Text of the determination
Determination
Case No: 424770 Determination Page 1 of 11
Case number: 424770 1 June 2017
1 Overview
1.1 Dispute
The applicants made a claim under their home building insurance policy with the
financial services provider (FSP) after a hot water pipe burst under the kitchen floor.
Investigations showed there had been an on-going leak for some time, causing a
large volume of water to pool beneath the house, and mould to grow.
The FSP accepted the claim and originally intended to complete the repairs.
However, after stripping the property in preparation for mould remediation, serious
pre-existing drainage and ventilation problems were discovered, which had caused
significant damage to the site. Because it could not guarantee the repairs until those
issues were remedied, the FSP decided to cash settle the claim instead.
The FSP ’s cash settlement was $87,638.35 for the internal building work, based on
their builder’s quote . It also paid $32,713.59 for other repairs and miscellaneous
expenses, $24,520 for mould removal, as well as the costs of temporary
accommodation.
The applicants are unhappy with the amount paid. To settle the dispute, they want
$80,189.45 (which is the difference between the FSP’s cash settlement amount of
$87,638.35 for the internal work, and their estimate of $167,827.80). They also
believe they should receive interest on that amount and on all other amounts paid by
the FSP, together with compensation for the way in which the FSP has handled the
matter.
1.2 Issues and key findings
Wh at is the extent of the FSP’s liability for the claim?
There is significant repair work required to the property; but not all of it is for damage
which was caused by the insured event of the burst water pipe. The FSP is only
liable for the costs of repairing damage arising from an insured event.
Is the FSP entitled to cash settle the claim?
The policy gives the FSP the option of repairing the damage or paying what it would
cost the FSP to repair or rebuild the building. It is fair, in the circumstances, that the
claim be cash settled. However, the FSP must ensure that the settlement amount is
sufficient to allow the applicants to carry out the necessary repairs.
Case No: 424770 Determination Page 2 of 11
Is the FSP required to increase the settlement amount?
The FSP’s cash settlement payment should be increased. That is because it was
effectively based on an ‘insurance only’ quote , and did not take appropriate account
of the likely cost to the applicants, including possible contingencies; nor did it allow
for the fact that the risk of the repairs was passing to the applicants.
Are the applicants entitled to compensation for non-financial loss?
The applicants are entitled to compensation for non- financial loss, because the FSP’s
handling of the claim caused avoidable inconvenience and concern.
1.3 Determination
This determination is in favour of the applicants.
The FSP is required to pay the applicants:
$13,145.76 (being an uplift of 15% on the cash settlement already paid)
interest on that amount calculated from 15 February 2016 to the date of
payment, in accordance with section 57 of the Insurance Contracts Act 1984
$300 compensation for non-financial loss.
Case No: 424770 Determination Page 3 of 11
2 Reasons for determination
I have decided this case on the basis of what I consider fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous FOS decisions.
I have taken into account all the material submitted by the parties. I am satisfied that
the documentation I have relied on has been provided to both parties. For the
purposes of this determination, I will deal with only those points considered relevant.
2.1 FSP’s liability is only for damage arising from insured events
Circumstances of loss
The applicants made the claim after a hot water pipe burst underneath the kitchen
floorboards of their house. Their plumber stopped the water flow, but found that the
pipe had been leaking for a long time, causing steaming under the house and water
to pool there.
The FSP accepted the claim. It arranged for the kitchen and other cabinets,
floorboards and some wall panels to be removed to allow for investigation of the
water and mould damage, and in preparation for repairs and remediation.
Because of the mould, and removal of the kitchen, the FSP also agreed to pay for
temporary accommodation for the applicants and their family.
Meanwhile, the FSP’s engineer found other ‘maintenance issues’ and drainage and
ventilation defects in the property which it said needed to be repaired before it could
deal with the claim-related work.
So the FSP decided to cash settle the claim, rather than attending to the claim-
related repairs itself. It explained this was because of the number of other issues at
the property, which meant it would be unable to provide a lifetime guarantee on the
repairs it was responsible for.
Policy covers damage caused by water leaking or bursting from drains
The FSP is responsible under the policy for loss or damage to the building caused by
liquid leaking, overflowing or bursting from ‘any drain, fixed pipes…rainwater
downpipes, drainage and sewage systems…’ .
The FSP accepts the claim arose from that insured event, and so is covering damage
attributable to the burst hot water pipe.
