Summary

Owners of a hail-damaged strata investment unit disputed the FSP's $16,784.96 cash settlement offer. AFCA ordered $26,000 for repairs including interest, $1,386 for an expert report, $5,000 for future lost rent, $1,000 compensation, and a new independent assessment of the garage and common area.

The FSP may cash settle under the policy, but the offer had to include the mould remediation and window-entry damage the FSP's own evidence supported, and the policy excludes carpets.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay compensationpay interestpay non financial lossreassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 416564 Determination Page 1 of 11 Case number: 416564 25 August 2016 1 Overview 1.1 Dispute The applicants are beneficiaries under a strata plan insurance policy between the Body Corporate and the FSP. The a pplicants’ investment property (unit 44) suffered damage following the 27 November 2014 Brisbane hailstorm. The FSP has made a cash settlement offer but the applicants contend the FSP ’s offer is inadequate as it does not take into account their own builder’s opinion. Further, the applicants say the FSP’s own builder agrees with their assessment but his opinion has been “muzzled” by the FSP. The applicants contend the FSP’s conduct has been misleading, deceptive and unconscionable in several instances and want this reviewed. They also say the FSP is in breach of contract by not reimbursing them the cost of their builder ’s report and scope of works. They consider this was a legitimate cost necessary as part of damage mitigation efforts. They submit the FSP should be liable for the cost they incurred in removing carpets, which they allege they were forced to do by the FSP. They also want to be paid for loss of rent when repairs commence. 1.2 Issues and key findings Is the FSP’s settlement offer for repairs fair in all the circumstances? The FSP’s settlement offer is not fair as it does not take into account damage caused when water entered unit 44 via broken windows and does not take into account an allowance for mould remediation in the hallway. The material establishes the FSP is entitled to cash settle and a fair settlement amount is $26,000 which includes statutory interest. In addition, the FSP is to appoint a new independent expert to assess the claimed damage to the common area and garage. Is the FSP liable for the c osts of NC’s report? While the material establishes NC’s report is not information required to make safe or for damage mitigation advice or for emergency mitigation action under the policy, as the panel found some of the material from NC was of assistance in coming to its determination, the material establishes it was fair in the circumstances the FSP pay $1,386 for NC’s report pursuant to FOS’s Terms of Reference. Case No: 416564 Determination Page 2 of 11 Is the FSP liable for the costs incurred in removing the carpet? The FSP is not liable for costs incurred in removing the carpet as the material establishes carpets are not covered under the FSP’s policy and NC had previously recommended the carpet be removed in December 2014. Is the FSP liable to pay the applicants for loss of rent? The material establishes no loss of rent to date. However the material also establishes repairs and mould remediation are required which will probably render the unit unfit for occupation for a number of weeks. In these circumstances, it is fair the FSP cash settles the applicants $5,000 for future lost rent. Are the applicants entitled to compensation? Insufficient probative evidence was provided regarding the alleged conduct of J, and the material provided was not sufficiently persuasive to establish the allegations made by the applicants concerning the FSP’s claims management. However, the material establishes the FSP took an unusual amount of time to resolve the situation which would have interfered with the applicants’ expectation of enjoyment or peace of mind. In these circumstances, it is fair the FSP pay to the applicants $1,000 compensation. 1.3 Determination This determination is partly in favour of the applicants. Should the applicants accept this determination, then, within seven days of acceptance, the FSP is to pay to the applicants:  $26,000 for repairs  $1,386 for the costs of NC’s report  $5,000 for future loss of rent  $1,000 compensation Within 14 days of acceptance, the FSP is also to appoint a new independent builder to attend unit 44 as soon as possible thereafter and assess the claimed damage to the garage and the common area pursuant to the terms and conditions of the policy. Case No: 416564 Determination Page 3 of 11 2 Reasons for determination 2.1 Is FSP’s settlement offer for repairs fair in all circumstances? FSP entitled to cash settle claims There is no dispute between the parties the applicants suffered a loss from a risk insured against or that the FSP accepted the claim. However, a dispute has arisen between the parties as to the FSP’s offer of settlement, which the applicants maintain is insufficient to remedy the damage from the claimed event. As the party seeking the benefit under the policy terms, the onus rests with the applicants to establish they are entitled to the benefit which they are seeking. The FSP’s policy insures the bui lding and common contents (as defined) against physical loss or damage occurring during the period of