Storm damage claim to roof and box gutter partly declined, internal water and mould damage, claims handling delay
Text of the determination
Determination
Case No: 424326 Determination Page 1 of 11
Case number: 424326 25 November 2016
1 Overview
1.1 Dispute
The applicant’s property was damaged during a storm event in April 2015. A claim
was lodged with the financial services provider (FSP). Following assessment the FSP
accepted part of the claim. The FSP declined cover for the applicant’s roof.
The applicant disputes the FSP’s decision, and seeks to have the roof repaired, as
well as the resultant damage. He criticis es the FSP’s claims handling and seeks
compensation.
The case manager provided the parties with a recommendation on the issues in
dispute. The recommendation was substantially in favour of the applicant.
The FSP accepted the recommendation but it was not accepted by the applicant as
he still required payment for the roof.
In the circumstances, the dispute has been referred to me for determination .
1.2 Issues and key findings
Was the FSP entitled to decline cover for the roof?
The material establishes maintenance and design issues with the roof not related to
the storm event at all. But the material provided also establishes on the balance of
probabilities the box gutter was damaged in the storm when rainwater pooled in the
gutter and penetrated through the sealant applied to the joins in the gutter
necessitating the replacement of the gutter. As the material establishes the box
gutter was already rusty, a fair outcome is the FSP pay to the applicant 50% of the
cost of replacing the box gutter with a new colour bond box gutter.
Is the FSP required to cover additional internal damages?
The material provided establishes on the balance of probabilities internal damage
was caused by a storm created opening when rainwater pooled in the gutter and
penetrated through the sealant applied to the joins in the gutter. Further, the material
establishes some damage was caused to the box gutter in the storm yet the FSP
refused to accept liability which resulted in further internal damage including mould
for which the FSP is liable.
Is the applicant entitled to compensation?
The applicant is entitled to compensation as the material establishes the FSP’s
claims handling caused delay in resolving the situation and delay has caused mould
Case No: 424326 Determination Page 2 of 11
damage. As the FSP’s delay and claims handling interfered with the applicant’s
expectation of enjoyment or peace of mind, the applicant is entitled to compensation.
1.3 Determination
This determination is substantially in favour of the applicant.
Upon acceptance of this determination by the applicant, the FSP is to pay to the
applicant $1,000 compensation.
Within 14 days of acceptance of this determination by the applicant, the parties are to
approach the make safe operator (BW) (and if he is unwilling, they are to approach
another agreed expert roofer) to provide a new quote to replace the box gutter with a
new colour bond box gutter. Thereupon, the FSP is to pay the applicant 50% of the
cost to repair the box gutter.
Also within 14 days of accep tance of this determination by the applicant, at the FSP’s
cost, the FSP is prepare and cost a scope of works for the additional internal damage
(including mould remediation works) and then is to elect whether it will repair the
additional internal damage as new or pay the applicant the cost of repairing the said
damage.
Case No: 424326 Determination Page 3 of 11
2 Reasons for decision
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
recommendation. I am satisfied the documentation I have relied on has been
provided to both parties.
New material provided after the recommendation
The FSP accepted the recommendation. The FSP said it would work with the
applicant to prepare a scope of works for the outstanding internal damage save that it
cannot disturb the asbestos roof.
The applicant consulted with his builder about the recommendation. The builder
advised the applicant if the cost of repairs to the roof were removed, the repairs
would cost $8,000. The applicant was willing to finalise the dispute for $8,000.
The FSP did not accept the offer of $8,000. Pursuant to the recommendation, it
wanted to arrange a further assessment of the damage to the property. A further
scope of works would then be prepared to enable settlement.
The applicant made further submissions in which he essentially reiterated his position
regarding the claim for damage to the roof and internal damage particularly mould
damage as the roof had not been repaired.
The FSP responded and the parties provided further material after the
recommendation which will be referred to where relevant in the determination.
2.1 Was the FSP entitled to decline cover for the roof?
Applicant must establish damage to roof caused by storm
The applicant must show on the balance of probabilities he has suffered a loss
caused by an event to which the policy responds. This is known as a prima facie
claim.
The FSP’s policy covers the applicant for loss or damage to the building or contents
caused by storm, rainwater and flood.
The FSP did not dispute the applicant’s property sustained water damage in the
storm event in April 2015. In September 2015, the FSP cash settled the applicant for
damage to contents, tree removal and some internal damage as well.
The dispute relates to the damage to the roof. The applicant contends the roof was
damaged in the storm. The FSP has declined to pay to repair the roof. It argues there
was no insurable damage and no storm created opening in the roof. It relies on policy
exclusions including inherent defects, structural defaults and poor maintenance.
