Home / Financial Firm (Unknown - Credit) / Determination 425044

Determination 425044

Hardship agreement ended, collections commenced, and complaint not answered with an IDR response

FirmFinancial Firm (Unknown - Credit)
Decided2016-09-29
ProductCredit · Credit card
OutcomeFor the complainant
Amount awarded—
Non-financial loss$3,500
Amount claimed—
SourceAFCA PDF

Summary

The applicant complained that the FSP ended his credit card hardship agreement, sent collection notices, failed to give an IDR response and breached debt collection limits. AFCA found in his favour and ordered $3,500 non-financial loss compensation applied to the account, a repayment arrangement and provision of statements on request.

The applicant substantively met his hardship repayments and the FSP gave unclear due dates, so ending the arrangement and recommencing collection was inappropriate under good industry practice and the Debt Collection Guideline.

Issues

Subjects and remedies

financial hardshiploan or hardship variationpay non financial lossprovide documents

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 425044 Determination Page 1 of 12 Case number: 425044 19 September 2016 1 Overview 1.1 Dispute On 14 January 2014, the Applicant and the FSP entered into a hardship agreement in relation to the repayment of the Applicant ’s credit card balance (the account). In mid-July 2014, the FSP ended the hardship agreement and referred the Applicant ’s account to its collections agent. This dispute is about whether the FSP acted appropriately, and in accordance with its obligations, in dealing with the Applicant as a customer in financial difficulty. 1.2 Issues and key findings Was the FSP entitled to end the hardship agreement? It was not clear, under the terms of the hardship agreement, exactly when (what date) the Applicant was required to make repayments. Despite this, the Applicant still met his obligations to make repayments on a monthly basis, under the hardship agreement. In these circumstances, the FSP should not have ended the hardship agreement. Did the FSP respond to the Applicant ’s complaint appropriately? The FSP failed to provide an appropriate response to the Applicant’s complaint, and consequently failed to meet its IDR obligations. Did the FSP breach the Debt Collection Guideline? The FSP’s debt collection activity breached the weekly contact limit on two occasions. That collections activity involved excessive and unnecessary SMS contact. What is an appropriate resolution to this dispute? I am satisfied that the FSP’s conduct (summarised above) would have caused the Applicant undue stress, for which it is appropriate to compensate him with an award of $3,500 in total non-financial compensation. That compensation is to be applied by the FSP to the account, to reduce the Applicant’s debt. The repayment arrangement outlined belo w (in section 1.3) must also be implemented. Case No: 425044 Determination Page 2 of 12 1.3 Determination This Determination is in favour of the Applicant. Should the Applicant accept this Determination within 30 days of its date, within a further 14 days of that acceptance, the FSP must:  pay $3,500 in non- financial loss compensation to the Applicant’s credit card account to reduce his debt  enter into a repayment agreement with the Applicant consistent with his current arrangement, to repay $400 per month until the credit card balance is repaid in full, but with a repayment due date of the 20 th day of each month (if these repayments are not made and the account falls into arrears, the FSP will be entitled to commence collection activity)  provide the Applicant with any further account statements that he asks for (for periods of time predating October 2016) within 7 days of his request and without charge, and ensure that it provides him with monthly statements of account going forward. Case No: 425044 Determination Page 3 of 12 2 Reasons for determination 2.1 Was the FSP entitled to end the hardship agreement? Background to the hardship agreement On 14 January 2014, the Applicant and the FSP entered into the hardship agreement. The Applicant agreed to make repayments of $350 a month, for 12 months, towards the credit card debt. Around 21 July 2014, the FSP ended the hardship agreement and referred the Applicant ’s account to its collections agent. The parties’ views on the ending of the hardship agreement The FSP says that the hardship agreement was ended because the Applicant did not make repayments to meet the relevant account statement cycles. During the mid- May 2014 to mid-June 2014 cycle, two payments were made. No payments were made during the mid-June 2014 to mid-July 2014 cycle. The FSP says this was a breach of the hardship agreement. The Applicant says that he made the required repayments. The Applicant considers that the account should never have fallen out of hardship. The due dates for payments in the hardship agreement were not clear The hardship agreement (formalised in a 20 January 2014 letter) stated that: ‘Your monthly payments have been set at $350 .00 … Your subsequent monthly repayments will need to be received by the due dates shown on each of your monthly statements.’ In reviewing the hardship agreement, I note that no explanation is given to distinguish subsequent monthly payments from initial monthly payments. Further, none of the account statements from mid-April 2014 contain any due date. The Applicant could not therefore have known which dates to pay, even if he had received the account statements (most of which the Applicant says he did not receive). The subsequent conversation did not clarify the due date The contact notes (see section 3.2 below) record that on 30 May 2014, the Applicant and the FSP discussed the due date for payments. However, no agreement was actually reached about the due date. Instead, the FSP representative said that the Applicant should try to pay by the 10 th of each month. Further, in any event, the FSP was aware that the Applicant received his salary around the 15 th of each month, so payments early on in the month would have been inappropriate and difficult for him to manage given his financial circumstances. (Knowledge of this circumstance is shown in the FSP’s contact note of 2 January 2014.) Case No: 425044 Determination Page 4 of 12 Good industry practice requires giving time to remedy a missed payment when a customer has a financial difficulty arrangement I t is good industry practice for an FSP to give 7 days’ notice if a repayment unde r a financial difficulty arrangement has not been met, before recommencing any recovery action. The contact notes record that on 19 June 2014, the FSP sent a copy of the mid-May to mid-June account statement to the Applicant. This showed two payments in one cycle. However, no covering letter or explanation was given. The FSP did not otherwise communicate with the Applicant to advise him that a payment was missed or effectively give him notice that it considered he had missed a repayment. FOS expects financial services providers to comply with standards of good industry practice. The Applicant substantively met his repayment obligations under his hardship agreement The Applicant made repayments of $350 or more each month from mid-February 2014 to mid-July 2014. (See section 3.3 below for further details). The Applicant therefore substantively met his obligation to pay $350 per month under his hardship agreement. Despite this, the FSP ended the hardship agreement around 21 July 2014. This was also despite a payment of $350 being made by the Applicant on 15 July 2014. The hardship agreement should not have been ended For the reasons set out above, it was inappropriate for the hardship agreement to be terminated by the FSP and collections activity initiated. That collections activity (including two collection notices sent in July and August 2014) would have caused the Applicant unnecessary stress. However, in mitigation, I recognise that the FSP’s collection agent and the Applicant negotiated in good faith to reach new financial difficulty agreements in mid- September 2014 and then in April 2015. Further, the FSP has refunded interest charged from September 2014 to February 2016. Overall therefore, it is fair in the circumstances to award the Applicant $1,000 in non- financial loss compensation for the inappropriate ending of the hardship agreement in July 2014 and premature recommencement of collections. 2.2 Did the FSP respond to the Applicant ’s complaint appropriately? The FSP’s IDR o bligations Under ASIC Regulatory Guide 165: Licensing: Internal and external dispute resolution , the FSP is required to have procedures in place to acknowledge complaints. It must also provide a final Internal Dispute Resolution (IDR) response in writing within 45 days. A final IDR response should inform the complainant of:  The final outcome of their complaint or dispute at IDR. Case No: 425044 Determination Page 5 of 12  Their right to take their complaint or dispute to External Dispute Resolution (EDR).  The name and contact details of the relevant EDR scheme. The FSP did not meet its IDR obligations to the Applicant in response to his strong and expressed dissatisfaction with the FSP’s conduct The contact notes (shown in section 3.2 below) record that between July-September 2014, and between March-April 2015, the Applicant expressed real dissatisfaction. The Applicant was continually dissatisfied with the ending of the hardship agreement, and the FSP’s explanation for it. Despite this, the FSP never provided an IDR response to the Applicant. Instead, informal explanations were given by phone or email to the Applicant that did not satisfy the FSP’s IDR obligations . The FSP did not therefore meet its IDR obligations on several occasions for long periods of time, causing the Applicant to suffer undue stress. For this, in the circumstances, it is appropriate to award the Applicant $1,000 in non-financial loss compensation. 2.3 Did the FSP breach the Debt Collection Guideline? The Debt Collection Guideline for Collectors and Creditors (the Guideline) sets industry standards for debt collection activity. The Guideline says:  A collector should not contact a debtor more than three times in a week.  Debtors should be free from excessive communications from collectors. Contact with a debtor should only be for a reasonable purpose.  