Home / Financial Firm (Unknown - Insurer) / Determination 420659

Determination 420659

Insurer elected to cash settle rather than repair storm and roof collapse damage

FirmFinancial Firm (Unknown - Insurer)
Decided2016-11-14
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$97,681
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Roof collapse damage was partly caused by the FSP's failure to make safe. The FSP disputed whether it had to repair or could cash settle. AFCA ordered repairs after the applicant completes pre-existing remediation, with a cash fallback of $97,680.99.

The FSP must exercise its policy discretion to repair or cash settle reasonably, and its liability is for the make-safe failure, so repairs per the FM scope of works are fair once remediation is done.

Issues

Subjects and remedies

home or building damagerepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 420659 Determination Page 1 of 4 Case number: 420659 21 October 2016 1 Overview 1.1 Dispute The applicant lodged a claim with the financial services provider (FSP) after noticing damage to his roof and ceiling on or about 27 December 2014. Whilst the FSP claims the damage was not a result of an insured event but rather to pre-existing damage it determined the collapse of the roof of the property would not have occurred had an appropriate make safe been carried out when the applicant first lodged the claim. The FSP offered to cash settle the applicant’s claim in accordance with the terms of the policy. The applicant rejected the offer and maintains the FSP should complete the repairs as identified in the scope of works by FM. This dispute was subject of a recommendation. The Case Manager recommended that subject to the applicant completing any remedial work as required, the FSP was to complete the repairs as per the scope of works prepared by FM. A copy of the recommendation is attached. The FSP rejected the recommendation. It concedes it is liable for the costs of repairs as per FM ’s scope of works but maintains it is entitled to elect cash settle the claim rather than complete the repairs under the terms of the policy. 1.2 Issues and key findings Is the FSP required to complete the repairs in accordance with the scope of work identified by FMG? Subject to the applicant completing the remedial work as required by the engineer, TG, the FSP is required to complete the repairs as per FM’s scope of works. 1.3 Determination This determination is in favour of the applicant. The FSP is required to complete the repair of applicant’s property as per the scope of works provided by FM once the applicant has completed the relevant remediation work identified by TG. Case No: 420659 Determination Page 2 of 4 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the information exchanged. The FSP provided a further submission on rejection of the recommendation. The FSP conceded that it is liable for the cost to repair all of the damage as per FM ’s statement of works. It maintains however that it is not obliged to complete the repair as the policy provides it with the discretion as to how to settle its liability. The FSP maintains the decision that the FSP carry out repairs falls outside the Financial Ombudsman Service Australia (FOS) jurisdiction as the liability does not stem from any claim under the policy. The applicant in response noted that there is nothing either cogent or persuasive in the additional notice of response from the FSP. In response to suggestions by the FSP that the applicant ’ s neighbour might not cooperate the applicant provided a statement from the neighbour confirming:  he has no objections to the FSP being required to manage the repair of the duplex rook including work on his property  he agrees to join and share with the applicant in any rectification work required to deal with the preexisting issues as per the Service’s recommendation including rectifying the footing issues evident in the premises The FSP has not responded to the applicant’s further submission . 2.1 The FSP is required to undertake the repairs The Terms of Reference under which FOS operates provide under Paragraph 9.1 that FOS may decide that an FSP or applicant undertake a course of action to resolve a dispute includi ng the meeting of a claim under an insurance policy by, for example, repairing, reinstating or replacing items of property. The guidelines accompanying the Terms of Reference note that when FOS decides on a remedy, the aim is to, as nearly as possible, either place the applicant in a position they would have been in if the conduct of the FSP had not caused a loss or compensate the applicant for the loss to the extent that FOS holds the FSP responsible. The overarching requirement of FOS when reaching a determination is to consider what is fair in all the circumstances having regard to relevant legal principles, applicable industry codes or guidance as to practice, good industry practice and prior relevant decisions. Quotations provided The FSP has provided two quotations for the repair of the applicant’s property . Both quotations indicate that the builder is unable to provide a guarantee for the repairs as there are pre-existing issues with the property. Case No: 420659 Determination Page 3 of 4 The builders do not say the repairs cannot be completed but that it is necessary for the pre-existing defects to be repaired before further