Home / NAB / Determination 420984

Determination 420984

Settlement delay, loan transfer and interest charges on construction loan

FirmNAB
Decided2016-10-10
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded$1,800
Non-financial loss$1,500
Amount claimed—
SourceAFCA PDF

Summary

Borrowers building a home complained of misleading loan process information, delayed settlement of their former property, and interest errors. AFCA found no misleading conduct or irresponsible lending, but ordered refunds and non-financial loss totalling $3,300 for the delayed title and an unexplained account transfer.

A lender that unreasonably delays settlement, or fails to explain an account transfer, must refund the resulting interest, fees and stress, but is not responsible for the builder's work.

Issues

Subjects and remedies

home or building damagepay interestpay non financial lossrefund fees or charges

Related

All NAB determinations · Find similar determinations

Text of the determination

Determination Case No: 420984 Determination Page 1 of 7 Case number: 420984 27 September 2016 1 Overview 1.1 Dispute In September 2014, the Applicants entered into a $440,000 Term Loan contract ending 1072 (Loan) to build a house on their vacant land at “W” (Construction). The dispute is about whether the FSP:  misled the Applicants about the Loan process and its role in the Construction  unreasonably delayed settlement of the sale of the Applicants’ property at “LP” (Property)  incorrectly applied interest to the Loan and to their account ending 7458 (Account). On 28 April 2016 the Case Analyst provided the parties with a Recommendation, which was substantially in favour of the FSP. A copy of the Recommendation is attached to this Determination. The terminology and references used in the Recommendation are adopted in this Determination. 1.2 Issues and key findings Did the FSP mislead the Applicants? The FSP did not mislead the Applicants about whether the FSP would check the builder’s work or was responsible for “backing up” the Applicants in relation to the building work. Did the FSP unreasonably delay settlement of the sale of the Property? The Recommendation found the FSP unreasonably delayed settlement and the Applicants were entitled to a refund in interest and fees. The Applicants are entitled to compensation of $3,300. Did the FSP meet its requirements under the National Consumer Credit Protection Act (NCCPA)? The FSP’s advance of the Loan was appropriate. The Applicants’ could afford to service the Loan without hardship. Did the FSP otherwise make an error in its dealings with the Applicants? In response to the Recommendation the Applicants’ said the FSP had made an error in applying interest to the Loan and failing to write to the builder at their request. Case No: 420984 Determination Page 2 of 7 The available information shows the FSP did not apply interest to the Loan for two months in 2015 and corrected this with the Transfer. The FSP was also not required to write to the builder at the Applicants request. 1.3 Determination This Determination is substantially in favour of the FSP. Should the Applicants accept this Determination within 30 days of its date (above), within a further 14 days of that acceptance, the FSP is required to refund a total of $3,300 to the Loan being:  $1,600 in interest,  $200 in relation to a transfer of interest, and  $1,500 non-financial loss. In the event the Applicants experience financial difficulty in repaying the Loan with the FSP, they should, 14 days after their acceptance of the Determination, provide to the FSP a statement of financial position together with a repayment arrangement proposal that will see the Loan repaid over a reasonable period of time. The FSP must give genuine consideration to the Applicants proposal, but is not obliged to accept it if the FSP does not consider it to be reasonable. If the parties are unable to agree on a repayment arra ngement within 30 days of the Applicants proposal, or no proposal is provided within the 14 days (of the parties acceptance of this Determination), the FSP will be entitled to take debt recovery action under the terms of the Loan to recover any outstanding balance, once the FOS dispute is closed. Case No: 420984 Determination Page 3 of 7 2 Reasons for Determination 2.1 Were the findings in the Recommendation correct? I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the Recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied that the Case Analyst’s Recommendation contains an acc urate summary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. Neither party raised any objection to the Case Analyst’s finding that the FSP correctly applied interest to the Loan and the Account. As I agree with the Case Analyst’s findings I have not further considered this issue in the Determination. 