The applicant claimed damage to her home from a toilet pipe leak and complained of claim delays and provider attendances while she was absent. AFCA found the damage claim unsubstantiated and no delay, but found providers attended without permission, with no loss shown.

The applicant had not linked her quotations to the claimed damage or to the actions of the FSP's provider, so the FSP was not required to contribute to settlement.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 417061 Determination Page 1 of 5 Case number: 417061 21 April 2016 1 Overview 1.1 Dispute The applicant lodged a claim for damage to her home which she believed was caused by a water leak. The financial services provider (FSP) assessed the damage claimed. It determined the water leak did not cause the claimed damage. The FSP denied the applicant’s claim. The applicant alleged the FSP’s provider (ALD) caused damage to a toilet pipe cap during their attendance at her home. The FSP acknowledged the issue and the toilet pipe cap has since been rectified. The FSP has requested the applicant quantify her claim for damages as a result of the leaking toilet pipe cap. To date she has not done so and as such, it cannot consider her claim for damages further. The applicant says she has provided the quotations for the replacement of the damaged items and wants the FSP to pay for the damage. She also complains of claim delays and the FSP’s providers acces sing her home when she was absent and without her permission. 1.2 Issues and key findings Has the applicant provided sufficient evidence in support of her claim for damage caused by ALD? The applicant has not provided sufficient evidence in support of her claim for the damage allegedly caused by ALD. Were there any unnecessary delays in the claims handling process? There is no evidence to suggest there were any unnecessary delays during the claims handling process. Did the FSP’s providers attend the applicant’s home while she was absent and/or without her permission? The evidence suggests the FSP’s providers did not always seek the applicant’s permission before attending the property or, the applicant was present during the attendances. Case No: 417061 Determination Page 2 of 5 1.3 Determination This determination is in favour of the FSP. Until such time the applicant quantifies the loss being claimed, the FSP is not required to make any settlement offer or payment to the applicant. Should the FSP require any future assessments of the applicant’s propert y it is to ensure its provider arranges a suitable time with the applicant to ensure she is present and aware of when the assessment will take place. Case No: 417061 Determination Page 3 of 5 2 Reasons for determination 2.1 Has the applicant provided sufficient evidence in support of her claim for damage caused by ALD? The applicant has not provided sufficient evidence The applicant alleges the actions of ALD have caused damage to her property. To this end, she provided quotations for relevant repairs and the replacement of some items. In an attempt t o assess and settle this aspect of the applicant’s complaint, the FSP attempted to arrange a further assessment. However, the applicant did not wish this to occur due to the actions of previously appointed providers. The applicant has not provided any evidence to link the quotations she has provided to the damage she is claiming or the cause of this damage. FOS invited the applicant to provide any additional information in support of her position including photographs of the damage. However, she did not pro vide the relevant material requested. The FSP has a right to request further information from any insured party in order to verify any claim made. The applicant has an obligation to assist the FSP with its enquiries and provide all information requested, providing it is reasonable and relevant to the issue being assessed. In this instance, I am satisfied the FSP has fairly requested further information in support of the applicant’s claim. Until such time the applicant provides evidence to support the quotations which relate to the damage claimed and evidence to show the damage was caused by the actions of ALD, the FSP is not required to contribute anything to the applicant in settlement of these items. Furthermore, the applicant may be required to allow the FSP access to the insured property to further assess the claimed damage and the cause of the claimed damage. 2.2 Were there any unnecessary delays during the claims handling process? There is no evidence to show the FSP caused any delays The applicant lodged her claim with the FSP on or about 14 September 2015. She in turn lodged a complaint with FOS on 15 October 2015. I acknowledge the applicant lodged her complaint mainly because of the damage caused by ALD, which is yet to be substantiated, but the material provided does not substantiate evidence of any delay caused by the FSP in handling the claim. Case No: 417061 Determination Page 4 of 5 Since lodging the claim, the FSP had assessed the damage, appointed a leak detection service to confirm a leak, appointed an engineer and provided the applicant with its decision relating to her original claim. The material establishes the FSP’s actions were timely and in accordance with usual insurance practice. From the material provided, I am not satisfied of delays caused by the FSP. 2.3 Did the FSP’s providers attend the applicant’s property while she was absent and/or without her permission? Good industry practice to ensure the insured is present There is no dispute the applicant originally agreed to allow the FSP’s providers to attend her property to assess the cause and extent of damage to her home when she lodged her initial claim. It would appear she provided permission for these providers to attend her home while she was absent. It also appears, a subsequent attendance was made by ALD when it became aware of the issue with the toilet pipe cap. ALD attended the premises to fix the cap and it is apparent the applicant was not present when this occurred. There is no evidence to confirm the applicant was advised of this visit or her permission was sought prior. It is good industry practice to ensure the owner of a property is present and/or at least aware of any providers’ attendance at a property, prior to attending. The applicant has not provided any evidence of any loss suffered by her as a result of this unauthorised attendance. If the applicant provides further information (as detailed in 2.1 above) and the FSP requires the property to be assessed further, any assessment should be arranged with the applicant prior to attendance, with her permission and with her present. Case No: 417061 Determination Page 5 of 5 3 Supporting information 3.1 FOS Approach As advised to the parties, FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS recommendation and has proceeded directly to determination. There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered for the purposes of this determination. This dispute has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only. 3.2 Policy Extracts The relevant policy terms are referred to in the FSP’s Notice of Response dated 8 December 2015 which was exchanged with the applicant. 3.3 Other material considered and relied on  Parties’ various submissions and attachments to submissions  Correspondence between the parties