handwritten rainfall records. The
rainfall records were intended to show that if crops had been sown, growth would
have followed and profits would have been realised.
The information provided does not allow loss to be calculated
The general argument that sown crops would have realised a return on investment is
accepted. However, the information is not specific enough to allow any actual
calculation of loss to be established. This is particularly so given that, as set out
above, only part of the delay can be attributed to the FSP. There is no information to
support the Applicant‟s recollection that the Company‟s accountan t rectified the
omissions within a day. In these circumstances, the FSP should not pay any
compensation to the Company in relation to the claim of consequential loss.
5.2 Did the FSP apply the correct interest rate to the loan?
The Applicant changed his claim in relation to the interest rate and charges
The Applicant claimed incorrect interest was charged on the loan between February
and June 2015. The Applicant did not provide any further information about this
claim, including whether he believed any error had been made, except to say that he
felt the amount was too high. Under the FOS Terms of Reference we are not able to
consider disputes about the level of a fee, premium charge or interest rate . However
in the course of consideration of this matter, the FSP agreed to an interest reduction,
the implementation of which gave rise to further interest rate disputes.
The FSP agreed in May 2016 to reduce the interest rate to 6.15%
On 17 May 2016, during the course of the dispute, the FSP stated: “we have agreed
to provide [the Applicant] a revised rate of 6.15% which is a 62bp [i.e. base point]
reduction from his current rate”. No date was given as to when this reduction would
be made. The Applicant noted, by letter dated 9 August 2016, the reduction had not
been made as of 1 June 2016.
The FSP applied the reduced interest rate, effective as of 1 June 2016
The FSP confirmed on 23 August 2016 that it would put the interest reduction of
62bp in place and backdate it appropriately. The following day it confirmed the
reduction was in place and had been backdated effective to 1 June 2016; and that it
would be reduced on 1 September 2016 by a further 12bp (i.e. from 6.15% to
6.03%).
The Applicant was notified of this reduction and in response, on 20 September 2016
he provided to FOS a copy of his 1 September 2016 loan statement showing the
Annual percentage rate of 6.030% circled, and placed a tick next to it. On this basis,
it is accepted he was, at that time, satisfied this matter had been appropriately
addressed. The Applicant asked FOS whether the calculation of the interest
adjustment was correct, however FOS does not act as an audit service.
Case No: 425058 Recommendation Page 4 of 6
The interest rate was not fixed by the transfer of ownership
On 23 September 2016, the Applicant raised a new concern that in the transfer of his
facility from the original credit provider to the current FSP, he was informed “current
loan obligations will remain”. The Applicant says this means the interest rate must not
be varied from the rate it was at the time of the transfer (which he says was 6.15%).
He says the subsequent interest rate was, he states, “in breach of the agreement”.
This argument fails, as the “loan obligations” referred to are the terms and conditions
of the product, which allow the FSP to vary the interest rate.
5.3 Should the FSP compensate the Applicant?
The Company cannot make a claim for non-financial loss
When a company lodges a dispute with FOS, it is the legal entity that makes a claim
for financial loss. Therefore the claim must be made by the legal representatives of
the company: that is, the directors of the company. However, the directors of a
company cannot make a claim for personal loss because the entity lodging the
dispute is the company. So, we cannot consider a claim by directors of a company
for inconvenience, distress or anxiety caused by the FSP‟s conduct with respect to
the C ompany‟s accounts.
The FSP should pay the Applicant non-financial loss compensation
In this dispute, the Applicant was one of four borrowers the overdraft and loan were
provided to. Non-financial loss includes claims for stress or inconvenience caused by
an error of the FSP. The maximum amount we can award for non-financial loss is
$3,000 for each claim. We will only award compensation for non-financial loss if there
has been an unusual degree or extent of inconvenience. When assessing whether
the circumstances are of an unusual nature we will review:
the degree or extent of physical inconvenience suffered
the general time taken to resolve the dispute
the extent to which the FSP‟s actions interfered with the Applicant‟s expectation
of enjoyment or peace of mind.
The Applicant is an elderly gentlemen working on a farm in a relatively remote area.
The initial delay by the FSP in assessing the application for the overdraft would have
caused him stress and inconvenience. However of the three month delay, the FSP
only caused the initial delay of one month. In these circumstances, the FSP should
pay to Applicant $500 non-financial loss.
Case No: 425058 Recommendation Page 5 of 6
6 Supporting information
6.1 The FSP’s contemporaneous “activity log”
Date Note
25 June 2014 Deficiencies: 1. Trust name [Trust Name A] or [Trust Name B]. 2.
ABN noted is noting entity as [Trust Name A] and not [Trust Name
B]? 3. ABN for partnership? 4. ABN [ Trust Name B] in own right?
5. Account ops seasonal? 6. Account ops T/loan? 7. Bus[iness]
purpose declaration [requires] execution.
4 July 2014 Deficiencies still outstanding: 1. Trust Deed amendment required to
[Trust Name A]. 2. Bus Purp Dec still requires execution.
10 July 2014 [the] deficiencies dated 4/7/14 are still [required] to be ad dressed.
23 July 2014 Deficiencies still outstanding: 1. Amendment to trust deed still
required.
5 August 2014 After being advised that there would be a Trust Deed amendment
signed and provided to amend the Trust to „[Trust Name A]‟, the
[accountant] has had the Trust name recorded against the ABN
changed to „[ Trust Name B]‟. I will have the joint borrowing entity
name changed […] and get re - approved.
6.2 Key documents referred to
I have reviewed all information provided by the FSP and the Applicant parties.
Documents which were particularly relevant to forming my view included:
Applicant‟s letter dated 6 April 2016
FSP‟s email dated 17 May 2016
Activity log six months preceding the opening of the overdraft.pdf (provided by
FSP by email 27 May 2016)
LAF 190614.pdf (i.e. the signed application form) (provided by FSP by email 27
May 2016)
Applicant‟s letter dated 9 August 2016
FSP‟s email dated 23 August 2016
FSP‟s email dated 24 August 2016
Applicant‟s letter dated 5 September 2016
Applicant‟s letter dated 20 S eptember 2016
Applicant‟s representative‟s email dated 23 September 2016
FSP‟s letter dated 1 November 2016
Applicant‟s letter dated 3 November 2016
Applicant‟s representative‟s letter dated 4 November 2016
Case No: 425058 Recommendation Page 6 of 6
6.3 Matters not considered in the recommendation
The loan repayment date
The Company originally said that it was inappropriate for the FSP to expect the
annual repayments to be made in February of each year.
During the course of investigation, the FSP agreed to change the instalment to
October of each year. It is understood that this issue has been resolved to the
satisfaction of the parties.
The Applicant says the loan interest rate is too high
FOS is not able to consider disputes about the level of interest rate charged. We can
only consider a dispute about an interest rate if it is not being charged in accordance
with the terms and conditions, or if it has in any way been misrepresented.
The FSP purchased the loan from another financial service provider
FOS can only review a dispute between an Applicant and their FSP which concerns
a direct financial service that the FSP has provided to them.
In this case, the Applicant and the Company are seeking information about
arrangements between the FSP and the original credit provider. The information
sought has no bearing on the Company‟s liability under the loan contract. FOS is
unable to obtain information about the commercial arrangement between the FSP
and the original credit provider.