insurance. The policy sets out definitions specific to cover. It is clear from the definitions, “building” does not include temporary floor coverings or carpets. The FSP’s policy also sets out how much it will pay and how. In the event of a claim it is clear the policy provides the FSP is entitled at its option to repair or replace the building or pay the reasonable cost of repair or replacement of the building, to a condition substantially the same as but not better or more extensive than when new. The FSP has offered to cash settle in the amount of $16,784.96. Having reviewed the policy terms, the panel is satisfied the FSP is entitled to cash settle the claim. The FSP says its offer is based on the most competitive quote from the builder J, and it contends J’s quote was in response to a scope of works designed by the FSP’s assessor and engineer. The applicants say the amount offered is inadequate as it does not take into account the quotation it obtained from NC. NC provided a quotation in the sum of $62,700 after inspecting and photographing unit 44 on 3 December 2014. The applicants also contend the FSP is suppressing a report from its own builder J who inspected the damage on 26 May 2015 and who agreed with their assessment of the costs of repairs. FSP’s experts establish damage to roof caused damage in hallway only The FSP’s engineer JH inspected and photographed unit 44 on 28 April 2015. The engineer found no evidence of water damage in the interior lounge dining room but photographed and noted water stains and mould in the hallway and shower water stains and mould in the bathroom. The FSP’s engineer also inspected the roof. He spoke with a member of the body corporate. He was advised capping flashing had lifted in the storm which allowed water entry into unit 44. He was told this had been repaired a few days earlier. Having inspecte d the roof, the FSP’s engineer was satisfied the capping defect was Case No: 416564 Determination Page 4 of 11 repaired and was consistent with the location and cause of the leak to the hallway. The engineer photographed the repairs. He found no other area of defective roofing. The FSP’s engineer concluded as a result of water ingress during the claimed event mould had developed in the ceiling of the hallway. As a result of this finding, the engineer recommended the following work be done:  the ceiling and cornice of the hallway be removed  the area and adjoining walls be cleaned and treated by a hygienist  the remainder of the unit be treated by a hygienist to remove mould and spores  the removed plaster be replaced and set  the remedial works be repainted. Although the engineer noted mould and water staining was evident in the bathroom area, he attributed this to the use of the shower area and lack of ventilation. In his opinion, this damage was not caused by water entry from the roof. The engineer also made a number of recommendations to eliminate the mould and water stain in the bathroom. C building services also provided a roofing report to the FSP. C inspected the east and west wing of the damaged building to check the integrity of the roof. C found no storm related issues to the roofs. C found the roofs, flashings and gutters to be in good condition. C noted previous repairs to the flashing were adequate. Specifically, C confirmed the roof above unit 44 had no storm related issues. C noted telecommunication towers directly above unit 44 had caused damage to that section of the roof. C reports the telecommunication company admitted liability and were performing repairs to the roof. NC inspected the premises and the roof on 3 December 2014. He said the roof sheeting was in excellent condition. However, he also described penetrations through the roof. He said the areas of penetration relied on silicone to waterproof them. He said the silicone was starting to break down. NC described issues with the lift shaft’s metal cladding. However, the panel considers none of the issues described by NC are caused by or relate to the claimed event. On the information provided, the panel accepts the material establishes as a result of the claimed event, some damage was caused to the roof which in turn allowed water into the hallway. The panel is satisfied the FSP’s engineer’s report establishes any issues with the roof have been repaired. And the panel is also satisfied C’s report establishes if there are ongoing issues with the roof, they are unrelated to the claimed event. J’s quote addresses the storm related repairs scoped by the engineer The panel has considered the quote prepared by J. The panel is satisfied the quote addresses the claim related repair issues to the hallway and bathroom identified by the FSP’s engineer (even though the engineer did not consider the damage in the bathroom was caused by the claim event). Further, J allowed $8,795 to uplift and replace the timber floating floor. Case No: 416564 Determination Page 5 of 11 NC’s quote does not establish all items relate to the claimed event On the other hand, NC’s quote does not establish the amounts claimed in relation to ceiling damage relate to damage caused to the roof by the claimed event. However, the panel accepts the storm event was very severe and notes NC’s comments water came in through a sliding door and windows in some of the rooms. The panel notes make safe costs included installing ply and pine to broken windows. NC’s