Case No: 424326 Determination Page 4 of 11
Material from applicant establishes box gutter damaged in storm
The applicant purchased the property in February 2014. He says neither he nor the
previous owner had any leaks until the storm event which occurred in April 2015. The
previous owners confirmed they had no leaks in the roof.
Before purchasing the property, the applicant arranged an inspection report which
confirmed the building was in above average condition and the roof, plumbing and
flashings were in acceptable condition. This is supported by photographs of the
home. However, the report makes the point there was actually no inspection of the
roof externally due to the roof being over 3.6m in height.
Shortly after the storm, the applicant engaged SL to assist with the storm damage
and debris. SL inspected the roof. After the recommendation, the applicant provided
an email from SL who wrote:
“When I inspected the roof the debris and damage was very evident, the roof had
sustained damage and so did a few solar panels. The obvious issue was a large
amount of tree debris from not only (the applicant’s) place bu t from the park across the
road.
What was evident was the amount of branches, leaves and twigs that had been
washed into the middle of the roof due to it being a "Butterfly Roof", this obviously
caused several blockages and hindered the box gutter doing what was required and
that is to remove excess water ASAP.”
SL also reported both the exterior colour bond roof and the asbestos roof beneath
were in good working condition. He also said although it seems some pipes/vents on
the roof are missing some cupping, on closer inspection, the asbestos roof provided
cover and protection.
He concluded:
“In my opinion the only reason (the applicant) has had internal and external damage is
solely due to the ferocious condition we all experienced in April 2015.”
The applicant also relies on BW who was engaged by the FSP to make the roof safe.
BW attended the property in July 2015. The applicant relies on a report and quotation
from BW. In addition, after the recommendation, the applicant provided to FOS an
email from BW dated 11 October 2015.
In the email, although BW acknowledges the top roof has been installed at an
insufficient pitch, he says it has been installed over the top of:
“existing super six asbestos roof sheets that are still intact, structurally sound and are
perfectly capable of preventing water from entering the b uilding.”
BW says he inspected the whole roof thoroughly at the time of his inspection in July
2015 in order to determine where the water entered the building. He concluded:
“….water was getting into the building through the box gutter joins only. There i s also
pipes that have no protective boots to prevent water entering the lower roof. It should
be sealed I do agree. But the roof below has no defects that will allow water to
penetrate the building. I would advise that protective boots are to be installed as a
preventive. As it has no impact towards further damage if they are not. There is rust
present in the gutters but has no bearing factor in the failure of the gutter. The rust has
to be addressed to prolong the life of the gutter.”
Case No: 424326 Determination Page 5 of 11
Neither BW’s repor t nor quotation discusses how the box gutter was damaged in the
storm. However after the recommendation, the FSP’s assessor spoke further with
BW and relayed the conversation to the FSP in an email dated 1 November 2016.
Further clarification is provided. It is reported BW said:
“….it appeared rainwater pooling in the gutter may have penetrated through the sealant
applied to the joins in the gutter.”
It is reported BW suspected there were pre -existing splits in the sealant but as there
had been no leaks prior to the storm event, BW said the splits had likely
increased/worsened as a direct result of the weight/volume of water which pooled
inside the gutter during the storm event.
The email identifies other reasons why water entered the building. BW is reported to
have said it was due to the box gutter being able to unable to cope with the volume of
rain experienced due to a combination of a number of factors, including not only the
split sealant applied to the joins in the box gutter, but also:
significant amount of leaf debris/branches blocking the downpipe supporting the
box gutter
the box gutter did not have adequate overflow slots
the box gutter needed larger profile/depth
BW identified surface rust to the gutter but his email makes it clear this was not t he
reason why water entered the building. The assessor says BW told him, unless the
guttering was actually physically removed and inspected, he could not definitely
confirm his findings regarding the cause of ingress. However, BW does not make this
comment in his written report or email.
Although the assessor says he does not agree with BW’s suggestion the water
pooling in the gutter damaged the sealant, I do not find this statement compelling in
view of the fact BW has inspected the whole roof thoroughly.
Further, if there was significant leaf debris and branches blocking the downpipe, it is
clear from the contemporaneous evidence of SL the debris was as a result of the
storm event. I am satisfied this, together with the rainwater pooling in the gutter
during the storm event was the proximate cause of the sealant splitting and
establishes on the balance of probabilities damage to the box gutter was caused by
the insured event of storm and rainwater.
Therefore, I am satisfied the applicant has established a prima facie claim.
Storm policy exclusion not relevant to the damage to the roof
Once so established, the onus shifts to the FSP to prove on the balance of
probabilities an exclusion applies if it seeks to deny or limit its liability for the loss.
The FSP relies on three policy exclusions.
