Home / Financial Firm (Unknown - Insurer) / Determination 424232

Determination 424232

Quality of replacement solar system and alleged roof damage by FSP contractor

FirmFinancial Firm (Unknown - Insurer)
Decided2016-05-27
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The FSP replaced storm-damaged solar panels, which were later holed by vermin or birds. The applicant claimed the replacement was inferior and that the FSP's inspecting contractor damaged the roof. AFCA found the bird or vermin damage excluded, the replacement not shown to be inferior, and the roof damage not established.

The policy excludes damage by vermin or birds, and the applicant provided no expert evidence that the replacement system was inferior or that the contractor caused the roof damage.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 424232 Determination Page 1 of 4 Case number: 424232 27 May 2016 1 Overview 1.1 Dispute The applicant’s claim for storm damage to his solar panel system was accepted and replaced by his home insurer, the Financial Services Provider (FSP). The applicant says the replacement is an inferior quality given damage occurred within four months. Therefore, he seeks another replacement unit of a better quality. The applicant also says one of the FSP’s contractors caused damage to his roof when inspecting the system. The FSP says the damage to the new system is due to vermin, is a suitable replacement and that its contractor did not cause damage to the roof. 1.1 Issues and key findings Is the FSP required to replace the solar panel system? The FSP is not required to replace the solar panel system because:  it was damaged by birds and/or vermin which is excluded under the policy, and  the evidence does not demonstrate the replacement system is an inferior quality. Did the FSP damage the roof? The evidence is inconclusive as to whether the roof was damaged by the FSP’s contractor. 1.2 Determination This determination is in favour of the FSP. The FSP is not liable to replace the solar panel system or repair any issues with the roof. Case No: 424232 Determination Page 2 of 4 2 Reasons for determination 2.1 Is the FSP required to replace the solar panel system? Damage caused by an event excluded by the policy There is no dispute the current system has approximately nine holes in it caused by animals, most likely vermin or birds. Whilst the policy covers damage caused by animals, it is subject to the following specific exclusion: “Loss or damage caused by:  …  insects, vermin or rodents …  animals pecking, biting, clawing, scratching, tearing or chewing the building … I am satisfied the loss falls within this exclusion clause. Evidence does not demonstrate replacement system is an inferior quality The applicant does not appear to dispute the cause of damage. Instead, the applicant says the damage supports his concern that the replacement system is an inferior quality and therefore should be replaced. Particularly given the old system had been damage free for seven years and the FSP’s contractor (HP) attempted to provide an inferior controller. The FSP obtained a report from HP regarding the replacement system that said the following of relevance: “1] The new system installed is a Boss Solar PVC Nitrile / modern equivalent, with the same 10 - tube system, the same wall thickness, the same 6mm channel diameter (see brochure and warranty attached). The new system has moulded manifolds with channel locking collars, no rubber grommets, or push in barb connections. It is a multilayer product providing many benefits above the previous system (see brochure). The new product installed is the modern equivalent to the older EPDM matting, which is no longer used due to it decaying on the inside of the water channel from pool chemical break down. The new product has a far more chemical resistant blue layer internally. The existing system was a Standard 10-tube EPDM rubber matting system. The replacement system is the modern equivalent of this system.” The FSP also obtained a second opinion from CP dated 30 December 2015 regarding this issue. CP said: “On inspection I could see where the repairs had been done but I b elieve the damage was done by birds as the absorber is a PVC Nitrile product made by Boss Rubber. Boss Rubber is the leading manufacturer of solar absorber in Victoria. The absorber on the roof is a quality product. (This is the same product that I use as but mine is a Premium PVC Nitrile which is multi layered. This one is not.)” There is no support from these experts that the replaced system was of lesser quality to the old one. In particular, HP’s report sets out relevant identifiable characteristics of the new system compared to the old one that supports its position about its quality. Further, there is no expert opinion to refute HP’s opinion. Nor does any of the information support the conclusion reached by the applicant. HP’s report also addressed th e differences in the controller and why it considered the one provided was a suitable equivalent. This refutes the applicant’s opinion that the Case No: 424232 Determination Page 3 of 4 controller was an inferior quality. In the absence of any contradictory expert evidence, I cannot accept the app licant’s position regarding the controller. Accordingly, after considering all the available evidence, I do not accept it demonstrates the replaced system was an inferior quality. Therefore, I am not satisfied the FSP is required to replace the system. 2.2 Did the FSP damage the roof? Applicant says roof damaged by CP The applicant alleges that CP caused damage to the roof when inspecting the system. CP responded to this allegation in a letter dated 9 November 2015 where it said the following: “I placed the ladder leading to the tin roof area and climbed up onto the tin roof and stepped onto the tile gable and climbed to the top of the gable and took some photos. I then asked my companion to climb up onto the gable and bring the ladder up so he could foot the ladder on the beam of the tin roof so I could get a close photo of the solar going over the ridge of the roof. This was done as the ladder could not be stabilized on the tile roof. AT NO STAGE did we damage the tin roof. Yes we placed the ladder on the beam and it was footed for a whole 30 seconds while I took a photo and that is all. I had asked the client prior to climbing on to the roof if it was alright to get up on the tin roof and he stated that it was. The client was in the rear yard and under the tin roof all the time while I was on the roof at the house.” The FSP subsequently engaged an assessor and builder to inspect the damage. The builder, JP, provided a report that said: … After their attendance the insured observed dents to approximately 3 ro of sheets of the rear pergola. The insured advised that they believed that these were caus ed by the trades whom attended site. Investigation & Cause Upon inspection of the roof sheets we observed damage to three only roof sheets, each of these roof sheets were dented in one place. The damage is consistent with that of impact, however, we are unable to confirm the cause of impact.” The FSP’s assessor was more definitive about his opinion as evident by the following: “Damage to the cladding is not consistent with position that the trade have advised that they have stepped on the Colour bond cladding, damages are spread out over various lengths of the cladding and not in the position the trade has entered the roof to access the tiled gable to walk across.” Evidence is inconclusive In my opinion, the evidence is inconclusive. The applicant and CP both dispute whether the damage was caused by CP. Whilst the applicant noted he had footage of the incident at one point, this is no longer available. There is also no e vidence, such as photographs, of the roof’s pre -existing state to support the applicant’s position. The photographs of the damage do not assist. Whilst it shows there were areas of the roof with obvious indents, these were not within close proximity of each other. Case No: 424232 Determination Page 4 of 4 In particular, the assessor concluded the damage is not consistent with the CP’s conduct when inspecting the roof. I also note JP was unable to determine the likely cause. JP was only prepared to say it was from impact. Given all this, I cannot be satisfied there is sufficient evidence to establish the damage to these roof sheets was caused by CP.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.