work can be completed. This is not an unreasonable. The applicant does not object to this and has agreed to conduct the appropriate remedial work. The applicant has provided a statement from his neighbour who confirms that he agrees to conduct any necessary remedial work so that his property may be repaired. Engineering reports The applicant provided an engineer’s report from TG. TG identified the remedial action required including the construction of a new vertical barrier, the underpinning of the front two rooms of the building, restumping of the three rooms of the building, restumping of the dining room and repairing any stormwater leaks and guttering and conducting any cosmetic repairs 12 months after the completion of the remedial work. FM identified differential movement in reactive soils has been a cause of some damage to the property not related to the recent roof collapse. The scope of works provided by FM did not cover damage caused by the long term foundation issues. I am satisfied based on the information obtained that the property is repairable subject to the remediation works being conducted which the applicant (and neighbour) have agreed to do. The FSP must exercise the discretion under the policy reasonably when settling a claim. The policy provides that the FSP has a discretion as to whether to repair or cash settle the claim for the cost of repairs. When exercising such discretion however the FSP must act reasonably and consistent with the contract it has with the applicant. The discretion should not be exercised without proper consideration of the circumstances of the loss and the capacity for the repairs to be completed based on the cash settlement. In this dispute it is impossible to determine the cost to repair the property until the remediation work is conducted by the applicant. The cost may be more or less than the amount quoted by the FSP’s builders . Given this I am satisfied that it is fair in the circumstances that the FSP be required to conduct the repairs to the property once the remediation work has been completed by the applicant (and his neighbour). FSP to complete repairs I agree with the findings contained in the recommendation. The applicant should complete the remediation work required to rectify the pre- existing issues with the building as per engineer TG’s report. Once this work is completed the FSP is required to complete the repairs as per FM’s scope of works. Case No: 420659 Determination Page 4 of 4 I accept the C ase Manager’s finding that a reasonable timeframe to commence and complete the remedial works would be six months from the date of acceptance of the determination. In the event that the applicant does not agree to completing the remediation works within the timeframe then I accept it reasonable for the FSP to cash settle the applicant’s claim for the sum of $97,680.99 as per the recommendation. Recommendation Case No: 420659 Recommendation Page 1 of 6 Case number: 420659 15 April 2016 3 Overview 3.1 Dispute The roof of the applicant’s house started to collapse and major cracks developed inside and outside his house. He lodged a claim with the financial services provider (FSP). The FSP accepted had make safe work been carried out, the roof would not have collapsed. However, it maintains it is not liable to rectify any pre -existing issues with the building or be liable for any work to the neighbour’s portion of the roof. The applicant says the FSP should carry out the repairs (in lieu of cash settlement). In the alternative, he says the cash settlement amount is insufficient. 3.2 Issues and key findings Who is responsible for the repairs? The FSP’s liability is limited to the dama ge caused by its failure to carry out appropriate make safe works. The applicant is responsible for any pre-existing issues with the building. Both parties are required to carry out repairs they are responsible and liable for. After the applicant completes the remedial work as per his engineer (TG), the FSP is required to undertake the repair work, as per the scope of works prepared by its engineer (FM). Is the FSP allowed to cash settle its liability? The FSP can cash settle its liability in certain circ umstances. If those circumstances are met, then the FSP is entitled to cash settle the applicant $97,680.99. This is a fair amount reflecting the scope of works prepared by FM. 3.3 Recommendation This recommendation is substantially in favour of the applicant. Within six months of acceptance of this recommendation by both parties, the applicant is required complete the remedial work required to rectify the pre-existing issues with the building, as per TG’s report. After this work is completed, the FSP is req uired to carry out the work required as per FM’s scope of works. Case No: 420659 Recommendation Page 2 of 6 The FSP may only cash settle in the circumstances set out in section 2.2 of this recommendation. If a cash settlement is to occur, the FSP is required to pay $97,680.99. 