Determination 417354

Fire damage repairs quality, incompleteness and delay, and cash settlement dispute

FirmFinancial Firm (Unknown - Insurer)
Decided2016-08-26
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$11,962
Non-financial loss$2,000
Amount claimed$19,921
SourceAFCA PDF

Summary

The applicant's home was damaged by fire and repaired by the FSP's builder, but repairs took over two years and she disputed their quality. AFCA found the home was reinstated to a reasonable standard, but ordered a further $10,000 for outstanding items, $1,500 financial loss, $462 expert report cost and $2,000 non-financial loss for delay.

An insurer must reinstate to a similar standard rather than an exact replica, but it is responsible for ensuring repairs are completed in a timely manner, so delay compensation was awarded.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 417354 Determination Page 1 of 10 Case number: 417354 15 August 2016 1 Overview 1.1 Dispute The Applicant holds a home and contents policy with the Financial Services Provider (FSP) under which a claim was lodged for fire damage to the premises occurring on 31 December 2013. The FSP accepted the claim and settled it by way of authorising repairs to the premises. The Applicant is dissatisfied with the time taken to complete the repairs and the quality of the works undertaken. She seeks the FSP or its builder 'L' to continue coverage for temporary accommodation until the repairs are complete and to complete the repairs. She is also seeking compensation for the manner in which the FSP managed her claim. 1.2 Issues and key findings Has the FSP fulfilled its policy obligations to the Applicant? The FSP has fulfilled its obligations to the Applicant as the policy has been reinstated to a condition reasonably similar to as when new. The FSP is not obliged to reinstate the property in an exact replica fashion. The quality issues raised by the Applicant have been remedied. The FSP is to pay the Applicant the further sum of $10,000 (in addition to the $10,000 paid in December 2015) in finalisation of the outstanding items on the claim. Is the Applicant entitled to additional temporary accommodation costs? The Applicant is not entitled to additional temporary accommodation costs as she has exhausted the policy benefit for this item. The property is habitable and the Applicant is at liberty to return to it at any time. This Service is unable to compel the builder to continue paying temporary accommodation costs as it does not have jurisdiction to consider this issue. Is the Applicant entitled to compensation for the manner in which the FSP managed the claim? The Applicant is entitled $1,500 compensation for financial loss of temporary accommodation costs and $462 for the expert report obtained by the Applicant. The Applicant is also entitled to $2,000 compensation for non financial loss for the manner in which the FSP managed the claim. The repair timeframe was excessive Case No: 417354 Determination Page 2 of 10 and exceeded the timeframe a repair of this magnitude could reasonably be expected to take. 1.3 Determination This Determination is partially in favour of the Applicant. The FSP is not required to undertake further works at the home as it has fulfilled its obligations under the terms of the policy. Should the Applicant accept this Determination, then within 7 days of acceptance, t he FSP is to pay to the Applicant the further sum of $10,000 in full and final settlement in respect of any outstanding defects, the outstanding exterior painting, cleaning of the property and contents removal. By way of compensation, the FSP is also to pay the Applicant:  $1,500 for financial loss  $2,000 for non-financial loss  $462 in respect of G’s report, if it has not already done so. Case No: 417354 Determination Page 3 of 10 2 Reasons for Determination 2.1 Has the FSP fulfilled its obligations under the policy terms? The Applicant must establish she is entitled to further policy benefits There is no dispute between the parties the Applicant suffered a loss from a risk insured against or that the FSP accepted the claim and arranged for repairs. However, a dispute has arisen between the parties regarding the quality of the repairs undertaken to the property and the manner in which the FSP handled the claim. The Applicant asserts the building firm L was responsible for delayed completion of the repairs to the point that more than two years after the loss occurring, she is still unable to return home not only because the repairs are incomplete or inadequate but because the home is not fit for occupation. Further, she says the works were completed without her knowledge or consent, or in a manner different from what was directed in the scope of works (SOW) or not to standard. She says a significant amount of items listed for reinstatement on the SOW either are not completed or completed to a low standard. As the party seeking the benefit under the policy terms, the onus rests with the Applicant to establish she is entitled to the benefit which she is seeking. The SOW has been changed since its initial preparation The parties are in agreement the original SOW was changed during the course of the claim repairs. The Applicant concedes she asked for alterations to the home to suit her needs better, and 'traded off' some items for others to be installed instead. However, she says she was unaware that by doing so, this would cause the length of the repairs to extend. She further maintains L altered many items without her knowledge or permission and installed cheaper items instead. For example, the Applicant states the skirting boards are now made of MDF, whereas initially they were hardwood, and therefore she should have hardwood replacements. The FSP is not obliged to replicate the house exactly In the