Home / Financial Firm (Unknown - Insurer) / Determination 421269

Determination 421269

Movement and water damage claim declined

FirmFinancial Firm (Unknown - Insurer)
Decided2016-12-30
ProductGeneral Insurance · Business / commercial
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicants claimed under their business insurance for movement and water damage to the rear extension of a tenanted commercial property. AFCA found the damage was not shown to be caused by an insured event such as escape of liquids or storm, and that the FSP is not liable.

The applicants did not establish the necessary causal link between an insured event and the damage, which was more consistent with excluded earth movement and gradual deterioration.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 421269 Determination Page 1 of 8 Case number: 421269 30 December 2016 1 Overview 1.1 Dispute The applicants lodged a claim under their business insurance policy with the financial services provider (FSP) for movement damage and water damage to a weatherboard extension at the rear of their tenanted commercial property. The applicants believe the movement damage occurred due to the effects of water leaking from various pipes at the property. They say the storm damage was caused by water leaking from box gutters which became blocked during a hail storm. The FSP denied the applicants’ claim on the basis that the damage was not caused by leaking pipes or a storm (or any other event insured against under the policy) but by poor construction, earth movement, gradual deterioration and/or a lack of maintenance . The FSP also says it has been severely prejudiced by the applicants’ delay in lodging their claim. 1.2 Issues and key findings Is the FSP liable for the damage to the rear extension? The FSP is not liable for the damage to the rear extension because the available information does not establish that the damage was caused by an insured event. While the applicants have identified a number of plumbing issues (and a storm) at the property over a period of several years, there is insufficient information to establish the necessary causal link between these events and the damage observed at the property (in part, due to the applicants’ delay in lodging their claim) . Further, the nature and extent of the damage at the property is consistent with it having been caused by factors which are outside the scope of cover under the policy, such as naturally occurring earth movement and gradual deterioration. 1.3 Determination This determination is in favour of the FSP. The FSP is not liable for the applicants’ claim . Case No: 421269 Determination Page 2 of 8 2 Reasons for determination 2.1 Is the FSP liable for the damage to the rear extension? Policy provides cover for insured events subject to exclusions The applicants are required to show that, on the balance of probabilities, they have suffered a loss caused by a risk insured against under the policy. This is known as a prima facie claim. If the applicants are able to establish a prima facie claim, then the onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to deny the claim. The applicants’ p olicy provides cover for damage caused by the events listed in the policy, including the insured events of “escape of liquids” and “storm or rainwater”. The reports prepared by the various contractors appointed by the parties (including the photographs contained therein) confirm that:  the rear extension at the applica nts’ property has suffered severe movement damage, resulting in uneven floors, cracking of internal wall linings and separation gaps between various parts of the building; and  there is internal water damage to the ground floor bedroom at the rear of the pr operty . However, the FSP will only be liable for the damage to the property if the proximate cause of the damage (that is, the real, effective or dominant cause) was one of the events insured against under the policy. The FSP says the claimed damage was no t caused by storm or escape of liquid, but by a combination of factors such as poor construction, naturally occurring earth movement, gradual deterioration and/or a lack of maintenance. As noted above, during the course of this dispute, the parties have appointed numerous contractors to determine the cause of the damage. The panel has carefully reviewed the reports prepared by the various contractors (together with the other information provided) in order to determine the cause of the damage. Parties disagree about cause of movement damage When the applicants lodged their claim in April 2014, they indicated that they believed the movement damage to the property had commenced several years earlier and had continued to worsen since that time . The applicants have subsequently provided a report from their building consultant (AR) which states that the applicants have advised that they first noticed signs of movement to the rear extension in September 2011, following which they engaged a plumber who located and repaired a broken mains water pipe in the rear yard of the property. In his report, AR identifies several other plumbing issues affecting the property between March 2011 and January 2015, including: Case No: 421269 Determination Page 3 of 8  a leaking sewer pipe which was identified and repaired in March 2011;  leaking storm water pipes, which were identified and repaired in July 2012; and  a leaking waste water pipe from the commercial kitchen at the neighbouring property (causing water to seep through the common wall), which was identified and repaired in January 2015. The applicants’ builder (AR) concluded that the movement damage to the property was consistent with having been caused by earth movement due to abnormal variations in the moisture content of the surrounding soils. AR considered that these changes in moisture content had occurred as a result of one or more of the plumbing issues identified above. Among other matters, AR noted that:  movement damage was not apparent in the photographs of the interior of the property taken by the real estate agent in 2009 (prior to purchase by the applicants the following year);  the timber stumps of the extension showed evidence of water scalding to a height of approximately 200 millimetres; and  if the damage was due to naturally occurring earth movement, it would be evident throughout the entire building, rather than confined to the extension. The engineer (SB) appointed by the FSP to inspect the property concluded that the damage had occurred due to subsidence of the timber stump footings supporting t he perimeter walls. SB considered the stump footings had subsided due to a combination of factors, including:  the manner in which the extension was constructed;  differential foundation movement as a result of naturally occurring variations in the moisture content of the surrounding soils; and  gradual deterioration over an extended period of time. Property has experienced long-term movement issues The applicants acknowledge that, sections of the rear extension have suffered damage over its lifetime, due to differential foundation movement resulting from naturally occurring changes in the moisture content of the surrounding soils. The applicants’ builder (AR ) has confirmed that the property is built on highly reactive clay soils which are susceptible to significant heaving and subsidence (of up to 125 millimetres) as a result of changes in moisture content. The reports provided by the various contractors include reference to prior repairs carried out to address damage caused by naturally occurring earth movement, including timber wedges added to the tops of doors and window sills to plug separation gaps. The applicants are not seeking to claim for damage to the property caused by long- term earth movement. They say that the damage which is the subject of the current claim is separately identifiable and has occurred solely as a result of water escaping from one or more of the leaking pipes identified above. Case No: 421269 Determination Page 4 of 8 Timing of movement damage is unclear As noted above, the applicants have been unable to identify exactly when the claimed damage occurred (beyond indicating that it occurred over several years, commencing in late 2011). While the front part of the building was leased to a commercial tenant, the rear extension was unoccupied for the entire period following the applicants’ purchase of the property in 2010. The real estate agent who managed the property for the applicants did not inspect the rear extension, whi le the applicants lived interstate and only inspected the property on a few occasions each year. The lack of certainty as to when the movement damage occurred makes it difficult to attribute the damage to one or more of the specific events identified by the applicants’ builder (particularly given the number of intervening events which have occurred in the meantime). The difficulty in determining the cause of the damage has been exacerbated by the applicants’ delay in notifying the FSP of their claim. The claim was not lodged until April 2014, approximately two and a half years after the applicants first noticed the damage. The panel acknowledges that the applicants may not have been aware of their ability to claim under the policy until they received advice from their builder in March 2015. Nevertheless, the extended delay by the applicants in progressing their claim has contributed to the difficulty in identifying the proximate cause of the damage. Further, the fact that the applicants initially noticed the movement damage to the extension in September 2011 calls into question whether the event which caused the damage occurred during the period of insurance (given the policy was not incepted until December 2011). Available information does not establish damage was caused by insured event Having carefully reviewed the available information, the panel is not satisfied that the movement damage to the extension was caused by an escape of water at the property (or any other event insured against under the policy). While the applicants’ builder (AR) identified five separate plumbing issues which might have resulted in water escaping from leaking pipes at the property, AR’s report does not include any explanation of the mechanism (for example, heaving, subsidence, erosion etc) by which one or more of these events could have caused the damage observed at the property. Further, the reports and photographs provided by the various contractors confirm that the movement damage has occurred throughout the entire extension, rather than being localised to a particular area (as might be expected in the event it had been caused by the escape of water from a leaking pipe). While the front, tenanted section of the property does not show any signs of differential foundation movement, this part of the building is of a fundamentally Case No: 421269 Determination Page 5 of 8 different construction. While the