Determination 418593

Storm and flood damage claim: ceiling water ingress and front fence excluded; rear fences, generator and pump disputed

FirmFinancial Firm (Unknown - Insurer)
Decided2016-08-30
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$500
Amount claimed—
SourceAFCA PDF

Summary

The applicants claimed storm and flood damage to their home, pumps, generator and fences, and the FSP denied the ceilings and front fence. AFCA ordered the FSP to indemnify the rear fences and generator on invoices, with interest on cash settlements and $500 non-financial loss.

The policy excludes rain entering other than through a storm-made opening and excludes storm damage to fences unless optional cover is held, but the FSP must indemnify accepted items promptly.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 418593 Determination Page 1 of 8 Case number: 418593 19 August 2016 1 Overview 1.1 Dispute The applicants lodged a claim for storm and flood damage which occurred on or about 21 April 2015. This affected the pumps and generators as well as the roof/ceiling and fences of the applicants’ home. The Financial Services Provider (FSP) accepted the storm occurred but said it was entitled to deny the claim as rain had not entered the insured property through an opening in the roof of the rooms that had been made directly by the storm. It also said it was entitled to deny indemnity in relation to damage to the front fence as storm damaged fences are not covered by the policy. It agreed to cover the water pump and will consider the generator and rear fences, subject to provision of requested material from the applicants. The case manager provided the parties with a recommendation on the issues in dispute. The recommendation was in favour of the applicants. The applicants accepted the recommendation but it was not accepted by the FSP. In the circumstances, the dispute has been referred to me for determination. 1.2 Issues and key findings Is the FSP obliged to indemnify the applicants for their loss? The FSP is not obliged to indemnify the applicants for the damage to the living room ceiling and games room. While the available evidence establishes there was water damage to the rooms caused by rain seeping into the living room and games room, the material establishes the water did not enter through an opening in the roof over the rooms that had been made directly by the storm or rain. In the circumstances, the FSP is entitled to rely on a policy exclusion to deny liability. The FSP is not obliged to indemnify the applicants for damage caused to the front fence as the material establishes the front fence was flooded by storm water run-off. Damage to fences are excluded under the insured event storm and the applicants did not elect the optional benefit available for storm damage to fences. The FSP is obliged to indemnify the applicants for the water pump (if it is not already done so) and the generator as the FSP’s assessor agreed the pump and the generator were damaged in the storm. Case No: 418593 Determination Page 2 of 8 The FSP is obliged to indemnify the applicants for tree damage to rear boundary fences as the material provided establishes the storm was a severe weather event and photographs provided show the storm caused trees and tree branches to fall on the applicants’ fences. Are the applicants entitled to compensation? The applicants are entitled to compensation as the FSP’s lack of proactivity in its assessment and settlement of the accepted parts of the claim has resulted in an unusual amount of time to resolve the situation and this delay would have interfered with the a pplicants’ expectation of enjoyment or peace of mind. 1.3 Determination This determination is partly in favour of the applicants. Should the applicants accept this determination, then upon provision to the FSP by the applicants of quotes or invoices for the cost to replace/repair the generator and rear fences, the FSP must indemnify them for the storm damage to the generator and rear boundary fences. If it has not done so already, the FSP is to pay the applicants $599 for the cost to replace the pump. To the extent that it is to provide a cash settlement for these items, the FSP must pay interest at the statutory rate from 16 October 2015 until the date of payment. The FSP is also to pay the applicants $500 compensation for non-financial loss. Case No: 418593 Determination Page 3 of 8 2 Reasons for Determination I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the recommendation. I am satisfied the documentation I have relied on has been provided to both parties. Submissions after recommendation After the recommendation was rejected, the FSP made a further submissions and provided further material from it s roofer. The FSP’s further submissions will be referred to where relevant within the determination. 2.1 Is the FSP obliged to indemnify the applicants for their loss ? Material establishes significant storm event on or about 21 April 2015 The applicants must establish on the balance of probabilities they have suffered a loss caused by an event to which the policy responds. It is not in dispute the FSP’s policy covers the applicants for damage to building and contents caused by storm, rain or flood. It is also not in dispute that on or about 21 April 2015 there was a significant storm event in the area of the insured property. On the material provided, I am satisfied the applicants have established a prima facie claim. FSP must establish policy exclusions Once so established, the onus shifts to the FSP to prove on the balance of probabilities an exclusion applies if it seeks to deny or limit its liability for the loss. The FSP relies on policy exclusions which say: ‘ We will not cover:  water damage to your building caused by storm or rain seeping or otherwise entering your building unless the water entered through an opening in the wall or roof that had been made directly by the storm or rain or as a direct result of it;  damage caused by water penetrating or entering your building because it has not been properly maintained or as a result of a design fault, structural defect or