Text of the determination
Determination
Case No: 415269 Determination Page 1 of 9
Case number: 415269 7 July 2016
1 Overview
1.1 Dispute
The applicant lodged a claim under her home insurance policy with the financial
services provider (FSP) after her property was damaged by a tropical cyclone in
February 2015.
The FSP accepted the claim and authorised repairs to the property, subject to the
applicant addressing certain pre-existing damage to the property so that the repairs
could commence. However, a dispute arose as to liability for various aspects of the
works and the FSP ultimately cash settled the claim for a total of $122,623.54.
The applicant says the cash settlement paid by the FSP is not sufficient to allow her
to repair all of the damage to her property caused by the c yclone. She wants the FSP
to either increase the cash settlement amount or undertake the repairs itself.
The applicant also seeks compensation for stress and inconvenience suffered as a
result of the manner in which the FSP handled her claim.
1.2 Issues and key findings
Is the FSP entitled to cash settle the claim?
The FSP is entitled to cash settle the claim, as the pre-existing damage to the
property meant that it was not feasible to carry out the claim-related repairs.
Is the FSP required to increase the settlement amount?
The cash settlement amount reflects the fair and reasonable cost of repairing the
damage to the property caused by the cyclone in February 2015. Accordingly, the
FSP is not required to increase the settlement amount.
Is the applicant entitled to any other amounts?
The applicant is entitled to interest due to the FSP’s delay in paying the cash
settlement amount. She is also entitled to compensation for stress and
inconvenience due to issues regarding the FSP’s handling of her claim.
Case No: 415269 Determination Page 2 of 9
1.3 Determination
This determination is substantially in favour of the FSP.
The FSP is not required to repair the applicant’s property or increase the settlement
amount.
However, the FSP is required to pay the applicant:
interest on the bulk of the cash settlement amount ($121,451.04), as set out in
section 2.3 below; and
the amount of $1,500 as compensation for non-financial loss.
Case No: 415269 Determination Page 3 of 9
2 Reasons for determination
2.1 Is the FSP entitled to cash settle the claim?
Insurer is generally bound by election to repair
Under the terms of the policy, the FSP may settle a claim for damage to the
applicant’s property by arranging for its contractors to repair the damage or by paying
the applicant the cost (to the FSP) of doing so.
It is clear from the terms of the policy that the FSP has the discretion to decide which
settlement method to adopt.
Once an insurer makes an election to repair the insured property (rather than to cash
settle the policyholder for the cost of the repairs), it is generally obliged to complete
the repairs in accordance with the terms of the policy.
However, particular circumstances may arise which make the conduct of repairs by
an insurer untenable. In such cases, it is reasonable for the insurer to seek to settle
the claim by way of a cash settlement, provided that the cash settlement amount is
sufficient to allow the policyholder to engage a builder directly to complete the
necessary repairs.
FSP has altered its position several times during the claim process
The FSP initially advised the applicant that it would cash settle her claim, based on
advice from its assessor (RM) that the undamaged areas of the property would not
support the claim-related repairs.
However, in July 2015, the FSP authorised its builder (A) to undertake the necessary
works, after the applicant expressed a strong preference for the FSP to arrange the
repairs and A confirmed that the repairs could be completed effectively.
The confirmati on provided by the FSP’s builder (A) was based on the understanding
that the applicant would be required to pay for the repair of cracking damage to the
garage concrete slab. The FSP considered the damage to the slab pre -existed the
storm and needed to be addressed before the claim-related repairs to the garage
could commence.
However, when the applicant advised the FSP that she was unable to afford the
repairs to the slab, A was no longer able to guarantee the repairs to the garage.
Accordingly, the FSP reverted to its initial offer of a cash settlement.
The applicant subsequently disputed that all of the damage to the slab was pre-
existing and advised that further damage had occurred during the cyclone in
February 2015. As a result, the FSP appointed an engineer (O) to determine the
cause of damage to the garage slab.
Based on O’s findings that the cyclone had exacerbated the pre -existing damage to
the slab, the FSP amended the approved scope of works for the repairs to provide for
a “top - up” slab to be po ured over the existing slab. This meant that the builder (A)
was once again willing and able to carry out the proposed repairs.
Case No: 415269 Determination Page 4 of 9
However, when the applicant raised further concerns about the scope of works, the
FSP engaged a second engineer (JH) to inspect the property and prepare a detailed
report identifying which aspects of the reported damage had been caused by the
cyclone and which aspects were pre-existing.
The FSP says the findings in JH’s report establish that it is unable to effectively repair
the cyclone-related damage, given the pre-existing issues with the property (in
particular, the damage to the garage slab and the subsidence of the stumps).
FSP is not liable for repair of pre-existing and excluded damage
As outlined above, during the course of the claim, the FSP has relied on several
different issues as a basis for cash settling the applicant’s claim, despite having also
offered to arrange the repairs at various stages during the claim process.