rear extension is a weather board construction built on timber stump footings, the front section is a brick building constructed on a perimeter strip footing and stumps. Accordingly, natural changes in the moisture content of the surrounding soils would have a significantly different effect on the rear extension, as compared to the front section of the building. This is evident from the extent of the previous damage to the extension (as indicated by the size of the timber wedges used to plug separation gaps), which the applicants have acknowledged was caused by naturally occurring earth movement. For the reasons outlined above, the panel is not satisfied that the movement damage to the extension was caused by an escape of water from a leaking pipe during the policy period. In particular, the panel notes that:  to the extent the damage was caused by plumbing issues which occurred before December 2011, it is not covered under the policy;  while there were a number of plumbing issues identified at the property between 2011 and 2015, there is insufficient information to establish a causal link between any of these events and the observed damage to the property;  the delay by the applicants in lodging their claim (although unintentional) has materially prejudiced the ability of either party to identify the cause of the damage; and  the nature and extent of the damage is more consistent with it having occurred as a result of differential foundation movement due to naturally occurring changes in the moisture content of the surrounding soils (to which the property is highly susceptible). Damage caused in this manner is excluded from cover under the policy. In respect of the internal water damage to the ground floor bedroom, the panel considers that there is insufficient information to establish the proximate cause of this damage. The applicants say the damage occurred when the box gutters at the property became blocked by hail during a storm in 2012. However, they have been unable to provide any contemporaneous information confirming this (for example, photographs taken at the time). The applicants have provided a copy of an invoice from a builder (LB) who carried out repairs at the property in July 2012. LB’s invoice indicates that he replaced leaking spouting and a leaking rainhead at the property, which tends to suggest that the failure of these items was the proximate cause of the damage, rather than the storm itself. In the absence of any contemporaneous information confirming the cause of the damage to the rear bedroom and given the delay of almost two years in lodging a claim, the panel is not satisfied that the proximate cause of the damage was the storm in 2012 (or any other event insured against under the policy). Case No: 421269 Determination Page 6 of 8 FSP is not liable for applicants’ claim For the reasons outlined above, the panel is not satisfied that the applicants have established that the claimed damage to the rear extension at their property has been caused by the escape of liquid, storm or any other event insured against under the policy. Accordingly, the FSP is not liable for the applicants’ claim. Case No: 421269 Determination Page 7 of 8 3 Supporting information 3.1 FOS approach to this dispute This dispute has not been the subject of a FOS recommendation. Due to the nature of the dispute, it has been referred directly to a panel for determination, in line with the Operational Guidelines to the FOS Terms of Reference. The panel consists of an Ombudsman and two representatives with consumer and insurance experience. The panel has decided this case based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. The panel has reviewed and considered all of the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination, the panel has restricted its commentary to those issues that it considers directly relevant to the outcome only. 3.2 Terms of policy Subject Terms Cover for Defined Events If your Certificate of Ins urance indic ates that you have taken out insurance under Section 1, we insure you against the Property at the Premises being lost, destroyed or damaged by one or more of the Defined Events listed below occurring during the Period of Insurance except as stated under We Will Not Pay … Escape of Liquids as a result of bursting, leaking discharging, or overflowing of pipes, tanks, fixed r oom heating or apparatus ... Storm or Rainwater … Specific e xclusions We do not insure you under Section 1 for the following circumstances … Earth Movement We will not pay for loss, destruction, or damage caus ed directly or indirectly by erosion, subside nce, landslide, or other earth movement … General conditions The General Conditions set out below apply to all the Sections of this policy. You must comply with all these General Conditions otherwise we may be entitled to refuse to pay a claim, or to reduce the amount you are entitled to receive. Claim Procedures If something happens which gives rise or may give rise to a claim under this policy… you must …  notify us as soon as possible, giving full particulars of the facts and Case No: 421269 Determination Page 8 of 8 Subject Terms circumstances, including loss, damage …  take all reasonable precautions to prevent or minimise further loss, damage … Reasonable Care You must at all times take reasonable care …  to maintain the Premises, structures, fittings, fixtures … and Property in sound condition …

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.