first instance, the FSP's obligation extends only so far as rebuilding the house to a similar standard as it was when new. This means the property reinstatement is required to be reasonably similar in finish, quality and amenity to the condition it was in pre-loss. It is not required to be an exact replica of that which existed prior to the loss occurring. As long as the property generally meets these requirements, the FSP will be considered to have fulfilled its obligations under the terms of the policy. Although the Applicant has provided a list of the items she says have not been reinstated to her satisfaction, I am not persuaded this necessarily means the FSP has failed in its obligation to her. Case No: 417354 Determination Page 4 of 10 For example, the Applicant has raised an issue about the lack of a wardrobe in one of the bedrooms, which existed originally. However, review of the material shows a wardrobe was installed in a different bedroom which did not originally have one. Further, it is clear from the material provided the builder has made numerous changes to the SOW to accommodate the Applicant's wishes. For example, the family room was converted into a fourth bedroom, the existing laundry was converted to the main bathroom and a wall was removed between the family room and kitche n rooms to create an open plan area. Old heating and cooling units were replaced by a ducted unit. These changes have been offset by options such as choosing a less expensive tile, the use of MDF instead of hardwood in the skirting boards and doorjambs and a reduction in the cupboard sizes and shelving supplied. I consider it unreasonable for the Applicant to be unaware that quite major changes to the property and SOW would affect the reinstatement works, both in the timeframe to repair and the repairs undertaken. The FSP is only required to repair the home to a similar standard to what existed prior to the loss, and its liability is limited to the amount it would cost to achieve that. In this instance, where the Applicant requested works over and above reinstatement, then it is not unreasonable to expect L to offset these accommodations elsewhere in the amount he was to invoice the FSP. Although the parties have provided limited information, the material supplied confirms there were discussions between the parties surrounding the need to offset the changes against the original SOW. It seems there may have been a lack of communication as to exactly what the implications of altering the SOW would be. Although this is regrettable and the parties would undoubted ly have benefitted from clarification of this, particularly in the early stages of the repair, I am not persuaded it automatically follows that the FSP has any further liability. The Applicant has not presented any evidence to suggest the reinstated home is not similar in quality, amenity and finish to that which existed when new. Accordingly, the FSP is not required to undertake additional works at the home. The repair quality issues raised have been mostly addressed The Applicant sourced her own report from building consultant firm "G", which set out a number of items which had either not been completed or not completed to standard. However, I note since the report was provided, the FSP has provided material including photographs confirming L has returned to the property to complete most, if not all, of the items G listed as defective. If there are remaining items, the material provided by the FSP satisfies me the remaining items (if there are any) are relatively minor such as installation of shade cloth, a large blind, robe doors, a security door, the laundry tub, and a trip hazard. Otherwise, to the more major matters, the FSP admits only the exterior painting and cleaning of the property remains. Although the Applicant claims further substantial works will be required, having considered photographs provided by the Applicant, I am not satisfied further Case No: 417354 Determination Page 5 of 10 substantial works are required. Further, the photographs provided by the Applicant are taken prior to further works undertaken by the builder in January 2016. Therefore I accept the items raised, bar the painting and cleaning, which I will address below, have been satisfactorily addressed. If there are items still to be completed, having considered the material provided, and particularly photographs, I consider those items to be relatively minor. On this basis, there are no outstanding major repairs required to the property and I consider the material establishes on the balance of probabilities the FSP has fulfilled its obligations. The FSP has cash settled for its estimate of cleaning, painting and removal The parties agree the cleaning, painting and removal of contents are outstanding. The parties also agree the FSP has sought to discharge its liability for these items by paying $10,000, which has been remitted to the Applicant. The Applicant denies agreeing to accept this in settlement of her claim, and says the amount offered is insufficient to undertake these works and her other complaints. The FSP says the Applicant initially agreed to settle on this basis however later changed her mind. The Applicant denies ever agreeing to the proposal. On reviewing the material provided, on balance, I am inclined to accept the FSP's position that the Applicant did initially accept the proposal, as it prepared her a Release to sign. However, it is clear the Applicant never actually signed the Release. In ordinary circumstances, an offer is only binding on the parties when it is made and accepted. In this instance, as the FSP required a Release to confirm the offer was accepted in full and final settlement of the claim, the Applicant's refusal to sign it means the criteria of acceptance was not met. Therefore, the