It appears that the original advice from the FSP’s assessor ( RM) that the property
could not be effectively repaired was based on concerns about the ability of the
undamaged areas to support the installation of a new roof.
RM’s concerns about the roof repairs were later established to be unfounded. The
FSP’s engineer (JH) confirmed in October 2015 that the roof framing was structurally
sound and the roof repairs could be completed effectively.
However, having carefully reviewed the available information, the Panel is satisfied
that there are aspects of the damage to the applicant’s property which pre -existed
the cyclone and make it unfeasible for the FSP to carry out the claim-related repairs.
The FSP’s engineer (JH) concluded that the initial cracking damage to the concrete
slab in the garage had occurred as a result of long-term movement.
The applicant’s husband confirmed that the crack in the slab pre -existed the cyclone,
but advised that following the cyclone the width of the crack had increased and
lipping to each side had occurred.
In his report, JH advised that the pre-existing crack had penetrated down to the
reinforcing steel, which had caused the corrosion of the steel. While JH agreed that
further movement of the slab had occurred during the cyclone, he co nsidered this to
be primarily due to the pre-existing condition of the slab.
JH also concluded that the noticeable drop in the floor on one side of the house had
not been caused by the cyclone in February 2015, but by long-term damage to the
timber stumps in that area, as a result of long-term decay.
The photographs included in JH’s report confirm that the timber stump directly under
the affected area had previously been packed with 30 millimetres of folding wedges,
indicating that the downwards movement of the stump preceded the storm. JH also
excavated the earth around this and other nearby stumps, revealing long -term decay.
The applicant acknowledges that there was pre-existing damage to the stump directly
under the affected area but says the movement of the floors only occurred after the
cyclone.
In order to determine whether the FSP is liable for the damage to the garage
concrete slab and the movement of the floors, it is necessary to identify the
Case No: 415269 Determination Page 5 of 9
proximate cause (that is the real, effective or domina nt cause) of the relevant
damage.
In the present case, the Panel is satisfied that the proximate cause of the damage to
the slab and the movement of the floors was the pre -existing issues identified by JH.
As an engineer, JH is appropriately qualified to determine the cause of the observed
damage to the applicant’s property. The Panel considers that JH’s report provides a
logical and rational explanation of how the damage occurred, which is consistent with
the observed facts and supported by the detailed, colour photographs included in
JH’s report.
While the applicant has disputed the findings in JH’s report, she has not provided any
independent information (for example, a report from a qualified engineer) which
refutes JH’s findings in relation to the cause of the damage to the garage slab and
the movement damage to the house.
In the absence of any such information, the Panel is satisfied that, to the extent that
further damage to these areas occurred during the storm, this damage was caused
by factors which are excluded under the policy (namely, long term earth movement
and/or gradual deterioration).
FSP is entitled to cash settle the claim
For the reasons outlined above, the Panel is satisfied that the FSP is not liable for
repairing the damage to the garage slab and restumping or re-levelling the house.
In these circumstances, the Panel accepts that it was reasonable for the FSP to cash
settle the applicant’s claim, rather than arranging for its builder to undertake the
cyclone-related repairs.
In this regard, the Panel notes that:
the FSP’s builder (A) has previously confirmed that the claim -related repairs to
the garage cannot be effectively completed, without the damage to the slab
being repaired; and
given the claim-related repairs include the repair of cracking damage to the
walls and ceilings, it is necessary for the damage to the stumps to be addressed
in order to prevent this damage reoccurring in the future.
Under the policy, the FSP guarantees the quality of any repairs undertaken by its
contractors. Accordingly, it is not reasonable to require the FSP to undertake repairs
in circumstances where pre-existing damage to the property may render the
proposed repairs ineffective.
On this basis, the Panel considers it was reasonable for the FSP to settle the
applicant’s claim by way of a cash settlement.
Accordingly, the Panel will now consider whether the amount of the cash settlement
paid by the FSP for the repair of the claim-related damage is fair and reasonable.
Case No: 415269 Determination Page 6 of 9
2.2 Is the FSP required to increase the cash settlement amount?
FSP’s scope of works for building repairs is generally appropriate
As outlined above, the FSP cash settled the applicant’s claim for a total of
$122,623.54.
The cash settlement amount was determined based on a quotation for $121,451.04
provided by the FSP’s builder (A) for carrying out the repair of the cyclone -related
damage, as set out in a detailed scope of works prepared by the FSP’s assessor and
reviewed by its engineer (JH).
The FSP had previously paid the applicant an amount of $1,172.50 for cyclone
damage to the rear boundary fence in December 2010, after she provided quotation
for the repair of this damage.
Having carefully reviewed the scope of works approved by the FSP, the Panel is
satisfied that it provides an accurate assessment of the works required to repair the
cyclone- related damage to the applicant’s property.
The repairs included in the scope of works are generally consistent with the claim-
related damage to the property as identified in the reports prepared , and the
photographs taken by, the FSP’s contractors following their assessments of the
property.