The FSP says it is not obliged to pay for loss or damage to the roof as the damage
has not occurred as a result of an opening made by storm. The policy exclusion is
irrelevant to this issue as the exclusion relates to loss or damage to the interior of the
building or to the contents. It does not apply to loss or damage to the exterior of the
building.
Case No: 424326 Determination Page 6 of 11
Furthermore, on the material provided, I am satisfied an opening in the roof occurred
because of the storm and so the FSP is liable to pay for loss and damage to the
interior of the building and to contents. I note the FSP has made some payments
already for contents and internal damage.
Dektites unrelated to claim
The FSP relies on two further policy exclusions. It says it is not liable to pay for
damage to the roof as the damage was caused by or resulted from inherent defects,
structural faults and poor maintenance.
The FSP relies on material from its assessor and its roofer. It says the precise point
of water ingress cannot be answered unless the entire colour bond roof is removed.
Nonetheless, it suggests the main reason water entered the building was through the
penetrations which lacked the necessary dektites. It also attributes water ingress to
blocked downpipes which caused water to overflow into the roof cavity. And it argued
it was possible rust holes in the box gutter or seals at the joints failed leading to more
water ingress.
However, the FSP does not take into account all expert opinion. Even its own expert
assessor was unsure about causation and says about the dektites:
“….while unrelated to the claimed event and not a requirement to be completed prior to
insurable repairs, we recommend the insured engage a qualified roofer install
appropriate dektite’s to roof penetrations (sic).”
As set out above, this view is confirmed by BW in his email to the applicant dated
11 October 2015 and by SL in his recent email to the applicant.
Although the FSP’s roofer identified the two penetrations which did not have dektites
over them which he said allowed water ingress on the asbestos roof below, while I
accept this as a maintenance issue rather than storm damage, I do not accept the
absence of dektites caused damage in the building in view of the assessor’s opinion
and in view of both SL and BW’s opinions the asbestos roof below was sound and
did not allow water ingress.
Internal damage not caused by rusted gutter
The roofer concedes the roof installed over the asbestos roof was in good condition.
Even if it was accepted the new roof was the wrong profile for the roof pitch or not
installed to standard, the roofer does not say this caused water to enter the building.
In view of BW’s definite opinion about the rust, the roofer’s opinion is insufficiently
compelling to establish on the balance of probabilities the damage in the building was
caused by rust in the gutter.
Water entered building through box gutter joins damaged in storm
The roofer posits it is possible the seal at the joins may have failed but says he
cannot determine this without lifting the colour bond roof. In any event, BW already
concluded the reason water entered the building was because of this failure.
Nowhere in his written opinions does BW say he cannot attribute the cause of
damage without lifting the colour bond roof.
Case No: 424326 Determination Page 7 of 11
Finally, the roofer viewed the roof after the debris had been removed. Therefore he
could not say if the downpipes were blocked causing the box gutter to fill and
overflow into the roof cavity. In any event, as set out earlier in this determination,
having considered the contemporaneous evidence of SL, I accept the downpipes
were blocked because of debris which washed onto the roof in the storm.
As for the recent suggestion BW also attributed the cause of damage to the fact the
box gutter did not have adequate overflow slots and the box gutter needed larger
profile or depth, in the absence of statement from BW himself, I do not find this
sufficiently compelling to override his written opinion about the cause of damage as
set out in his report to the FSP dated 20 July 2015 and his email to the applicant
dated 11 October 2015. In both written opinions it is clear BW concluded the water
was getting into the building through the box gutter joins only.
Box gutter was damaged in the storm but also had pre-existing damage (rust)
Having reviewed all the expert opinion provided both before and after the
recommendation, and the photographs of the roof, any issues with the pitch of the
roof, the installation of the colour bond roof sheets over the asbestos roof, and the
need for dektites are not storm damage and are not the responsibility of the FSP.
However, I accept the box gutter was damaged in the storm as described by BW and
requires replacement. But, I also accept the box gutter had surface rust.
BW provided a quote on 19 October 2015 to replace the box gutter with a new colour
bond box gutter. However, the quote is over a year old, and the quote is not itemised.
Within 14 days of acceptance of this determination by the applicant, the parties are to
approach BW (and if he is unwilling, they are to approach another agreed expert
roofer) to provide a new quote to replace the box gutter with a new colour bond box
gutter.
Fair the FSP pay 50% of the cost to replace the box gutter
As the box gutter was already rusty (not storm damage) and as I accept some
damage to the box gutter was caused in the storm, I am satisfied it is fair in the
circumstances the FSP pay to the applicant 50% of the cost to replace the box gutter
with a new colour bond box gutter.
