Determination 419544

Cyclone claim settled under under-insurance clause

FirmFinancial Firm (Unknown - Insurer)
Decided2016-08-18
ProductGeneral Insurance · Business / commercial
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A plumbing business partnership's cyclone damage claim under its business property cover was cash settled at $19,723.72 after the FSP applied the under-insurance clause based on a quantity surveyor's estimate. AFCA found the clause validly applied, the settlement fair, and the claim not unreasonably delayed, so no further payment is ordered.

The under-insurance clause applies where the sum insured is below 80% of full insurable value, and responsibility for choosing an adequate sum insured rests with the insured and its broker.

Issues

Subjects and remedies

broker or intermediarynatural disastersmall businessno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 419544 Determination Page 1 of 8 Case number: 419544 18 August 2016 1 Overview 1.1 Dispute The applicant operates a commercial plumbing business through a family partnership. He lodged a claim under his business insurance policy for cyclone damage to his property in February 2015. The claim was accepted by the financial services provider (FSP). After the FSP ‟s assessor observed that the property appeared to be substantially under-insured, the FSP engaged a quantity surveyor (CQ) to determine the full insurable value of the property. Based on CQ‟s findings, the FSP applied the under- insurance clause in the policy to reduce the settlement amount. The applicant disputes the FSP‟s ability to rely on the under -insurance clause, as well as the information used to determine the replacement cost of the property. He also says the FSP has unreasonably delayed the settlement of his claim. 1.2 Issues and key findings Can the FSP apply the under-insurance provisions? The available information establishes that the applicant‟s property is significantly under-insured. The under-insurance provisions are clearly set out in the policy documents. Accordingly, the FSP is entitled to apply these provisions for the purpose of calculating the settlement amount. Is the FSP required to increase the settlement amount? The FSP has applied the under-insurance provisions fairly and reasonably, based on advice received from its quantity surveyor (adjusted to adopt a conservative approach which favoured the applicant). Has the FSP unreasonably delayed settlement of the claim? The FSP managed the claim reasonably in the circumstances and therefore the applicant is not entitled to compensation. 1.3 Determination This determination is in favour of the FSP. The FSP is not required to make any further payment to the applicant. Case No: 419544 Determination Page 2 of 8 2 Reasons for determination 2.1 Can the FSP apply the under-insurance provisions? Under-insurance clause applies where property sum insured is too low The „Business Property‟ section of the applicant ‟s policy provides cover for physical loss or damage to the insured property which occurs during the period of insurance, subject to the conditions and exclusions set out in the policy. The business property section contains an underinsurance clause which provides that, where the sum insured for the property shown in the schedule is less than 80% of the “ full insurable v alue” of the property, the FSP is entitled to reduce its liability for damage to the property by a proportionate amount. The expression “full insurable value” is not defined in the policy. However, the general description of the policy terms and conditions which appears at the start of the Product Disclosure Statement (PDS) highlights the under-insurance clause and states that: “The Business Property cover section … contain[s] under -insurance provisions which require you to insure for full value. If you do not, we may pay you a lower amount after taking into account the proportion of under-insurance or you may be required to pay a portion of the loss yourself.” The applicant‟s policy schedule contains wording to similar effect. When he took out the policy, the applicant specified a sum insured of $260,000 for the “building” covered under the busines s property section of the policy. This amount included $60,000 for a shed situated on the property which was leased to a third party. The policy defines “building” to mean any permanently fixed structure at the insured premises, including:  sheds fixed to foundations at the premises;  walls, foundations, storage tanks;  gates, fencing, pavements, roads and other structural improvements related to the buildings; and  external fixed items including lights, signs and air conditioning units Based on the terms of the policy as set out above, the FSP will be entitled to apply the under-insurance clause if the full value of the insured buildings exceeds $260,000 by 20% or more. Available information establishes property is under-insured The insured property comprises the applicant‟s main business premises (the upper storey of which is used as a living area), together with various sheds and other outbuildings, including a large steel-framed shed which is leased to a third party. During his initial assessment of the pro perty, the FSP‟s assessor expressed concern that the property was significantly under-insured. Case No: 419544 Determination Page 3 of 8 Accordingly, the FSP appointed a quantity surveyor (CQ) to advise on the actual replacement cost of the buildings and related infrastructure at the property. CQ estimated the total replacement value at $2,148,678.41. This value included all items which fell within the definition of “buildings” under the property, including the sealed driveway and bitumen paving, boundary fencing and masonry retaining wall. The FSP subsequently adjusted this amount downwards to exclude the cost of rebuilding four sheds at the property, which it accepted the applicant had not intended to insure. The resulting figure of $2,016,887.80 reflected CQ‟s estimate of the cost of replaci ng the main building and the leased shed at