Home / Financial Firm (Unknown - Insurer) / Determination 417733

Determination 417733

Insurer denied water damage to basement and cellar as not covered

FirmFinancial Firm (Unknown - Insurer)
Decided2016-09-13
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$250,000
SourceAFCA PDF

Summary

The applicant, represented by a solicitor, claimed about $250,000 for basement and cellar water damage under a home policy after the insurer denied the claim. AFCA decided in favour of the insurer, finding the damage came from stormwater run-off over time rather than a single insured event.

The insured must show a loss caused by an insured event; the evidence did not establish that a leaking mains pipe caused the inundation, and ongoing run-off damage is not covered by the storm or escape of liquid cover.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 417733 Determination Page 1 of 8 Case number: 417733 13 September 2016 1 Overview 1.1 Dispute The applicant lodged a claim under his home insurance policy with the financial services provider (FSP), after he discovered that the basement and cellar of his property had been inundated with water in June 2014. The applicant initially advised that the inundation had been caused by flooding due to stormwater run-off. However, he now believes the damage was caused by a leaking cold water main. The FSP denied the claim on the basis that the damage was not caused by the leaking pipe (or any other event insured against under the policy), but by ongoing water entry issues. 1.2 Issues and key findings Is the FSP liable for the claimed damage? The available information does not establish that, on the balance of probabilities, the water entry issues which affected the property were caused by the leaking pipe identified in January 2015. It is more likely that the damage occurred due to the effects of stormwater run-off over a period of time, as a result of inadequate drainage measures. Damage caused in this manner is not subject to cover under the policy. Accordingly, the FSP is not liable for the applicant‟s claim . 1.3 Determination This determination is in favour of the FSP. The FSP is not liable for the applicant‟s claim . Case No: 417733 Determination Page 2 of 8 2 Reasons for determination 2.1 Is the FSP liable for the claimed damage? Policy provides cover for damage caused by insured events The applicant is required to show that, on the balance of probabilities, he has suffered a loss caused by a risk insured against under the policy. This is known as a prima facie claim. If the applicant is able to establish a prima facie claim, then the onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to deny the claim. The applicant‟s property is insured for loss or damage caused by any of the specific insured events listed in the policy (including „storm‟ and „escape of liquid‟), subject to the conditions and exclusions set out in the policy. The policy states that an „insured event‟ is a single event, accident or occurrence which the policyholder did not intend or expect to happen. The insured event of „escape of liquid‟ provides cover for damage caused by liquid leaking, overflowing or bursting from any drain, fixed pipe, roof gutters, rainwater downpipes or drainage and sewerage systems. The photographs provided by the applicant to the FSP shortly after claim lodgement confirm that the basement and cellar area of the property was inundated in June 2014. The depth of the water is not clear from the photographs but has been estimated at approximately 50 centimetres. The basement and cellar are located approximately two metres below ground level and are accessible by a set of concrete steps leading down from the garden. The applicant seeks cover for damage to the basement and cellar area (including excavation and replacement of the concrete slab), as well as repairs to the ground floor area and replacement of the wastewater plumbing system. The applicant has advised that the property is now subject to rising damp (which he attributes to the leaking pipe) and estimates the total cost of repairs at approximately $250,000. Parties disagree about source of water affecting downstairs area When the applicant initially lodged his claim, he advised that the underground cellar had been flooded by stormwater run-off. However, the applicant now believes the water that inundated the basement and cellar area came from a leak in the incoming cold water pipe near the front boundary of his property. The FSP says there is insufficient information to show that the inundation of the basement and cellar area occurred as a result of the leaking cold water pipe. Case No: 417733 Determination Page 3 of 8 The FSP considers the water entry to the basement area during a series of rainfall events occurred over a period of time, as a result of inadequate drainage measures at the property. The FSP says the moisture issues affecting the property have been exacerbated by the lack of an adequate waterproof membrane in the basement area. Applicant’s e ngineer advised inundation was caused by stormwater The applicant initially notified the FSP of the inundation on 7 June 2014, when he advised that the underground cellar had been flooded by stormwater run-off which overflowed from a stormwater pipe. While the applicant was provided with a claim number, the incident was recorded as a report only without a formal claim being lodged. On 1 August 2014, the applicant‟s wife (LS) called the FSP to progress a claim for contents items stored in the cellar which had suffered water damage. The FSP‟s claim notes reflect that, during this call, LS advised that there was no visible damage to the concrete walls or floor of the cellar (which was used for storage). LS confirmed that the water had been pumped away by the applicant and had not returned (indicating it had likely been caused by heavy rainfall). The FSP‟s assessor (MG) attended the property on 2 October 2014 and confirmed that the cellar was largely free of water at this time. Photographs taken by MG show a small hole in the thin concrete floor which the applicant had made to accommodate a pump used to remove the water from the cellar. The