Text of the determination
Determination
Case No: 417780 Determination Page 1 of 7
Case number: 417780 23 November 2016
1 Overview
1.1 Dispute
The applicant lodged a claim under his farm insurance policy with the financial
services provider (FSP) after several buildings at his property were damaged by a
cyclone in February 2015.
The FSP accepted the claim and offered to cash settle the applicant for the damage
to his main residence in the amount of $194,815.39, being the estimated cost of
repairs. The FSP has subsequently provided a revised offer of $255,568.57, based
on an updated quotation obtained during the FOS dispute process.
The applicant says the amount offered by the FSP is not sufficient to carry out the
necessary repairs to the property. He considers the claim should be settled on a total
loss basis by payment of the building sum insured ($358,000) or the FSP should be
required to undertake the repairs.
1.2 Issues and key findings
Is the FSP entitled to cash settle the claim?
Under the terms of the policy, the FSP has the discretion to elect to cash settle the
claim, rather than arranging for its contractors to repair the property.
Is the cash settlement offered by the FSP fair and reasonable?
The cash settlement should be increased by 5% to reflect additional building costs
associated with a potentially higher bushfire risk. The FSP should also be required to
contribute to the applicant’s temporary accommodation costs.
1.3 Determination
This determination is partly in favour of the applicant.
The FSP is required to pay the applicant the following amounts in full and final
settlement of his claim:
$268,347 for the costs of repairing the cyclone-related damage to the
applicant’s property, plus interest on this amount as set out in section 2.1 below;
and
$3,000 as a contribution to temporary accommodation costs for the applicant
and his family while the repairs are carried out.
Case No: 417780 Determination Page 2 of 7
2 Reasons for determination
2.1 Is the FSP entitled to cash settle the claim?
FSP is entitled to cash settle claim
Under the terms of the policy, the FSP may settle a claim for damage to the
applicant’s property by:
arranging for its contractors to repair or reinstate the damaged buildings on a
new for old basis; or
paying the applicant the cost of doing so.
It is clear from the terms of the policy that the FSP has the discretion to decide which
settlement method to adopt.
In the present case, the FSP elected to cash settle the claim after its consultants
advised that there was damage to the property which pre-existed the cyclone in
February 2015.
Having reviewed the reports provided, the panel is satisfied that there was pre-
existing damage to the property, including termite damage to the timber wall framing
and corrosion of the roof sheets and gutters.
In these circumstances, the panel considers that the FSP acted reasonably in
deciding to cash settle the claim.
However, in determining the amount of the cash settlement, the FSP was required to
ensure that this amount was sufficient to allow the applicant to engage a builder to
repair the damage to his property caused by the cyclone.
The policy provides that, in addition to the costs associated with restoring the
property, the FSP is required to pay any further costs necessary to ensure that the
building complies with government or local authority bylaws. Accordingly, any cash
settlement paid by the FSP must provide for such costs.
2.2 Is the cash settlement offered by the FSP fair and reasonable?
FSP obtained updated scope of works and quotations
After the applicant lodged his claim, the FSP appointed a building consultant (SB) to
identify the damage to the property caused by the cyclone and prepare a scope of
works for the necessary repairs.
As part of this process, SB engaged a structural engineer (CA) to identify the extent
to which movement damage observed at the property had been caused by the
effects of the cyclone or by naturally occurring earth movement (which is excluded
from cover under the policy).
The FSP’s in itial settlement offer of $194,815.39 was based on the lower of two
quotations provided by its builders for the repairs set out in SB’s scope of works.
Case No: 417780 Determination Page 3 of 7
After the applicant disputed the amount of the cash settlement, the FSP agreed to
engage an independent building consultant to carry out a further inspection of the
property and prepare a new scope of works for the repair of the damage caused by
the cyclone. The applicant nominated MB for this purpose.
Following receipt of MB’s report, the FSP offered to cash settle the applicant for
$255,568.57, based on a quotation provided by its builder (AD) for the repairs set out
in MB’s scope of works.
Applicant says cash settlement underestimates cost of building repairs
The applicant says that the scope of works p repared by MB (on which AD’s quotation
is based) does not include all of the items which are necessary to repair the damage
to the property in a manner which complies with applicable building codes.
In particular, the applicant says that MB’s quotation has been prepared on the basis
that the property has a bushfire rating of BAL-LOW (very low risk), whereas the
property should have been assessed as BAL-19 (moderate risk). The difference in
the bushfire rating has potential implications for the manner in which the repairs need
to be carried out.
