Determination 416994

claim_amount_dispute

FirmFinancial Firm (Unknown - Insurer)
Decided2017-02-22
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$109,000
Non-financial loss$1,500
Amount claimed—
SourceAFCA PDF

Summary

An individual's building claim for water leak damage was disputed over how it should be settled, and the FSP offered a cash settlement it said reflected repair quotes. AFCA ordered cash settlement of $109,000 including mould remediation and additional costs, plus $1,500 for non-financial loss from poor claims handling.

Once the relationship had irretrievably broken down after the insurer elected to repair, cash settlement at the reasonable cost of repairs was required, adjusted for passage of time and the insurer's handling.

Issues

Subjects and remedies

pay claimpay compensationpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 424238 Determination Page 1 of 13 Case number: 416994 10 February 2017 1 Overview 1.1 Dispute The applicant lodged a claim under her building insurance policy with the financial services provider (FSP) for damage to her property caused by leaking water pipes in August 2014. The FSP accepted the claim and sought to arrange for the repair of the property. However, after the parties were unable to agree on a scope of works, the FSP offered to cash settle the applicant for the estima ted cost of the repairs. The applicant says the amount offered by the FSP is not sufficient to carry out the necessary repairs, including remediation of mould at the property. She also seeks payment of additional amounts, including reimbursement of costs i ncurred to mitigate further damage and an allowance for alternative accommodation. The applicant is also dissatisfied with the manner in which the FSP has managed her claim and seeks compensation for various losses incurred as a result. 1.2 Issues and key findings How should the claim be settled? Given the breakdown of the relationship between the parties, it is appropriate that the claim be cash settled. Is the cash settlement offered by the FSP fair and reasonable? The cash settlement amount for building repairs should be increased to $88,000 (plus an additional $18,000 for mould remediation works) to more accurately reflect the cost of carrying out the necessary repairs to the property. The applicant is entitled to an additional amount of $3,000 as a contribution to reasonable travel and accommodation costs incurred during the claim process and while the repairs are completed. Is the applicant entitled to compensation? The applicant is entitled to compensation of $1,500 for non-financial loss due to the manner in which the FSP handled her claim. Case No: 424238 Determination Page 2 of 13 1.3 Determination This determination is partly in favour of the applicant. The FSP is to pay the applicant the amount of $109,000 in full and fina l settlement of her claim. The FSP is not required to pay interest on this amount. The FSP is to pay the applicant an additional amount of $1,500 as compensation for non-financial loss. Case No: 424238 Determination Page 3 of 13 2 Reasons for determination 2.1 How should the claim be settled? Insurer is generally bound by election to repair Under the terms of the policy, the FSP may settle a claim for damage to the applicant’s property caused by an insured event by:  repairing or rebuilding the damaged part of the property; or  paying the applicant the reasonable cost (to the FSP) of doing so . It is clear from the terms of the policy that the FSP has the discretion to decide which settlement method to adopt. However, FOS expects an insurer to act reasonably in exercising its discretion, having regard to the circumstances of the claim. In the present case, the FSP initially sought to repair the damage to the property caused by the water leak. Accordingly, the FSP arranged for its contractors to attend the property and prepare a scope of works and sought quotations from builders to carry out the necessary repairs. Once an insurer makes an election to repair the insured property (rather than to cash settle the policyholder for the cost of the repairs), it is generally obliged to complete the repairs in accordance with the terms of the policy. However, particular circumstances may arise which make the conduct of repairs by an insurer untenable. In such cases, it is reasonable for the insurer to seek to settle the claim by way of a cash settlement, provided that the cash settlement amount reflects the reasonable cost of carrying out the necessary repairs. Parties were unable to agree on the scope of works The FSP’s building consultant (IT) inspected the applicant’s property in late September 2014 and prepared a scope of works for the necessary repairs, which was provided to the applicant on or around 20 October 2014. At this stage, it appears to have been the mutual intention of both parties that the repairs would be arranged by the FSP (rather than the claim being cash settled). However, even at this early stage, there was not a clear understanding between the parties as to their respective roles. In her correspondence with the FSP in early October 2014, the applicant set out a proposed structure for implementing a staged scope of works for the repair of the property. The applicant had previously provided the FSP with a list of her preferred local contractors to undertake the repairs. Where an insurance claim is lodged, the insurer is responsible for determining the extent of repairs required to the insured property, so that it can accurately assess its liability under the claim. Case No: 424238 Determination Page 4 of 13 To the extent that the insured person has concerns that the scope of works is inadequate to repair the claim-related damage, they are entitled to raise these issues for consideration (and to dispute any subsequent decision of the insurer). However, the insured person does not have primary responsibility for determining how the repairs