Determination 416356
Delayed malicious damage claim, repair scope and consequential travel costs
Summary
The landlord's malicious damage claim was settled after lengthy delays and disputes over repairs. AFCA ordered $1,000 non-financial loss compensation and $600 for the hot water system and balustrades, and rejected the claim for return airfares.
Under paragraph 9.3 of the Terms of Reference, unreasonable delay caused unusual inconvenience warranting non-financial compensation, and the insurer's prejudice from early replacement limited its liability to 50%.
Issues
- Delay primary · upheld
“The applicant is entitled to compensation for non-financial loss due to the unreasonable delays in the resolution of the claim”
- Claim amount dispute secondary · upheld
“the FSP's liability with respect to these items be limited to 50% of the cost incurred”
- Poor claim handling secondary · not upheld
“I am not satisfied such expenses were necessarily incurred as a result of the FSP's claims handling”
Subjects and remedies
travel or overseaspay claimpay non financial loss
Text of the determination
Determination
Case No: 416356 Determination Page 1 of 6
Case number: 416356 24 June 2016
1 Overview
1.1 Dispute
The applicant held a Landlord’s Insurance Policy with the FSP.
On 17 March 2015 the applicant reported her property had been maliciously
damaged by her tenants. The claim was lodged on 14 May 2015. The FSP accepted
liability for the claim however issues arose with delays in the repairs and scope of
works.
The applicant lodged a dispute with the Service relating to:
costs of repair of the roof which the applicant had paid for
loss of rental income and incorrect calculation of rental income
cost of damage to dining table
damage to property caused by dogs
compensation for non-financial loss.
The majority of these issues have now resolved. The issues that remain in dispute
and subject of this determination are as follows:
compensation for cost of applicant’s airfares to return to Australia to supervise
repairs
cost of repair of balustrades, hand rails and replacement of hot water service
non-financial compensation
1.2 Issues and key findings
Is the applicant entitled to compensation for non-financial loss?
The applicant is entitled to compensation for non-financial loss pursuant to paragraph
9.3 of the Terms of Reference due to the unreasonable delays in the resolution of the
claim. In am satisfied an amount of $1,000 is fair and reasonable .
Is the applicant entitled to compensation for consequential loss for her travel
expenses?
The applicant is not entitled to compensation for consequential loss for the travel
expenses. I am not satisfied such expenses were necessarily incurred as a result of
the FSP’s claims handling.
Is the FSP liable to meet the costs of replacement of the hot water service and
repair of the balustrades?
I am satisfied it is fair in the circumstances that the FSP pay 50% of the $1,200 cost
to replace the hot water service and repair the balustrades and hand rails.
Case No: 416356 Determination Page 2 of 6
1.3 Determination
This determination is partially in favour of the applicant.
It is fair in the circumstances that the FSP pay the applicant the sum of $1,000 by
way of compensation for non-financial loss pursuant to paragraph 9.3 of the Terms of
Reference and $600 for the damage sustained to the hot water service, balustrades,
and hand rails.
Case No: 416356 Determination Page 3 of 6
2 Reasons for determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the information
exchanged.
In addition, I have been able to speak with both parties to discuss these issues.
The applicant agrees the remaining issues in dispute relate to:
1. Cost of repairs to the balustrades and handrails – the applicant repaired these
at a cost of approximately $200. The FSP refused to include these in the
statement of works.
2. Replacement of the hot water service – the applicant replaced the rusted hot
water service with a gas hot water service. The applicant seeks the replacement
cost of the hot water system only at $1,000.
3. Cost of return airfare to Australia. Applicant maintains because of ongoing
delays and bungling by the FSP, she lost her property manager and was
required to return from England to sort out the repairs and deal with the issues.
4. Compensation for non-financial loss due to the delays.
2.1 Is the applicant entitled to compensation for non-financial loss?
The applicant is entitled to compensation for non-financial loss
The Terms of Reference provide under paragraph 9.3 that compensation of up to
$3,000 may be awarded for non-financial loss where an applicant has experienced
an unusual degree of inconvenience or delay in the resolution of the dispute.
Claims history
The applicant notified the FSP on 17 March 2015 of possible malicious damage
sustained to her property by her tenants after the tenants had vacated the property.
The FSP’s internal records confirm notification however it appears the FSP lost the
applicant’s contact details and email address.
The applicant subsequently contacted the FSP in May 2015. A ccording to the FSP’s
claim notes, a repair assessment was requested from BMC on 14 May 2015.
The assessment of the property was conducted on 22 June 2015 . It appears the FSP
either did not receive or review the report from BMC until 20 July 2015.
When discussed with the applicant on 20 July 2015 the FSP advised they had
received the report but they did not have a quote and they would speak with BMC to
obtain a quote.
The claim notes confirm that after that conversation the FSP arranged an internal
assessor to attend the property, report and provide a Scope of Works.