4 Reasons for recommendation 4.1 Who is responsible for the repairs? FSP’s liability is limited to its failure to make safe The FSP accepted had it carried out appropriate make safe works shortly after the claimed was lodged, the applicant’s roof would not have collapsed. The FSP’s liability is therefore limited to the damage caused by its failure to carry out appropriate make safe works. Its liability does not stem from any claim under the policy. FSP needs to base its settlement as per FM’s scope of works The FSP engaged an engineer (FM) to assess the damage and provide a scope of works to establish what repairs are required. Section 3.1 of this recommendation contains a summary of FM’s report and scope of works. The parties disagree as to the extent FSP is required to adhere to FM’s scope of works. In particular, the FSP says FM’s scope of works goes beyond its liability because the scope of works includes works to the neighbour’s property and it is not liable to repair neighbour’s property. Furthermore, there are pre -existing with the applicant’s building. It says it is not liable to repair/rectify any pre -existing issues. Having carefully reviewed all the information exchanged, the FSP’s objections to FM’s scope of works are not accepted. The applicant’s house shares its roof st ructure with the neighbouring house. Therefore, to carry out the repairs to the applicant’s roof, FM’s scope of works included work to the neighbour’s property. FM does not outline any other method to repair the applicant’s roof. In the absence of any other information, it appears the only way to effect the necessary repair to the applicant’s roof is to also carry out some work on the neighbour’s property. Given this, the FSP is required to, as per FM’s scope of works carry out the works to the neighbour’s property. In relation to the pre- existing issues with the applicant’s building, the applicant accepts the FSP is not liable for these issues. The applicant in his response to this Service states: “There has never been a suggestion that liability (under my claim) extends to the neighbouring property or obliges FSP to rectify any pre -existing issues (ground movement, subsequent cracking, etc).” Case No: 420659 Recommendation Page 3 of 6 Given this, the FSP is required to settle its liability as per FM’s scope of works because:  FM’s scope of works does not include any work to rectify pre -existing issues  the applicant accepts the FSP is not required to rectify these issues. Resolution requires both parties’ cooperation It is necessary for both parties to cooperate in good faith to repair the damage to the applicant’s house. In relation to the pre-existing issues with the building, the applicant is responsible for the cost and rectification of this. The applicant needs to undertake the remedial actions as set out by his engineer (TG). After this is completed (barring the last point about the cosmetic repairs), the FSP is required undertake repairs as per FM’s scope of works. The full details of what is required are set out in TG and FM’s reports and scopes of work. 4.2 Is the FSP allowed to cash settle its liability? A cash settlement is only appropriate certain circumstances The FSP says a cash settlement is appropriate in the circumstances because:  the terms of the policy allows it to pay the applicant the cost to repair the building instead of repairing it  it is not liable for the neighbour’s portion of the roof  the FSP cannot authorise repairs to the neighbour’s property. Having considered the FSP’s argument, they are not accepted because the FSP’ s liability in this instance does not stem from any claim under the policy, as such it cannot rely on its terms to cash settle the claim. In addition, the FSP has not shown a viable way to repair the applicant’s roof without working on the neighbour’s roof . In the absence of any other information, the FSP is required to do what is necessary to effect the repairs to the applicant’s roof. This includes working on the neighbour’s roof. To date, the FSP has not provided any information to suggest the neighbour objects to the FSP doing work to their property. However, there are appropriate circumstances in which the FSP is entitled to cash settle:  If the neighbour objects to the work, and does not give its consent for its completion. The FSP in this instance cannot compel the neighbour to agree to the work, so would be prevented to effect the repairs as per FM’s scope of works.  If the applicant does not undertake and complete the remedial work to rectify the pre-existing issues with the building in a reasonable timeframe. If the pre- existing issues are not rectified first, the FSP is not obliged to carry out the repairs as per FM’s scope of works. For the sake of clarity, a reasonable timeframe to complete the works is six months from the date of acceptance of this recommendation by both parties. Case No: 420659 Recommendation Page 4 of 6  The applicant elects to have a cash settlement. If any of the above conditions are met, then the FSP is entitled to cash settle the applicant. If a cash settlement is to occur, the FSP is required to pay $97,680.99 The FSP sought two repair quotations based on FM’s scope of works. One builder (PI) quoted $86,998.45 and the other Builder (BB) quoted $69,291.13. Neither quotations include the cost to repair the neighbour’s property. This is a clear departure to what work is required under FM’s scope of works. The applicant says the FSP’s cash settlement is inadequate. However, he has not provided any alternative quotations to support his position. A fair cash settlement amount should reflect the FSP’s liability as per FM’s s cope of works. This includes the work required to neighbour’s property. In the absence of any other information, it is fair in the circumstances, in the event of a cash settlement for reasons given above, the FSP pay the applicant $97,680.99. This amount is calculated on the average of the two FSP builders’ quotations, plus an additional 25% to cover the cost of repairs to the neighbour’s property. Case No: 420659 Recommendation Page 5 of 6 5 Supporting information 5.1 Key documents relied on Record Key points Applicant’s engineer (BC) Report 28.7.2010  Cracking throughout the applicant and the neighbour’s house. He noted the damage was mostly to the front of the property.  