If an arrangement is being complied with, no collection activity should occur. The FSP used excessive and unnecessary SMS collection activity From October 2014 to February 2016, the FSP sent 25 SMSs to the Applicant. The SMSs were in the form of reminders or requests to confirm that payment was made. These SMSs breached the Guideline because they took place while the Applicant was complying with new repayment arrangements. Further, the SMSs served no reasonable purpose because the Applicant substantively met his repayment obligations, and so no payment was outstanding. (This is shown in section 3.4 below.) Because of the length of time and high number of SMSs, it is appropriate to award the Applicant $1,000 in non-financial loss compensation, to recompense him for the stress he suffered as a result of the FSP’s excessive collections activity . The FSP breached the weekly debt collection limit On two occasions, the FSP made five collection contacts with the Applicant in a week (see section 3.5 below for further details). This breached the limit of three per week allowed under the Guideline. Case No: 425044 Determination Page 6 of 12 It is appropriate in these circumstances to award $500 in non-financial loss compensation to the Applicant for these breaches. 2.4 What is an appropriate resolution to this dispute? The Applicant should be awarded a total of $3,500 in non-financial loss compensation The Applicant should be awarded a total of $3,500 in non-financial loss compensation for the stress caused to him for the various elements of the FSP’s conduct discussed earlier in this Determination. The components of that compensation sum, used to calculate the total compensation, are set out in section 3.6 below. The Applicant should maintain repayments going forwards The Applicant has confirmed that he does not require any further assistance. The Applicant should therefore continue to maintain the existing repayment arrangement of $400 per month until the credit card is repaid in full. However, the Applicant should have until the 20 th of each month to make each repayment. This allows time for the Applicant ’s pay cycle of between the 9 th and the 15 th of each month, and provides a grace period for weekends etc. If these repayments are not made and the account falls into arrears, the FSP is entitled to recommence collection activity. Account statements should be provided on request During the FOS process, the Applicant has been provided with all account statements from mid-January 2014 to August 2016. However, the Applicant has said that since 2014, he has not ever received account statements from the FSP, on a normal, periodic basis. If the Applicant requests any further account statements in the future (predating October 2016), the FSP must provide them within 7 days of his request, free of charge. The FSP must also going forward, ensure that the Applicant is provided with account statements and confirm where these are to be sent with him. Case No: 425044 Determination Page 7 of 12 3 Supporting information 3.1 Decision basis and process This dispute has been the subject of a preliminary view in favour of the Applicant, which was not accepted by the FSP. I have considered all the material submitted by the parties, both before and after the preliminary view was issued, in order to reach my decision. I am satisfied that the material I relied upon in reaching my findings has been exchanged between the parties. I have had regard to what is fair in all the circumstances, considering legal principles, applicable industry codes or guidance as to practice, good industry practice and previous relevant decisions of FOS or its predecessors (though I am not bound by these). 3.2 Relevant extracts from the contact notes and correspondence In the table below, key events from the various contact notes and correspondence are described: ‘CN’ refers to collection notes ‘AN’ refers to notes provided by the FSP’s collections’ agent. ‘Com’ refers to complaint notes. ‘Corro’ refers to FSP collections correspondence or hardship correspondence. Date Ev ent Source 2 January 2014 Applicant advises that his main salary is received on 15 th of each month. CN 14 January 2014 Applicant agrees verbally to ent er hardship agreement. As part of the agreement, card will be cancelled if it goes 90 days overdue. CN 20 January 2014 Hardship agreement letter, noting the FSP will consider reinstating the credit card after the 12 mont hs if the Applicant has capacity. Corro 15 April 2014 Notice cancelling card. Corro 30 May 2014 Applicant called to check account was okay because he got letter. Advised to disregard letter as in hardship programme and customer is keeping payments so is okay. Advised to try and make payments around 10 th or before so payment does not update after cycle cut, as possibly will be exited from programme. CN 19 June 2014 June 2014 account statement posted to Applicant today. CN 18 July 2014 - 21 July 2014 Account removed from hardship and transferred to FSP’s collections agent. CN and AN 21 July 2014 Notice demanding full payment of the balance owing. Corro Case No: 425044 Determination Page 8 of 12 4 August 2014 Notice demanding payment, although $0 is said to be overdue. Corro 14 August 2014 Applicant says he is not happy the account was referred to FSP’s agent, and that he had previously made required repayments. AN 28 August 2014 Applicant says he was previously paying the same amount every month and suddenly the matter was referred out of hardship. Applicant is really disappointed by this. AN 1 September 2014 Email sent from Applicant attaching documentation, and expressing his concerns that there was no due dat e on the account statements and that he had called previously to confirm the hardship agreement was on foot. Applicant says the situation is highly stressful. AN 4 September 2014 Applicant again expresses real concerns that his account was wrongly removed from the hardship programme. The FSP’s agent says it will refer the matter to the FSP. AN 4 September 