Method of repair for storm damage to building
Summary
Applicants with storm-damaged foundations disputed the insurer's chosen repair scope, cash settlement offer and unreimbursed engineering costs. The panel ordered repairs under the original scope 1 with supervision, reimbursement of engineering report costs subject to invoices, and $2,000 non-financial loss.
The insurer's discretion over repairs must be used fairly, and the original engineer's scope was the most effective method of repair.
Issues
- Repairs or contractors primary · upheld
“the FSP should proceed to complete the repairs to the applicants' property in accordance with the first scope of works (scope 1).”
- Claim amount dispute secondary · upheld
“the FSP should reimburse the applicants for the costs incurred subject to the applicants providing relevant invoices for each report.”
- Delay secondary · upheld
“it would have been reasonable for the FSP to have commenced the repairs in accordance with Scope 1 at that time.”
Subjects and remedies
home or building damagenatural disasterpay compensationpay non financial lossrepair or rectify
Text of the determination
Determination
Case No: 422112 Determination Page 1 of 9
Case number: 422112 21 October 2016
1 Overview
1.1 Dispute
The applicants lodged a claim on their Home and Contents Policy held with the
financial services provider (FSP), after the property suffered storm related damage
on 25 December 2011. The initial claim was for contents damage.
Approximately 12 months later, the applicants lodged, a further claim for damage to
the building after noticing cracks develop over the 12 month period since the storm.
The FSP accepted liability for the applicants building claim but dispute as arisen as
to:
the method of repair
payment of the cost incurred by the applicants during the claims process
compensation for the applicants claims experience.
1.2 Issues and key findings
What is the most appropriate scope of works?
The Panel is satisfied that the FSP should proceed to complete the repairs to the
applicants’ property in accordance with the first scope of works (scope 1) .
Are the applicants entitled to payment of costs incurred?
The applicants are entitled to payment of the professional costs under paragraph 9.4
of the Terms of Reference of the Financial Ombudsman Service Australia (TOR) for
the reports of AC and PTL subject to providing relevant invoices for these reports.
Are the applicants entitled to compensation for non-financial loss?
The applicants are entitled to compensation of $2,000 pursuant to paragraph 9.3 of
the TOR for non-financial loss due to the time taken to resolve this dispute.
1.3 Determination
This determination is in favour of the applicants.
The FSP is to repair the applicants’ property in accordance with the scope of works
provided by IL (scope 1) and contribute to the professional fees incurred by the
applicants in obtaining engineering reports and statements from AC and PTL subject
to providing the FSP with the invoices for the reports.
The FSP is to pay the applicants the sum of $2,000 as compensation for non-
financial loss pursuant to paragraph 9.3 of the Terms of Reference,
Case No: 422112 Determination Page 2 of 9
Case No: 422112 Determination Page 3 of 9
2 Reasons for determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the information
exchanged.
In view of the complexity of the issues in dispute, this matter has been referred to a
Panel for determination.
The Panel has based this determination on what is fair in all the circumstances
having considered all of the information exchanged, the relevant legal principles,
terms of the policy, good industry practice, including relevant codes of practice and
prior determinations where applicable.
2.1 Scope 1 is the most appropriate scope of works
The applicants’ policy is a Home Building and Contents Policy that provides cover for
a number of listed events including st orm. There is no dispute that the applicants’
home was damaged during a storm on 25 December 2011. The applicants notified
the FSP of having water damage to their contents but no claim was lodged for
damage to the home until 27 December 2012.
Following investigation of the claim and receipt of report from an engineer IL the FSP
accepted that the storm water had inundated the sub floor of the applicants’ home
that subsequently led to cracks appearing in the property.
The dispute is not as to the cause of damage but as to the scope of works chosen.
Engineering and scope of works
On 17 January 2013 IL provided a detailed report as to the cause of damage and
considered that to obtain a further understanding, geological works were to be
undertaken. IL recommended a further inspection of the property after it had been
given an opportunity to dry out.
On 28 October 2013, JLG were appointed and recommended the use of an engineer.
IL attended the applicants’ property on 11 November 2013 and provided a detailed
scope of works (scope 1) covering the design, underpinning, removal and
replacement of concrete paving, internal repairs and recommending an allowance for
additional cosmetic damages that are likely to occur as a result of floor relevelling
works.
A further report was obtained by the FSP from C. C attended the property on
27 November 2013. C raised concern as to the contribution to the damage that may
have been caused by back filled soil within the zone influencing the foundations, and
recommended a geotechnical inspection of the property.
PG conducted a geotechnical inspection of the property and concluded that the
movement observed to the applicants’ property was consistent with the earlier
findings by IL and was directly related to the flood (storm) event.