When he reviewed the scope of works in October 2015, JH took into account any
additional deterioration which had occurred as a result of the delay in repairi ng the
damage caused by the cyclone.
On this basis, the Panel is satisfied that the scope of works approved by the FSP is
appropriate.
Cash settlement amount is fair and reasonable
The applicant says the cash settlement paid by the FSP is insufficient to allow her to
restore the property to its condition before the cyclone. She believes the quotation
provided by the FSP’s builder (A) significantly underestimates the actual cost of
carrying out the necessary repairs.
In part, the applicant’s concerns arise out of the fact that she is unable to afford to
repair the damage to the garage slab and the timber stumps.
However, the Panel has found the FSP is not liable for these aspects of the damage,
for the reasons outlined above.
Further, the cash settlement amount includes an allowance of $2,560 towards these
repairs (which the FSP paid on the basis that this amount had been offered earlier in
the claim process, before further information about the cause of damage was
obtained).
The applicant has provided quotations obtained from her own builders for various
aspects of the repairs, together with a statement from another builder which
describes the property as “unrepairable” .
Case No: 415269 Determination Page 7 of 9
However, none of the quotations provided by the applicant are directly comparable
with A ’s quotation, as they are not based on the approved scope of works.
Further, the fact that the applicant’s builders have quoted higher amounts for the
repairs than the FSP’s builder (A) does not of itself establish that A’s quotation is
inadequate.
It is clear from the claim records that A was willing to undertake the repairs set out in
the scope of works for the amount quoted, subject to concerns about the impact of
the pre-existing damage.
For the reasons outlined above, the Panel is satisfied that A’s quotation represents a
reasonable basis for determining the cash settlement amount .
Accordingly, the FSP is not required to increase the cash settlement of $122,623.54
paid to the applicant for the repair of the claim-related damage.
2.3 Is the applicant entitled to any additional amounts?
FSP is required to pay interest
The FSP paid the bulk of the settlement amount ($121,451.04) to the applicant on 13
January 2016.
The Panel acknowledges that, for several months prior to this payment, the FSP was
seeking to negotiate with the applicant and obtain further information regarding the
disputed aspects of the scope of works.
Nevertheless, the Panel considers the FSP should have acted more promptly to cash
settle the applicant for an amount reflecting its liability for the undisputed aspects of
the damage, particularly given the applicant had advised the FSP on several
occasions that she was a low income earner.
In these circumstances, the FSP is required to pay the applicant interest on the
amount of $121,451.04 at the rate calculated in accordance with section 57 of the
Insurance Contracts Act 1984 (Cth) for the period from 1 September 2015 (when the
FSP received A’s revised quotation) until 13 January 2016.
Applicant is entitled to compensation for non-financial loss
Under the Terms of Reference, FOS may award compensation (capped at $3,000)
for non-financial loss where an applicant has suffered an unusual degree or extent of
physical inconvenience, time taken to resolve the situation or interference with their
expectation of enjoyment or peace of mind.
The applicant has raised a number of concerns about the manner in which the FSP
has managed her claim. Among other things, the applicant says:
the FSP’s assessors has tried to bully her into accepting a cash settlement;
the FSP’s employees have been rude and condescending; and
the FSP’s contractors have deliberately lied and provided misleading reports
about the cause of the damage to her property.
Case No: 415269 Determination Page 8 of 9
Having carefully reviewed the claim history, the Panel considers there are various
aspects of the claim which the FSP could have handled better. In particular, the
Panel considers that:
the FSP’s initial decision to cash settle the claim was based on an
unsubstantiated and incorrect assessment by its assessor (RM);
the FSP should have communicated more clearly to the applicant the basis on
which it authorised A to undertake repairs in July 2015;
the FSP should have provided the applicant with appropriate information (such
as a copy of the approved scope of works) in order to enable her to make an
informed decision as to whether or not to accept the cash settlement offer (as
opposed to the applicant being required to actively seek this information
herself); and
the difference between the FSP’s initial settlement offer of approximately
$89,000 and the final settlement amount suggests that some of the cyclone-
related damage to the property may have been omitted from the original
assessment.
However, the Panel is not satisfied that the available information establishes serious
misconduct on the part of the FSP’s contractors (such as the deliberate falsifying of
information) as asserted by the applicant.
The Panel accepts that the claims handling issues outlined above have exacerbated
the stress and inconvenience experienced by the applicant during the claim process.
In these circumstances, the Panel considers that an award of $1,500 for non-financial
loss is appropriate.
Case No: 415269 Determination Page 9 of 9
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS recommendation. Due to the nature
of the dispute, it has been referred directly to a Panel for determination, in line with
the Operational Guidelines to the FOS Terms of Reference. The Panel consists of an
Ombudsman and two representatives with consumer and insurance experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous Financial Ombudsman
Service (FOS) decisions.
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
The Panel has reviewed and considered all of the material provided by the parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, the Panel has restricted its commentary to those issues that it
considers directly relevant to the outcome only.