will be carried out. Further, where an insurer decides to settle a claim by authorising repairs to the property, the insurer is entitled to use its own contractors to undertake the works (subject to such contractors having the appropriate skill and expertise to do so). It is open to an insured person to propose local contractors or to provide comparative quotes from such contractors for consideration by the insurer. However, the decision as to which contractors to appoint is ultimately a decision for the insurer (as it is liable for the quality of the repairs). In circumstances where the insured person wants the repairs to be carried out by their preferred contractors (rather than the insurer’s preferred contractors), it is more appropriate for the claim to be cash settled. However, i n such cases, the i nsurer will still need to obtain and approve a scope of works and quotations, in order to determine the amount of the cash settlement. In the present case, the correspondence between the FSP and the applicant suggests that the role of each party in finalising the scope of works, as well as the relevance of any quotations obtained from local contractors, was never clearly understood. Following receipt of the scope of works prepared by IT, the applicant wrote to the FSP proposing several variations to the scope of works. The variations proposed by the applicant were intended to address issues including:  the extent of the remediation works required to address mould growth at the property (and the adequacy of the measures proposed by IT);  details of the replacement floor coverings to be used for the kitchen/dining room and granny flat kitchenette areas, as well as minor modifications to the repairs proposed for these areas (with the applicant offering to cover any increased costs to the extent the changes resulted in betterment); and  the costs of taking up and relaying of carpet and underlay in the first floor lounge and sitting room area. The FSP did not respond directly to the issues raised by the applicant but instead proposed an onsite meeting with its building consultant (IT) to discuss her queries regarding the scope of works. However, the applicant indicated that, while she wanted to meet with the FSP to finalise the scope of works, she was not willing to meet at the insured property. It later became apparent that the applicant’s reluctance to attend an onsite meeting was due to concerns about privacy and being put under pressure by the FSP’s representatives, as well as the fact that she considered the scope of works to be largely an administrative matter. Case No: 424238 Determination Page 5 of 13 The parties’ inability to agree on the appropriate next steps led to an impasse for several months, during which time the applicant sought further advice from third parties about appropriate mould remediation measures. As a result of the issues raised by the applicant, the FSP offered to have its mould cleaning specialist (RD) attend the property in order to review the remediation measures required. However, the applicant was not satisfied with this offer due to her concern that RD was not appropriately qualified and her belief that the FSP was disputing the extent of mould contamination at the property. It is appropriate that the claim be cash settled The inability of the parties to move forward resulted in the dispute being referred to the FSP’s internal dispute resolution (IDR) department in January 2015. However, despite further discussions over several months (including a face to face meeting in June 2015), the parties were unable to agree on a final scope of works. Based on subsequent correspondence, it appears that the parties also had differing understandings of what had been agreed at the face to face meeting in relation to the way forward. During this period, the applicant undertook further investigations at the property, including a structural inspection and asbestos testing of damaged building materials. In late August 2015, the FSP raised the possibility of cash settling the claim, which the applicant declined. In her submissions during the course of the dispute process, the applicant has raised a number of concerns about the conduct of the FSP and its contractors. Among other matters, the applicant has:  queried w hether the FSP’s contractors have the necessary skills and qualifications to undertake the works required; and  suggested that the FSP and its employees have acted in various ways which raise issues of serious misconduct. Given the nature of the concerns held by the applicant, I consider that she is unlikely to ever have sufficient confidence in a repair process managed by the FSP as the relationship between the parties has irretrievably broken down. In these circumstances, the only feasible manner in which the claim can be resolved is by way of a cash settlement. 2.2 Is the cash settlement offered by the FSP fair and reasonable? FSP offered to cash settle claim based on scope of works and quotation The FSP has offered to cash settle the claim for the estimated cost of the repairs, based on a quotation provided by its builder (SB) dated 9 August 2015 for the repairs set out in the scope of works prepared b y its building consultant (IT) on 1 October 2014. Case No: 424238 Determination Page 6 of 13 In addition to the amount of $58,965 quoted by SB, the FSP has agreed to include:  the amount of $345.95 paid by the applicant to her plumber for locating the source of the water leak;  the amount of $7,480 quoted by its mould cleaning specialist (RD) for mould remediation works (in addition to the $2,000 for mo uld treatment included in SB’s quotation);  costs of $2,541 incurred by the applicant during the claim process in identifying and removing water damaged asbestos ceiling material; and  the cost of replacing the tiles in the upstairs kitchen/dining area and the downstairs kitchenette with the closest available replacement (in respect