pump was not in the hole when the photographs were taken. The applicant engaged an engineer (KC) to inspect the basement on 6 October 2014. In his report, KC advised that stormwater had entered the basement by way of the access stairs leading down from the garden in the southwest corner. KC ‟s report includes a photograph o f water staining on the external wall of the house above the entrance to the stairs, which he considered indicative of a blocked downpipe or gutter in this area. KC concluded that the downpipe may have become blocked with tree debris which had accumulated over time, causing stormwater to overflow from the short length of gutter and cascade down the wall and into the basement (via the stairs and/or the perimeter paving slabs). KC advised that the poor quality crushed rubble base underneath the thin slab had become fully saturated and was holding free water. KC advised that the existing slab and sub-grade material should be replaced with a suitable sub-base and a thicker concrete slab. KC noted that a proper waterproofing membrane should be installed and a submersible pump placed at the bottom of the stairs, to address future water entry from the stairs. KC also recommended the installation of a network of agricultural drains to drain sub-slab water to the drainage pit. The applicant engaged a plumber to install additional above ground drains in or around November 2014. Case No: 417733 Determination Page 4 of 8 FSP’s engineer confirmed inadequate drainage arrangements Following receipt of KC‟s report, the FSP appointed its own engineer to inspect the property and determine the cause and extent of water damage. FM attended the property on 2 December 2014. FM concluded that the basement and cellar area had been subject to ongoing water and moisture infiltration over an extended period of time due to inadequate stormwater and surface drainage provisions, together with the absence of a waterproof membrane. In this respect, FM‟s findings largely reflect those of the applicant‟s engineer (KC). In particular, FM advised that:  the inundation of the underground area in June 2014 had been caused by the inadequate design and subsequent deterioration of the stormwater system (including the corroded guttering near the access stairs, inadequate spacing of downpipes along the side wall and the inability of the small grate drain near the top of the stairs to cope with heavy rainfall). This had resulted in water entering the underground area by way of the stairs;  the state of the stormwater system (downpipes and stormwater pit) was likely to have resulted in water discharging onto and/or dispersing into the surrounding ground, resulting in moisture entering through the bluestone walls. FM noted that the moisture readings of the perimeter walls were higher in the cellar (where the observed drainage issues were more significant) than in the basement area; and  the drainage issues, together with the absence of a waterproof membrane, had resulted in ongoing moisture infiltration through the bluestone walls over an extended period of time. Based on a review of meteorological records, FM confirmed that, while there was limited rainfall in the week prior to the applicant becoming aware of the inundation, there had been consistent rainfall over the previous two months, which may have resulted in water entering the underground area. Leaking pipe was identified in January 2015 The FSP denied the appl icant‟s claim following receipt of FM‟s report, on the basis that the water damage to the basement and cellar had not been caused by a one -off event but had occurred over an extended period of time. In June 2015, the applicant‟s solicitor wrote to the F SP disputing the denial. In his letter, the solicitor advised that a leak in the incoming mains water pipe adjacent to the property had been identified in late January 2015 and repaired by the water authority in February 2015. The applicant‟s solicitor enc losed a report from an engineer (WM), in which WM confirmed that when he attended the property on 30 January 2015, the incoming copper water pipe was leaking at the mechanical joint prior to the water meter. WM described the water leak as “very obvious and substantial” and estimated the rate of leakage at approximately two litres per minute. Case No: 417733 Determination Page 5 of 8 In his report, WM stated that the leaking water appeared to be entering the basement and cellar area. He advised that the leaking water was seeping through the sand underlay, where it would then follow the path of least resistance. The applicant subsequently provided reports from a building consultant (JB), as well as two further engineers (DA and DC). In his report dated 11 April 2015, the applicant‟s building consultan t (JB) confirmed that moisture had affected the walls and floors of the basement over an extended period of time. JB advised that he considered WM‟s explanation that the source of the water was the leaking pipe to be more feasible than the explanation provided by FM. JB provided a diagram which indicated that water leaking from the mains pipe approximately 16 metres from the front of the property had flowed through the sandy soil and entered the cellar at floor level. The applicant‟s additional engineers confirmed WM‟s conclusion that the inundation in June 2014 was due to hydrostatic pressure caused by the leaking mains pipe. In their respective reports:  DC stated that the causal connection between the two events was clear, definite and irrefutable. However, he did not provide any further information about the basis on which he had reached that conclusion; and  DA stated that the volume of rain experienced in the five weeks prior to June 2014 would have been insufficient to cause the inundation reported by the applicant. The FSP provided the reports prepared by the applicant‟s consultants to its engineer (FM) for review. However, FM considered the leak had occurred subsequent to the inundation in June 2014, based on the condition of the underground area at the time of his inspection in December 2014. Available information does not establish damage was caused by leaking pipe Having carefully