because of defective workmanship; …’ The applicants have provided a number of photographs which show the insured property and some fences were severely inundated with rain. It is not in dispute there was water damage to the ceiling of the living room and the games room caused by storm or rain seeping into the rooms through an opening in the roof over those rooms. What is in dispute is whether the opening was made directly by the storm or rain or as a direct result of it. The applicants provided a sketch of the home and indicated water entered and damaged the ceiling of the living room near the fireplace. The applicants have also Case No: 418593 Determination Page 4 of 8 annotated the FSP’s roof inspection and report and photographs. Via the annotations the applicants say:  the ceiling damage in the living room is around the top of the fireplace flue  water entered through the chimney above the lounge room on the western roof  the only silicon applied to the seal around the chimney was applied by the FSP  there was no water damage in the bedrooms  the roof over the separate games room is eight years old  the roof over the house does not leak in the two areas where dents were caused by the water tank being blown over the roof during the storm. The applicants also contend water could not have entered where indicated by the FSP’s roofer as the bedrooms directly below this area have no water damage or leaks. Rather, the applicants say the water came into the fireplace and into the roof. The applica nts provided a video of the sound of “the water running in the roof via the fireplace.” The FSP relies on reports from its assessor and a roofer. The assessor inspected and photographed the damage on 4 June 2015 with the male applicant. The assessor agreed damage was caused by water ingress into ceiling cavities of both the games room and living room. He did not identify any building faults or maintenance issues with the main roof or living room roof. But, as for the games room, he says there was significant misalignment of the roof sheeting. He says the sheeting appears to have been silicone sealed previously. He thought the damage to the sarking pre-existed the storm. On 12 August 2015 the FSP’s roofer inspected and photographed the damage to the roof of the house. He reports the following:  the chimney above the lounge room on the western roof of the house allows rain water to enter through the seal around the chimney. He applied silicone to seal the leak but says the flashing around the chimney is not adequate .  he photographs and discusses the eastern roof, because he was told this was the point of water entry. The applicants have submitted to FOS the water did not the house enter at this point.  there are dents in the tin roof sheets and top ridge caused by a water tank being blown during the storm from the backyard onto the roof and across to the front yard of the eastern roof but this damage is cosmetic only. Water did not enter through an opening which was made by the storm Both the applicants and the roofer agree the top ridge and roof sheets which are dented are not leaking. The roofer describes the damage caused by the dents as cosmetic only. In these circumstances, having considered the material provided by the parties and in particular the photographs of the dents in the roof, I am satisfied, although the dents in the roof were caused by the storm, the dents did not cause an opening in the roof and water did not enter the building through the dents. The comments made by the roofer regarding the join on the eastern roof are not relevant to this claim as the applicants say the rooms below this area did not sustain water damage and the water entered the living room via the chimney. Case No: 418593 Determination Page 5 of 8 The assessor photographed the roof chimney but had no criticism of its structure. However, the roofer is clear in his opinion the leak in the living room was caused by the poor seal around the chimney. After the recommendation he reiterates the cause of water entry around the chimney is most likely from inadequate flashing. He says adequate flashing would have prevented water ingress in this location. I accept the roofer has the necessary expertise to comment. Further the applicants agree water entered the living room via the chimney. Having considered the material provided and in particular the roofer’s photographs of the chimney and the annotations made by the applicants, I am satisfied water entered into the living room because of the inadequate flashing around the chimney. The material provided does not establish the seal was broken by the storm or by the water tank which was thrown onto the eastern side of the roof in the storm. As for the damage to the games room, the roofer does not appear to have examined or reported on the games room. However, the assessor was clear in his initial opinion which was there was significant misalignment of the roof sheeting. Further, photographs taken by the assessor show silicone seals applied to the games room roof. Although the applicants say the roof on the games room was only eight years old, the age of the roof is not determinative of the issue. Rather, from the photographs and information provided, I am satisfied although the games room was damaged because water entered into it, the water did not enter through an opening in the roof which had been made directly by the storm or rain. Storm damaged fences not covered by policy The applicants have provided a sketch of the property and indications where boundary fences were broken. The sketch indicates where the front fence was broken. The sketch is annotated. Various photographs were provided of fallen trees and flooded fences including a photograph annotated “water that damaged front fence.” The FSP’s assessor agrees the front fence was damaged. A photograph is taken of the fence which shows damage. The photograph does not show damage from a fallen tree. The FSP says the front fence was flooded by the stormwater run-off. The applicants appear to agree with that statement. The FSP submits damage to gates and fences are excluded under the insured event