Case No: 416356 Determination Page 4 of 6
The next action recorded on the applicant’s file is on 6 August 2015 following the
internal assessor’s review.
The FSP appointed BMC to complete the repairs. BMC notified the applicant on 29
August 2015 of its intention to commence repairs that day. BMC provided limited
notice about this to the applicant.
The applicant became frustrated with the process and quality of repairs completed by
BMC.
On 28 October 2015 a second repairer LSC was appointed. It was to attend and
assess further works required.
The FSP ultimately settled the applicant’s claim for the costs of repairs and for loss of
rent for the period 17 March 2015 to 20 October 2015 save for the cost of repairing
the balustrades and hand rails and replacing the hot water service.
I am not satisfied the FSP has adequately explained why the delays have occurred. I
accept some delay would have been caused by the applicant’s circumstances
however the majority of the problems relate to issues c aused by the FSP’s initial
builder and assessor. The delays and issues with the repairs have caused
considerable distress for the Applicant.
In the circumstances, I am satisfied that the applicant did experience an unusual
degree of inconvenience as a result of the claims handling process. In my view
compensation of $1,000 for non-financial loss pursuant to paragraph 9.3 of the
Terms of Reference would be fair and reasonable in the circumstances.
2.2 Is the applicant entitled to compensat ion for consequential loss?
The applicant has claimed the sum of GBP1090 (approximately 2,200 AUD) being
the cost of her return flight from UK , to manage the repairs and deal with the issues
The applicant maintains that due to the delays she lost her prope rty manager and
she was required to return to Australia. She provided her e-ticket showing she left
England on 2 July 2015 and returned on 7 January 2016. I note the email with the e-
ticket was provided to the applicant on 16 June 2015. Presumably the applicant
decided to return to Australia around that time.
According to the FSP internal notes the claim was activated on 14 May 2015
following an email from the applicant.
There is no indication in the information exchanged that the applicant’s property
manager had refused to deal with FSP at this time. An assessment of the property
was arranged for 22 June 2015. The delay in arranging the assessment was
associated with difficulties in arranging a suitable time with the applicant. There is no
indication that the property manager had left at this stage.
Case No: 416356 Determination Page 5 of 6
The applicant had moved to the UK with her husband who was in employment in the
UK. The applicant’s decision to return to Australia may have been influenced by her
claim but I am not satisfied it was necessary in order for the works to be properly
completed. It is clear the return flight had been arranged prior to the assessment by
BMC and prior to any dispute with the FSP arising.
In the absence of evidence from the property manager I am not satisfied the
expe nses could be reasonably said to be consequential to the FSP’s delays. At the
time the airfares were arranged only one month had elapsed since lodgement of the
claim.
To the extent that the applicant considered it was necessary, then I am satisfied that
such inconvenience is covered within the compensation paid under paragraph 9.3 of
the Terms of Reference for non-financial loss.
2.3 Is the FSP liable for the cost of repair of the balustrade and hand
rails and replacement of the hot water service?
The applicant claims that the roof was maliciously damaged causing water to leak
onto the hot water system. The applicant believes this caused the hot water system
to rust out. The applicant replaced the electric hot water system with a gas hot water
system. The applicant seeks payment for the cost of the unit, not installation.
Further, the applicant believes the timber balustrades and hand rails were damaged
maliciously. The hand rails and balustrades were repaired at the cost of
approximately $200.
The FSP disputes the hot water system was maliciously damaged. As the system
was replaced prior to it having the opportunity to inspect the system it has prejudiced
its ability to assess the damage.
The applicant disputes this and maintains the FSP was aware of the damage from
the start.
I note the FSP’s assessor commented the damage was due to wear and tear and
possibly rust but had not inspected the hot water service.
I also note the FSP’s assessor following inspection of the property on 6 November
2015 considered the balustrades and hand rails to be loose and the damage not
malicious but rather wear and tear.
There is no other information about the damage to the hot water system, balustrades
or hand rails. I am concerned that the available information does not properly
determine the extent of liability with either of these items.
I have looked at photographs of the applicant’s property and I accept the damage to
the balustrades and hand rails could well have been deliberate . I also accept that the
damage to the hot water system could have occurred as a result of malicious
damage.
I also accept that the FSP has been prejudiced by the applicant’s conduct in
replacing the hot water service prior to its inspection of the same. Again, I accept that
Case No: 416356 Determination Page 6 of 6
part of this could be due to frustration experienced by the applicant because of the
initial delays involving the original builder and assessor.
Having regard to the Terms of Reference under which the Service operates and
given the limited information available, it is fair in the circumstance that the FSP’s
liability with respect to these items be limited to 50% of the cost incurred.
As the applicant’s claim is for the items is $1,200 then I am satisfied the FSP is
entitled to limit its liability to $600 for the damage.