Case No: 422112 Determination Page 4 of 9
The Panel accepts the findings of IL and PG with respect to the cause of damage
and that the damage to the underpinning was directly related to the storm event of
25 December 2011.
IL in a subsequent report of 18 March 2014 confirmed its view that all reported
cracking and movement was primarily attributable to the water inundating the
subfloor area following the storm event in December 2011. IL recommended that the
engineers, building consultants and preferred builders meet to discuss the most
appropriate method of repair to allow for an exact scope of works to be compiled.
A second scope of works (scope 2) was provided by IL on 3 April 2013. The Panel
notes that this refers to scope of works for stage 1. Given the earlier comments of IL,
the Panel is concerned whether this scope of works would be adequate to complete
the repairs.
A third scope of works was provided by PB for the FSP’s builder which is largely
consistent with scope of works 1. The Panel notes the FSP claims to have not
received this scope of works, although it has been provided in the information
exchanged by the applicants.
Applicants engineering reports
The applicants provided a report from AC who examined the scope of works provided
by IL (scope 1 – 4 December 2013); scope 2 (3 April 2014) and the underpinning
drawings provided by PB.
AC considered that scope of works 2 only partially addressed the problem by
choosing to underpin the external walls only. This was inadequate and formed the
view that the original scope of works (scope 1) should adequately achieve a suitable
outcome.
The applicants provided an engineering report from PTL. PTL also examined the
scope of works 1, scope of works 2 and the underpinning drawings. PTL considered
that the most prudent method of repair was to adopt scope 1 or scope 3.
There was also an email from JP dated 18 November 2014. According to JP, the
scope of works recommended by IL is an appropriate method.
The Panel has considered the various engineering reports and is satisfied based on
the information provided that the most effective method of repairing the applicants’
property is to adopt the original scope of works as recommended by IL on
4 December 2013.
Terms of policy – settling the claim
The applicants’ policy provides that in the event that the F SP agreed to cover a claim
for building insurance, it will either:
repair or rebuild that part of your home which has sustained loss or damage or
pay you the cost to repair or rebuilding, whichever is smaller.
Should the FSP choose to repair or rebuild the home, it has the discretion to
nominate the repairer, supplier or builder.
Case No: 422112 Determination Page 5 of 9
Discretion must be used fairly
Whilst the Panel accepts that the FSP has a discretion under the terms of the policy,
that discretion must be used fairly. In determining whether to exercise the discretion
to cash settle the claim, the FSP must take into account all reasonable factors
including the nature of the repairs required and whether a cash settlement would
adequately ensure the applicants are able to properly complete all repairs.
In the Panel’s view, given the information provided and the likelihood of additional
expenses being incurred during the repair process as a result of additional damage
arising from the repair process, it would be unfair for the FSP to cash settle this
dispute unless this was agreed to by the applicants.
The applicants and the FSP have obtained a number of quotations. HC has provided
two quotations – one for $94,820 involving 29 underpins and a second more
consistent with scope 1 for $115,720 involving 41 underpins. There is a further quote
from WF for $67,320 that appears to relate to the repairing of damage caused by the
settling of the building and any underpinning process.
The FSP on the other hand provided a quote from JLG of $88,337.50 based on
installing 28 underpins and 12 micro piles. This is not consistent with scope of works
1. Whilst the FSP has indicated it is prepared to repair the property and provide a
lifetime guarantee based on the repairs quoted by JLG, it has in the alternative
offered to cash settle the applicants’ claim for $88,337.50 in line with the cost of
repairs quoted by JLG.
At all times, the applicants have been prepared to have the FSP complete the
repairs, although the dispute subsequently arose as the applicants were not prepared
to allow the FSP’s builder JLG to complete the works as quoted based on Scope 2.
The FSP offered in the alternative to cash settle the claim based on the quote from
JLG based on Scope 2.
As indicated the Panel believes Scope 1 is the appropriate scope of works. If the
claim were to be cash settled it would need to be based on Scope 1.
FSP must complete the repairs
In the Panel’s view, given the uncertainty as to the ultimate cost of repairs, it is fair
that the FSP attend to the repairs in accordance with Scope 1.
The Panel accepts that the FSP is entitled to appoint its builder to complete these
repairs but any repairs should be supervised by a suitably qualified engineer to
ensure the repairs are adequately completed in accordance with Scope 1.
2.2 The applicants are entitled to the cost of professional fees
The policy provides that the FSP will pay the reasonable cost of locating the cause of
damage if it is not known and demolishing and removing any debris.
According to the information, the applicants were required to have sections of
concrete piles removed in order to excavate the footings. This was required by the
FSP’s engineer but the cost incurred by the applicants.
Case No: 422112 Determination Page 6 of 9
In the event that the FSP has not reimbursed the applicants for the cost of the
removal of sections of the concrete path, the FSP should do so in accordance with
the terms and conditions of the policy.
