Fire damage repairs quality, incompleteness and delay, and cash settlement dispute
Text of the determination
Determination
Case No: 417354 Determination Page 1 of 10
Case number: 417354 15 August 2016
1 Overview
1.1 Dispute
The Applicant holds a home and contents policy with the Financial Services Provider
(FSP) under which a claim was lodged for fire damage to the premises occurring on
31 December 2013.
The FSP accepted the claim and settled it by way of authorising repairs to the
premises. The Applicant is dissatisfied with the time taken to complete the repairs
and the quality of the works undertaken. She seeks the FSP or its builder 'L' to
continue coverage for temporary accommodation until the repairs are complete and
to complete the repairs. She is also seeking compensation for the manner in which
the FSP managed her claim.
1.2 Issues and key findings
Has the FSP fulfilled its policy obligations to the Applicant?
The FSP has fulfilled its obligations to the Applicant as the policy has been reinstated
to a condition reasonably similar to as when new. The FSP is not obliged to reinstate
the property in an exact replica fashion.
The quality issues raised by the Applicant have been remedied. The FSP is to pay
the Applicant the further sum of $10,000 (in addition to the $10,000 paid in December
2015) in finalisation of the outstanding items on the claim.
Is the Applicant entitled to additional temporary accommodation costs?
The Applicant is not entitled to additional temporary accommodation costs as she
has exhausted the policy benefit for this item. The property is habitable and the
Applicant is at liberty to return to it at any time. This Service is unable to compel the
builder to continue paying temporary accommodation costs as it does not have
jurisdiction to consider this issue.
Is the Applicant entitled to compensation for the manner in which the FSP
managed the claim?
The Applicant is entitled $1,500 compensation for financial loss of temporary
accommodation costs and $462 for the expert report obtained by the Applicant.
The Applicant is also entitled to $2,000 compensation for non financial loss for the
manner in which the FSP managed the claim. The repair timeframe was excessive
Case No: 417354 Determination Page 2 of 10
and exceeded the timeframe a repair of this magnitude could reasonably be
expected to take.
1.3 Determination
This Determination is partially in favour of the Applicant.
The FSP is not required to undertake further works at the home as it has fulfilled its
obligations under the terms of the policy.
Should the Applicant accept this Determination, then within 7 days of acceptance, t he
FSP is to pay to the Applicant the further sum of $10,000 in full and final settlement in
respect of any outstanding defects, the outstanding exterior painting, cleaning of the
property and contents removal.
By way of compensation, the FSP is also to pay the Applicant:
$1,500 for financial loss
$2,000 for non-financial loss
$462 in respect of G’s report, if it has not already done so.
Case No: 417354 Determination Page 3 of 10
2 Reasons for Determination
2.1 Has the FSP fulfilled its obligations under the policy terms?
The Applicant must establish she is entitled to further policy benefits
There is no dispute between the parties the Applicant suffered a loss from a risk
insured against or that the FSP accepted the claim and arranged for repairs.
However, a dispute has arisen between the parties regarding the quality of the
repairs undertaken to the property and the manner in which the FSP handled the
claim.
The Applicant asserts the building firm L was responsible for delayed completion of
the repairs to the point that more than two years after the loss occurring, she is still
unable to return home not only because the repairs are incomplete or inadequate but
because the home is not fit for occupation.
Further, she says the works were completed without her knowledge or consent, or in
a manner different from what was directed in the scope of works (SOW) or not to
standard. She says a significant amount of items listed for reinstatement on the SOW
either are not completed or completed to a low standard.
As the party seeking the benefit under the policy terms, the onus rests with the
Applicant to establish she is entitled to the benefit which she is seeking.
The SOW has been changed since its initial preparation
The parties are in agreement the original SOW was changed during the course of the
claim repairs. The Applicant concedes she asked for alterations to the home to suit
her needs better, and 'traded off' some items for others to be installed instead.
However, she says she was unaware that by doing so, this would cause the length of
the repairs to extend. She further maintains L altered many items without her
knowledge or permission and installed cheaper items instead. For example, the
Applicant states the skirting boards are now made of MDF, whereas initially they
were hardwood, and therefore she should have hardwood replacements.
The FSP is not obliged to replicate the house exactly
In the first instance, the FSP's obligation extends only so far as rebuilding the house
to a similar standard as it was when new. This means the property reinstatement is
required to be reasonably similar in finish, quality and amenity to the condition it was
in pre-loss. It is not required to be an exact replica of that which existed prior to the
loss occurring.
As long as the property generally meets these requirements, the FSP will be
considered to have fulfilled its obligations under the terms of the policy.
