Text of the determination
Determination
Case No: 420659 Determination Page 1 of 4
Case number: 420659 21 October 2016
1 Overview
1.1 Dispute
The applicant lodged a claim with the financial services provider (FSP) after noticing
damage to his roof and ceiling on or about 27 December 2014.
Whilst the FSP claims the damage was not a result of an insured event but rather to
pre-existing damage it determined the collapse of the roof of the property would not
have occurred had an appropriate make safe been carried out when the applicant
first lodged the claim.
The FSP offered to cash settle the applicant’s claim in accordance with the terms of
the policy. The applicant rejected the offer and maintains the FSP should complete
the repairs as identified in the scope of works by FM.
This dispute was subject of a recommendation. The Case Manager recommended
that subject to the applicant completing any remedial work as required, the FSP was
to complete the repairs as per the scope of works prepared by FM. A copy of the
recommendation is attached.
The FSP rejected the recommendation. It concedes it is liable for the costs of repairs
as per FM ’s scope of works but maintains it is entitled to elect cash settle the claim
rather than complete the repairs under the terms of the policy.
1.2 Issues and key findings
Is the FSP required to complete the repairs in accordance with the scope of
work identified by FMG?
Subject to the applicant completing the remedial work as required by the engineer,
TG, the FSP is required to complete the repairs as per FM’s scope of works.
1.3 Determination
This determination is in favour of the applicant.
The FSP is required to complete the repair of applicant’s property as per the scope of
works provided by FM once the applicant has completed the relevant remediation
work identified by TG.
Case No: 420659 Determination Page 2 of 4
2 Reasons for determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the information
exchanged.
The FSP provided a further submission on rejection of the recommendation. The
FSP conceded that it is liable for the cost to repair all of the damage as per FM ’s
statement of works. It maintains however that it is not obliged to complete the repair
as the policy provides it with the discretion as to how to settle its liability.
The FSP maintains the decision that the FSP carry out repairs falls outside the
Financial Ombudsman Service Australia (FOS) jurisdiction as the liability does not
stem from any claim under the policy.
The applicant in response noted that there is nothing either cogent or persuasive in
the additional notice of response from the FSP.
In response to suggestions by the FSP that the applicant ’ s neighbour might not
cooperate the applicant provided a statement from the neighbour confirming:
he has no objections to the FSP being required to manage the repair of the
duplex rook including work on his property
he agrees to join and share with the applicant in any rectification work required
to deal with the preexisting issues as per the Service’s recommendation
including rectifying the footing issues evident in the premises
The FSP has not responded to the applicant’s further submission .
2.1 The FSP is required to undertake the repairs
The Terms of Reference under which FOS operates provide under Paragraph 9.1
that FOS may decide that an FSP or applicant undertake a course of action to
resolve a dispute includi ng the meeting of a claim under an insurance policy by, for
example, repairing, reinstating or replacing items of property.
The guidelines accompanying the Terms of Reference note that when FOS decides
on a remedy, the aim is to, as nearly as possible, either place the applicant in a
position they would have been in if the conduct of the FSP had not caused a loss or
compensate the applicant for the loss to the extent that FOS holds the FSP
responsible.
The overarching requirement of FOS when reaching a determination is to consider
what is fair in all the circumstances having regard to relevant legal principles,
applicable industry codes or guidance as to practice, good industry practice and prior
relevant decisions.
Quotations provided
The FSP has provided two quotations for the repair of the applicant’s property . Both
quotations indicate that the builder is unable to provide a guarantee for the repairs as
there are pre-existing issues with the property.
Case No: 420659 Determination Page 3 of 4
The builders do not say the repairs cannot be completed but that it is necessary for
the pre-existing defects to be repaired before further work can be completed. This is
not an unreasonable.
The applicant does not object to this and has agreed to conduct the appropriate
remedial work. The applicant has provided a statement from his neighbour who
confirms that he agrees to conduct any necessary remedial work so that his property
may be repaired.
Engineering reports
The applicant provided an engineer’s report from TG. TG identified the remedial
action required including the construction of a new vertical barrier, the underpinning
of the front two rooms of the building, restumping of the three rooms of the building,
restumping of the dining room and repairing any stormwater leaks and guttering and
conducting any cosmetic repairs 12 months after the completion of the remedial
work.