2.2 Did the FSP mislead the Applicants? The Applicants say that the FSP informed them that the FSP would come out at every stage of the build which was not known to the Applicants until frame stage. While the FSP indicated at an earlier time that it would come out at every stage of the build, that was corrected before the building contract became binding. The FSP has provided a recording of a conversation between the Applicant and FSP on 8 August 2014. At the time this conversation took place, Mrs Applicant had signed the building contract but Mr Applicant had not. As such, the building contract was not binding at that stage. To the extent that the Applicants believed it was binding at that stage, that belief was not caused by the FSP. Mrs Applicant indicated in the course of that conversation that she believed the FSP was standing behind her so that if there were problems with the building contract or the builder, the FSP would step in to assist them. During the course of the conversation, the FSP told the Applicant to obtain her own legal advice on a number of occasions. In relation to the inspection of the property, the FSP said in response to the Applicant’s comment that the FSP was “behind” her by going out at every stage, that the FSP did not do that. The FSP clearly informed the Applicant that the FSP only sends someone out at the beginning and at the final stage. It may be that the Applicant did not take in what the FSP told her at that time. However, it is my view that the Applicant was on notice before the building contract was binding that the FSP did not inspect the property at every stage. The Applicants would therefore be responsible for ensuring that the work done by the builder was done to quality required by the contract and within the time allowed for by the contract. To the extent that the Applicants have suffered loss as a result of a lack of quality or time delays, they should take these matters up with the builder. Case No: 420984 Determination Page 4 of 7 Other information provided by the Applicants does not change the outcome In their response to the Recommendation, the Applicants set out a number of other reasons why they believed the FSP was liable. These are addressed in turn below:  The Applicants believed the building contract was binding once the female Applicant had signed it. Despite what the Applicants say they understood, the building contract did not become binding until the male Applicant had signed it. It was at all times open to the Applicants to obtain their own legal advice on this issue and indeed the building contract; they elected not to.  The Applicants’ submission about whether the FSP obtained a valuation and gave this to them do not assist them with their claim. When a financial services provider obtains a valuation it does so for its own benefit as a prospective mortgagee and not to protect the customers’ interests. It is not obliged to provide a copy to a customer (though, at FOS’s request, the FSP has recently done so). Whether the Applicants have overcapitalised is not some thing for which the FSP is responsible,  The Applicants ’ correctly say that had they obtained a valuation or obtained legal advice this would not have impacted the FSP’s decision to lend. However had they done so it would likely have assisted them to better protect their own interests . It was not the FSP’s role to do this. 2.3 Did the FSP meet its requirements under the NCCPA? The FSP’s advance of the Loan was appropriate In their response to the Recommendation, the Applicants said it was a gross exaggeration to say they were considered as high net worth individuals. Applicants said that the:  female Applicant does not work, and  male Applicant provided all his income payslips to the FSP at the time they applied for the Loan. However the available information show s the FSP’s advance of the Loan was appropriate as the FSP:  did not rely on the female Applicant’s income, and  appropriately assessed that the Applicants could service the Loan without hardship. Whilst the Applicants may not consider themselves high net worth individuals, in the context of establishing whether they could afford to service the Loan this was an appropriate assessment. In relation to whether the Applicants were in a position to pay for items not included in the contract. The FSP made it clear to the Applicants how much money the FSP was providing. The Applicants were responsible for ensuring that they had sufficient funds to pay for the building project they were entering into. In any event, the FSP provided funds to cover some of the additional costs and this loan was also affordable. Case No: 420984 Determination Page 5 of 7 2.4 Did the FSP unreasonably delay settlement of the sale of the Property? The Recommendation found the FSP unreasonably delayed settlement In their response to the Recommendation, the Applicants provided substantive submissions and supporting documents to show they had notified the FSP of their subdivision plans as early as 12 October 2015. It is clear from these submissions that the FSP was on notice of the subdivision from that time. In my view nothing really turns on the exact date the FSP became aware of the subdivision. Whether it was 12 October 2015 or early November, the FSP had sufficient time either way to produce the title much ea rlier than it did. I agree that the FSP unreasonably delayed the settlement by not producing the Certificate of Title until 23 November 2015. However, the remedy was not correct The Recommendation