Although the Applicant has provided a list of the items she says have not been
reinstated to her satisfaction, I am not persuaded this necessarily means the FSP
has failed in its obligation to her.
Case No: 417354 Determination Page 4 of 10
For example, the Applicant has raised an issue about the lack of a wardrobe in one
of the bedrooms, which existed originally. However, review of the material shows a
wardrobe was installed in a different bedroom which did not originally have one.
Further, it is clear from the material provided the builder has made numerous
changes to the SOW to accommodate the Applicant's wishes. For example, the
family room was converted into a fourth bedroom, the existing laundry was converted
to the main bathroom and a wall was removed between the family room and kitche n
rooms to create an open plan area. Old heating and cooling units were replaced by a
ducted unit. These changes have been offset by options such as choosing a less
expensive tile, the use of MDF instead of hardwood in the skirting boards and
doorjambs and a reduction in the cupboard sizes and shelving supplied.
I consider it unreasonable for the Applicant to be unaware that quite major changes
to the property and SOW would affect the reinstatement works, both in the timeframe
to repair and the repairs undertaken.
The FSP is only required to repair the home to a similar standard to what existed
prior to the loss, and its liability is limited to the amount it would cost to achieve that.
In this instance, where the Applicant requested works over and above reinstatement,
then it is not unreasonable to expect L to offset these accommodations elsewhere in
the amount he was to invoice the FSP.
Although the parties have provided limited information, the material supplied confirms
there were discussions between the parties surrounding the need to offset the
changes against the original SOW. It seems there may have been a lack of
communication as to exactly what the implications of altering the SOW would be.
Although this is regrettable and the parties would undoubted ly have benefitted from
clarification of this, particularly in the early stages of the repair, I am not persuaded it
automatically follows that the FSP has any further liability.
The Applicant has not presented any evidence to suggest the reinstated home is not
similar in quality, amenity and finish to that which existed when new. Accordingly, the
FSP is not required to undertake additional works at the home.
The repair quality issues raised have been mostly addressed
The Applicant sourced her own report from building consultant firm "G", which set out
a number of items which had either not been completed or not completed to
standard.
However, I note since the report was provided, the FSP has provided material
including photographs confirming L has returned to the property to complete most, if
not all, of the items G listed as defective. If there are remaining items, the material
provided by the FSP satisfies me the remaining items (if there are any) are relatively
minor such as installation of shade cloth, a large blind, robe doors, a security door,
the laundry tub, and a trip hazard. Otherwise, to the more major matters, the FSP
admits only the exterior painting and cleaning of the property remains.
Although the Applicant claims further substantial works will be required, having
considered photographs provided by the Applicant, I am not satisfied further
Case No: 417354 Determination Page 5 of 10
substantial works are required. Further, the photographs provided by the Applicant
are taken prior to further works undertaken by the builder in January 2016.
Therefore I accept the items raised, bar the painting and cleaning, which I will
address below, have been satisfactorily addressed. If there are items still to be
completed, having considered the material provided, and particularly photographs, I
consider those items to be relatively minor.
On this basis, there are no outstanding major repairs required to the property and I
consider the material establishes on the balance of probabilities the FSP has fulfilled
its obligations.
The FSP has cash settled for its estimate of cleaning, painting and removal
The parties agree the cleaning, painting and removal of contents are outstanding.
The parties also agree the FSP has sought to discharge its liability for these items by
paying $10,000, which has been remitted to the Applicant.
The Applicant denies agreeing to accept this in settlement of her claim, and says the
amount offered is insufficient to undertake these works and her other complaints.
The FSP says the Applicant initially agreed to settle on this basis however later
changed her mind. The Applicant denies ever agreeing to the proposal.
On reviewing the material provided, on balance, I am inclined to accept the FSP's
position that the Applicant did initially accept the proposal, as it prepared her a
Release to sign. However, it is clear the Applicant never actually signed the Release.
In ordinary circumstances, an offer is only binding on the parties when it is made and
accepted. In this instance, as the FSP required a Release to confirm the offer was
accepted in full and final settlement of the claim, the Applicant's refusal to sign it
means the criteria of acceptance was not met. Therefore, the offer is not binding
against either party, notwithstanding the FSP later paid the money to the Applicant.
The Applicant has provided quotations for repairs from her builder. One quotation
includes the cost of exterior painting in the amount of $9,900. The quotations list
other work too which includes installing skirtings, repainting doorjambs, supplying a
linen cupboard and ceiling and subfloor installation. The Applicant says as a result of
the builder’s failure to consult with her, she is now left with a large number of works
not completed or not completed as agreed. She says the remaining works cannot be
completed for $10,000. She says she has begun to obtain quotes for rectification
which at the time of her submissions, amounted to $19,921.
