Partial claim declined for cracking and movement damage after 2011 flood

FirmFinancial Firm (Unknown - Insurer)
Decided2016-10-12
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$2,500
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant's home suffered cracking damage he attributed to the February 2011 flood. The FSP offered $10,500 and denied the rest under earth movement and workmanship exclusions, and AFCA ordered it to pay 50% of an estimated $26,000 repair cost, an extra $2,500 plus interest.

The insurer may rely on clearly stated exclusions but bears the onus on the remainder where the flood is a proximate cause, and with mixed causes AFCA apportioned the loss at 50%.

Issues

Subjects and remedies

home or building damagelanguage or cultural barriernatural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 416137 Determination Page 1 of 10 Case number: 416137 29 September 2016 1 Overview 1.1 Dispute In November 2013, the applicant lodged a claim under his home insurance policy with the financial services provider (FSP), for cracking and movement damage to his property. The applicant considers the damage was caused by the inundation of his property during severe storms and floods in February 2011. The FSP offered to cash settle the claim for $10,500 (being part of the estimated repair costs), on the basis that some of the claimed damage had been caused by the flood in February 2011. However, the FSP declined liability for the remainder of the repair costs, on the basis that the bulk of the damage was caused by factors which are excluded under the policy (such as naturally occurring earth movement and/or faulty design or workmanship). The applicant considers the FSP should be required to cover at least 50% (if not all) of the repair costs. He says it is unfair to allow the FSP to rely on the policy exclusions, as he was not made aware of them when he took out the policy. 1.2 Issues and key findings Is the FSP entitled to rely on the terms of the policy? The FSP is entitled to rely on the terms of the policy because:  the terms were clearly set out in the policy documents, a copy of which were provided to the applicant; and  the FSP was not obliged to highlight any specific exclusions which might apply, given the location of the applicant‟s property. Is the FSP required to increase the settlement amount? Having regard to the extent of the damage and the likely contributing factors, it is fair in all the circumstances that the FSP contribute to 50% of the cost of repairs. Case No: 416137 Determination Page 2 of 10 1.3 Determination This determination is partly in favour of the applicant. The FSP is to increase the cash settlement amount of $10,500 (less the policy excess of $500), by an additional amount of $2,500 plus interest on this amount as set out in section 2.2 below. Case No: 416137 Determination Page 3 of 10 2 Reasons for determination 2.1 Is the FSP entitled to rely on the terms of the policy? Applicant says FSP should have highlighted policy exclusion The applicant does not dispute that he was provided with a copy of the policy schedule and the Product Disclosure Statement (PDS) setting out the terms of his policy. However, the applicant says it is unfair to allow the FSP to rely on the terms of the policy (and in particular, the exclusion for earth movement) because the FSP did not make this exclusion sufficiently clear to him at the time he took out the policy. The applicant considers the FSP should have been required to highlight the relevant exclusion, given his property is located in an area which is susceptible to earth movement due to the characteristics of the soil. The applicant also says the FSP should have been aware that he was from a non- English speaking background and was inexperienced in dealing with home insurance policies. FSP is entitled to rely on terms of policy In the ordinary course of its business, an insurer is likely to become aware of various issues which may affect some of the properties it insures more than others. However, the insurer‟s duties do not extend to advising each policyholder of specific risks to which their property may be subject, and particular exclusions which may apply. The exclusion for earth movement on which the FSP seeks to rely is clearly set out in the policy documents, a copy of which were provided to the applicant. Exclusions of this nature appear in most home insurance policies. In these circumstances, it was the applicant‟s responsibil ity to review the terms and conditions on which cover was offered, to determine whether they were appropriate for his needs. In the event the applicant required assistance, he could have sought advice from a friend or family member, or contacted the FSP directly. The applicant says the FSP agreed to insure the property in the condition it was in when he took out the policy. Accordingly, he considers the FSP should be prevented from relying on exclusions in relation to any structural defects which existed at that time. However, the FSP‟s agreement to insure the applicant‟s property was subject to the terms and conditions set out in the policy documents (including any relevant exclusions). As the exclusions for damage caused by structural defects and faulty design or workmanship were clearly set out in the policy documents, the FSP is entitled to rely on these exclusions, for the purposes of considering the applicant‟s claim. Case No: 416137 Determination Page 4 of 10 For the reasons set out above, I am satisfied that the FSP is entitled to rely on the terms of the policy (including the relevant exclusions), as set out in the PDS. 2.2 Is the FSP required to increase the settlement amount? Policy provides cover for storm and flood damage subject to exclusions The applicant is required to show that, on the balance of probabilities, he has suffered a loss caused by a risk insured against under the policy. This is known as a prima facie claim. If the applicant is able to establish a prima facie claim, then the onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to deny the claim. The applicant‟s policy provides cover for damage caused by the events listed in the policy (including the insured event of „storm, rainwater, flood or wind‟, subject to the conditions and exclusions contained in the policy. The policy contains general