said that the Applicants were charged interest totalling $5,592.86 in interest after the due date of settlement on 23 November 2015. However, in calculating compensation, the Recommendation deducted $5,000 the FSP paid the Applicants in September 2015. The Applicants said that the $5,000 received in September s hould not be deducted because it was a payment for something different. I agree that the $5,000 paid in September 2015 is unrelated to a delay in settlement in November 2015 and so should not be deducted. However, in working out the interest charged after 23 November 2015, the Case Analyst included all of the interest charged by the FSP on 30 November 2015 across four loans, one of which was not going to be paid out on settlement. The additional interest charged that needs to be refunded is only on those loans that were to be repaid at settlement and only for the period after 23 November 2015. The FSP did not charge interest on any of the three loans for December 2015. Therefore the Applicants are entitled to a refund of the interest charged between 23 November 2015 and 30 November 2015. This totals $855.45 being $310.49 for loan 9251, $287.63 for loan 9674 and $257.33 for loan 2907. The FSP should also pay the sum of $700 for interest accrued on the partial repayment of $181,907.89 to loan 1072 between 23 November 2016 and 31 December 2015 and compounding interest on that amount to 23 October 2016. The FSP should pay the Applicants the sum of $2,600 calculated as follows:  $855.45 in interest applied to the three Loans from 23 November 2015 to 30 November 2015 (there being no interest charged in December 2015 for these three loans),  Interest on that amount for the period from November 2015 and the date of payment rounded up to $44.55;  $700 in interest applied to loan 1072 from 23 November 2015 to 31 December 2015; and Case No: 420984 Determination Page 6 of 7  award $1,000 non-financial loss for causing settlement to be unreasonably delayed. These amounts are to be paid to the Loan to reduce the balance. 2.5 Did the FSP otherwise make an error in its dealings with the Applicants? The Applicants raised two new claims In their response to the Recommendation, the Applicants said the FSP:  incorrectly transferred $3,370.89 from the account ending 1633 to the Loan account 1072 on 4 January 2016 ( Transfer ). It told them this figure was two interest payments it overcharged them in 2015.  should have written to the builder to prompt the builder’s com pletion of the Construction, because they say the builder delayed the Construction. The Applicants did suffer a financial loss as a result of the Transfer Account 1633 became overdrawn on 31 July 2015 when interest on loan 1072 was charged to the 1633 account. A further interest charge of 1,759.22 was also charged on 31 December 2015. As the account 1633 was overdrawn, interest and charges accrued on that account. A reconstruction of account 1633 is set out below. As account 1633 should not have been o verdrawn, the FSP transferred the balance to loan 1072 on 4 January 2016 to ensure that there was a nil balance on account Account 1633 30-May-15 C/fwd balance 1,188.66 -$ 23-Jun-15 LSF 10.00 $ 1,198.66 -$ 30-Jun-15 Int 16.46 $ 0.10 $ 1,215.02 -$ 20-Jul-15 Cr 8,145.69 $ 6,930.67 $ 21-Jul-15 Wdl 6,930.00 $ 0.67 $ 22-Jul-15 Cr 70.00 $ 70.67 $ 23-Jul-15 LSF 10.00 $ 60.67 $ 31-Jul-15 int - 1072 1,487.58 $ 1,426.91 -$ int 13.87 $ 1,440.78 -$ 21-Aug-15 LSF 10.00 $ 1,450.78 -$ 31-Aug-15 Int 19.33 $ 1,470.11 -$ 23-Sep-15 LSF 10.00 $ 1,480.11 -$ 30-Sep-15 Int 24.74 $ 1,504.85 -$ 23-Oct-15 LSF 10.00 $ 1,514.85 -$ 30-Oct-15 Int 24.19 $ 1,539.04 -$ 23-Nov-15 LSF 10.00 $ 1,549.04 -$ 30-Nov-15 Int 29.04 $ 1,578.08 -$ 23-Dec-15 LSF 10.00 $ 1,588.08 -$ 31-Dec-15 Int 23.59 $ 1,611.67 -$ Int-1072 1,759.22 $ 3,370.89 -$ 4-Jan-16 3370.89 - $ Case No: 420984 Determination Page 7 of 7 1063. The Applicants have not been double charged for interest on the loan. Rather it has been transferred from one account to another. However, to the extent that the interest charged on the overdrawn balance on account 1633 exceeds the interest that would have been charged if the interest was debited to the loan account in the first place, the Applicants are entitled to a refund o f $134.96. Loan service fees charged to account 1633 totalling $60 should also be refunded. The refund should be rounded up to $200. The Applicants are entitled to an award of non-financial loss The Transfer was a result of the Applicants having insufficient funds in account 1633. However Applicants were entitled to an explanation about the Transfer, which to date the FSP has failed to adequately provide. In the circumstances, it is reasonable to accept the FSP’s failure to provide this explanation has caused the Applicants unnecessary and avoidable stress and inconvenience. The FSP is required to pay the Applicants an award of $500 ($250 each) in non-financial loss. This is to be paid to reduce the current Loan balance. The FSP was not required to write to the builder The Applicants have provided an email trail between them and the FSP from 7 July 2015 to 9 July 2015, where they asked the FSP to write to the builder because