FM identified differential movement in reactive soils has been a cause of some
damage to the property not related to the recent roof collapse. The scope of works
provided by FM did not cover damage caused by the long term foundation issues.
I am satisfied based on the information obtained that the property is repairable
subject to the remediation works being conducted which the applicant (and
neighbour) have agreed to do.
The FSP must exercise the discretion under the policy reasonably when
settling a claim.
The policy provides that the FSP has a discretion as to whether to repair or cash
settle the claim for the cost of repairs. When exercising such discretion however the
FSP must act reasonably and consistent with the contract it has with the applicant.
The discretion should not be exercised without proper consideration of the
circumstances of the loss and the capacity for the repairs to be completed based on
the cash settlement.
In this dispute it is impossible to determine the cost to repair the property until the
remediation work is conducted by the applicant. The cost may be more or less than
the amount quoted by the FSP’s builders .
Given this I am satisfied that it is fair in the circumstances that the FSP be required
to conduct the repairs to the property once the remediation work has been completed
by the applicant (and his neighbour).
FSP to complete repairs
I agree with the findings contained in the recommendation.
The applicant should complete the remediation work required to rectify the pre-
existing issues with the building as per engineer TG’s report. Once this work is
completed the FSP is required to complete the repairs as per FM’s scope of works.
Case No: 420659 Determination Page 4 of 4
I accept the C ase Manager’s finding that a reasonable timeframe to commence and
complete the remedial works would be six months from the date of acceptance of the
determination.
In the event that the applicant does not agree to completing the remediation works
within the timeframe then I accept it reasonable for the FSP to cash settle the
applicant’s claim for the sum of $97,680.99 as per the recommendation.
Recommendation
Case No: 420659 Recommendation Page 1 of 6
Case number: 420659 15 April 2016
3 Overview
3.1 Dispute
The roof of the applicant’s house started to collapse and major cracks developed
inside and outside his house. He lodged a claim with the financial services provider
(FSP).
The FSP accepted had make safe work been carried out, the roof would not have
collapsed. However, it maintains it is not liable to rectify any pre -existing issues with
the building or be liable for any work to the neighbour’s portion of the roof.
The applicant says the FSP should carry out the repairs (in lieu of cash settlement).
In the alternative, he says the cash settlement amount is insufficient.
3.2 Issues and key findings
Who is responsible for the repairs?
The FSP’s liability is limited to the dama ge caused by its failure to carry out
appropriate make safe works. The applicant is responsible for any pre-existing issues
with the building.
Both parties are required to carry out repairs they are responsible and liable for. After
the applicant completes the remedial work as per his engineer (TG), the FSP is
required to undertake the repair work, as per the scope of works prepared by its
engineer (FM).
Is the FSP allowed to cash settle its liability?
The FSP can cash settle its liability in certain circ umstances. If those circumstances
are met, then the FSP is entitled to cash settle the applicant $97,680.99. This is a fair
amount reflecting the scope of works prepared by FM.
3.3 Recommendation
This recommendation is substantially in favour of the applicant.
Within six months of acceptance of this recommendation by both parties, the
applicant is required complete the remedial work required to rectify the pre-existing
issues with the building, as per TG’s report. After this work is completed, the FSP is
req uired to carry out the work required as per FM’s scope of works.
Case No: 420659 Recommendation Page 2 of 6
The FSP may only cash settle in the circumstances set out in section 2.2 of this
recommendation. If a cash settlement is to occur, the FSP is required to pay
$97,680.99.
4 Reasons for recommendation
4.1 Who is responsible for the repairs?
FSP’s liability is limited to its failure to make safe
The FSP accepted had it carried out appropriate make safe works shortly after the
claimed was lodged, the applicant’s roof would not have collapsed.
The FSP’s liability is therefore limited to the damage caused by its failure to carry out
appropriate make safe works. Its liability does not stem from any claim under the
policy.
FSP needs to base its settlement as per FM’s scope of works
The FSP engaged an engineer (FM) to assess the damage and provide a scope of
works to establish what repairs are required.
Section 3.1 of this recommendation contains a summary of FM’s report and scope of
works.
The parties disagree as to the extent FSP is required to adhere to FM’s scope of
works. In particular, the FSP says FM’s scope of works goes beyond its liability
because the scope of works includes works to the neighbour’s property and it is not
liable to repair neighbour’s property. Furthermore, there are pre -existing with the
applicant’s building. It says it is not liable to repair/rectify any pre -existing issues.