Among other things, the applicant also says that the cash settlement amount does
not adequately provide for:
the removal of asbestos at the property;
the extent of roof repairs required;
the rewiring of the property and the upgrading of the electrical switchboard;
the repainting of the property;
a builder’s margin of 20%; and
additional benefits such as demolition costs, consultant’s fees and council
approvals.
The applicant has provided a quotation from his builder (TS) for $324,155.97. While
TS’s quote is not itemised, it appears to be based on MB’s scope of works amended
as necessary to reflect a bushfire rating of BAL-19.
Consultants have provided conflicting information about bushfire rating
As outlined above, the various consultants engaged by the parties have provided
conflicting advice about the appropriate bushfire rating for the applicant’s property.
The bushfire rating in any given case is to be determined according to the process
set out in the provisions of the applicable Australian Standard, based on factors
including the relevant Fire Danger Index, the classification of vegetation at the
property and the slope of the site.
The bushfire rating adopted by the independent building consultant (MB) for the
purpose of his scope of works was based on advice provided by a qualified building
certifier (GD). GD classified the property as BAL-LOW (having a very low risk of
potential exposure to fire), after assessing each of the specific factors referred to
above.
Case No: 417780 Determination Page 4 of 7
T he applicant disputes GD’s assessment of the property, which he says failed to give
sufficient consideration to the different types of vegetation present within the
immediate vicinity. He notes that GD reached his conclusions based on aerial
photographs of the property but did not actually inspect the site himself.
The applicant has provided several photographs of the vegetation around the
property (although it is not entirely clear how far from the property the photographs
were taken). He says that the occurrence of several bushfires in the vicinity of the
property in recent years of itself establishes that the risk of fire damage is more than
“very low”.
As noted above, the quotation provided by the applicant’s builder (TS) states that the
property should be assessed as BAL-19 (moderate risk) and refers to the additional
requirements for construction in bushfire prone areas.
However, nowhere does TS expressly refer to the criteria contained in the relevant
Australian Standard or otherwise indicate on what basis he determined that an
assessment of BAL-19 was appropriate.
The bushfire assessment obtained by the FSP’s first building consultant (SB) in the
course of preparing the initial scope of works classified the property as having a
bushfire rating of BAL-12.5 (low risk).
While not as high a rating as that adopted by the applicant’s builder (TS), a rating of
BAL-12.5 nevertheless imposes additional construction requirements (and therefore
higher costs). However, these obligations are not as stringent as those associated
with a rating of BAL-19.
Cash settlement should be increased by 5% to allow for additional repair costs
Having carefully reviewed the available information, the panel is not satisfied that the
applicant’s property is correctly classifie d as having a bushfire rating of BAL-19.
The applicant’s builder (TS) has provided insufficient information to support the basis
for his assessment of the property, having regard to the criteria set out in the
Australian Standard.
In contrast, the building certifier (GD) engaged by MB has clearly set out his findings
in relation to each of the key assessment parameters, which supports his
assessment of the site as BAL-LOW.
Nevertheless, the panel acknowledges the potential limitations associated with GD’s
desktop review.
Further, the panel notes that the initial consultants (EL) engaged by the FSP
classified the site as BAL-12.5. While the FSP has suggested that EL took a
conservative approach, there is nothing to suggest this was inappropriate in the
circumstances.
Having regard to the matters outlined above, the panel considers it fair in all the
circumstances that the cash settlement amount be increased by 5% (ie $12,778.43)
to allow for additional building costs associated with a potentially higher bushfi re risk.
Case No: 417780 Determination Page 5 of 7
Cash settlement for building repairs is otherwise appropriate
Having carefully reviewed MB’s scope of works, the panel is satisfied that it
accurately reflects the repairs required to address the damage to the property caused
by the cyclone in February 2015.
The FSP’s obligation under the policy extends to repairing the claim -related damage,
including any associated improvements to comply with applicable building
regulations.
However, the FSP is not obliged to repair or replace items of damage which pre-
existed the cyclone and/or were caused by factors which are excluded under the
policy (such as corrosion, rot, wear and tear and gradual deterioration).
Based on the reports provided by the various contractors (and the photographs
included therein), the panel is satisfied that there was significant pre-existing damage
to various parts of the property at the time the cyclone occurred.