quote includes the replacement of carpet which is dealt with separately in this determination. Although NC describes water coming through the unit ceilings as putrid dirty water, NC’s report does not establish water entered unit 44 as a result of damage to the roof caused in the claimed event. The FSP’s offer is insufficient Although the panel does not accep t NC’s quotation adequately reflects the cost of repairs caused by the claimed event, the panel considers J’s quote and the offer made by the FSP is inadequate. Most significantly, the offer made does not include the cost to clean and treat the mould in the hallway in unit 44 as described by the FSP’s engineer. Further, the quote does not take into account some of the damage which may have been caused in some of the rooms because water came in through the windows. The FSP obtained a report regarding remediation procedures from R who inspected the premises with the engineer. R’s quote to complete mould rem ediation work in May 2015 was $10,274 plus GST. However, R says the remediation work includes not just remediation required because of the mould affected ceiling plaster and cornice in the hallway and the ensuite but also restoration works required because of affected carpet. The applicants claim there are outstanding issues regarding the garage. None of the material provided addresses damage to the garage. Fair in all circumstances the FSP cash settle in the total sum of $26,000 Having considered the reports regarding the roof, the panel is satisfied any damage to the ceilings in unit 44 as a result of the claimed event is limited to the hallway. However, the panel notes the storm event was very severe and broke windows. The panel accepts some further damage as described by NC in some of the rooms. The panel accepts the FSP is entitled to cash settle the claim. The panel takes into account the amount alre ady offered by the FSP, an allowance of 50% of R’s quote for remediation works caused by the mould in the hallway, and an allowance for damage to some of the rooms caused by rain coming in the windows. In order to finalise this protracted matter, the panel considers it is fair in all circumstances the FSP cash settle the applicants in the total sum of $26,000 which includes statutory interest. Case No: 416564 Determination Page 6 of 11 New independent expert to assess claimed damage to garage only The panel notes the applicants complain not only of leaking into the garage, but they claim the western wing roof continues to leak into the hallway, water leaks into the en suite and there is leaking into the main bedroom western wall. However, considering NC says the roof sheeting is in excellent condition and taking into account the reports from both the engineer and the builder C, the panel is not satisfied any further leaks would have resulted from the claimed event. If there is still a problem with the roof, it may be because of the telecommunications tower and is not properly the subject of this claim. Using a new independent builder, the FSP is to attend and assess the claimed damage to the garage. It may remain necessary for liability and quantum to be determined in relation to the claimed damage to the garage. The panel encourages the parties to resolve any issues which might arise but the parties can refer that issue back to FOS if they are unable to resolve issues arising from the claimed damage to the garage. Insufficient probative evidence provided regarding the alleged conduct of J The panel has also considered the applicants’ contentions about collusion between the assessor and J so that J was forced to underquote. The FSP says while it was not privy to any on-site discussions between the applicants and J, it says there is no financial gain for its assessor to collude with J. Further, it says general discussion between the assessor and J in relation to the provision of a quote and a report based on the engineer ’s scope of works and caused by the claimed event, is usual industry practice. In any event, the FSP said J can be requested to provide site visit notes to satisfy the applicants’ concern no information has been withheld. Having considered the parties’ su bmissions and all the information provided, and noting the FSP’s offer to provide J’s site visit notes, the panel does not accept the applicants have established J was overborne or there are hidden documents or information such that J’s quote is to be disr egarded. New independent expert to assess claimed damage to common area The applicants also claim the FSP has failed to properly restore the common area outside unit 44 which they say is water damaged. The FSP says all damage to common areas has already been addressed and attended to. The FSP says if further additional damage relating to the claimed event can be identified then the policy will respond to appropriate reinstatement costs upon appropriate investigation of the areas. Neither party has provided sufficient information to make a determination in relation to this issue. Accordingly, in appointing a new independent builder to inspect the garage, that builder is also to attend and assess the claimed damage to the common area outside unit 44. Case No: 416564 Determination Page 7 of 11 It may remain necessary for liability and quantum to be determined in relation to the claimed damage to the common area. The panel encourages the parties