Having carefully reviewed all the information exchanged, the FSP’s objections to
FM’s scope of works are not accepted.
The applicant’s house shares its roof st ructure with the neighbouring house.
Therefore, to carry out the repairs to the applicant’s roof, FM’s scope of works
included work to the neighbour’s property. FM does not outline any other method to
repair the applicant’s roof.
In the absence of any other information, it appears the only way to effect the
necessary repair to the applicant’s roof is to also carry out some work on the
neighbour’s property.
Given this, the FSP is required to, as per FM’s scope of works carry out the works to
the neighbour’s property.
In relation to the pre- existing issues with the applicant’s building, the applicant
accepts the FSP is not liable for these issues.
The applicant in his response to this Service states:
“There has never been a suggestion that liability (under my claim) extends to the neighbouring
property or obliges FSP to rectify any pre -existing issues (ground movement, subsequent
cracking, etc).”
Case No: 420659 Recommendation Page 3 of 6
Given this, the FSP is required to settle its liability as per FM’s scope of works
because:
FM’s scope of works does not include any work to rectify pre -existing issues
the applicant accepts the FSP is not required to rectify these issues.
Resolution requires both parties’ cooperation
It is necessary for both parties to cooperate in good faith to repair the damage to the
applicant’s house.
In relation to the pre-existing issues with the building, the applicant is responsible for
the cost and rectification of this. The applicant needs to undertake the remedial
actions as set out by his engineer (TG).
After this is completed (barring the last point about the cosmetic repairs), the FSP is
required undertake repairs as per FM’s scope of works. The full details of what is
required are set out in TG and FM’s reports and scopes of work.
4.2 Is the FSP allowed to cash settle its liability?
A cash settlement is only appropriate certain circumstances
The FSP says a cash settlement is appropriate in the circumstances because:
the terms of the policy allows it to pay the applicant the cost to repair the
building instead of repairing it
it is not liable for the neighbour’s portion of the roof
the FSP cannot authorise repairs to the neighbour’s property.
Having considered the FSP’s argument, they are not accepted because the FSP’ s
liability in this instance does not stem from any claim under the policy, as such it
cannot rely on its terms to cash settle the claim.
In addition, the FSP has not shown a viable way to repair the applicant’s roof without
working on the neighbour’s roof . In the absence of any other information, the FSP is
required to do what is necessary to effect the repairs to the applicant’s roof. This
includes working on the neighbour’s roof. To date, the FSP has not provided any
information to suggest the neighbour objects to the FSP doing work to their property.
However, there are appropriate circumstances in which the FSP is entitled to cash
settle:
If the neighbour objects to the work, and does not give its consent for its
completion. The FSP in this instance cannot compel the neighbour to agree to
the work, so would be prevented to effect the repairs as per FM’s scope of
works.
If the applicant does not undertake and complete the remedial work to rectify
the pre-existing issues with the building in a reasonable timeframe. If the pre-
existing issues are not rectified first, the FSP is not obliged to carry out the
repairs as per FM’s scope of works. For the sake of clarity, a reasonable
timeframe to complete the works is six months from the date of acceptance of
this recommendation by both parties.
Case No: 420659 Recommendation Page 4 of 6
The applicant elects to have a cash settlement.
If any of the above conditions are met, then the FSP is entitled to cash settle the
applicant.
If a cash settlement is to occur, the FSP is required to pay $97,680.99
The FSP sought two repair quotations based on FM’s scope of works. One builder
(PI) quoted $86,998.45 and the other Builder (BB) quoted $69,291.13.
Neither quotations include the cost to repair the neighbour’s property. This is a clear
departure to what work is required under FM’s scope of works.
The applicant says the FSP’s cash settlement is inadequate. However, he has not
provided any alternative quotations to support his position.
A fair cash settlement amount should reflect the FSP’s liability as per FM’s s cope of
works. This includes the work required to neighbour’s property.
In the absence of any other information, it is fair in the circumstances, in the event of
a cash settlement for reasons given above, the FSP pay the applicant $97,680.99.
This amount is calculated on the average of the two FSP builders’ quotations, plus an
additional 25% to cover the cost of repairs to the neighbour’s property.