The FSP says the amounts claimed exceed the quotations it obtained for work
required and its offer of $10,000 was therefore designed to bring the matter to
finalisation. However, the FSP has not provided any of its quotations for review.
The FSP’s quotes are not provided and t he Applicant’s quotes are not for a similar
scope. The Applicant’s quotes were referred to the FSP’s builder L who comments
variously the quotes are for work already done by L or not in the scope of works.
Having considered the material provided, including the scope of works and various
emails between the parties about the scope of works and the work to be completed, I
accept the observations made by L.
Case No: 417354 Determination Page 6 of 10
The Applicant challenges the opinions of the builder L, the FSP’s adjuster and the
builder A engaged by the FSP to comment. However, having carefully considered all
the material provided, their opinions and the photographs provided, I am not
persuaded their opinion is without merit or the issues remaining in dispute require the
further time and expense of the retention of an independent building inspector.
Accordingly, in order to bring this long standing matter to a conclusion, I consider it
fair in all the circumstances for the FSP to pay to the Applicant the further sum of
$10,000 (in addition to the S10,000 already paid) in respect of the outstanding items
remaining in dispute in order to fulfil its policy obligations.
The Applicant is not entitled to further temporary accommodation costs under
the policy terms
The Applicant maintains the property is not fit for habitation and has refused to
vacate her temporary accommodation to return to the risk address. She cites the G
report in support of her position that the property is uninhabitable.
The FSP has provided a copy of the certificate of occupancy issued on 11 December
2015, showing the property is certified as habitable.
A careful review of the G report shows no major structural defects were found.
Although G has listed some minor defects, a review of the body of the report shows
these items were mostly cosmetic such as doors requiring re-hanging and sealing
and grouting and silicone to tiling to be remedied. Crucially for the Applicant, at no
time does G state the property is uninhabitable or that the certificate of occupancy
has been prematurely issued, as claimed by the Applicant.
The FSP's policy does not define what it considers to be uninhabitable. However, this
Service generally holds the term to mean that a property is not fit for habitation where
it is exposed to the elements, without connection to utilities, and/or where
contaminants which pose a health risk are present.
Reviewing the material on file, none of these elements are present at the risk
address. Accordingly, I am satisfied the property is habitable and able to be re-
occupied by the Applicant.
Further, in this instance, the FSP's policy is clear in stating the maximum entitlement
for temporary accommodation benefits is 12 months. The Applicant exhausted that
benefit some time ago. Since that time, her temporary accommodation costs have
been covered by L in recognition of the extended timeframe the repairs have taken.
This Service can only award an entitlement under the policy terms and is not able to
compel an insurer to pay benefits pursuant to a policy outside of its contractual
obligations. Further, the agreement in place, up until 24 January 2016, was that L
was paying for the temporary accommodation. However, this Service can only
consider disputes against financial service providers and has no jurisdiction to
consider a dispute against the builder, for an arrangement entered into between the
Applicant and the builder.
Case No: 417354 Determination Page 7 of 10
Therefore, this Service cannot award any further costs in relation to the temporary
accommodation. Pursuant to the policy, the FSP is not responsible for meeting these
costs post 24 January 2016.
2.2 Is the Applicant entitled to compensation?
Compensation may be awarded in certain circumstances
However, the Service can award compensation (with a $3,300 cap) for direct loss or
consequential loss. Direct losses are losses, such as out of pocket expenses or other
liabilities, which are caused directly as a result of the FSP’s conduct. Consequential
losses are losses which are indirectly caused by the FSP’s conduct.
When deciding on a remedy such as compensation, the Service seeks to achieve to
place an Applicant in the position they would have been in if the conduct of the FSP
had not caused the loss or to compensate the Applicant for their loss to the extent
the Service holds the FSP responsible for the loss.
Policy does not prevent compensation for loss caused by the FSP’s conduct
The Service will not provide compensation for direct or consequential loss or non-
financial loss in a dispute arising from a claim on a general insurance policy which
expressly excludes liability for such loss.
I acknowledge the policy term in the FSP’s policy which says it does not pay for
consequential loss. However, I am not satisfied the policy term prevents an award of
compensation under the Terms of Reference for losses caused as a result of the
FSP’s conduct.
The FSP is to pay $1,500 compensation for financial loss
While the FSP lists various reasons as to why its builder was not responsible for
delays, I am not satisfied they are sufficiently compelling in circumstances where the
FSP and/or its assessors and adjusters are responsible for ensuring repairs are
completed in a timely fashion.