offer is not binding against either party, notwithstanding the FSP later paid the money to the Applicant. The Applicant has provided quotations for repairs from her builder. One quotation includes the cost of exterior painting in the amount of $9,900. The quotations list other work too which includes installing skirtings, repainting doorjambs, supplying a linen cupboard and ceiling and subfloor installation. The Applicant says as a result of the builder’s failure to consult with her, she is now left with a large number of works not completed or not completed as agreed. She says the remaining works cannot be completed for $10,000. She says she has begun to obtain quotes for rectification which at the time of her submissions, amounted to $19,921. The FSP says the amounts claimed exceed the quotations it obtained for work required and its offer of $10,000 was therefore designed to bring the matter to finalisation. However, the FSP has not provided any of its quotations for review. The FSP’s quotes are not provided and t he Applicant’s quotes are not for a similar scope. The Applicant’s quotes were referred to the FSP’s builder L who comments variously the quotes are for work already done by L or not in the scope of works. Having considered the material provided, including the scope of works and various emails between the parties about the scope of works and the work to be completed, I accept the observations made by L. Case No: 417354 Determination Page 6 of 10 The Applicant challenges the opinions of the builder L, the FSP’s adjuster and the builder A engaged by the FSP to comment. However, having carefully considered all the material provided, their opinions and the photographs provided, I am not persuaded their opinion is without merit or the issues remaining in dispute require the further time and expense of the retention of an independent building inspector. Accordingly, in order to bring this long standing matter to a conclusion, I consider it fair in all the circumstances for the FSP to pay to the Applicant the further sum of $10,000 (in addition to the S10,000 already paid) in respect of the outstanding items remaining in dispute in order to fulfil its policy obligations. The Applicant is not entitled to further temporary accommodation costs under the policy terms The Applicant maintains the property is not fit for habitation and has refused to vacate her temporary accommodation to return to the risk address. She cites the G report in support of her position that the property is uninhabitable. The FSP has provided a copy of the certificate of occupancy issued on 11 December 2015, showing the property is certified as habitable. A careful review of the G report shows no major structural defects were found. Although G has listed some minor defects, a review of the body of the report shows these items were mostly cosmetic such as doors requiring re-hanging and sealing and grouting and silicone to tiling to be remedied. Crucially for the Applicant, at no time does G state the property is uninhabitable or that the certificate of occupancy has been prematurely issued, as claimed by the Applicant. The FSP's policy does not define what it considers to be uninhabitable. However, this Service generally holds the term to mean that a property is not fit for habitation where it is exposed to the elements, without connection to utilities, and/or where contaminants which pose a health risk are present. Reviewing the material on file, none of these elements are present at the risk address. Accordingly, I am satisfied the property is habitable and able to be re- occupied by the Applicant. Further, in this instance, the FSP's policy is clear in stating the maximum entitlement for temporary accommodation benefits is 12 months. The Applicant exhausted that benefit some time ago. Since that time, her temporary accommodation costs have been covered by L in recognition of the extended timeframe the repairs have taken. This Service can only award an entitlement under the policy terms and is not able to compel an insurer to pay benefits pursuant to a policy outside of its contractual obligations. Further, the agreement in place, up until 24 January 2016, was that L was paying for the temporary accommodation. However, this Service can only consider disputes against financial service providers and has no jurisdiction to consider a dispute against the builder, for an arrangement entered into between the Applicant and the builder. Case No: 417354 Determination Page 7 of 10 Therefore, this Service cannot award any further costs in relation to the temporary accommodation. Pursuant to the policy, the FSP is not responsible for meeting these costs post 24 January 2016. 2.2 Is the Applicant entitled to compensation? Compensation may be awarded in certain circumstances However, the Service can award compensation (with a $3,300 cap) for direct loss or consequential loss. Direct losses are losses, such as out of pocket expenses or other liabilities, which are caused directly as a result of the FSP’s conduct. Consequential losses are losses which are indirectly caused by the FSP’s conduct. When deciding on a remedy such as compensation, the Service seeks to achieve to place an Applicant in the position they would have been in if the conduct of the FSP had not caused the loss or to compensate the Applicant for their loss to the extent the Service holds the FSP responsible for the loss. Policy does not prevent compensation for loss caused by the FSP’s conduct The Service will not provide compensation for direct or consequential loss or non- financial loss in a dispute arising from a claim on a general insurance policy which expressly excludes liability for such loss. I acknowledge the policy term in the FSP’s policy which says it does not pay for consequential loss. However, I