2014 and 30 September 2014 Repayment arrangement agreed of $375 per mon th for 6 months, to be paid on 15 th of eac h month. AN 24 September 2014 Applicant says that the FSP had promised to get back to him re leaving the hardship programme. AN 30 September 2014 Applicant was informed of the reply from the FSP regarding leaving the hardship programme. Applicant was upset and cannot understand the respons e given by the FSP. Applicant says he paid the account every month and the FSP did not do the right thing. Informed Appli cant he missed the July payment, so hardship cancelled. AN 20 March 2015 Applicant called in wanting to lodge a complaint as the account had gone to collections, despite Applicant being told in January 2014 he needed to pay $350 per month. Applicant said he paid every month, and was not notified that account was removed from hardship. FSP says it will raise enquiry. Com and CN 23 March 2015 FSP tells Applicant still yet to hear back from hardship team. CN 2 April 2015 Applicant ups et that no one from har ds hip has called him. CN Mid - April 2015 Repayment arrangement agreed of $400 per month ongoing, to be paid around 15 th of each month. AN 9 July 2015 Continued repayment arrangement of $400 per month. Date of repayment changed to 8 th of the month. AN 3.3 Payments made between January and July 2014 The table below records the payments shown on the account statements between January and July 2014. These payments were made before the hardship agreement was ended on 18 July 2014. Case No: 425044 Determination Page 9 of 12 Date Payment made $ 7 January 2014 400.00 17 January 2014 400.00 18 February 2014 416.67 17 March 2014 350.00 15 April 2014 350.00 15 May 2014 350.00 13 June 2014 350.00 15 July 2014 350.00 3.4 Payments made in later repayment arrangements and SMSs sent The tables below shows the payments recorded on the account statements from August 2014 to January 2016. It also shows the repayment arrangement that was on foot at the time and the reminder collection SMSs that were sent. The date of the SMSs are recorded in the agent notes. The SMSs were in the form of reminders or requests to confirm that payment was made. The table also demonstrates that often an SMS was sent even after the Applicant had already made the monthly payment due under the repayment arrangement. Repayment arrangement of $375 per month due on 15 th of each month Date payment of $375 due Date payment of $375 or more actually made Date SMSs sent 15 October 2014 15 October 2014 15 October 2014 15 November 2014 17 November 2014 17 November 2014 15 December 2014 15 December 2014 15 December 2014 15 January 2015 14 January 2015 15 January 2015 15 February 2015 16 February 2015 No SMS 15 March 2015 17 March 2015 16 March 2015 and 18 March 2015 Case No: 425044 Determination Page 10 of 12 Repayment arrangement of $400 per month due on 15 th of each month Date repayment of $400 due Date repayment of $400 actually made Date SMSs sent 15 April 2015 14 April 2015 13 April 2015 15 May 2015 14 May 2015 15 May 2015 15 June 2015 11 June 2015 13 June 2015 15 July 2015 8 July 2015* No SMS * $330 was actually paid on this day. However, at this time the parties were in verbal contact and a new repayment arrangement of $400 on the 8 th of each month was arranged. Repayment arrangement of $400 per month due on 8 th of each month Date repayment of $4 00 due Date repayment of $400 or more actually made * Date SMSs sent 8 August 2015 7 August 2015 6 August 2015 and 10 August 2015 8 September 2015 10 September 2015 6 September 2015, 8 September 2015, 9 September 2015 and 11 September 2015. 8 October 2015 9 October 2015 6 October 2015, 8 October 2015, 10 October 2015 8 November 2015 10 November 2015 6 November 2015 8 December 2015 9 December 2015 7 December 2015, 8 December 2015, 10 December 2015 8 January 2016 12 January 2016 6 January 2016, 8 January 2016, 9 January 2016 8 February 2016 9 February 2016 No SMS * Although payments are sometimes a few days late during t his repayment arrangement, the Applicant ’s salary was going in around the time payment was due, explaining the slight delay. For example, the agent notes of 8 and 12 January 2016 record this difficulty. Case No: 425044 Determination Page 11 of 12 3.5 Contact which breached the weekly debt collection limit The tables below shows that from 7-10 December 2015, the FSP made five collection contacts. From 6-12 January 2016, the FSP also made five collection contacts. These contacts were in the form of payment reminders or requests to confirm that payment was made. This breached the weekly limit of three contacts per week. The information set out below is provided by the agent notes. 7 - 10 December 2015 Event 7 December 2015 SMS sent 8 December 2015 SMS sent 8 December 2015 Email sent 10 December 2015 SMS sent 10 December 2015 Email sent 6 - 12 January 2016 Event 6 January 2016 SMS sent 8 January 2016 SMS sent 8 January 2016 Email sent 9 January 2016 SMS sent 12 January 2016 Email sent 3.6 Total non-financial loss awarded The table below shows the total non-financial loss awarded to the Applicant. It is calculated by adding together the various awards of non-financial loss discussed in the sections immediately above. Category Non - financial loss awarded $ Ending the hardship agreement 1,000 Not meeting IDR obligations 1,000 Excessive/unnec essary SMS contact 1,000 Breaching the weekly collection limit 500 Total $ 3,500 Case No: 425044 Determination Page 12 of 12