The applicant's storm-damaged home was restumped by the FSP's contractor, but the work was found non-compliant and cash settlement was disputed. AFCA ordered an independent building surveyor inspection, further works as needed and repairs by the FSP, but found the roof damage was not covered.

The restumping was not shown to comply with regulations, cash quotes were unreliable, and the roof defects were attributed to poor original construction rather than the insured event.

Issues

Subjects and remedies

home or building damagenatural disasterrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 421071 Determination Page 1 of 5 Case number: 421071 30 June 2016 1 Overview 1.1 Dispute The applicant’s property suffered substantial damage in a storm in January/February 2011. A dispute arose as to the extent of the storm related damage and was subject of a determination (No.323420). The Panel determined the FSP restump the applicant’s property and after sufficient time to allow for the property to settle, obtain a Scope of Works for the balance of the damage and to settle the applicant’s claim for 85% of the work required. The FSP has restumped the property and offered to cash settle the applicant for the balance of repairs. A dispute had arisen as to: 1. the quality of the restumping 2. cost of repairs. 3. damage to the roof of the property 1.2 Issues and key findings Have the restumping works been completed in accordance with relevant building regulations? The Panel accepts that there are issues with the restumping of the property. The FSP is to appoint an independent building surveyor to inspect the restumping works for compliance and if necessary complete any additional restumping work required. Is the FSP entitled to cash settle the claim? Given the different estimates as to the cost of repairs, the Panel determines it is fair the FSP attend to the actual repairs unless otherwise agreed between the parties, once the restumping has settled. Is the damage to the roof related to the applicant’s claim? The Panel is satisfied that the damage identified to the roof is consistent with construction defects in the property and not consistent with damage resulting from the storm/flood or restumping of the property. The FSP is not liable to repair the roof. Case No: 421071 Determination Page 2 of 5 1.3 Determination This determination is partially in favour of the applicant. The FSP is to appoint an independent building surveyor to ensure the restumping works carried out are compliant. In the event of non-compliance, the FSP is to arrange for any additional works required to ensure complia nce. Once the property has had the opportunity to settle following the completion of any restumping works, the FSP is to attend to the repairs to the property, unless the parties otherwise agree as per section 2.2 of this determination. The FSP is not liable to meet the costs of repairs to the roof as the Panel is satisfied that the damage to the roof is consistent with poor construction used when extending the property. Case No: 421071 Determination Page 3 of 5 2 Reasons for determination 2.1 Has the property been restumped in accordance with relevant building regulations? The Panel is not satisfied based on the available information that the restumping of the property is compliant with relevant regulations. The applicant supplied a detailed report from T Pty Ltd supported by a number of photographs following the initial restumping of the property. The report dated 24 April 2015 notes:  bearers were unsupported  new concrete stumps were poorly installed  some stumps could be moved by hand  some old stumps had been removed and not replaced  no ant caps installed  gas heating duct work had been crushed. The photographs supplied with the report supported these comments. The report strongly recommended a structural engineer be appointed to assess the condition of the stumps. After the applicant’s complaints, the FSP appointed RL to attend the property to respond to the applicant’s report. RL attended the property on 16 July 2015. The report whilst brief confirms the builder’s inspection revealed some defects with the restumping and damage to the ducted heating. According to a report of 5 August 2015, the restumpers were to have attended the property and rectified the defects in accordance with the Scope of Works. The Panel has not been provided the Scope of Works. They were also required to remove and replace the damaged gas heating system. The FSP arranged for an engineer RC to inspect the applicant’s property on 27 August 2015. RC considered the stumps used came with relevant certificate of accreditation from the Building Regulations Advisory Committee, that the stumps had been installed in accordance with the aforementioned installation guide. RC did not observe any of the concerns raised by T but noted that the inspection occurred after the restumping contractor was finalising additional works to the restumping in response to T’s concern. RC recommended a relevant building surveyor be engaged to inspect the restumping works for compliance. The FSP has not provided any information to confirm that a relevant building surveyor has certified the restumping as compliant. The applicant is still concerned with the restumping and whether the restumping is compliant. The applicant is concerned that the FSP has failed to inform her of what actual restumping works were completed. The Panel is concerned that despite the recommendation of the engineer RC, no building surveyor certification has been obtained. The Panel is satisfied that an Case No: 421071 Determination Page 4 of 5 independent building surveyor should be appointed by the FSP within 14 days of acceptance of this determination. In the event that the restumping work is not compliant the FSP must appoint a certified restumping contractor to complete all works required to obtain certification from the building surveyor. Copy of the certification is to be provided to the applicant. 2.2 Is the FSP entitled to cash settle the claim? The terms of the FSP’s policy provide that it may choose whether to repair, replace or cash settle the damage. The Determination 323420 determined the FSP could settle for 85% of the assessed damage. However, given the time since the original claim and the ongoing issues since the Panel’s determination in April 2014, the Panel believes it would be fairer that the FSP should attend to the claim related repairs. The quotations provided by the FSP vary significantly. The Panel notes that the quotations are based purely on a cash settlement. They are not quotations based on the likely cost to the FSP to repair the property. The quotations relied upon by the FSP do not include items such as builder’s margin s or contingencies. The builders concerned were not prepared to complete the repairs. The quotation provided by the applicant is quite brief. It includes the cost of restumping and repairs to the roof. It does not adequately break down the insured damage and non-insured damage. In the Panel’s view given the continued uncertainties to the costs to repair the property rather than cash settle the applicant’s claim, the FSP should attend to the repairs. The Panel determines that the FSP within 14 days of a report from the independent building surveyor confirming the restumping is compliant that the FSP should make arrangements for a builder to attend the property to quote on repairs and commence the repairs. Should the applicant not be prepared to allow the FSP to attend to the repairs then the FSP must cash settle the balance of the claim for the insured damage. Any cash settlement must be based on the cost to repair the property as assessed by a builder who is prepared to attend to the repairs. 2.3 Is the damage to the roof related to the original storm/flood damage and/or subsequent restumping of the property? In the original determination the Panel identified that there were other problems that were factors in the damage caused to the applicant’s home. The facto rs included a leaking pipe in the ceiling, which might have been claimable as a separate event, a disconnected downpipe, the age of the home and runoff problems. Case No: 421071 Determination Page 5 of 5 Engineering advice at that time was that the house be restumped so that the floor could be relevelled internally with the roof trusses then inspected to evaluate the structural integrity of the home. The applicant’s building contractor T Pty Ltd inspected the home on 24 April 2015. That inspection was limited to the building interior/exterior, roof exterior, sections of the roof void, and sub-floor. Insofar as the roof was concerned, his visual inspection identified the roof appeared wavy due to settling of the roof beams. He identified dislodged roof tiles in areas and recommended a roofing tiling contractor be engaged for advice and recommendations. RC who inspected the property on 27 August 2015 considered the roof damage was caused by the poorly constructed roof framing alternations made to the original roof framing during the construction of the extension as well as long term creep and shrinkage of the timber most likely due to the timber being installed when ‘green’. RC’s report includes a number of photographs of the roof area. The photographs show split timber, roof batons finishing short of the original hip rafters and packing. The Panel is satisfied these defects are not related to the storm flood event or restumping of the property. On balance, the Panel is satisfied that the wavy appearance of the roof and other roofing defects are most likely associated with the poor construction of the roof rather than any insured event. The Panel is satisfied the FSP is not liable to meet the cost of repairs to the roof.