The fire damage occurred on 31 December 2013 and yet repairs and rectifications
were not completed until mid-January 2016. Alternate accommodation has been paid
by the FSP and by the builder up until and including 24 January 2016. At that time,
some minor works were still required. At the very least, the works included some
minor repairs inside, exterior pai nting, cleaning and moving the Applicant’s contents
into her home. I consider it is unlikely this remaining work would take longer than 6
weeks. Material on the file indicates rent was around $1,000 a month.
Taking all matters into account, I consider it is fair in the circumstances the FSP pay
the Applicant a further $1,500 compensation for this aspect of her claim.
Case No: 417354 Determination Page 8 of 10
The FSP is to pay the Applicant $462 for G’s report
The Applicant claims $462 being the cost of G’s $460. The FSP is not obliged to
reimburse the cost but said it would be prepared to consider such a cost on a without
prejudice basis.
The Terms of Reference provide the Service may decide the FSP contribute to
professional costs incurred by the Applicant in the course of the dispute. In all the
circumstances, I consider it is fair the FSP reimburse the Applicant for G’s report.
The FSP is to pay the Applicant $2,000 compensation for non-financial loss
The Service’s Terms of Reference enable the Service to compensate an Applicant
for non-financial loss (capped at $3,000).
The Applicant claims $3,000 compensation saying she and her family have had to
live away from home and in rental property not suitable to their needs for two years.
She claims it has taken a toll on their mental health and significant distress has been
caused by the attitude of the FSP and the builder towards her concerns regarding the
delay and actual works.
Compensation for non-financial loss is limited. The Service may decide an FSP
should compensate an Applicant for such loss only where there has been an unusual
amount of physical inconvenience, time taken to resolve a situation, or interference
with the Applicant’s expectation of en joyment or peace of mind.
The Service takes a conservative approach to compensation for non-financial loss
and expects an Applicant to be moderately robust and bear the usual degree of
inconvenience when managing an insurance claim. Nonetheless, in the
cir cumstances of this matter, I am satisfied the FSP’s claims handling was not timely
and would have interfered with the Applicants’ peace of mind.
This Service does not have the power to grant entitlements not provided for under
the terms of the insurance contact. T he Service’s Terms of Reference also
specifically excludes from the powers of the Service, the ability to award punitive,
exemplary or aggravated damages.
Having considered the timeframes, I am not satisfied the FSP has handled this
matter in a timely fashion. The repairs have taken an extraordinarily long time to
complete. Although I have previously accepted the repairs are now complete in the
main and the FSP has fulfilled its policy obligations, this took a period of over two
years. Whilst the property was extensively damaged, and it was reasonably
foreseeable such a large scale repair would take a significant time to complete, I find
two years is excessive.
The timeline provided by L shows there were significant delays at times including
obtaining permits and sourcing trades to commence the work. I accept not all of the
delays can be attributed to either the FSP or L. However, as the party responsible for
authorising the repairs, it is the FSP's obligation to ensure these are completed in a
timely manner.
I accept the Applicant has been somewhat compensated for the delays by way of L
continuing to pay her temporary accommodation costs whilst repairs continued.
Case No: 417354 Determination Page 9 of 10
However, the delay in completing the reinstatement would have interfered with the
Applicant's peace of mind and caused undue stress and hardship. On this basis, I
consider an award of $2,000 compensation is fair in all the circumstances.
Case No: 417354 Determination Page 10 of 10
3 Supporting information
3.1 FOS approach to this dispute
As advised to the parties, FOS has considered it appropriate to expedite this dispute
in accordance with the Operational Guidelines to the FOS Terms of Reference, due
to the nature of the dispute. Accordingly, this dispute has not been the subject of a
FOS Recommendation and has proceeded directly to Determination.
There has been a full exchange of all material information relied on for the purposes
of this Determination and each party has had the opportunity to address any issues
raised by the other. All of the material provided by the parties has been reviewed and
considered for the purposes of this Determination.
This dispute has been decided on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous Financial Ombudsman Service
(FOS) decisions.
While the parties have raised numerous issues in their submissions, for the purposes
of this Determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
It is an accepted principle of general insurance law that an insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie claim. Once so
established, the onus shifts to the insurer to prove on the balance of probabilities that
an exclusion applies if it seeks to deny or limit its liability for the loss.
The Applicant is represented in this matter and statements from the Applicant and
her representative shall jointly be referred to as 'the Applicant'.
3.2 Relevant policy extracts
The relevant policy extracts are referred to in the FSP’s Notice of Response dated 19
January 2016. Both the policy document and the Notice have been exchanged with
the Applicant.
3.3 Other relevant material considered and relied on
Parties’ submissions and attachments to submissions
Correspondence between the parties