of which the applicant has provided a quotation for $6,420). During the dispute process, the FSP also agreed to vary IT ’s scope of works to include the reasonable cost of relaying carpet in the lounge room, which the applicant’s contractor has since quoted at a cost of between $495 and $2,240 (depending on whether the existing carpet can be reused). The applicant says the amount offered by the FSP is not sufficient to repair all of the damage to the property caused by the water leak in August 2014 and the subsequent actions of the FSP and its contractors. The applicant has provided copies of quotations prepared by her own contractors for the cost of restoring the property to its condition prior to the water leak. She says the settlement amount offered by the FSP should be increased to reflect the amount of these quotations. Settlement amount for building repairs should be increased to $88,000 The total settlement amount offered by the FSP for the building repairs is approximately $70,000 excluding any allowance for mould remediation works , which are addressed separately below. As outlined above, SB’s quotation is now approximately eighteen months old and was based on a scope of works prepared by IT around eight months earlier. In these circumstances, it is likely that the cost of completing the repairs has increased, due to changes in supplier costs. It is also possible that the damage to the property has worsened, due to repairs not having commenced. The applicant has provided quotations totalling approximately $80,000 for the building repairs (excluding mould remediation works ). The applicant’s quotations were obtained in the first half of 2016 and therefore are likely to more accurately reflect the current cost of the repairs than the quotation provided by the FSP. Due to the manner in which both sets of quotations have been prepared, it is not possible to undertake a detailed comparison on a like for like basis. Nevertheless, given the context in which they were obtained (and the overall pricing differential of less than 15%), I am satisfied that they are reasonably similar in scope. To the extent that the applicant’s quotations reflect the additional worsening of the damage over time, I consider it is appropriate that the FSP bear responsibility for a significant portion of this damage. Case No: 424238 Determination Page 7 of 13 While the applicant may have appeared unwilling to follow the FSP’s standard processes, she remained committed to exploring ways to achieve an agreed outcome and reiterated this desire on a number of occasions. While the applicant subsequently lost faith in the abilities of the FSP and its contractors, this was partly due to the FSP having failed to respond to her requests for variations to the scope of works and specific queries about the repair process. Had the FSP been prepared to respond directly to the issues raised by the applicant during the early stages of the claim process, it is possible that her concerns could have been addressed and the ultimate impasse between the parties could have been avoided. There were also further delays and a lack of clear communication after the applicant’s dispute was referred to the FSP’ s IDR department, before face to face meetings were held in June 2015 and a reinspection of the property was arranged in July 2015. Once again, the parties appear to have left these meetings with a different understanding of the proposed way forward. These ongoing communication difficulties were not helped by the FSP’s apparent reluctance to provide a written summary of the outcome (which, in the circumstances, is likely to have been helpful). In light of the various factors outlined above, on balance I consider it is appropriate that the cash settlement amount for the building repairs be based on the figure of $80,000. I further consider that it is fair in all the circumstances that this figure be increased by an additional 10% (to $88,000), by way of a buffer to allow for:  cost increases due to the time which has passed since the most recent quotations were prepared; and  any necessary variations and/or the repair of additional damage which may become apparent during the course of the repairs. In determining the cash settlement amount of $88,000 for the building repairs, I have taken into account the passage of time. Accordingly, the FSP is not required to pay interest on this amount. Settlement amount for mould remediation should be increased to $18,000 The property is subject to widespread mould contamination due to the effects of the leaking pipes in August 2014 and the ongoing lack of repairs. The applicant says the mould contamination has been exacerbated by the FSP’s failure to carry out appropriate make safe measures (drying and dehumidification) after the claim was lodged. The FSP says such measures were carried out, but has not provided any information which confirms that this in fact occurred. One of the applicant’s primary concerns during the dispute process was to ensure that the mould remediation at the property was carried out using effective methods implemented by appropriately qualified personnel. Case No: 424238 Determination Page 8 of 13 The applicant’s initial concerns arose largely due to the limited provision for mould remediation contained in IT’s scope of works and SB’s quotation (which allowed only $2,000 for such measures). Subsequent assessments by contractors engaged by both parties indicate this amount was inadequate. When the FSP failed to adequately respond to the applicant’s concerns, she conducted extensive research and engaged her own consultants in order to determine the nature and extent of the mould remediation works required at the property. In December 2014, the FSP offered to have its mould cleaning contractor (RD) attend the property to undertake remediation works, while acknowledging that an accredited mould specialist would be required to undertake any testing