they were having issues with the Construction. The FSP had no responsibility or duty to write to the builder. The FSP told the Applicants this when it responded to their email on 9 July 2015, and suggested contacting the appropriate insurer to see if they could pursue the matter further. The Applicants have the responsibility for managing the building contract, including any issues with the contract and the quality of the building. The FSP is not required to compensate the Applicants in this regard. Case number 420984 Applicant s Ms Cathy O'Connell & Mr Michael Fahey Case No: 420984 Recommendation Page 2 of 2 Financial Services Provider National Australia Bank Limited (FSP) Recommendation Case No: 420984 Recommendation Page 1 of 8 Case number: 420984 28 April 2016 1 Overview 1.1 Dispute In September 2014, the Applicants entered into a $440,000 Term Loan contract ending 1072 (Loan) to build a house on their vacant land at “W” (Construction). The dispute is about whether the FSP:  misled the Applicants about the Loan process and its role in the Construction  unreasonably delayed settlement of the sale of the Applicants’ property at “LP” (Property)  incorrectly applied interest to the Loan and to their account ending 7458 (Account). A full list of the Applicants loans are se t out at section 3.1 below. 1.2 Issues and key findings Did the FSP mislead the Applicants about the Loan process and its role in the Construction? The FSP initially provided incorrect information to the female Applicant about the FSP’s role in the Constructio n in a telephone call on 22 May 2014. However, by 8 August 2014, the FSP had corrected that information. They did not rely on any misleading information, as it was corrected before the male Applicant signed the building contract and before the FSP had unco nditionally approved the Loan. Did the FSP met its requirements under the National Consumer Credit Protection Act (NCCPA)? The FSP’s advance of the Loan was appropriate and met its obligations under the NCCPA. Did the FSP unreasonably delay settlement of the sale of the Property? On balance the FSP delayed settlement of the Property between 23 November and 23 December 2015. The Applicants were entitled to a total refund of $5,592.86 interest, fees and charges, of which the FSP has already refunded $5,000. The FSP is therefore required to refund to the Loan a further $592.68 plus $500 for the Applicants non-financial loss. Case No: 420984 Recommendation Page 2 of 8 Did the FSP incorrectly apply interest to the Loan and the Account? The FSP applied interest correctly. It agreed to, and did, reduce the interest rates on all the Loans as at 16 October 2016. The interest rates increased soon after in line with market conditions. The Loan statements show that from drawdown, the Applicants have on occasions had insufficient funds in the Account to cover the interest payments. The FSP has charged back the failed interest payment to the Loan and increased its balance. It has not applied penalty interest to the Loan or the Account. 1.3 Recommendation This Recommendation is substantially in favour of the FSP. Should the Applicants accept this Recommendation within 30 days of its date (above), within a further 14 days of that acceptance, the FSP must refund a total of $1,092.68 to the Loan (being $592.68 financial loss plus $500 non-financial loss). In the event the Applicants experience financial difficulty in repaying the Loan with the FSP, they should, 14 days after their acceptance of the Recommendation, provide to the FSP a statement of financial position together with a repayment arrangement proposal that will see the Loan repaid over a reasonable period of time. The FSP must give genuine consideration to the Applicants proposal, but is not obliged to accept it if the FSP does not consider it to be reasonable. If the parties are unable to agree on a repayment arrangement within 30 days of the Applicants proposal, or no proposal is provided within the 14 days (of the parties acceptance of this Recommendation), the FSP will be entitled to take debt recovery action under the terms of the Loan to recover any outstanding balance, once the FOS dispute is closed. Case No: 420984 Recommendation Page 3 of 8 Reasons for Recommendation 2.1 Did the FSP mislead the Applicants about the Loan process and its role in the Construction? The FSP initially misled the female Applicant The FSP accepts that it initially misled the female Applicant about the Loan process and its role in the Construction. This was during a telephone conversation on 22 May 2014, during which it concedes it incorrectly told her that it would:  arrange for its valuer to review the building contract once it was signed  send out its valuer after each stage of the Construction is complete  arrange for its legal team to review the building contract. The FSP corrected the misleading information on 8 August 2014 On 8 August 2014, during its telephone conversation with the female Applicant the FSP corrected the erroneous information it had previously given to her. During this call, it told her:  its conditional Loan approval would be valid for 90 days  to progress with the Loan application, it