FSP is also to pay for additional internal damage including mould
As for additional internal damage, the material establishes:
the FSP has already made some payments to the applicant for damage to the
inside of the building and contents
as the FSP refused to accept liability for storm damage to the roof, the roof
continued to leak and caused further internal damage
photographs show not only is there is water damage in bedroom 1 (the son’s
room) but in two other bedrooms
photographs also show there is now mould damage
BW’s quote indicates insulation should be removed as it may be a mould hazard
Case No: 424326 Determination Page 8 of 11
FSP to prepare and cost scope of works
At the FSP’s cost, the FSP is prepare and cost a scope of works for this additional
damage which is also to include mould remediation works.
The FSP’s policy says if it accepts a claim it can decide whether it will repair the
building as new or pay the cost of repairing it at its discretion. The FSP is to make the
election upon receipt of the scope of works.
If it elects to cash settle, it remains necessary for the amount of the cash settlement
to be agreed, based on the scope of works to be prepared by the FSP. The scope of
works and cash settlement will take into account the building works already accepted
and paid by the FSP.
FOS encourages the parties to this dispute to resolve any issues which might arise
during that process. However, the parties can return to FOS if they are unable to
resolve any issues arising from the scope of works a nd/or the costing of that work.
2.2 Is the applicant entitled to compensation?
Compensation paid in some circumstances
FOS’s Terms of Reference allow the payment of compensation (capped at $3,000)
for non-financial loss. FOS may decide an FSP should compensate an applicant for
such loss only where there has been an unusual amount of physical inconvenience,
time taken to resolve a situation, or interference with the applicant’s expectation of
enjoyment or peace of mind.
FOS takes a conservative approach to compensation for non-financial loss.
When the applicant brought his dispute to FOS he said there was black mould in his
son’s room and his son had been unable to sleep there for some six months. He also
complained water marks had developed in two other bedrooms.
He said nobody seems to care about it or our health and he was “stressed to the max
and actually hated living in my new home.”
The FSP briefly addressed compensation in its notice of response. It said no
compensation payment would be forthcoming as it had acted fairly and
comprehensively when dealing with the dispute.
Fair the FSP pay $1,000 compensation to the applicant
The material provided shows the applicant has been complaining about the mould
damage for over a year. At about this time, he also expressed concerns further water
damage was occurring in other rooms.
In September 2015 and January 2016, some payments were made to the applicant
for damage to contents, the building and tree removal.
Some of the material relied on in this determination was provided by the applicant
recently. However, in its decision making, the FSP relied mainly on its roofer and
assessor without giving due consideration to BW’s view.
Case No: 424326 Determination Page 9 of 11
In all the circumstances, I consider the FSP’ s claims handling has caused delay in
resolving the situation. Further, the material establishes delay has caused mould
damage. I accept the FSP’s delay and claims handling has interfered with the
applicant’s expectation of enjoyment or peace of mind.
Therefore I am satisfied it is fair in all the circumstances the FSP pay to the applicant
$1,000 compensation.
Case No: 424326 Determination Page 10 of 11
3 Reasons for determination
3.1 FOS Approach
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All of the material provided by the parties has been reviewed and
considered for the purposes of this determination.
This dispute has been decided on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
It is an accepted principle of general insurance law that an insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie claim. Once so
established, the onus shifts to the insurer to prove on the balance of probabilities that
an exclusion applies if it seeks to deny or limit its liability for the loss.
3.2 Relevant policy extracts
The relevant policy extracts are referred to in the FSP’s Notice of Response dated 5
February 2016. Both the policy document and the Notice have been exchanged with
the applicant.
Insured Event – You are
covered for loss or damage
to your building or contents
(as applicable) caused by
Exclusions to Insured Events (see also What is not
covered under your policy, pages 26 – 27) – You are
not covered for
Storm, rainwater and Flood Loss or damage:
…
To the interior of your building or to your contents if the
damage or loss has not occurred as a result of an
opening made by the Storm
What is not covered under your policy
Exclusions
The following general exclusions apply to all covers under your policy.
You are not covered for any loss or damage caused by or resulting from, or the
costs incurred from or of:
inherent defects, structural faults, faulty workmanship or faulty design;
poor maintenance and failure to maintain the property in good repair;
Case No: 424326 Determination Page 11 of 11
3.3 Other relevant material considered and relied on
Parties’ various submissions, emails and photographs
Correspondence between the parties
Pre-purchase inspection report
FSP’s assessor’s report dated 18 May 2015
BW’s report dated 20 July 2015
FSP’s roofer’s report dated 6 August 2015
Email from BW dated 11 October 2015
BW’s quote dated 19 October 2015
Email from vendor to applicant dated 20 April 2016
Email from SL to applicant dated 14 July 2016
Email from FSP’s assessor to FSP dated 1 November 2016
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.