of storm. Further, it says the applicants have not elected the optional cover available for these items. The FSP’s policy clearly e xcludes damage caused by storm, rain or flood to gates and fences. For an additional premium, an insured can obtain storm damage cover for gates and fences. The applicants do not dispute they did not take up this optional cover. On the information provided, I am satisfied the front fence was damaged as it was flooded by stormwater run-off. However, this cause of damage is specifically excluded from cover. The applicants do not dispute they did not take out the optional storm damage cover for fences. Accordingly, the FSP is not obliged to indemnify the applicants for the damage to the front fence. Case No: 418593 Determination Page 6 of 8 FSP to indemnify the applicants for tree damage to rear boundary fences The applicants have provided a sketch of the property which indicates several areas where they claim trees and branches have come down on boundary fences. Various photographs are provided of fallen trees close to and on fences. The assessor did not comment on fences other than the front fence. The FSP says this was because the issue was not raised by the applicants. The FSP acknowledges photographs of felled trees resting on fences but say the photographs do not adequately demonstrate the extent of the damage. The FSP says it will consider the claimed damage upon production of a repair quote. After the recommendation, the FSP said it accepted liability for the impact damaged rear fence. However, the sketch provided by the applicants indicates several areas of the four fences behind the house were impacted by trees and branches falling on the fe nces. The FSP acknowledges this aspect of the claim was discussed by the applicants with the FSP in October 2015. There has been ample time for the FSP to assess and make a decision regarding this aspect of the applicants’ claim. I accept the storm was a severe weather event. From the photographs provided, I accept the storm caused trees and tree branches to fall on the applicants’ property and it is probable , fences were impacted and damaged because of the storm. As the FSP has not elected to reassess the damage, or quote the damage, I am satisfied it is fair in all the circumstances it indemnify the applicants for this damage. The applicants are to engage a local fencer to repair the storm damage to the boundary fences as illustrated in the sketch provided by the applicants and seek reimbursement from the FSP. The FSP has reimbursed the applicants $599 for the pump The applicants claim a water pump and generator were damaged. The FSP’s assessor agreed. However he did not provide an assessment of the cost to replace the pump and generator. The FSP said it was willing to consider the applicants’ claim for replacement of water pump and generator upon production of relevant invoices. The applicants provided an invoice in the sum of $599 for a pressure system less tank. The FSP says it passed th is to the claims area for urgent payment. The applicants’ annotation on a diary entry provided indicates the $599 was paid not long after the telephone call to the FSP chasing payment. The FSP is to reimburse the applicants for the cost to replace the generator The FSP’s assessor took a photograph of the generator. The applicants say they have yet to replace it. After the recommendation, the FSP says it will meet the cost of the generator on provision of an invoice. The FSP’s assessor agreed the generato r was damaged in the storm. However he provided no assessment of the loss. I am satisfied it is fair in all the circumstances Case No: 418593 Determination Page 7 of 8 the applicants replace this item and supply the relevant invoice to the FSP for payment. 2.2 Are the applicants entitled to compensation? FOS may award compensation in some circumstances The applicants say the whole claims experience has caused stress and heartache. They say the claims process has been dragging on and the mental toll has been extreme. The FSP does not comment on these contentions. The Terms of Reference allow the payment of compensation (capped at $3,000) for non-financial loss. FOS may decide an FSP should compensate the applicant for such loss only where there has been an unusual amount of physical inconvenience, time taken to resolve a situation, or interference with the a pplicant’s expectation of enjoyment or peace of mind. FOS takes a conservative approach to compensation for non-financial loss. Fair in all the circumstances the FSP pay $500 compensation While I a ccept the FSP was entitled to deny the applicants’ claim in relation to damage to the ceilings in the living room and games room, and to the front fence, I am not satisfied the FSP’s claims handling has been optimum in consideration of the rest of the appl icants’ claims. I consider the FSP’s lack of proactivity in its assessment and settlement of the accepted parts of the claim has resulted in an unusual amount of time to resolve the situation and this delay would have interfered with the a pplicants’ expec tation of enjoyment or peace of mind. I am satisfied it is fair in all the circumstances the FSP pay to the applicants $500 compensation. Case No: 418593 Determination Page 8 of 8 3 Supporting information 3.1 FOS Approach As advised to the parties, FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS recommendation and has proceeded directly to determination. There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered for the purposes of this determination. This dispute has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only. It is an accepted principle of general insurance law that an insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. 3.2 Relevant policy extracts The relevant policy extracts are referred to in the FSP’s Notice of Response dated 3 December 2015. Both the policy document and the Notice have been exchanged with the applicants. 3.3 Other relevant material considered and relied on  Parties’ submissions, emails and photographs .  Correspondence between the parties.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.