to resolve any issues which might arise but the parties can return to FOS if they are unable to resolve issues arising from the claimed damage to the common area. 2.2 Is the FSP liable for the costs of NC’s report? FSP liable for NC’s costs pursuant to paragraph 9.4 of the Terms of Reference The applicants claim $1,386 reimbursement for the report they commissioned from NC. The applicants claim this amount on the basis this information was to make safe and was for damage mitigation advice. They further claim the FSP’s failure to pay is a breach of contract. The FSP says NC attended the site on 3 December 2014 after the glaziers, carpet cleaners and handymen had attended and made the premises safe. It also says NC’s report did not add value to the claims process and was not approved by the FSP given the number of relevant personnel attending to urgent mitigation and make safe works across all units in the building. The FSP’s policy provides where an insured is required to protect against further loss or damage in the case of emergency, the FSP gives an insured authority to incur costs in taking emergency mitigation action. The panel has considered the material from NC. NC took photographs and provided a quotation to repair unit 44. It is clear from the report work was already underway to dry out unit 44. Further, the applicants have provided a number of invoices showing make safe work had been done by others. Having considered the material, the panel is not satisfied NC’s report can be classified as information required to make safe or for damage mitigation advice or for emergency mitigation action under the policy However FOS’s Terms of Reference provides FOS may decide the FSP contributes to the professional costs incurred by an applicant in the course of a dispute. Unless exceptional circumstances apply, FOS will not require the FSP to contribute more than $3,000 to these costs. Although the FSP says NC’s report did not add value to the claims process, the panel found some of the material from NC provided assistance in coming to its determination. The panel considers it is fair in all the circumstances the FSP pay $1,386 for NC’s report pursuant to the Terms of Reference. 2.3 Is the FSP liable for the costs incurred in removing carpet? NC recommended the carpet be removed The applicants also claim to be entitled to reimbursement of costs incurred in relation to the removal of carpets and underlay and purchase of rugs. The FSP says its policy does not extend to cover carpet. Further, it contends the applicants were told on many occasions the damage to the carpet within the unit was Case No: 416564 Determination Page 8 of 11 not covered. Consequently, the FSP contends any subsequent building damage or loss of rent from the lack of action to remove the carpets is the responsibility of the applicants and/or their contents insurer. The material establishes the applicants engaged CD to provide an assessment report on water damage. CD’s report dated 2 December 2014 confirms water damage to carpets in three bedrooms and the hallway. CD said the carpet was not restorable because of safety concerns regarding fragments of glass in the carpet. CD quoted mitigation and make safe costs which included installing drying equipment for four days and anti-microbial treatment. The material provided shows on 10 December 2014 the applicants paid CD to undertake this work. NC inspected unit 44 on 3 December 2014. Even though NC notes the applicants had fans to dry the areas out, he notes the carpet in each room had mould growing on the back of it. In his report and in an email to the applicants dated 7 December 2014, NC recommended the carpet be removed and replaced along with the underlays and smooth edge. Although the applicants describe ensuing problems, the panel is satisfied the material clearly establishes the applicants were on notice from NC shortly after the event t he carpets would need to be removed. Correspondence provided by the parties establishes the applicants’ broker confirmed that advice. Correspondence between the applicants and their broker also confirms carpets are not covered by the FSP’s policy but is a matter for the contents insurer. The panel has considered the FSP’s policy. It is clear carpets are not covered under the FSP’s policy. The material establishes the applicants removed the carpet and underlay in the main bedroom and hallway in May 2015. MCS removed the carpet. MCS report notes although there was no signs of mould on the carpet or the underlay, there was mould on the smooth edge. In view of this, the opinions of CD and NC and the reports from the remediation experts, the panel is satisfied on the information known at the time, it was necessary to remove the carpet. In the circumstances, the panel is not satisfied the FSP is liable for the costs the applicants incurred in removing the carpets and underlay. 