the premises, as well as the other infrastructure items. The applicant suggests this amount is excessive. In support of his position, he has provided a quotation from his builder (WF) for $330,000, being the estimated cost of rebuilding the upper level of the property (based on a rebuild cost of $1,250 per square metre for the 264sqm area). The applicant has subsequently clarified that the rebuilding cost per square metre should be increased to $1,700 to reflect the fact that the property is a two storey building. The Panel assumes this amount excludes GST. However, the applicant has indicated that the increased rebuild cost estimate should only be applied in respect of the 264sqm upper level of the building (resulting in an overall cost of $448,800), on the basis that the bottom level is commercial and “a very basic structure”. The applicant also provided a quotation from his own supplier (TS) to replace the leased shed which was insured under the policy for $60,000. The quotation provides for a replacement cost of $74,458.04 (excluding GST). Based on the quotations provided by the applicant, the full value of the insured buildings would be $523,258.04. The buildings sum insured of $260,000 specified in the policy schedule is less than 50% of this amount. Accordingly, even if the applicant‟s estimate is adopted, the property would be under - insured for the purposes of the policy. FSP is entitled to apply under-insurance clause The applicant arranged cover through his insurance broker, who acted as his agent for this purpose. In these circumstances, the FSP is not required to give the applicant a copy of the policy schedule and PDS. In any event, the applicant does not dispute having received the policy documentation. As outlined above, the PDS clearly sets out the circumstances in which the under- insurance clause is triggered and includes a worked example as an aid to Case No: 419544 Determination Page 4 of 8 understanding its operation. The policy schedule also outlines the potential implications of the under-insurance clause. Where the sum insured is less than 80% of the full insurable value, the under- insurance clause applies to every claim for property damage, unless the amount claimed is less than 10% of the sum insured. For the reasons outlined above, the Panel is satisfied that the sum insured is less than 80% of the full insurable value. In the present case, the estimated repair costs of $100,403.64 (excluding GST), exceeds 10% of the sum insured of $260,000. On this basis, the FSP is entitled to apply the formula set out in the under-insurance clause for the purposes of determining the settlement amount. 2.2 Is the FSP required to increase the settlement amount ? Settlement amount is fair and reasonable As outlined above, the FSP‟ s quantity surveyor (CQ) estimated the cost of replacing the main building, the leased shed and the related infrastructure items at the property at $2,016,887.80, which figure excludes the four sheds which the applicant did not intend to insure. The Panel considers that, as a quantity surveyor, CQ is qualified to provide an accurate estimate of the likely cost of rebuilding the various structures at the property. CQ‟s estimate includes an itemised listing of the various costs associated with rebuilding each of these structures. The FSP subsequently agreed to reduce CQ‟s adjusted estimate by a further 20%, in recognition of the fact that the actual rebuilding cost may be up to 20% higher or lower than estimated. The FSP used the resulting figure of $1,613,510.24 as the full insurable value of the insured property for the purpose of applying the under-insurance clause. As outlined above, the applicant provided quotations totalling $523,258.04 for the replacement of the main building and the leased shed. WF‟s quotation of $448,800 for the replacement of the main building is based on an overall cost per square metre figure only, and does not include an itemised costing reflecting the specific features of the relevant buildings. Further, the quotation is for the replacement of the upper level only and does not include any allowance for costs in respect of the lower level. On this basis, the Panel considers that F‟s quotation underestimates the cost of replacing the main building. The FSP‟s quantity surveyor (CQ) reviewed the quotations provided by the applicant for replacing the main building and the leased shed and advised that they did not take into account all relevant building materials and methods required to replace the existing buildings. Case No: 419544 Determination Page 5 of 8 The applicant has not provided any further information in support of his position or to refute CQ‟s findings. Further, the applicant has not provided any alternative costings for the various other infrastructure items (such as the paving, fencing and retaining wall) which are included in CQ‟s estimate. These items of themselves account for over $650,000 in rebuilding costs. As outlined above, the definition of “building” for policy purposes is broad and includes the additional infrastructure items specified by CQ. Accordingly, the FSP is entitled to take these items into account in estimating the full insurable value of the property. Having carefully reviewed the available information, the Panel is satisfied that the cost estimate provided by CQ (as adjusted) provides a fair and reasonable assessment of the full insurable value of the property. The reduction of the estimated amount to reflect a 20% “margin for error” reflects the adoption of a conservative approach which worked in the applicant‟s favour . On this basis, the Panel is satisfied that the full insurable value of $1,613,510.24 adopted by the FSP was reasonable in the circumstances. The FSP used the following formula set out in the under-insurance clause to calculate the settlement amount: Sum Insured x Loss = Settlement amount 80% of full value of risk The application of the formula produced the following outcome : $260,000 x $100,403.64 = $20,223.72 $1,290,808.19 (80% x $1,613,510.24) The FSP