Additional damage arose from maintenance issues and unknown defects
T he FSP’s e xpert reports indicate that additional damage identified after work on the
site commenced was not caused by the insured event. Instead, it was the combined
result of certain maintenance issues (roots blocking the storm water and sewer lines,
a downpipe allowing water to fall directly to the ground) and pre-existing defects in
the drainage and ventilation (the subfloor level sitting below the external soil level,
Case No: 424770 Determination Page 4 of 11
allowing water to track below the subfloor). That had led to water pooling in the
subsoil of the property and associated ground movement.
The defective drainage and ventilation was not itself damaged as a result of the
insured event (the burst pipe); nor has it been shown that those pre-existing
maintenance issues and defects caused the pipe to burst in the first place.
However, the evidence suggests the possibility of some overlap in damage to some
areas from the insured event and the drainage/ventilation issues. So while the FSP
is not strictly required to pay for the additional damage identified, it has paid for
repairs to the external paving, French doors and for re-stumping, which is fair under
the circumstances.
2.2 FSP is entitled to cash settle the claim
The applicants’ policy commenced in August 2014 and renews annually. It provides
building risk with complete replacement cover, and a contents risk for a specified
sum insured.
Additional benefits under the policy include temporary accommodation costs when
the home cannot be lived in, for the time it takes to repair or rebuild the building to a
liveable condition, for up to 52 weeks.
The policy provides that where the FSP agrees to pay the claim, it may decide
whether to repair or replace the damaged property or pay the amount it would cost
the FSP to repair or replace the property to ‘as new’ condition.
Although it initially intended to undertake the repairs, it is not unreasonable the FSP
decided to cash settle after preparatory work revealed other extensive issues not
attributable to the claim.
2.3 FSP should increase the cash settlement amount
Cash settlement did not take appropriate account of relevant factors
Where the FSP decides to cash settle a claim, it must ensure that it takes all
reasonable factors into account, including the nature of the work required, whether a
cash settlement would enable the applicants to complete all necessary repairs, and
making some allowance for contingencies and necessary variations.
As well, it is important to acknowledge that in making a cash settlement, the risk
associated with the repairs transfers from the FSP to the applicants.
The cash settlement should also provide for any additional benefits which are
payable under the policy (such as temporary accommodation costs), if they have not
otherwise been paid.
Scope of works and costs for internal repairs
The FSP and applicants broadly agreed the scope of works for the internal damage
and obtained quotes for the repair costs, for which the FSP is responsible under the
Case No: 424770 Determination Page 5 of 11
policy. However, the remaining point of contention in this dispute is the quantum of
those costs.
The FSP made an offer and payment based on the quote from AB, one of the two
builders it consulted. However, the quotes were obtained after the FSP had decided
to cash settle, and can reasonably be regarded as being for ‘insurance only’
purposes – that is, there is no suggestion that the builders were quoting on the basis
that they might be doing the work themselves for the applicants as retail consumers;
nor indeed that they would be doing any actual building work for the FSP. Instead,
the evidence indicates the quotes were prepared specifically for the purposes of the
anticipated cash settlement.
The applicants have repeatedly raised the understandable concern that those quotes
reflected trade prices which were not accessible to them in the open marketplace.
The applicants ’ own quotes identify a significantly higher amount for the internal
repair work.
In response to the applicants ’ concerns, the FSP did eventually confirm that AB were
prepared to do the work for the cash settlement amount of $87,638.35 (plus
$8,970.28 for other work – architraves and re-stumping of kitchen/dining/family
rooms – which was in line with a quote obtained by the applicants).
However, it has not been shown that this was ever communicated to the a pplicants,
or if it was , whether that was before February 2016 when they commenced the work
with their own builders (and by which time the FSP had paid them the $87,638.35, on
the basis that they would be arranging for the repairs themselves) .
Nor is it clear from AB ’s later letter, dated 31 March 2016, that AB were actually
prepared to undertake the works privately for the applicants, at the price quoted,
rather than for the FSP. The letter just confirms that AB ‘are able to complete the
repairs’ as per the scope of works previously submitted, and the quote for the other
architrave/re-stumping work. AB ’s letter also notes that ‘we have not allowed for any
unforeseen damages [sic]’; and I consider it fair that any cash settlement should
include some allowance for contingencies.
Under the circumstances, I am not persuaded that the amount paid on the basis of
AB ’s quote represents a fair estimate of the reasonable cost of completing the
necessary repairs.
Applicants have incurred costs greater than the cash settlement amount
The applicants have said that as at May 2016 they had already paid $111,956 for
internal repairs, with several items still to be invoiced.
