Home / Financial Firm (Unknown - Insurer) / Determination 422112

Determination 422112

Method of repair for storm damage to building

FirmFinancial Firm (Unknown - Insurer)
Decided2016-11-21
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss$2,000
Amount claimed—
SourceAFCA PDF

Summary

Applicants with storm-damaged foundations disputed the insurer's chosen repair scope, cash settlement offer and unreimbursed engineering costs. The panel ordered repairs under the original scope 1 with supervision, reimbursement of engineering report costs subject to invoices, and $2,000 non-financial loss.

The insurer's discretion over repairs must be used fairly, and the original engineer's scope was the most effective method of repair.

Issues

Subjects and remedies

home or building damagenatural disasterpay compensationpay non financial lossrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 422112 Determination Page 1 of 9 Case number: 422112 21 October 2016 1 Overview 1.1 Dispute The applicants lodged a claim on their Home and Contents Policy held with the financial services provider (FSP), after the property suffered storm related damage on 25 December 2011. The initial claim was for contents damage. Approximately 12 months later, the applicants lodged, a further claim for damage to the building after noticing cracks develop over the 12 month period since the storm. The FSP accepted liability for the applicants building claim but dispute as arisen as to:  the method of repair  payment of the cost incurred by the applicants during the claims process  compensation for the applicants claims experience. 1.2 Issues and key findings What is the most appropriate scope of works? The Panel is satisfied that the FSP should proceed to complete the repairs to the applicants’ property in accordance with the first scope of works (scope 1) . Are the applicants entitled to payment of costs incurred? The applicants are entitled to payment of the professional costs under paragraph 9.4 of the Terms of Reference of the Financial Ombudsman Service Australia (TOR) for the reports of AC and PTL subject to providing relevant invoices for these reports. Are the applicants entitled to compensation for non-financial loss? The applicants are entitled to compensation of $2,000 pursuant to paragraph 9.3 of the TOR for non-financial loss due to the time taken to resolve this dispute. 1.3 Determination This determination is in favour of the applicants. The FSP is to repair the applicants’ property in accordance with the scope of works provided by IL (scope 1) and contribute to the professional fees incurred by the applicants in obtaining engineering reports and statements from AC and PTL subject to providing the FSP with the invoices for the reports. The FSP is to pay the applicants the sum of $2,000 as compensation for non- financial loss pursuant to paragraph 9.3 of the Terms of Reference, Case No: 422112 Determination Page 2 of 9 Case No: 422112 Determination Page 3 of 9 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the information exchanged. In view of the complexity of the issues in dispute, this matter has been referred to a Panel for determination. The Panel has based this determination on what is fair in all the circumstances having considered all of the information exchanged, the relevant legal principles, terms of the policy, good industry practice, including relevant codes of practice and prior determinations where applicable. 2.1 Scope 1 is the most appropriate scope of works The applicants’ policy is a Home Building and Contents Policy that provides cover for a number of listed events including st orm. There is no dispute that the applicants’ home was damaged during a storm on 25 December 2011. The applicants notified the FSP of having water damage to their contents but no claim was lodged for damage to the home until 27 December 2012. Following investigation of the claim and receipt of report from an engineer IL the FSP accepted that the storm water had inundated the sub floor of the applicants’ home that subsequently led to cracks appearing in the property. The dispute is not as to the cause of damage but as to the scope of works chosen. Engineering and scope of works On 17 January 2013 IL provided a detailed report as to the cause of damage and considered that to obtain a further understanding, geological works were to be undertaken. IL recommended a further inspection of the property after it had been given an opportunity to dry out. On 28 October 2013, JLG were appointed and recommended the use of an engineer. IL attended the applicants’ property on 11 November 2013 and provided a detailed scope of works (scope 1) covering the design, underpinning, removal and replacement of concrete paving, internal repairs and recommending an allowance for additional cosmetic damages that are likely to occur as a result of floor relevelling works. A further report was obtained by the FSP from C. C attended the property on 27 November 2013. C raised concern as to the contribution to the damage that may have been caused by back filled soil within the zone influencing the foundations, and recommended a geotechnical inspection of the property. PG conducted a geotechnical inspection of the property and concluded that the movement observed to the applicants’ property was consistent with the earlier findings by IL and was directly related to the flood (storm) event. Case No: 422112 Determination Page 4 of 9 The Panel accepts the findings of IL and PG with respect to the cause of damage and that the damage to the underpinning was