Case No: 420659 Recommendation Page 5 of 6
5 Supporting information
5.1 Key documents relied on
Record Key points
Applicant’s engineer
(BC)
Report
28.7.2010
Cracking throughout the applicant and the neighbour’s house. He
noted the damage was mostly to the front of the property.
Movement of the brick walls likely due to foundation movement
caused by differential foundational moisture conditions. The trees
planted near the building has dried out and shrink the founding
soils.
Recommended for removal of all nearby trees.
FSP’s builder (JL )
Report
27.12. 2014
Tiled roof has partially collapsed and bricks walls were starting to
collapse. He deemed the property too dangerous for tradespeople
to work in. An engineer is required to inspect the damage.
FSP’s assessor (PP )
Report
31.12.2014
T he front half of the ho me has large c racks to the walls and
ceilings. He was unable to inspect the roof due safety reasons, but
could see the roof has a sag in the middle. Recommends an
engineer be appointed to determine the cause of damage and
prepare scope of works.
FSP’s e ngineer (FM )
Report
27.1.2015
Damage to the timber roof framing above the hallway and front
bedroom, partial collapse of the brickwork to the northern wall
under the collapsed section of the roof, split of timber under purlins
and valley beams, brickwork c racking to the northern wall,
brickwork cracking to the western and northern walls of the hallway
and front bedroom.
In relation to the timber roof framing damage, this occurred over
many tears as a res ult of long term creep and shrinkage of the
timber me mbers, resulting in the reduction of the structural
capacity of the framing under the weight of the terracotta roof tiles.
In relation to the splitting/warping of the timber beams roof framing,
this is due to long term creep deflection and overstressing of timber
beams being installed in a unseasoned condition.
The roof structure had inadequate structural capacity to support
the additional loading condition caused by high wind on
03.01. 2015. The collapse of the roof would not have happened
during the storm had appropriat e make safe work been carried out
when assessor PP inspected the damage.
The location and pattern of the walls cracks observed in the front
section of the house is typical of damage caused by differential
foundation movement in reactive soi ls. This damage is not related
to the recent roof collapse.
FSP’s engineer (FM )
Scope of works
8.4.2015
The scope of works is for purposes of reinstating the collapsed
section of the roof structure. It does not cover damage caused by
long term foundation and undamaged sections of the roof
structure.
T he scope of works details out the following areas requires work:
Case No: 420659 Recommendation Page 6 of 6
replace the northern section of the timber framing with new roof
trusses, replace roof tiles to match existing (undamaged tiles to be
reused), reinstate eaves gutters, soffit linings, flashing and sarking,
reinstate roof insulation/sisalation, replace the top four courses of
external brickwork at the northern side of the house, reinstate the
internal plasterboard ceilings, co rnices, skirting, architraves,
lighting and fittings to the northern section of the applicant and
neighbour’s house, replacement of all electrical wiring in the roof
ceiling space, install new downpipes, eaves gutters and box gutter.
FSP’s builder (BB)
Repair quotation
30.4.2015
The builder is unable to carry out the repairs as per the quotation.
The quotation is based on the scope of works. However, a number
of items were not included. The quotation does not include the cost
to: repairing the neighbou r’s roof, obtaining a building permit to
compartmentalise the roof spac e of the properties, repairing the
wall cracks, investigating and remediating the building’s movement
and settlement.
The quotation is subject to the repairs to neighbour’s roof be
unde rtaken concurrently (not included in the quotation).
Applicant’s engineer
(TG)
Report
18.11.2015
The brick cracking to the front of the building, and ceiling has
pulled away from the front wall in the hall way.
The damage is caused by a number of facto rs: tree drying
settlement, minor drying settlement and minor edge heave.
The wall movements did not caused the roof structure to collapse
because the magnitude of the movements is not enough to allow
the rafters and ceiling joists to drop out of the pock ets in the brick
walls. The front nort hern wall has insufficient tie back to the roof
structure. If the roof had been suitability tied into the front wall, the
level of brick work cracking and wall rotation would have been
minimised.
The roof failure was not caused by wind pressure either.
Remedial action required: construct a new vertical barrier, underpin
the front two rooms of the building, restump the front three rooms
of the building, restumping of the dining room, check and repair
any leaking stormw ater downpipes and guttering, repair any
cosmetic issues twelve months (one full normal seasonal cycle)
after the completion of the remedial work.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.