It is worth noting that:
included in that amount are replacement kitchen fittings (gas cook top, sink,
mixer tap costing $2,621) which the FSP was not required to pay for, as they
represent upgrades
the applicants have not provided invoices or evidence of other additional work
completed since May 2016, so it is unclear what they have actually spent on the
repair work, and to what extent any of those further costs might relate to
variations over and above the original scope of works or quotes. Some of the
Case No: 424770 Determination Page 6 of 11
quotes that have been provided, while not specific as to the actual work
involved, do refer to ‘variations and additional works’. Again, if those
represented upgrades, rather than repair or replacement, then they would not
be the responsibility of the FSP in any case
invoices that have been provided also indicate that the applicants have used
the builder who gave the lower of the 2 quotes they obtained, although the
calculation of the difference they claim from the FSP appears to be based on
the other higher quote
the applicants have said that certain items included in one of their quotes and in
the calculation of the amount they claim (for the built-in seating and
entertainment units at a cost of $34,900 ) were not repaired or replaced, but that
they chose instead to alter a second set of French doors into a window. It is not
clear what that cost was.
The applicants believe that the settlement to which they are entitled is not what they
actually spend on the work, but rather what the cost of reinstatement is for the
damaged property in accordance with the quotes they provided. While I am not
satisfied that the FSP’s cash settlement amount of $87,638.35 adequately reflects a
reasonable cost to repair the claim- related damage to the applicant’s property, that
does not necessarily mean that it could not be done for less than the ap plicants’
builders’ quotes , or the applicants’ own overall estimate of $167,827.80 .
The fundamental purpose of a policy of insurance is to indemnify the insured for loss
or damage caused by an insured event. So here the FSP’s obligation is to
appropriately indemnify the applicants by putting them, as far as possible, back in the
position they were in before the damage occurred, in accordance with the policy
terms and conditions. That does not include allowances for betterment or
improvements; and it does not require that the amount payable should strictly be
what the applicants’ higher quote identified (particularly when the available
information suggests that was not fully utilised).
Under the circumstances, I consider it fair and reasonable that the cash settlement
amount should be increased by 1 5% , and that interest be paid on that additional 15%
at the statutory rate, since the applicants have been without those funds during the
period they have been dealing with the repairs.
The applicants are entitled to temporary accommodation and other costs
The applicants are entitled, under the policy, to reasonable temporary
accommodation costs for the time taken to repair or rebuild the building to a liveable
condition, for up to 52 weeks. They claimed the cost of temporary accommodation
which they say they needed to use for the period from about 10 July 2015 to 29 April
2016. They have confirmed the FSP has paid the costs, and that is not now in
dispute.
The FSP has also already paid other miscellaneous costs arising from the need for
the applicants to vacate the house for the period of repairs. These include removalist
fees, mail re-direction and cleaning costs. I consider that fair, and I understand that
was also acceptable to the applicants.
Case No: 424770 Determination Page 7 of 11
While I appreciate the applicants may not always have received immediate payment
or reimbursement of the various costs incurred, I do not consider it reasonably
necessary under the circumstances for the FSP to pay interest on other amounts,
apart from the uplift to the cash settlement figure itself.
2.4 The applicants are entitled to compensation for non-financial loss
Paragraph 9.3 of our Terms of Reference provides that FOS can award up to $3,000
by way of compensation for non-financial loss. This is for situations where an
applicant has incurred an unusual degree of physical inconvenience or time taken to
resolve the situation or interference with their expectation of enjoyment or peace of
mind.
In determining whether to award compensation for non-financial loss, we take a
conservative approach, and acknowledge that in any claim there will be a degree of
inconvenience to be expected as a normal part of dealing with the incident itself.
Here, while the matter has taken some time, and the claim could have been
progressed more efficiently and smoothly, I am not persuaded that the FSP is
responsible for undue delays overall . I appreciate that the FSP’s cash settlement
amount was not paid until several months after it had the reports and quotes on
which it then acted. However, given the time of year and difficulty the applicants
themselves have acknowledged in finding tradespeople ready to undertake the work,
the potential impact of that particular delay will have been reduced. In any case, the
FSP’s expert did recommend that the sub-floor be allowed to dry for two seasons
before works commenced, but the applicants made the decision to proceed sooner.
The fact, also, that significant problems were identified after preliminar y work began
at the property, necessarily meant other investigations and assessments had to be
carried out and the results reviewed. The FSP cannot reasonably be held responsible
for those issues or the resulting delays.
The FSP has, however, acknowledged that the applicants had to make several
requests for responses on certain questions they had about the claim (including
about whether or not the maintenance issues would be covered); and the applicants
also expressed dissatisfaction about the possible bias of one of the FSP’s assessors.
I appreciate these issues will have exacerbated an already difficult time for the
applicants, but I do not consider they warrant compensation in this case; nor am I
persuaded that the FSP has breached its obligations of good faith in the handling of
the claim.
