Determination 421710

Building claim for cracking damage declined under earth movement exclusion

FirmFinancial Firm (Unknown - Insurer)
Decided2016-08-04
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$4,530
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The FSP declined a building claim for cracking damage it attributed to earth movement, after a leaking pipe was identified. AFCA found the exclusion not established, ordered the FSP to scope the repair or cash settlement within 14 days, and to pay $4,529.80 in expert costs plus statutory interest.

Once the insured shows a prima facie loss from escaping water, the insurer must prove the earth movement exclusion applies, and the FSP's engineering evidence did not discharge that onus.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay interestreassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 421710 Determination Page 1 of 8 Case number: 421710 27 July 2016 1 Overview 1.1 Dispute The applicants lodged a claim for damage caused by a leak in their bathroom in 2009. The FSP eventually agreed to cover this claim and cash settled the claim in late 2011. The a pplicants‟ contractor completed the necessary repair work in early 2012. Subsequently, the applicants noticed cracking in the home again and lodged a second claim with the FSP in March 2013. The FSP said this damage was not related to the 2009 event and not caused by any subsequent identifiable insured event. After reviewing reports from its plumber and engineer, it declined to cover the cracking damage. The applicants retained an engineer and a plumber. The plumber identified several leaks. The engineer considered the damage at the house was caused by these leaks. 1.2 Issues and key findings Is the FSP entitled to deny the applicants’ claim? The FSP is not entitled to deny the applicants‟ claim as the material provided establishes on the balance of probabilities the cracking damage to the house was caused by escape of water which is an insured event. In consideration of the totality of the material provided, it does not establish on the balance of probabilities the cracking damage was caused by the policy exclusion, earth movement. The material establishes there was severe cracking damage to the property. In order to rebut the FSP‟s experts, the applicants required expert advice about the cause of damage. The advice was of considerable assistance in making this determination. It is fair in the circumstances the FSP pay the applicants‟ experts‟ costs. 1.3 Determination This determination is in favour of the applicants. Within 14 days of acceptance of this determination by the applicants, the FSP is to:  prepare and cost a Scope of Works and decide whether it will repair the damage or cash settle the damage based on the Scope of Works  pay the applicants $4,529.80 for their expert reports Case No: 421710 Determination Page 2 of 8  pay the applicants statutory interest on $4,529.80 from the date the applicants incurred the costs. Case No: 421710 Determination Page 3 of 8 2 Reasons for determination 2.1 Is the FSP entitled to deny the applicants’ claim ? Applicants have established a prima facie claim The applicants must establish on the balance of probabilities they have suffered a loss caused by water or liquid escaping from a fixed pipe. This is known as a prima facie claim. While there was a sewer leak in the bathroom in 2009, which was identified in 2011, this leak and damage was repaired in early 2012. The material establishes the applicants noticed cracks in the entry hallway and bathroom in late December 2012 . Photographs taken in March 2013 by the FSP‟s contractor show minor cracking. The FSP arranged water leak investigation and testing in March 2014. The plumber reported all the plumbing able to be tested was in sound condition. In July 2015, the applicants‟ engineer arranged a level survey plan. He reported: “The house showing central heav e, or settlement of the eastern and western ends. This is due to a change in the soil moisture conditions under the house footings.” He goes on to say the movement of the soils is caused by the soils wetting up or drying around the edges of the building. As the 2011 leak was repaired, he expected the soil under the centre of the house where the leak was would dry and the centre of the house would settle rather than heave. He concluded: „The severity and suddenness of the cracking problem suggests a pipe leak.” He recommended all plumbing pipes be rechecked for leaks. This was done by a plumber used both by the FSP in 2011 and now used at this time by the applicants. The plumber undertook a number of tests and noted a number of leaks and issues including a large leakage to the laundry waste pipe branch external or adjacent to the footings. The plumber said the leakage was large; approximately 6 litres per minute. Further, the soil in the area of the laundry branch pipe external to the footings was boggy. The applicants‟ engineer reviewed the plumber‟s report and