directly related to the storm event of 25 December 2011. IL in a subsequent report of 18 March 2014 confirmed its view that all reported cracking and movement was primarily attributable to the water inundating the subfloor area following the storm event in December 2011. IL recommended that the engineers, building consultants and preferred builders meet to discuss the most appropriate method of repair to allow for an exact scope of works to be compiled. A second scope of works (scope 2) was provided by IL on 3 April 2013. The Panel notes that this refers to scope of works for stage 1. Given the earlier comments of IL, the Panel is concerned whether this scope of works would be adequate to complete the repairs. A third scope of works was provided by PB for the FSP’s builder which is largely consistent with scope of works 1. The Panel notes the FSP claims to have not received this scope of works, although it has been provided in the information exchanged by the applicants. Applicants engineering reports The applicants provided a report from AC who examined the scope of works provided by IL (scope 1 – 4 December 2013); scope 2 (3 April 2014) and the underpinning drawings provided by PB. AC considered that scope of works 2 only partially addressed the problem by choosing to underpin the external walls only. This was inadequate and formed the view that the original scope of works (scope 1) should adequately achieve a suitable outcome. The applicants provided an engineering report from PTL. PTL also examined the scope of works 1, scope of works 2 and the underpinning drawings. PTL considered that the most prudent method of repair was to adopt scope 1 or scope 3. There was also an email from JP dated 18 November 2014. According to JP, the scope of works recommended by IL is an appropriate method. The Panel has considered the various engineering reports and is satisfied based on the information provided that the most effective method of repairing the applicants’ property is to adopt the original scope of works as recommended by IL on 4 December 2013. Terms of policy – settling the claim The applicants’ policy provides that in the event that the F SP agreed to cover a claim for building insurance, it will either:  repair or rebuild that part of your home which has sustained loss or damage or  pay you the cost to repair or rebuilding, whichever is smaller. Should the FSP choose to repair or rebuild the home, it has the discretion to nominate the repairer, supplier or builder. Case No: 422112 Determination Page 5 of 9 Discretion must be used fairly Whilst the Panel accepts that the FSP has a discretion under the terms of the policy, that discretion must be used fairly. In determining whether to exercise the discretion to cash settle the claim, the FSP must take into account all reasonable factors including the nature of the repairs required and whether a cash settlement would adequately ensure the applicants are able to properly complete all repairs. In the Panel’s view, given the information provided and the likelihood of additional expenses being incurred during the repair process as a result of additional damage arising from the repair process, it would be unfair for the FSP to cash settle this dispute unless this was agreed to by the applicants. The applicants and the FSP have obtained a number of quotations. HC has provided two quotations – one for $94,820 involving 29 underpins and a second more consistent with scope 1 for $115,720 involving 41 underpins. There is a further quote from WF for $67,320 that appears to relate to the repairing of damage caused by the settling of the building and any underpinning process. The FSP on the other hand provided a quote from JLG of $88,337.50 based on installing 28 underpins and 12 micro piles. This is not consistent with scope of works 1. Whilst the FSP has indicated it is prepared to repair the property and provide a lifetime guarantee based on the repairs quoted by JLG, it has in the alternative offered to cash settle the applicants’ claim for $88,337.50 in line with the cost of repairs quoted by JLG. At all times, the applicants have been prepared to have the FSP complete the repairs, although the dispute subsequently arose as the applicants were not prepared to allow the FSP’s builder JLG to complete the works as quoted based on Scope 2. The FSP offered in the alternative to cash settle the claim based on the quote from JLG based on Scope 2. As indicated the Panel believes Scope 1 is the appropriate scope of works. If the claim were to be cash settled it would need to be based on Scope 1. FSP must complete the repairs In the Panel’s view, given the uncertainty as to the ultimate cost of repairs, it is fair that the FSP attend to the repairs in accordance with Scope 1. The Panel accepts that the FSP is entitled to appoint its builder to complete these repairs but any repairs should be supervised by a suitably qualified engineer to ensure the repairs are adequately completed in accordance with Scope 1. 