Movement of the brick walls likely due to foundation movement caused by differential foundational moisture conditions. The trees planted near the building has dried out and shrink the founding soils.  Recommended for removal of all nearby trees. FSP’s builder (JL ) Report 27.12. 2014  Tiled roof has partially collapsed and bricks walls were starting to collapse. He deemed the property too dangerous for tradespeople to work in. An engineer is required to inspect the damage. FSP’s assessor (PP ) Report 31.12.2014  T he front half of the ho me has large c racks to the walls and ceilings. He was unable to inspect the roof due safety reasons, but could see the roof has a sag in the middle. Recommends an engineer be appointed to determine the cause of damage and prepare scope of works. FSP’s e ngineer (FM ) Report 27.1.2015  Damage to the timber roof framing above the hallway and front bedroom, partial collapse of the brickwork to the northern wall under the collapsed section of the roof, split of timber under purlins and valley beams, brickwork c racking to the northern wall, brickwork cracking to the western and northern walls of the hallway and front bedroom.  In relation to the timber roof framing damage, this occurred over many tears as a res ult of long term creep and shrinkage of the timber me mbers, resulting in the reduction of the structural capacity of the framing under the weight of the terracotta roof tiles.  In relation to the splitting/warping of the timber beams roof framing, this is due to long term creep deflection and overstressing of timber beams being installed in a unseasoned condition.  The roof structure had inadequate structural capacity to support the additional loading condition caused by high wind on 03.01. 2015. The collapse of the roof would not have happened during the storm had appropriat e make safe work been carried out when assessor PP inspected the damage.  The location and pattern of the walls cracks observed in the front section of the house is typical of damage caused by differential foundation movement in reactive soi ls. This damage is not related to the recent roof collapse. FSP’s engineer (FM ) Scope of works 8.4.2015  The scope of works is for purposes of reinstating the collapsed section of the roof structure. It does not cover damage caused by long term foundation and undamaged sections of the roof structure.  T he scope of works details out the following areas requires work: Case No: 420659 Recommendation Page 6 of 6 replace the northern section of the timber framing with new roof trusses, replace roof tiles to match existing (undamaged tiles to be reused), reinstate eaves gutters, soffit linings, flashing and sarking, reinstate roof insulation/sisalation, replace the top four courses of external brickwork at the northern side of the house, reinstate the internal plasterboard ceilings, co rnices, skirting, architraves, lighting and fittings to the northern section of the applicant and neighbour’s house, replacement of all electrical wiring in the roof ceiling space, install new downpipes, eaves gutters and box gutter. FSP’s builder (BB) Repair quotation 30.4.2015  The builder is unable to carry out the repairs as per the quotation.  The quotation is based on the scope of works. However, a number of items were not included. The quotation does not include the cost to: repairing the neighbou r’s roof, obtaining a building permit to compartmentalise the roof spac e of the properties, repairing the wall cracks, investigating and remediating the building’s movement and settlement.  The quotation is subject to the repairs to neighbour’s roof be unde rtaken concurrently (not included in the quotation). Applicant’s engineer (TG) Report 18.11.2015  The brick cracking to the front of the building, and ceiling has pulled away from the front wall in the hall way.  The damage is caused by a number of facto rs: tree drying settlement, minor drying settlement and minor edge heave.  The wall movements did not caused the roof structure to collapse because the magnitude of the movements is not enough to allow the rafters and ceiling joists to drop out of the pock ets in the brick walls. The front nort hern wall has insufficient tie back to the roof structure. If the roof had been suitability tied into the front wall, the level of brick work cracking and wall rotation would have been minimised.  The roof failure was not caused by wind pressure either.  Remedial action required: construct a new vertical barrier, underpin the front two rooms of the building, restump the front three rooms of the building, restumping of the dining room, check and repair any leaking stormw ater downpipes and guttering, repair any cosmetic issues twelve months (one full normal seasonal cycle) after the completion of the remedial work.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.