2.4 Is the FSP liable to pay the applicants for loss of rent Unit will probably be unfit to be occupied while repair/remedial work is done The applicants also claim for loss of rent in the future. The FSP says unit 44 has remained habitable throughout the life of the claim. When the event occurred, unit 44 was tenanted. The weekly rent was $850. The tenancy ended in May 2015. The unit has been re-tenanted. On the material provided, there is no evidence the applicants have lost rent to date. However, the material also establishes repairs and mould remediation are required. Case No: 416564 Determination Page 9 of 11 The policy provides the FSP will pay for loss of rent if an insured loss or damage renders the unit unfit to be occupied. Having considered the repairs and mould remediation work required, the panel is satisfied the unit wo uld probably be unfit to be occupied while the repair work and remedial work is carried out. The material provided does not give an estimate of the time taken to undertake the repairs and remediation work. In order to bring this protracted matter to an end, and taking into account a reasonable estimate of 4 - 6 weeks to complete the repair work and remedial work, the panel considers is fair in all the circumstances to cash settle this aspect of the claim in the amount of $5,000. 2.5 Are the applicants entitled to compensation? Compensation is paid in some circumstances FOS’s Terms of Reference enable FOS to compensate an applicant for non-financial loss but this award is capped at $3,000. Compensation for non-financial loss is limited. FOS may decide an FSP should compensate an applicant for such loss only where there has been an unusual amount of physical inconvenience, time taken to resolve a situation, or interference with the a pplicant’s expectation of enjoyment or peace of mind. FOS takes a conservative approach to compensation for non-financial loss and expects an applicant to be moderately robust and bear the usual degree of inconvenience when managing an insurance claim. Costs incurred or time spent in managing the claim are not compensable by FOS. FOS does not have the power to grant entitlements not provided for under the terms of the insurance contact. However, policy terms are not relevant to the issue if it is the FSP’s conduct which causes the loss. The FOS Terms of Reference also specifically excludes from the powers of FOS, the ability to award punitive, exemplary or aggravated damages. The applicants allege misleading, deceptive, unconscionable and unacceptable conduct by the FSP. The allegations mainly refer to relying on material (or ignoring material from J) to issue a limited scope of works and quotation for cost of repairs caused by the event. However, as set out earlier in this determination, the panel does not accept the applicants have established these allegations. The applicants also say there has been unconscionable conduct on behalf of the FSP or its agents. They refer to sending the FSP’s representatives to unit 44 without prior notification, relying on incorrect conclusions regarding carpet mould and incorrectly issuing a warning to remove the carpets. The panel has addressed the issues regarding the carpet earlier in this determination. The panel is not satisfied the applicants have established their contentions. The FSP acknowledges it did not advise of their representatives’ arriv al but say it was an error and when attending unit 44 their representatives did ask permission before entering. Having considered all the material, the panel accepts the FSP’s explanations. Case No: 416564 Determination Page 10 of 11 Further, the applicants complain lengthy correspondence was ignored or answered only in part. The applicants submit not responding to their communications is unacceptable. Fair in all the circumstances the FSP pay the applicants $1,000 compensation The panel notes this was a catastrophic event. Even within the same building, there were several claims. When considering an overall view of the correspondence, and all the circumstances facing the FSP, the panel is satisfied the FSP was reasonably responsive. However despite the circumstances, the panel considers the FSP has taken an unusual amount of time to resolve the situation. The storm event occurred on the 27 November 2014. In a report dated 4 February 2015, the FSP indicates it would obtain an expert opinion from an engineer. Yet the engineer’s opinion is not obtaine d until 12 May 2015 and J does not inspect the property until 26 May 2015. The panel is satisfied this unusual amount of time taken to resolve the situation would have interfered with the applicants’ expectation of enjoyment or peace of mind. The panel considers it is fair in all the circumstances the FSP pay to the applicants $1,000 compensation. Case No: 416564 Determination Page 11 of 11 3 Supporting information 3.1 FOS Approach As advised to the parties, FOS has considered it appropriate to refer this matter directly to a panel in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS recommendation and has proceeded directly to determination. This decision has been made by a panel consisting of an Ombudsman and two representatives with consumer and insurance experience. There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered for the purposes of this determination. This dispute has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only. It is an accepted principle of general insurance law that an insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. 3.2 Relevant policy extracts The relevant policy extracts are referred to in the FSP’s Notice of Response dated 10 February 2016. Both the policy document and the Notice have been exchanged with the applicants. 3.3 Other relevant material considered and relied on  Parties’ submissions, emails , photographs and all attachments to emails  Correspondence between the parties