Paragraph 9.4 of the Terms of Reference
Paragraph 9.4 of the Terms of Reference provides that the Service may determine
an FSP contribute to legal or other professional costs incurred by an applicant in the
course of a dispute. Unless exceptional circumstances apply, FOS will not require an
FSP to contribute more than $3,000 to these costs.
The applicants obtained engineering reports, from AC and PTL. Both reports have
been exchanged and although brief, both reports support the applicants ’ claim that
the preferred scope of works to complete the repairs is either scope 1 or scope 3.
When determining whether an FSP should contribute to the payment of professional
fees incurred, the Service will take into account the complexity of the dispute,
whether the advice was reasonably needed and whether the costs incurred were
because the expert advice was genuinely required.
In the Panel’s view the applicant s incurred the costs of both engineering reports
necessarily to assist in establishing their case. In the circumstances the Panel is
satisfied that the FSP should reimburse the applicants for the costs incurred subject
to the applicants providing relevant invoices for each report.
The applicants are entitled to compensation for non-financial loss.
Paragraph 9.3 of the Terms of reference provides that the Service can award up to
$3,000 by way of compensation for non-financial loss where an applicant has
incurred an unusual degree of physical inconvenience or time taken to resolve the
situation or interfere with an applicants ’ expectation of enjoyment of peace of mind.
In determining whether to award compensation for non-financial loss the Panel takes
a conservative approach and acknowledges that in any claim there will be a degree
of inconvenience as a normal part of doing business.
The Panel notes the applicants ’ claim for the damage to the building was lodged in
December 2012. The applicants provided reasonable access to the FSP to allow for
the damage to be assessed. The FSP’s first engineer report from IL is dated
17 January 2013 and recommended further assessment after the property had been
given 6 months to dry.
The applicants had to contact the FSP on 2 October 2013 to arrange for a further
assessment. It was not prompted by the FSP.
Due to the FSP’s questioning of IL’s report of the 24 October 2013, further
assessments were conducted. It was again confirmed on 22 February 2014 that the
damage was directly due to the storm event.
The FSP then requested a further report from IL and an amended scope of works.
The applicants responded by providing the reports from AC and PTL.
Case No: 422112 Determination Page 7 of 9
In the Panel’s view as the FSP had all the reports by December 2014 it would have
been reasonable for the FSP to have commenced the repairs in accordance with
Scope 1 at that time.
The applicants have referred to the considerable stress that the delays and the
dispute has caused. They have referred to the time lost i n attending meetings and
assessments and looking for alternative accommodation, concrete cutters, builders,
draftsmen and the impact that this has had on their health.
The Panel accepts that the applicants have experienced an unusual degree of
inconvenience and time taken to resolve this dispute which has caused considerable
stress and pressure to the applicants.
The Panel determines pursuant to paragraph 9.3 of the Terms of Reference that the
FSP pay $2,000 to the applicants by way of compensation for non-financial loss.
Case No: 422112 Determination Page 8 of 9
3 Supporting information
3.1 FOS Terms of reference
9.3 Other compensation
a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial Services Provider compensate the Applicant for consequential
financial loss or damage. Any amount awarded must not exceed the
amount specified in Schedule 3.
b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial Services Provider compensate the Applicant for non-financial loss
but only where:
(i) an unusual degree or extent of physical inconvenience, time taken
to resolve the situation or interference with the Applicant’s
expectation of enjoyment or peace of mind has occurred; or
(ii) in the case of a Dispute pertaining to an individual’s privacy rights -
injury has occurred to the Applicant’s feelings or humiliation has
been suffered by the Applicant.
The maximum amount of compensation for non-financial loss will be
$3,000 per claim made in the Dispute.
c) Notwithstanding paragraphs 9.3 a) and b), FOS will not provide
compensation for:
(i) consequential financial loss; or
(ii) non-financial loss,
in a Dispute arising as a result of a claim on a General Insurance Policy that
expressly excludes such liability.
d) The cap on liability in paragraph 9.3 a) does not in any way restrict
FOS’s ability to make an interest award under paragraph 9.5.
9.4 Applicant’s costs in pursuing the matter
FOS may decide that the Financial Services Provider contribute to the legal or
other professional costs or travel costs incurred by the Applicant in the course of
the Dispute. Unless exceptional circumstances apply, FOS will not require the
Financial Services Provider to contribute more than $3,000 to these costs.
3.2 Settling claims
Settling claims – under buildings
If we agree to cover a claim under building insurance, we will:
repair or rebuild that part of your home which sustained loss or damage, or
pay you the cost to repair or rebuild it, whichever is smaller
Case No: 422112 Determination Page 9 of 9
However
if we choose to repair or rebuild your home, we can nominate the repairer,
supplier or builder