exclusions for loss or damage caused by:  settling, shrinkage or any earth movement (other than landslide or subsidence in certain limited circumstances); or  a defect in an item, structural defects, faulty or poor workmanship or design. FSP says bulk of damage was caused by excluded factors The reports prepared by the FSP‟s consultants confirm that there is cracking damage to various wall linings at the applicant‟s property. The floors are uneven and slope downwards towards the exterior walls, indicating relative differential settlement towards the perimeter of the property. The FSP accepts that part of the cracking and movement damage was caused by the severe storms in February 2011. During the storms, flood waters inundated the sub- floor area of the applicant‟s property to a height just below floor level (but did not enter the property itself). The FSP has offered to cash settle the applicant for $10,500 (less the policy excess), which represents just over a third of the total estimated repair costs. The FSP considers this is a fair and reasonable estimate of the cost of repairing that portion of the damage which was caused by the floods. On this basis, I am satisfied that the applicant has established a prima facie claim. Accordingly, the FSP bears the onus of establishing that, on the balance of probabilities, it is entitled to rely on a policy exclusion to deny liability for the rem ainder of the applicant‟s claim. The FSP says it is not liable for the remainder of the claimed damage because the bulk of the damage was not caused by the inundation of the property in February 2011, but by:  naturally occurring earth movement over an extended period of time, exacerbated by features of the sub-floor; and Case No: 416137 Determination Page 5 of 10  the addition of a number of lean-to structures, which have compromised the integrity of the original building. The FSP also says it has been prejudiced by the fact that the applicant did not lodge his claim until approximately 18 months after the flood and commenced renovations to the property in the meantime. FSP’s liability for disputed damage depends on proximate cause In order to determine the extent of the FSP‟s liability for the crac king and movement damage to the applicant‟s property, it is necessary to identify the proximate cause of the damage. The proximate cause is the dominant, efficient or operative cause of the damage. However, it is not required to be the sole cause or the last in time. The identification of the proximate cause is a question of fact that depends on the circumstances of each particular case. FSP’s engineers have provided differing views regarding effects of flood During the claim process, the FSP appointed two engineers to determine the cause of the cracking and movement damage to the applicant‟s property. The first engineer (MP) concluded that none of the damage to the property had been caused by the flooding in February 2011. He considered the damage was more likely to have been caused by naturally occurring seasonal variations in the moisture content of the foundation soils. MP‟s view was primarily based on the timing of the damage, which the applicant advised had not become apparent until late 2013 (other than some minor hairline cracking to the kitchen ceiling immediately following the flood). The applicant advised that he had not repaired any cracks during the intervening period. MP considered that, had the differential movement at the property been caused by the flood, the effects would have been apparent within a few weeks (or at most, a couple of months). MP noted that, in this event:  the flood waters saturating the surrounding soils would have initially caused them to expand, resulting in heave (upwards movement); and  the subsequent drying out of the soils over time would have resulted in reverse downwards movement (settlement), causing the cracks to begin to close up. On this basis, MP concluded that the new cracks which appeared in late 2013 were inconsistent with the size and direction of the damage which would be expected, had this damage occurred as a result of the flood in February 2011. The FSP initially denied the applicant‟s claim in its entirety, based on the findings in MP‟s report. After the applicant disputed the denial, the FSP engaged a second engineer (RB) to provide his opinion as to the cause of the damage. In his report, RB agreed with MP that the damage was caused by differential movement of the foundation soils, due to variations in moisture content. However, RB Case No: 416137 Determination Page 6 of 10 also noted that the moisture variations occurred due to changes in the height of the water table under the house. RB observed that the flood had “a massive effect o n the water t able at the time”, which would have continued even after the visible flood waters had subsided. RB did not consider that the timing of the cracking and movement damage was necessary inconsistent with the damage having been caused by the flood. RB noted that the sub-floor soils were likely to dry out at different rates, particularly given the presence of various mounds and hollows (which would trap water in some areas, while allowing it to evaporate more quickly in others). However, while RB acknowledged the effects of the flood on the sub-floor soils, he also noted that the water table was subject to ongoing fluctuations causing further movement. Following receipt of RB‟s report, the FSP accepted that part of the claimed damage had been caused by the flood and offered to cash settle the applicant for $10,500. However, the applicant says the FSP ‟s cash settlement underestimates the extent to which the flood caused or contributed to the damage observed at his property. FSP is required to increase cash settlement The FSP determined the settlement amount of $10,500 based on what it considered to be a fair and reasonable contribution to the repair costs, given the circumstances. The issues considered by the FSP included the extent to which other causes were likely to have contributed to the flood-related damage, as well as the alleged prejudice it had suffered as a result of the applicant‟s actions following the flood. Having regard to the views expressed by the FSP‟s engineers, I accept that some of the claimed damage is likely to have occurred as a result of