reviewed the reports provided by the various contractors, the Panel is not satisfied that the applicant has established that, on the balance of probabilities, the water entry issues which affected the property were caused by the leaking pipe identified in January 2015. There is limited information available regarding the leak in the pipe and the subsequent repair. In particular, it is unclear how the applicant became aware of the leak in the pipe. The FSP was not advised of the leak until almost six months after it was discovered. At this time, the applicant‟s solicitor advised that a loss adjuster had been appointed by the water authority to investigate any damage caused by the leak. However, the Panel has not been provided with any information regarding the loss adjuster‟ s findings (or any photographs confirming the nature and location of the leak). Case No: 417733 Determination Page 6 of 8 In these circumstances, the Panel is not satisfied that the applicant has established any link between the inundation of the basement in June 2014 (and any subsequent damage) and the leaking pipe identified in January 2015. Neither the applicant‟s engineer (KC) nor the FSP‟s engineer (FM), wh o inspected the property between October 2014 and December 2014 reported any sign of a leaking pipe. Nor did the plumbers who attended the property in late 2014 identify any such issue. Further, the Panel considers that the nature and extent of the water-related issues affecting the underground area of the applicant‟s property are not consistent with having been caused by a leak from the mains pipe at the front of the property. The applicant says the inundation in June 2014 was caused by the leaking pipe. He says he was only able to prevent the ongoing inundation of the underground area by operating the pump continuously over the ensuing six month period. However, the applicant‟s position is not consistent with results of KC and FM‟s inspections during the relevant period. The photographs taken by KC and FM show free water under the slab (visible through the hole created by the applicant to pump out the water). However, the water level was roughly equivalent with the concrete slab itself and the pump was no t operating at this time. In these circumstances, it appears unlikely that the property was subject to the ongoing effects of a leaking mains water pipe, such as would have been sufficient to have caused the inundation of the basement to the extent experienced in June 2014. The Panel acknowledges that the applicant has provided reports from his own consultants which conclude that the claimed damage was caused by the leaking pipe. However, the conclusion s drawn by the applicant‟s consultants are subject to a number of critical assumptions, which have been shown to be incorrect or unsubstantiated. For example, in his report, the applicant‟s engineer (WM) assumed that there was no stormwater flowing into the basement, the ground water levels were low and adequate drainage measures were in place to manage ground water. However, both KC and FM clearly identified signs of stormwater having flowed down the stairs and into the basement, including stains on the adjacent wall and a length of corroded guttering in the immediate area. Further, by the time WM inspected the property, additional stormwater drainage measures had been installed and therefore his observations did not reflect the position at the time the original inundation occurred. WM also noted that a geotechnical report would be required to confirm his assumptions about the flow of water from the location of the leak through the surrounding soils. It does not appear that a geotechnical report was ever undertaken. Case No: 417733 Determination Page 7 of 8 For the reasons outlined above, the Panel does not consider that, on the balance of probabilities, the claimed damage was caused by the leaking pipe. FSP is not liable for claimed damage On balance, the Panel accepts the findings of the FSP‟s engineer (FM) that the inundation of the underground area discovered in June 2014 was caused by the inflow of stormwater due to inadequate drainage measures. While the applicant‟s engineer says the rainfall experienced during May and June 2014 was insufficient to cause the inundation observed, the FSP‟s en gineer (FM) considers the rainfall figures for the period April to June 2014 do indicate sufficient rainfall. FM concluded the stormwater run-off had built up during this period of time. As outlined above, the applicant‟s policy provides cover for damage c aused by storm. However, cover is not available where the claimed damage occurs due to the effects of ongoing rainwater run-off, rather than as a result of a single storm event. The applicant says the basement area did not exhibit any signs of water damage prior to the inundation in June 2014. He has provided a letter from the real estate agent who managed the property confirming that the area was carpeted and used as a library by the previous owner. However, the reports prepared by the engineers (KC and FM) who inspected the property following the inundation identified various issues with the drainage system ( such as blockages and corrosion) which may have arisen following the applicant‟s acquisition of the property, causing the flow of stormwater into the basement area. For the reasons outlined above, the FSP is not liable for the applicant‟s claim. Case No: 417733 Determination Page 8 of 8 3 Supporting information 3.1 FOS approach to this dispute This dispute has not been the subject of a FOS recommendation. Due to the nature of the dispute, it has been referred directly to a Panel for determination, in line with the Operational Guidelines to the FOS Terms of Reference. The Panel consists of an Ombudsman and two representatives with consumer and insurance experience. The Panel has decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. The Panel has reviewed and considered all of the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination, the Panel has restricted its commentary to those issues that it considers directly relevant to the outcome only.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.