cash settled the claim for $19,723.72 (being $20,223.72 less the $500 excess) in September 2015. For the reasons outlined above, the Panel is satisfied that the payment of this amount satisfies the FSP‟s obligati ons under the policy. Applicant (and broker) are responsible for ensuring policy meets needs The applicant says the FSP should not be entitled to apply the under-insurance clause as he has acted in good faith and could not reasonably have been aware of the actual replacement cost of the property. It appears the applicant acquired the property for approximately $350,000 some years earlier. As outlined above, the policy documentation clearly sets out the terms of the under- insurance provisions, including the potential consequences if the applicant failed to insure the property for its full value. In these circumstances, it was the broker‟s responsibility to advise the applicant of the potential risks associated with the under-insurance clause and the steps he Case No: 419544 Determination Page 6 of 8 should take in order to mitigate this risk. It was the applicant‟s responsibility to specify an appropriate sum insured, in light of this advice. While outside the scope of this determination, the Panel notes that any failure by the broker to advise the applicant about the nature and effect of the under-insurance clause may constitute a breach of duty. The applicant also says that an under-insurance clause would not have applied, had the main building at the property been insured under a home insurance policy rather than under a business insurance policy. It is not clear whether the applicant would have been able to obtain cover under a home insurance policy, given the building was used for commercial activities. In any event, the applicant (with the benefit of his broker‟s advice) chose to take out a business insurance policy. The inclusion of an underinsurance clause is a relatively common feature of such policies and is included to prevent the policyholder obtaining a benefit disproportionate to the premium paid (which is calculated based on the sum insured). In these circumstances, it was the responsibility of the applicant and his broker to review the terms of the policy (including the under-insurance clause) and ensure the cover offered was approp riate for the applicant‟s needs. 2.3 Has the FSP unreasonably delayed settlement of the claim? FSP has not caused any unreasonable delays The applicant says the FSP unreasonably delayed the processing of his claim. He says his broker made several calls to follow up on the progress of the claim, which he considers should have been finalised sooner than it was. Having reviewed the history of the claim, the Panel is satisfied the FSP has managed the claim reasonably in the circumstances. While the loss occurred on 20 February 2015, the claim was not lodged by the applicant (through his broker) until 24 March 2015. Following lodgement, the FSP appointed its assessor (C) to inspect the damage and prepare a scope of works for the necessary repairs. During C ‟s inspection, it was agreed that the applicant would obtain quotations for the repairs from his preferred contractors. However, it appears the applicant obtained quotations for some of the repairs only, which were not provided to the FSP until August 2015. In the interim, the FSP engaged its own builder to provide a quotation. In the intervening period, the FSP arranged for its quantity surveyor (CQ) to provide an estimate of the replacement cost of the building, in order to address the under - insurance issue. After the applicant disputed CQ‟s estimate, the FSP revised this figure downwards, to exclude certain structures and allow for a margin of error (as discussed above). Case No: 419544 Determination Page 7 of 8 Accordingly, settlement of the applicant‟s claim took just over five months from the date the claim was lodged. While this timeframe would not be ideal in normal circumstances, the Panel is satisfied that the FSP has acted reasonably in the present case. In this regard, the Panel notes that:  the applicant‟s loss arose from a cyclone which w as classified as a catastrophic event. In these circumstances, the Panel accepts insurers‟ resources were stretched to cater for the exceptionally large volume of claims received;  the applicant‟s delay in obtaining quotations for the repairs has contribute d to the time taken to resolve the claim; and  the need to obtain expert advice for the purpose of applying the under- insurance clause has contributed to the delays involved. This occurred as a result of the applicant (and his broker) selecting a sum insured which was less than the full value of the property. As outlined above, during the claim process, the FSP agreed to reduce the full insurable value downwards for the purpose of applying the under -insurance clause, to take account of concerns raised by the applicant. In these circumstances, the Panel does not consider that any delays experienced during the claim process are such as to justify the award of compensation. Case No: 419544 Determination Page 8 of 8 3 Supporting information 3.1 FOS approach to this dispute This dispute has not been the subject of a FOS recommendation. Due to the nature of the dispute, it has been referred directly to a Panel for determination, in line with the Operational Guidelines to the FOS Terms of Reference. The Panel consists of an Ombudsman and two representatives with consumer and insurance experience. The Panel has decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. The Panel has reviewed and considered all of the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination, the Panel has restricted its commentary to those issues that it considers directly relevant to the outcome only. During the course of this dispute, the applicant has been represented by his insurance broker. For the purposes of this determination, submissions made by the applicant‟s broker have been taken as if they had been made by the applicant himself.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.