required a fully executed building contract  it encouraged her several times to seek independent legal advice about any concerns she may have about entering into a building contract and the Loan  it would not send someone to the Construction at each stage but rather, only at the beginning and final stages of Construction  once it receives the executed building contract, its assessment team would order the valuation. This could not be completed until the executed building contract was provided  provided it had no concerns with the documentation, it would unconditionally approve the Loan The Applicants did not rely on the misleading information To establish their claim for misleading conduct, the Applicants must show:  the FSP made the misrepresentation or engaged in the other misleading conduct  they relied on the misrepresentation and changed their position, and  they suffered loss as a result. The female Applicant says that had the FSP not misled her about its role, she would not have entered into the building contract or the Loan contract. The FSP initially provided incorrect information to the female Applicant about its role in the Construction. However, even if she continued to rely on the incorrect information when she signed the building contract on 26 July 2014, the FSP had corrected this information before:  the male Applicant signed the building contract on 13 August 2014, and  they had both signed the Loan contract on 21 October 2014. Case No: 420984 Recommendation Page 4 of 8 The building contract was between the female Applicant as Owner 1 and the male Applicant as Owner 2 on the one hand, and the builder on the other. Under the building contract, the builder agreed to build a house at W on the terms set out in the contract. Although the female Applicant signed it on 26 July 2014, the building contract did not come into effect until at least 13 August 2014, when the male Applicant signed it. It is clear the female Applicant had time, from when the FSP had corrected its positon about its role in the Construction on 8 August 2014, to reconsider whether to proceed with the building contract and in particular, have the male Applicant sign it. There was also time for the Applicants to obtain legal and other advice about the building contract and the Loan. The FSP encouraged the female Applicant in its telephone call on 8 August 2014 to consider obtaining legal advice. She says she chose not to do so because it was too late, however this is incorrect. A detailed timeline of events is set out at section 3.2 below. 2.2 Did the FSP met its requirements under the NCCPA? The FSP’s advance of the Loan was appropriate The NCCPA introduced requirements on credit providers and those providing credit assistance to ensure that a regul ated loan, such as the Loan was “not unsuitable” for the consumer. A loan is regulated under the NCCPA if it is for personal, household, or domestic use or for residential investment. A loan will be unsuitable if the consumer cannot comply with their financial obligations without substantial hardship, or if the loan did not meet the consumer’s requirements and objectives. The female Applicant says the FSP:  failed to appropriately assess the building contract, leading to her borrowing a further $55,000 under the Loan and using an additional $100,000 of her own savings to complete the Construction, and  ought to have determined there was insufficient funding to complete the Construction without her having to borrow more money. The FSP has not provided any information to show whether it considered how the Applicants would fund the exclusions under the building contract. However, in the circumstances the availabl e information shows the FSP’s advance of the Loan was appropriate and that it met its NCCPA obligations as:  the FSP appropriately assessed the Applicants’ as high net worth individuals who could service and repay the Loan without substantial hardship  the FSP appropriately assessed the total Loan to Value ratio after completion of the Construction at less than 25%  a term loan with building conditions met the Applicants’ requirements to fund the Construction and objectives to build a home to live in  the Applicants and the FSP were aware of the exclusions set out in the building contract and of the requirement they would need to privately fund any increase in costs. That is, where the actual cost of the Prime Cost Items and work for which Case No: 420984 Recommendation Page 5 of 8 Provisional Sums had been specified exceed the estimates set out in the building contract and the Excluded Items set out in Schedule 5 to the building contract  when the Applicants made the application to the FSP in February 2015 to borrow a further $55,000 to complete the Construction, it agreed and advanced this on 6 March 2015. 