Determination 419569
Dispute over extent of storm damage and settlement amount for home claim
Summary
The applicant's storm damage claim was accepted, but the extent of loss was disputed after a variation quote. AFCA ordered the FSP to pay the additional $35,071.10 from the first variation quote, with no interest or compensation.
The FSP had not shown it met its policy obligations for the storm loss, and the assessor had confirmed the first variation quote as fair and reasonable.
Issues
- Claim amount dispute primary · upheld“The FSP has not established that it has met its obligations in respect to the loss and must pay the additional sum of $35,071.10.”
Subjects and remedies
home or building damagenatural disasterpay claim
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
Case No: 419569 Determination Page 1 of 4
Case number: 419569 23 June 2016
1 Overview
1.1 Dispute
This matter involves a claim by the applicant under her Home and Contents
Insurance Policy held with the financial service provider (FSP), following damage to
the home in a storm on 24 April 2015.
The FSP accepted the applicant’s claim but a dispute has arisen as to the extent of
loss and damage to be covered under the terms and conditions of the policy.
1.2 Issues and key findings
Has the FSP met its obligations in respect to the loss under the terms and
conditions of the policy?
The FSP has not established that it has met its obligations in respect to the loss
under the terms and conditions of the policy and must pay the applicant the
additional sum of $35,071.10.
1.3 Determination
This determination is in favour of the applicant. The FSP is required to pay the
applicant the additional amount of $35,071.10.
The FSP is not required to pay interest or compensation.
Case No: 419569 Determination Page 2 of 4
2 Reasons for determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the material exchanged.
This determination follows consideration of all of the information exchanged and is
based on what is fair in the circumstances, having regard to the relevant legal
principles, terms of the policy, good industry practice and where applicable, prior
determinations.
2.1 Has the FSP met its obligations under the terms and conditions of
the policy?
The FSP has not met its obligations under the terms and conditions of the
policy
As stated, the FSP has accepted the applicant’s claim in relation to loss and damage
to the applicant’s home following a storm on 24 April 2015.
A dispute has arisen as to the extent of the loss and coverage to be provided by the
terms and conditions of the applicant’s Home and Contents Insurance Policy.
Following lodgement of the claim, the FSP arranged for an assessor to attend at the
property to assess the loss and damage and the coverage to be provided by the
policy.
In the first of numerous reports, the assessor advised that the home was impacted by
a significant storm of strong winds, heavy rain and hail.
The assessor confirmed the applicant’s statement to the effect that water entered the
building through the ceiling into several rooms and through the air conditioning vents
in the living room and that on the following Monday, the ceiling in the kitchen
collapsed.
Within that first report, the assessor provided a detailed summary of the water
damage.
Within the second report from the assessor, the assessor confirmed that he had
requested builders (PB) to submit a repair quotation.
Within the third report from the assessor, reference was made to the repair quotation
from PB in the amount of $28,124.80. A copy of the quotation from PB dated 18 May
2015 was attached to the assessor’s third report.
Within the third report, the assessor confirmed:
‘We have now received a repair quotation from (PB) for an amount of $28,124.80 (incl
GST). We have reviewed same and believe it to be fair and reasonable… We would
recommend an authority to repair and seek your approval in this matter…’
The quotation from PB is five pages in length and quite detailed.
Case No: 419569 Determination Page 3 of 4
The evidence exchanged confirms that the applicant requested a cash settlement in
respect to the PB quotation and this was provided by the FSP. At the same time the
FSP also provided a copy of the quotation from PB.
Within its sixth report, the assessor advised:
‘ We have now received a variation quotation from (PB) for an amount of $35,071.10
(incl GST). We requested an explanation from the builder in respect to such a large
variation and we have attached their email reply, which we believe is self-explanatory
and acceptable. We have reviewed the variation in detail and believe it to be fair and
reasonable… We would recommend, at the request of the insured, a cash settlement
be considered as they intend renovating the dwelling…’
The sixth report from the assessor attaches the variation 1 quotation which contains
much less detail than the original quotation of 18 May 2015 referred to above.
The Service notes that the variation 1 quotation appears to be undated and the
reference to a quotation date of 18 May 2015, appears to be a reference to the
original quotation provided by PB.
The applicant sought payment of the variation 1 amount from the FSP. In response to
this request the FSP says it made several attempts to obtain further information from
the assessor regarding the variation but was unsuccessful.
It is not clear as to why the FSP was unable to contact the assessor between
20 August 2015, when contacted by the applicant, and 14 September 2015, when at
the prompting of the applicant, the FSP finally contacted the office of the assessor to
be advised that the original loss adjustor was no longer with the assessing firm.
At this time the applicant engaged her own builder and obtained a quotation dated
7 October 2015 in the amount of $138,000, inclusive of GST.
Whilst this quotation does provide some detail, it is not prepared in the form of a
Scope of Works and nor does it provide details of costs on an item by item basis.
Eventually, the FSP spoke to the assessor’s office and was advised that PB had not
attended the property to carry out an inspection which warranted what the FSP says
was the increased Scope of Works.
An appointment was then made for a building consultant to attend on site with the
applicant on 21 October 2015.
Subsequently, the FSP has provided a further variation 2 from PB in the amount of
$16,948.80.
The FSP says that whilst the applicant maintains that they were entitled to receive an
additional payment of $35,070.17 (sic) as advised by the assessor, the FSP says that
it is apparent the assessor has miscommunicated this information to the applicant
and given the applicant a false expectation.
The FSP says that the assessor requested a re-attendance to be carried out by the
building consultant and that only following the re-attendance on 21 October 2015 was
it identified that there were non claim related damages and at that time the assessor
requested the building consultant to provide a Scope of Works and quotation for
these items.
Case No: 419569 Determination Page 4 of 4
The FSP maintains that the assessor has incorrectly passed on a figure originally
provided by the building consultant for the damages that were deemed to be non-
event related.
The FSP maintains that the original amount of $28,124.80 that was paid to the
applicant was incorrect and resulted in a financial benefit of $11,176 to the applicant.
Having reviewed the exchanged material, it is difficult to accept the FSP’s position.
The Service has been greatly assisted by a number of helpful photographs which
have been provided by the applicant and the assessor. These photographs show that
the applicant’s home was significantly affected by the storm on 24 April 2015.
On the basis of the evidence exchanged, the Service does not accept that the
undated variation 2 quotation in the amount of $16,948.80 adequately represents the
cost of storm repairs, notwithstanding the fact that the report from PB of 4 February
2016 suggests that the quote followed the onside assessment on 21 October 2015
and does not include any items that PB deem to be non-event related.
The Service has difficulty understanding how PB now says the storm related damage
is $16,948.80, when originally PB provided a quotation in the amount of $28,124.80,
and this quotation was varied to and included an additional amount of $35,071.10.
The assessor confirms that not only have they checked the variation with PB, but
also the assessor believed the quotation to be fair and reasonable.
Further, it is clear to the Service from the photographs and the extensive details
provided within the original PB quotation, that the storm related damage is unlikely to
be addressed within the variation 2 quotation.
Given the events that have transpired during the course of this dispute, the Service is
satisfied that it is fair in the circumstances that the FSP pay the applicant the
additional amount detailed within the variation 1 quotation, of $35,071.10.
The Service is conscious of the fact that this finding is for the full amount of variation
1 quotation, but payment in this amount is appropriate given that the amount was
checked by the assessor with PB and confirmed as fair and reasonable.
Noting that there are now four different quotations applicable to this dispute, the
Service is also satisfied that the payment of interest and/or compensation is not
appropriate for the circumstances of this dispute.