required. However, the applicant rejected this approach, on the basis of advice received from her own consultants as to the appropriate methodology for mould assessment and remediation. In the circumstances, I consider that it was not unreasonable for the applicant to seek her own advice to confirm that the remediation measures proposed by the FSP were appropriate. However, I am not satisfied that all of the steps taken by the applicant were necessarily reasonable in the circumstances, given her obligations under the policy and the fact that, at the time, the FSP retained primary responsibility for scoping and arranging the necessary repairs. As outlined above, the FSP has offered to cash settle the applicant for $9,480 for mould remediation works (including the amount of $2,000 originally provided for in SB’s quotation). It appears from the claim notes that the FSP has also previously agreed to cover the costs of preparatory mould assessment and testing. The applicant has provided quotations for mould testing, assessment, remediation and clearance in the range of approximately $20,000 to $25,000 (including amounts incurred to date for which she is seeking reimbursement). Having regard to the factors outlined above, I consider that the FSP should be primarily responsible for the costs of remediating the mould issues which are currently affecting the property. However I am not satisfied that the FSP should be responsible for all of the amounts sought by the applicant, as to some extent th e applicant’s actions during the dispute process have resulted in a duplication of work which would otherwise have been undertaken during the course of repairs. Having reviewed all of the information in respect of mould remediation provided by both parties, I consider it fair in all the circumstances that the settlement amount for this aspect of the works (including testing, assessment, remediation and clearance) be increased to $18,000. Case No: 424238 Determination Page 9 of 13 Applicant is entitled to an allowance for additional expenses The applicant seeks cover for the costs of temporary accommodation for an estimated period of six to eight weeks while the repairs to the property are completed. The policy provides for payment of reasonable alternative accommodation costs incurred by the applicant where her property becomes uninhabitable due to an insured event. It appears from the information provided that the insured property was not the applicant’s sole residence at the time of the water leak in August 2014. Shortly after the claim was lodged, the applicant advised the FSP that she and her husband had relocated to alternative accommodation at no cost. On this basis, under the terms of the policy, the applicant is not entitled to payment of temporary accommodation costs, as she has not incurred any additional expenses due to the water leak in August 2014. However, the applicant says that the FSP’s poor handling of her claim has led to her now having to manage the repair process herself, necessitating accommodation in the local area during the repair period (as the insured property is located several hundred kilometres from the applicant’s alternative residence ). The applicant also seeks reimbursement of travel and other expenses incurred during the claim process, as a result of having had to return to the property at regular intervals to implement measures to prevent the damage worsening and mitigate any further loss. For the reasons outlined above, I consider that the manner in which the FSP handled the claim contributed to the deterioration of the relationship between the parties which ultimately resulted in a cash settlement being the only feasible outcome. In these circumstances, I consider it is appropriate that the cash settlement amount be increased to include an allowance reflecting the reasonable additional costs incurred by the applicant as a result of having to manage the repairs and attend the property during the claim process (given such expenses would not have been incurred had the claim been settled in the manner originally intended). However, such costs do not extend to renting a property of a comparable size and condition to the insured property, as such accommodation is not reasonably required for the purpose of managing the repairs. Having carefully reviewed the available information, I consider it is fair in all the circumstances that the FSP be required to cash settle the applicant for the amount of $3,000 in respect of the additional expenses referred to above. FSP is required to cash settle claim for $109,000 In acco rdance with the above, the FSP is required to cash settle the applicant’s claim for a total amount of $109,000. For the reasons outlined above, the FSP is not required to pay interest on this amount. Case No: 424238 Determination Page 10 of 13 For the avoidance of doubt, this figure represents the entirety of the FSP’s liability for all of the individual items of damage to the property (and expenses incurred for the purposes of investigating or mitigating such damage), regardless of whether or not each such item has been expressly referred to in this determination. 