2.3 Did the FSP unreasonably delay settlement of the sale of the Property? The FSP likely caused settlement to be delayed The Applicants say the FSP unreasonably delayed settlement of the sale of the Property between 23 November 2015 and 23 December 2015, because it did not have the appropriate Property title. The available documents show that:  on 28 October 2015, the FSP received the Contract of Sale which contained the Applicants subdivision plans for the Property  the Property was initially supposed to settled on 23 November 2015 (see the Statement of Adjustments provided by the FSP)  the FSP lodged a request with the Department of Environment, Land, Water & Planning (DELWP) on 23 November 2015 to have the title amended. The FSP says it only received notice of the Applicants’ intentions to subdivide the Property by telephone on 4 November 2015. Despite repeated requests, the FSP has not provided any information to support this and its contact notes contain no record of this call. On balance therefore the FSP was aware of the subdivision plan from 28 October 2015 and should have made the request to the DELWP in time for settlement to proceed on 23 November 2015. The FSP caused settlement to be unreasonably delayed between 23 November and 23 December 2015. The FSP is required to compensate the Applicants for their loss The remedy for the FSP’s unreasonable delay to settlement between 23 November and 23 December 2015 would be a refund of interest, fees and charges applied to the Loan between that period. The FSP had previously agreed to cap the interest payable on their Loans from 23 November 2015. However, the statements for all of the Loans show the FSP continued to charge interest during this period totalling $5,592.68. On 22 September 2015, in an attempt to resolve the dispute, the FSP made an ex gratia payment of $5,000 to the Account. The Applicants withdrew this money on 23 September 2015. The Applicants are therefore entitled to a refund of a further $592.68 to the Loan. This represents the difference between the interest charged across all the Loans from 23 November 2015 to 23 December 2015, less the $5,000 ex gratia payment already made. Case No: 420984 Recommendation Page 6 of 8 In addition, the FSP should pay the Applicants an award of $500 non-financial loss for causing settlement to be unreasonably delayed. This amount is to be paid to further reduce the balance of the Loan. 2.4 Has the FSP incorrectly applied interest to the Loan and the Account? The FSP applied interest rate reductions to the Loans The female Applicant requested the FSP reduce the interest rates on the Loans, which is supported by the FSP’s letter of response to the dispute dated 12 October 2015. Effective 16 October 2016, the FSP agreed to reduce all of the Loans’ interest rates to 4.34%.The Loans statements show this reduction occurred. The interest rates on all of the Loans rose to 4.51% in line with market conditions. The FSP announced this increase in late October 2015. The FSP applied the increases to the Loans in line with this on 12 November 2015. The interest charges were correct The female Applicant says the FSP incorrectly charged debit interest to the Account from the Loan. The statements for the Loan and the Account show interest reversals have occurred from time to time on the Account and the Loan. This is because there was insufficient funds in the Account to cover interest payments on the Loan at those times. When this has occurred, the FSP reversed the interest charge back to the Loan, thereby increasing the Loan balance. The FSP has not applied penalty interest to the Loan or the Account. The Applicants have not established the FSP has incorrectly applied interest to the Loan and the Account. Case No: 420984 Recommendation Page 7 of 8 Supporting information 3.1 The Applicants loans with the FSP Loans/Ac count A/c number ending Current Balance Banking Account ( Account ) 7458 $9,524.62 CR as at 28 April 2016 Home Loan Account (Interest only) ( Loan) 1072 $321,302 outstanding as at 28 April 2016 Home Loan Account (Principal & Interest) 9251 Paid out and closed on 24 December 2015 Home Loan Account (Principal & Interest) 9674 Paid out and closed on 24 December 2015 Home Loan Account (Principal & Interest) 2907 Paid out and closed on 24 December 2015 3.2 Timeline of events Date Event 2014 22 May 2014 The female Applicant telephones the FSP and discusses a Loan to fund the Construction of a house at W and the FSP’s role in the construction process. 4 July 2014 The FSP grants conditional approval of the Loan. 26 July 2014 The female Applicant signs the Building Contract. 8 August 2014 The female Applicant telephones the FSP and further discusses the Loan and the Construction. 13 August 2014 The male Applicant signs the Building Contract. 29 September 2014 The FSP unconditionally approves the Loan. 21 October 2014 The Applicants sign the Loan contract. 22 October 2014 The Loan draws down. 2015 6 March 2015 The FSP advances a further $55,000 under the Loan. 22 September 2015 The FSP makes an ex gratia payment of $5,000 to the Account. 12 October 2015 The FSP issues its IDR response and reduces the interest rates applicable to each of the four Loans. 4 November 2015 The FSP receives notification of the Applicant’s intention to subdivide the Property. 23 November 2015 The sale of the Property is s cheduled for settlement but did not proceed. Case No: 420984 Recommendation Page 8 of 8 23 December 2015 The sale of the Property settled.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.