concluded: “…. the cause of the damage to the house is due to heave of the soils under the house, which is due to increased moisture content from leaking pipes. ” In those circumstances, I am satisfied the applicants have established on the balance of probabilities they have suffered a loss caused by water or liquid escaping from a fixed pipe. I am satisfied the applicants have established a prima facie claim. Both parties engaged expert engineers and plumbers Once so established, the onus shifts to the FSP to prove on the balance of probabilities the damage was as a result of or caused by the settling, shrinkage or any movement of earth. Case No: 421710 Determination Page 4 of 8 The FSP also relies on th e opinion of an engineer and a plumber. The FSP‟s plumber reported in March 2014 all the plumbing (able to be tested) was in sound condition. The FSP‟s engineer conducted a level survey of the buildings parameter brickwork in May 2014 and in December 2015. In May 2014, the engineer reported the result of the level survey indicated settlement of the home at the north east rear corner had occurred as well as settlement along the home‟s front elevation. In December 2015, he reported the survey level result i ndicates the front of the house had remained relatively static while the rear had settled further with the south eastern corner settling considerably more. The engineer reported to the FSP: „The reported recent sewer pipe leak (laundry branch) has not resu lted in an increase of level along the home‟s northern side, which would be expected if leakage was contributing to soil heaving at this point. In fact, the level survey suggests further settlement has occurred. There appears to be other factors affecting the home‟s eastern end which might be overriding any leak induced soil heave.” The engineer provided some photographs and aerial images. He says they show a significant increase in growth of trees and vegetation over the past six years in a reserve which b acks onto the applicants‟ property at the back of the property. The back of the property faces east. He makes a number of observations. He said the further movement damage can be explained by the environmental drying influence of sustained and continued g rowth of this vegetation in the reserve and, as the eastern end of the home settles, it increases the cracking to the centre of the home. He also suggests as a result of continued environmental drying, the pipework cracked and leaked. Further, he says as the cracking damage significantly increased from the time of repairs in 2012 to the plumbing testing in 2014 it cannot have been the result of localised heaving of foundation soil, as the 2014 testing showed no leaks. Cracking damage is probably not caused by earth movement The applicants challenge these findings. They say they stopped using the laundry drain soon after the break was found in late October 2015 and this (together with hot summer conditions) explains why there was decreased moisture in the soil in December 2015. Whereas they submit the first survey level was performed in May 2014 when it is generally wetter than December and the drain was in full use. The applicants also rely upon advice from the local council and the urban forestry department who inspected the reserve in February 2016. The applicants were told the nearest large tree was 11 metres from the back fence and would not interfere with pipes and damage the house. No report was provided but an email confirmed trees and vegetation in the reserve were not the cause of damage to the house. The FSP submits the email should not be relied on without the provision of the report. The FSP says it is not possible to determine on what basis the conclusion was reached the trees and vegetation were not the cause of d amage to the applicants‟ home. Whilst I acknowledge the provision of the report would have been optimum, Case No: 421710 Determination Page 5 of 8 nonetheless, the senior urban forest officer has clearly and unequivocally stated in the email correspondence with the applicants the trees and vegetation in the adjacent reserve are not the cause of the damage to the house. The FSP acknowledges the difference in expert opinions. The FSP submits its expert should be preferred for reason set out in its Notice of Response. However, the FSP‟s engineer‟s opinion is very reliant on the FSP‟s plumber‟s findings. The FSP‟s plumber conducted tests in March 2014 and concluded the plumbing services were in a sound condition. But the many photographs taken by the applicants‟ plumber in September 2015 do not show plumbing services in a sound condition. The applicants‟ plumber describes and photographs severe breakage and cracking to and holes in pipes. In the absence of further explanation, it is difficult to reconcile the difference in the two reports. As the FS P‟s engineer discounts leaks causing the damage because of reliance on the FSP‟s plumber‟s report, he attributes the damage to downward settlement at the north