ongoing earth movement over time, due to naturally occurring changes in the moisture content of the surrounding soils. This damage is excluded from cover under the policy due to the exclusion for damage caused by settling, shrinkage or any other earth movement. However, to the extent that part of the damage is attributable to the flood waters, I do not consider that the FSP is entitled to rely on the other issues identified (in particular, the design of the sub-floor) to deny or reduce its liability for this portion of the damage. As outlined above, the FSP‟s second engineer (RB) noted that the hollows and mounds on the surface of the sub-floor soils would have extended the time it took for parts of the soil to dry out following the flood, resulting in differential settlement. RB also considered that the fact that the sub-floor area was lower than the surrounding area would have contributed to the time taken for the soils to dry out. As outlined above, th e FSP‟s liability depends on the proximate cause of the damage. In circumstances where there are several causes operating Case No: 416137 Determination Page 7 of 10 contemporaneously, each must be examined for the qualities of predominance and efficiency as the active cause that set the relevant train of events in motion. In the present case, the applicant‟s property was affected by a significant weather event in February 2011, which resulted in the inundation of a significant number of properties in the area. While certain features of the applican t‟s sub -floor may have exacerbated the effects of the flood waters on his property, I am nevertheless satisfied that the storm and resulting inundation is properly characterised as the proximate cause of any such damage. The other factors relied on by the FSP are not sufficient to constitute a concurrent cause of equal efficiency. The FSP has also referred to the construction of lean-to structures attached to the original property as contributing to the damage caused. In his report, RB refers to these extensions as possibly not having been built to an appropriate standard and contributing to “complications” at the property. However, he does not clearly explain how these structures would have contributed to the cracking and movement damage observed. Further, I am not satisfied that the FSP is entitled to reduce its liability as a result of any delay by the applicant in lodging his claim. The applicant has advised that he lodged his claim as soon as he became aware that there was significant damage to his property. The fact that the damage did not become apparent until sometime after the flood is not attributable to any act or omission on his behalf. However, I accept that the applicant‟s conduct of renovations prior to addressing the movement issues at his property (for example, retiling sloping floors) may have resulted in additional damage. FSP is required to increase settlement amount by $2,500 For the reasons outlined above, I consider that some (but not all) of the damage to the applicant‟s property was caused by the flood in February 2011. The FSP has acknowledged that it is liable for a portion of the damage. The FSP‟s engineer (RB) concluded that it was not possible to determine with any certainty what percentage of the damage was caused by the flood. In these circumstances, I consider it is appropriate that the FSP be required to contribute to 50% of the costs of repairing the damage. The FSP obtained quotations for the repair of the property from three builders – TR ($23,950), BB ($25,975) and PI ($28,666). Each of these quotations included some provision for internal repairs (in addition to re-stumping), although these allowances were rough estimates only. Case No: 416137 Determination Page 8 of 10 It is likely that the quotations included the repair of some damage which was attributable to the applicant‟s ongoing conduct of renovations (rather than the flood itself). On the other hand, the FSP‟s loss adjuster (C) considered the quotations made insufficient provision for further internal damage to the property which is typically triggered by the re-stumping process. Having carefully reviewed all of the available information, I consider the amount of $26,000 represents a fair and reasonable estimate of the total cost of repairs. Accordingly, the FSP is liable for 50% of this amount. On this basis, the FSP is required to increase the settlement offer of $10,500 (less the policy excess of $500), by an additional amount of $2,500. The FSP is to pay interest on this additional amount at the rate calculated in accordance with section 57 of the Insurance Contracts Act 1984 (Cth), from 4 May 2015 until the payment date. Case No: 416137 Determination Page 9 of 10 3 Supporting information 3.1 FOS approach to this dispute This determination follows the review of a recommendation provided on behalf of the Financial Ombudsman Service (FOS) on 17 February 2016. The recommendation was rejected by the applicant. There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered for the purposes of this determination. This dispute has been decided based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only. During the course of this dispute, the applicant has been represented by his lawyer. For the purposes of this determination, submissions made by the applicant‟s lawyer have been treated as if they had been made by the applicant himself. 3.2 Terms of policy Subject Terms Defined event – storm or flood The specific events that your buildings are covered for are listed in the table below … Storm, rainwater, flood or wind We will cover …loss or damage as a result of  storm (including named cyclone)  rainwater  flood, or  wind. We won’t cover … water entering your buildings:  through an opening made for any building, renovation or repair work  because of a structural defect, faulty design or faulty workmanship General exclusions What we will not pay for We will not pay for any loss or damage which is caused directly or indirectly by :  settling, shrinkage or any movement of earth  settling, shrinkage or expansion in buildings, foundations, walls or pavements  erosion, rust, gradual deterioration, depreciation, wear or tear …  a defect in an item, structural defects, faulty or poor workmanship or Case No: 416137 Determination Page 10 of 10 Subject Terms design