Where I do consider the FSP’s actions do warrant compensation, is in the way it
arrived at and handled the cash settlement amount and payment, and the avoidable
concern, upset and uncertainty this has caused the applicants. I consider $300
compensation is fair in the circumstances.
Case No: 424770 Determination Page 8 of 11
3 Supporting information
3.1 Experts’ reports
Record Key points
FSP’s expert ( S )
Report and scope of
works
September 2015
b uilding defect: non - compliance with Building Code of
Australi a 1990 re drainage, ventilation and sub - floor
level
m aintenance - related issue: severely corroded metal
downpipes (below the paving level) causing water to
escape into sub - floor area .
FSP’s expert (ALD)
Report
30 September 2015
downpipe to the front right corner of the house falls to
the ground
root intrusion in stormwater line and sewer line
sub - floor soil level sits lower than the soil level external
to the house
water was tracking below sub floor and unable to
escape contributing to the saturated soil below the sub
floor.
FSP ’s expert ( FM )
Engineering
Investigation Report
15 October 2015
observed water ponding throughout sub floor
claimed leak in supply line contributed to water in
vicinity of kitchen
abnormal soil conditions (soil saturation) caused
differential movement of stumps
debris in drains and roots in stormwater and sewer line
general construction of subfloor and subfloor ventilation
do not meet requirements of National Construction
Code 2015 .
FSP ’s expert (FM )
Supplementary report 1
29 January 2016
in FM’s opinion, damage to the French doors, external
pavers, and stumps (and the need to re - stump), was not
from the insured water leak
under normal moisture conditions the footings would
perform well
the damage was caused by long term water ingress into
the subfloor from external sources identified in previous
report , and associated ground movement
likely non - compliance of subfloor and ventilation with
Building Code of Australia 1990
Case No: 424770 Determination Page 9 of 11
3.2 Product disclosure statement
Page Extract
22 Escape of liquid
We cover
Loss or damage to the building caused by liquid leaking,
overflowing or bursting from any of the following: …
any drain, fixed pipes, roof gutters or guttering and
rainwater downpipes , drainage and sewage
systems;…
We do not cover
…
loss or damage caused by wear, tear, rust, fading,
rising damp, mould, mildew, corrosion, rot.
Exploratory costs
We will pay the reasonable cost of locating, at the insured
address, the source of the escaped liquid and to repair
and restore the damage to the b uilding caused by our
exploratory work but only if the escape of liquid is covered
under this insured event.
28 Temporary accommodation
When an insured event damages the building to the extent
you cannot live there, and we agree, we will pay for your
reas onable temporary accommodation costs for the time it
will take to repair or rebuild the building to a liveable
condition. The most we will pay is:
up to 4 weeks in short term accommodation agreed
by us…
up to another 48 weeks in residential
accommodation o f a similar standard to the
building.
We will also pay for the reasonable and necessary costs
for:
redirection of mail from the insured address for up to
52 weeks;
utility connection costs at the temporary
accommodation residence;…
Case No: 424770 Determination Page 10 of 11
Limit
The most we will pay for any one event is 10% of the
building sum insured…
45 How we settle building claims
If we agree to pay a claim for loss, theft or damage to the
building, we will decide if we will:
repair damage to the building;
rebuild the building;
pay you what it would cost us to repair or rebuild the
building;
…
If we repair (or pay you what it would cost us to repair), we
will at our option do so on a ‘new for old’ basis or repair to
a similar condition to what the building was in before the
loss or damage occ urred.
We will not:
p ay more tha n the relevant sum insured…or policy
limit;
p ay extra to repair or rebuild the building to a better
standard, specification or quality than it was before
the loss or damage occurred … ;
f ix a fault that existed before the loss or damage
occurred.
49 Dealing with defects
If an unknown defect is the cause o f the damage
If an incident covered by your policy damages the building
and an unknown defect was the cause or part of the
cause, we will pay for the resulting damage. If the
unknown defective part of the building is also damaged by
the same incident, we will fix this as well.
Case No: 424770 Determination Page 11 of 11
50 Lifetime guarantee on building repairs
When we repair or rebuild the building, we guarantee the
quality of materials and workmanship of that work for the
lifetime of the building if we:
authorise;
arrange; and
pay the builder or repairer directly for this work.
What we guarantee
We guarantee the material used and standard of the
workmanship to be free of defects. If a defect arises in the
lifetime of t he building as a result of poor quality
workmanship or use of incorrect materials, then we will
rectify the problem. It is a condition of our guarantee that
we reserve the right to decide w ho will undertake the
rectification work.
This guarantee does not apply:
to repairs you authorise or make yourself; …
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.