The panel notes that MB’s updated scope of works provides for the restumping of the
property in its entirety, despite the FSP having previously obtained a structural
engineer’s report indicating that a substantial proportion of this damage had occurred
prior to the cyclone, as a result of factors which are excluded under the policy.
The scope of works also provides for the removal and replacement of all of the roof
sheeting (other than a limited area at the rear of the property which was not damaged
by the cyclone), in circumstances where it appears there was pre-existing corrosion
in a number of areas.
In relation to some of the more significant issues raised by the applicant, the panel
notes as follows:
the quotation provided by AD provides for the removal of asbestos from the
western wall of the property, as set out in MB’s scope of works. This was the
area where the asbestos material had cracked due to the settlement of the
stumps, which needed to be addressed. However, any requirement to replace
the asbestos throughout the remainder of the building did not arise as a result of
the damage caused by the cyclone;
the applicant has not provided any independent information to dispute SB ’s
findings that there was no cyclone-related damage to the roof framework itself;
the available information does not establish that the additional items referred to
by the applicant (such as repainting and rewiring) were required as a result of
damage caused by the cyclone. Accordingly, the FSP is not liable for these
items;
AD’s quotation includes a builder’s margin of 15% which is reasonable in
circumstances where AD has confirmed he is willing to carry out the repairs.
The fact that other builders may impose a higher margin (or charge more
overall) does not of itself mean that AD’s quot ation is inadequate; and
the applicant has not established an entitlement to payment of additional costs,
noting that AD’s quotation includes an allowance for items such as the
engagement of structural engineers, soil testing and building application fees.
Case No: 417780 Determination Page 6 of 7
FSP is required to pay interest on building settlement amount
The panel has carefully considered whether the FSP should be required to pay
interest on the settlement amount.
The panel acknowledges that the applicant refused to accept the undisputed amount
of $194,815.39 (reflecting the FSP’s initial settlement offer), despite being advised
repeatedly that this would not prejudice the outcome of his dispute.
Nevertheless, the panel considers it appropriate that the FSP be required to pay
interest in order to reflect the fact that it has had the use of the funds during this
period. However, the panel considers interest should be payable at a reduced rate of
2.5% during this period.
The FSP is required to pay interest on the 5% increase in the settlement amount at
the rate determined in accordance with section 57 of the Insurance Contracts Act
1984 (Cth) from 2 October 2015 until the payment date.
FSP is required to contribute to temporary accommodation costs
Under the policy, the applicant’s entitlement to te mporary accommodation benefits is
capped at $12,920, being 20% of the contents sum insured. The FSP has confirmed
that it has cash settled the applicant for this amount.
The applicant seeks payment of additional temporary accommodation costs, while
the repairs to his property are carried out. The applicant says he and his family have
been forced to live in a shed at the property for an extended period of time, pending
the resolution of this dispute.
As noted above, the applicant’s financial difficulties wo uld have been lessened
considerably, had he agreed to accept the proportion of the settlement amount which
was not in dispute.
Nevertheless, the panel considers that the FSP’s actions have also contributed to the
time taken to resolve the claim.
In partic ular, the panel notes that, following receipt of MB’s updated scope of works,
the FSP initially made a revised settlement offer of $90,000 (based on a quotation
provided by AB) despite this amount being manifestly inadequate, having regard to
the previous quotations obtained.
Further, the updated scope of works and quotation obtained by the FSP during the
dispute process ultimately led to a significantly higher settlement offer for the building
repairs, which suggests that the consultants initially appointed by the FSP may have
failed to identify all of the damage attributable to the cyclone.
In these circumstances, the panel considers that the FSP should be required to
contribute an amount of $3,000 to the costs of temporary accommodation for the
applicant and his family while the repairs are carried out. The FSP is not required to
pay interest on this amount.
Case No: 417780 Determination Page 7 of 7
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS recommendation. Due to the nature
of the dispute, it has been referred directly to a panel for determination, in line with
the Operational Guidelines to the FOS Terms of Reference. The panel consists of an
Ombudsman and two representatives with consumer and insurance experience.
The panel has decided this case based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous Financial Ombudsman Service (FOS) decisions (which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
The panel has reviewed and considered all of the material provided by the parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, the panel has restricted its commentary to those issues that it
considers directly relevant to the outcome only.
During the course of this dispute, the applicant has been represented by a claims
adjuster. For the purposes of this determination, submissions made by the
applicant’s claims adjuster have been treated as if they had been made by the
applicant himself.