2.3 Is the applicant entitled to compensation? FOS may award compensation for financial and non-financial loss Under the Terms of Reference, FOS may award compensation (capped at $3,300) for consequential financial loss suffered by an applicant in connection with their claim. In addition, FOS may award compensation (capped at $3,000) for non-financial loss where an applicant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. The fact that the applicant’s policy excludes cover for consequential losses does not preclude the award of compensation where such losses have occurred as a result of the way in which the FSP has handled her claim, rather than as a result of the insured event itself. However, FOS adopts a conservative approach to the award of compensation for non-financial loss. FOS expects applicants to be moderately robust and bear the usual stress and inconvenience associated with an insurance claim. FOS may also require a FSP to reimburse an applicant for legal fees incurred by the applicant in the course of their dispute, in certain limited circumstances. Applicant is dissatisfied with FSP’s claims handling The applicant is dissatisfied with the manner in which the FSP has handled her claim. Among other things, the applicant says that:  the FSP and its contractors failed to implement appropriate make safe measures during the early stages of the claim, including arranging for the drying and dehumidification of the property and identifying asbestos-containing building materials;  the FSP engaged contractors who were not suitably qualified and were subject to a conflict of interest as they were on the FSP’s panel; and  the FSP unreasonably delayed settlement of her claim and failed to treat her fairly during the claim process. The applicant seeks compensation for certain consequential financial losses incurred as a result of the FSP’s claims handling. Some of these losses have been addressed in section 2.2 above (such as the costs of undertaking mould investigations at the property and additional travel and accommodation costs related to loss mitigation and the repair process). Case No: 424238 Determination Page 11 of 13 The applicant also says she has suffered significant stress, inconvenience and loss of enjoyment of the insured property during the extended period of time it has taken to resolve this dispute. Applicant is not entitled to compensation for consequential financial loss The additional costs for which the applicant seeks reimbursement include legal fees incurred for the purpose of the applicant’s husband swearing an affidavit reflecting his account of the meeting with the FSP’s contractors on 31 July 2015, as well as other out of pocket costs incurred during the dispute process. FOS will not generally require an FSP to reimburse an applicant for legal fees unless the dispute raises complex legal or technical issues. This is because the dispute resolution processes available for policyholders (including the FOS process) are designed to be accessible to applicants without the need for legal advice. Further, such processes are not bound by strict evidentiary requirements. In the circumstances, I am not satisfied that it was necessary for the applicant to incur legal fees in respect of the swearing of an affidavit by her husband, when a statement of the facts would have been a sufficient record. While it was open to the applicant to do so, it is appropriate that she bear any costs incurred as a result. FOS does not generally award compensation for incidental out of pocket expenses incurred in the course of a dispute (such as telephone and postal charges a nd research costs). Having carefully reviewed the applicant’s submissions, I am satisfied that an award of compensation for consequential loss is not appropriate in the circumstances. Applicant is entitled to compensation of $1,500 for non-financial loss For the reasons outlined earlier in this determination, I consider that many of the difficulties encountered during the claim process could have been resolved, had the FSP and its contractors managed the claim more effectively at an early stage in the process. In the circumstances, I consider an award of compensation for non-financial loss in the amount of $1,500 is appropriate. Case No: 424238 Determination Page 12 of 13 3 Supporting information 3.1 FOS approach to this dispute FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS Preliminary View and has proceeded directly to Determination. This dispute has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues which are considered directly relevant to the outcome only. During the course of this dispute, the applicant has been represented by her husband. For the purposes of this determination, the applicant and her husband have been referred to collectively as “the applicant” and submissions made by the applicant’s husband have been treated as if they had been made by the applicant herself. 3.2 Terms of policy Subject Terms Settlement of building claims If we agree to pay your claim, we will decide whet her to:  repair or rebuild the lost or damaged part of your building;  replace your building;  provide you with a store credit or voucher for the amount we determine to be the reasonable cost of repairing or rebuilding the lost or damage part of your building up to the sum insured stated on your Certificate of Insurance; or  pay you the amount we det ermine to be the re asonable cost of repairing or rebuilding the lost or damaged part of your building up to the sum insured stated on your Certificate of Insurance …. The amount we will pay will be reduced by any applicable excess and/or outstanding premium … If discount arr angements we have in place with suppliers result in us replacing or repairing any part of your building for less than the sum insured or its retail value, we will not refund the premium or pay the differenc e. Alternative accommodation costs If we agree to pay your building and/or contents claim as a result of an Insured Event and we agree that the damage at your insured address is so extensive that you can no longer live there, we will pay, up to a maximum of 52 weeks: Case No: 424238 Determination Page 13 of 13 Subject Terms  your reasonable alternative accommoda tion costs if you own your insured address and have building cover … If we agree to pay your alternative accommodation costs, we will do so from the time your insured address becomes unliveable until it is repaired, rebuilt, replaced or liveable, for up to a maximum of 52 weeks … Limits The amount we will pay is the amount we det ermine is reasonable and appropriate in your particular circumstances up to a maximum of 52 weeks.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.