east rear corner and the front of the house because of environmental drying influences from the adjacent reserve at the rear of the house. The downward settlement at the front of the house is attributed to “some minor drying influences to the front of the site” but these influences are not specified. However, as the plumbing services were not in a sound condition, as the drying influences to the front of the site are not specified, as the trees in the reserve are not close to the house, and as the local council rebuts the finding the vegetation in the reserve is the cause of damage to the house, I am not satisfied the FSP has established, on the balance of probabilities, the cracking damage claimed by the applicants is caused by earth movement. FSP to prepare and cost a Scope of Works The applicants‟ expert recommended all pipes be repaired to allow the soils under the house to dry and the house to settle which might take one or two years. He said when all movements ceases, the internal damage to the house can be repaired. From reviewing the applicants‟ plumber‟s report, it is assumed the pipes are r epaired. In any event, the policy does not cover the cost of repairing the pipes. The material provided does not include an estimate of the cost of repairs of the damage caused by the escape of water. The policy sets out how the FSP will settle a buildings claim. At its option, it can repair or pay the reasonable costs of repairs. The FSP is to prepare and cost a Scope of Works and decide whether it will repair the damage or cash settle the damage based on the Scope of Works. If the FSP opts to cash settle, it remains necessary for the amount of the cash settlement to be agreed, based on the Scope of Works to be prepared by the FSP. FOS encourages the parties to this dispute to resolve any issues which might arise during the process. However, the parties can return to FOS if they are unable to resolve any issues arising from the Scope of Works and/or the costing of that work. Case No: 421710 Determination Page 6 of 8 FSP to pay applicants ’ experts costs FOS may decide the FSP contribute to the professional costs incurred by the applicant in the course of the dispute. Unless exceptional circumstances apply, FOS will not require the FSP to contribute more than $3,000 to these costs. FOS decides whether the FSP should make such a contribution by considering what is fair in the circumstances. FOS makes this decision taking into account the complexity of the dispute and whether the applicant incurred costs because they genuinely required expert assistance. The applicants have provided an invoice from their expert plumber in the amount of $1,768.80. Two invoices are also provided from the engineer in the amount of $2,211 and $550. The invoices total $4,529.80. The material establishes there was severe cracking damage to the property. The FSP engaged experts. The applicants required expert advice about the cause of damage. The reports provided by the applicants were of considerable assistance in making this determination. In these circumstances, I am satisfied it is fair the FSP pay the applicants $4,529.80 plus statutory interest on the said sum from the date the applicants incurred the costs. Case No: 421710 Determination Page 7 of 8 3 Supporting information 3.1 FOS Approach As advised to the parties, FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS recommendation and has proceeded directly to determination. There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered for the purposes of this determination. This dispute has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only. It is an accepted principle of general insurance law that an insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. 3.2 Relevant policy extracts Water or liquid damage  We will cover your buildings or contents for loss or damage caused by water or liquid. We will also cover the cost of finding where the water or liquid escaped from, including the cost of repairing any damage that occurs while looking for the cause. We will only cover loss or damage as a result of water or liquid escaping from: • a fixed pipe or an object attached to a pipe, fixed gutter, fixed tank or a drain • a bath, basin, sauna, spa, shower base or shower wall, sink, toilet or tiled floor that has drainage holes • a washing machine or dishwasher • an aquarium • a waterbed.  We will not cover the cost of repairing the item that caused the escape of water or liquid escaped from. Or the cost of fixing or finding leaks that have not caused loss or damage to your buildings or contents . Any cover we provide is subject to the following exclusions. We will not cover any loss or damage as a result of or caused by:  the settling, shrinkage or any movement of earth…” Case No: 421710 Determination Page 8 of 8 3.3 Other relevant material considered and relied on  Parties‟ submissions, emails , reports, photographs and all material attached to submissions  Correspondence between the parties