2.2 The applicants are entitled to the cost of professional fees The policy provides that the FSP will pay the reasonable cost of locating the cause of damage if it is not known and demolishing and removing any debris. According to the information, the applicants were required to have sections of concrete piles removed in order to excavate the footings. This was required by the FSP’s engineer but the cost incurred by the applicants. Case No: 422112 Determination Page 6 of 9 In the event that the FSP has not reimbursed the applicants for the cost of the removal of sections of the concrete path, the FSP should do so in accordance with the terms and conditions of the policy. Paragraph 9.4 of the Terms of Reference Paragraph 9.4 of the Terms of Reference provides that the Service may determine an FSP contribute to legal or other professional costs incurred by an applicant in the course of a dispute. Unless exceptional circumstances apply, FOS will not require an FSP to contribute more than $3,000 to these costs. The applicants obtained engineering reports, from AC and PTL. Both reports have been exchanged and although brief, both reports support the applicants ’ claim that the preferred scope of works to complete the repairs is either scope 1 or scope 3. When determining whether an FSP should contribute to the payment of professional fees incurred, the Service will take into account the complexity of the dispute, whether the advice was reasonably needed and whether the costs incurred were because the expert advice was genuinely required. In the Panel’s view the applicant s incurred the costs of both engineering reports necessarily to assist in establishing their case. In the circumstances the Panel is satisfied that the FSP should reimburse the applicants for the costs incurred subject to the applicants providing relevant invoices for each report. The applicants are entitled to compensation for non-financial loss. Paragraph 9.3 of the Terms of reference provides that the Service can award up to $3,000 by way of compensation for non-financial loss where an applicant has incurred an unusual degree of physical inconvenience or time taken to resolve the situation or interfere with an applicants ’ expectation of enjoyment of peace of mind. In determining whether to award compensation for non-financial loss the Panel takes a conservative approach and acknowledges that in any claim there will be a degree of inconvenience as a normal part of doing business. The Panel notes the applicants ’ claim for the damage to the building was lodged in December 2012. The applicants provided reasonable access to the FSP to allow for the damage to be assessed. The FSP’s first engineer report from IL is dated 17 January 2013 and recommended further assessment after the property had been given 6 months to dry. The applicants had to contact the FSP on 2 October 2013 to arrange for a further assessment. It was not prompted by the FSP. Due to the FSP’s questioning of IL’s report of the 24 October 2013, further assessments were conducted. It was again confirmed on 22 February 2014 that the damage was directly due to the storm event. The FSP then requested a further report from IL and an amended scope of works. The applicants responded by providing the reports from AC and PTL. Case No: 422112 Determination Page 7 of 9 In the Panel’s view as the FSP had all the reports by December 2014 it would have been reasonable for the FSP to have commenced the repairs in accordance with Scope 1 at that time. The applicants have referred to the considerable stress that the delays and the dispute has caused. They have referred to the time lost i n attending meetings and assessments and looking for alternative accommodation, concrete cutters, builders, draftsmen and the impact that this has had on their health. The Panel accepts that the applicants have experienced an unusual degree of inconvenience and time taken to resolve this dispute which has caused considerable stress and pressure to the applicants. The Panel determines pursuant to paragraph 9.3 of the Terms of Reference that the FSP pay $2,000 to the applicants by way of compensation for non-financial loss. Case No: 422112 Determination Page 8 of 9 3 Supporting information 3.1 FOS Terms of reference 9.3 Other compensation a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for consequential financial loss or damage. Any amount awarded must not exceed the amount specified in Schedule 3. b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for non-financial loss but only where: (i) an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant’s expectation of enjoyment or peace of mind has occurred; or (ii) in the case of a Dispute pertaining to an individual’s privacy rights - injury has occurred to the Applicant’s feelings or humiliation has been suffered by the Applicant. The maximum amount of compensation for non-financial loss will be $3,000 per claim made in the Dispute. c) Notwithstanding paragraphs 9.3 a) and b), FOS will not provide compensation for: (i) consequential financial loss; or (ii) non-financial loss, in a Dispute arising as a result of a claim on a General Insurance Policy that expressly excludes such liability. d) The cap on liability in paragraph 9.3 a) does not in any way restrict FOS’s ability to make an interest award under paragraph 9.5. 9.4 Applicant’s costs in pursuing the matter FOS may decide that the Financial Services Provider contribute to the legal or other professional costs or travel costs incurred by the Applicant in the course of the Dispute. Unless exceptional circumstances apply, FOS will not require the Financial Services Provider to contribute more than $3,000 to these costs. 3.2 Settling claims Settling claims – under buildings If we agree to cover a claim under building insurance, we will:  repair or rebuild that part of your home which sustained loss or damage, or  pay you the cost to repair or rebuild it, whichever is smaller Case No: 422112 Determination Page 9 of 9 However  if we choose to repair or rebuild your home, we can nominate the repairer, supplier or builder

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.