am not satisfied the policy term prevents an award of compensation under the Terms of Reference for losses caused as a result of the FSP’s conduct. The FSP is to pay $1,500 compensation for financial loss While the FSP lists various reasons as to why its builder was not responsible for delays, I am not satisfied they are sufficiently compelling in circumstances where the FSP and/or its assessors and adjusters are responsible for ensuring repairs are completed in a timely fashion. The fire damage occurred on 31 December 2013 and yet repairs and rectifications were not completed until mid-January 2016. Alternate accommodation has been paid by the FSP and by the builder up until and including 24 January 2016. At that time, some minor works were still required. At the very least, the works included some minor repairs inside, exterior pai nting, cleaning and moving the Applicant’s contents into her home. I consider it is unlikely this remaining work would take longer than 6 weeks. Material on the file indicates rent was around $1,000 a month. Taking all matters into account, I consider it is fair in the circumstances the FSP pay the Applicant a further $1,500 compensation for this aspect of her claim. Case No: 417354 Determination Page 8 of 10 The FSP is to pay the Applicant $462 for G’s report The Applicant claims $462 being the cost of G’s $460. The FSP is not obliged to reimburse the cost but said it would be prepared to consider such a cost on a without prejudice basis. The Terms of Reference provide the Service may decide the FSP contribute to professional costs incurred by the Applicant in the course of the dispute. In all the circumstances, I consider it is fair the FSP reimburse the Applicant for G’s report. The FSP is to pay the Applicant $2,000 compensation for non-financial loss The Service’s Terms of Reference enable the Service to compensate an Applicant for non-financial loss (capped at $3,000). The Applicant claims $3,000 compensation saying she and her family have had to live away from home and in rental property not suitable to their needs for two years. She claims it has taken a toll on their mental health and significant distress has been caused by the attitude of the FSP and the builder towards her concerns regarding the delay and actual works. Compensation for non-financial loss is limited. The Service may decide an FSP should compensate an Applicant for such loss only where there has been an unusual amount of physical inconvenience, time taken to resolve a situation, or interference with the Applicant’s expectation of en joyment or peace of mind. The Service takes a conservative approach to compensation for non-financial loss and expects an Applicant to be moderately robust and bear the usual degree of inconvenience when managing an insurance claim. Nonetheless, in the cir cumstances of this matter, I am satisfied the FSP’s claims handling was not timely and would have interfered with the Applicants’ peace of mind. This Service does not have the power to grant entitlements not provided for under the terms of the insurance contact. T he Service’s Terms of Reference also specifically excludes from the powers of the Service, the ability to award punitive, exemplary or aggravated damages. Having considered the timeframes, I am not satisfied the FSP has handled this matter in a timely fashion. The repairs have taken an extraordinarily long time to complete. Although I have previously accepted the repairs are now complete in the main and the FSP has fulfilled its policy obligations, this took a period of over two years. Whilst the property was extensively damaged, and it was reasonably foreseeable such a large scale repair would take a significant time to complete, I find two years is excessive. The timeline provided by L shows there were significant delays at times including obtaining permits and sourcing trades to commence the work. I accept not all of the delays can be attributed to either the FSP or L. However, as the party responsible for authorising the repairs, it is the FSP's obligation to ensure these are completed in a timely manner. I accept the Applicant has been somewhat compensated for the delays by way of L continuing to pay her temporary accommodation costs whilst repairs continued. Case No: 417354 Determination Page 9 of 10 However, the delay in completing the reinstatement would have interfered with the Applicant's peace of mind and caused undue stress and hardship. On this basis, I consider an award of $2,000 compensation is fair in all the circumstances. Case No: 417354 Determination Page 10 of 10 3 Supporting information 3.1 FOS approach to this dispute As advised to the parties, FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. There has been a full exchange of all material information relied on for the purposes of this Determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered for the purposes of this Determination. This dispute has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. While the parties have raised numerous issues in their submissions, for the purposes of this Determination, commentary has been restricted to those issues considered directly relevant to the outcome only. It is an accepted principle of general insurance law that an insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. The Applicant is represented in this matter and statements from the Applicant and her representative shall jointly be referred to as 'the Applicant'. 3.2 Relevant policy extracts The relevant policy extracts are referred to in the FSP’s Notice of Response dated 19 January 2016. Both the policy document and the Notice have been exchanged with the Applicant. 3.3 Other relevant material considered and relied on  Parties’ submissions and attachments to submissions  Correspondence between the parties