Outstanding rebuild, demolition and loss of rent after fire settlement with another insurer
Text of the determination
Determination
Case No: 415203 Determination Page 1 of 8
Case number: 415203 27 May 2016
1 Overview
1.1 Dispute
The Applicant‟s investment home building were insured with the financial services
provider (FSP 2) for $140,000. The building was also insured with FSP 1 and FSP 3
at the time.
The property sustained damage as a result of a fire and FSP 3 paid $250,000 for
property damage and $4,500 for loss of rent as the full and final settlement of the
claim. The Applicant remains unhappy with the settlement and says the cost to
rebuild the property amounts to over $600,000.
The Applicant seeks further compensation from FSP 1 and FSP 2.
FSP 1 and FSP 2 deny any compensation is payable to the Applicant for the building
on the basis he has been fully indemnified for his loss by FSP 3.
1.2 Issues and key findings
Is FSP 2 required to make any payment for the building?
FSP 2 must pay the Applicant half the following outstanding amounts (which are
inclusive of GST):
$40,000 for demolition and rebuilding of the home (including fence)
$3,300 for loss of rent.
The Applicant is not entitled to recover for any loss relating to the workshop or the
sheds.
No determination is made in respect of the neighbour‟s property.
1.3 Determination
This determination is substantially in favour of the Applicant.
FSP 2 must pay the Applicant $21,650 in accordance with the terms and conditions
of the policy. No interest is payable.
Case No: 415203 Determination Page 2 of 8
2 Reasons for determination
2.1 Is FSP 2 required to make any payment to the Applicant?
The Applicant held multiple policies
The Applica nt‟s home policy held with FSP 2 included cover for fire to the building up
to $140,000. Demolition costs are included in this amount, but up to 52 weeks loss of
rent is not.
The Applicant had the property insured with three insurers because of the additional
benefits offered under each insurer. Due to personal commitments the Applicant left
for overseas before cancelling the policies he did not intend to keep. The loss
occurred on 27 August 2014 whilst he was still overseas.
On 28 August 2014, the Applicant notified FSP 1 and FSP 2 of the fire. However, it
was not until February 2015 that the Applicant lodged claims with FSP 1 and FSP 2.
This is because it was not until this time that he realised the settlement he had
negotiated from FSP 3 was not adequate to rebuild the property.
Settlement was made by FSP 3 for $254,000
FSP 3 explained the basis of its settlement offer as follows:
The sum insured with FSP 3 was $288,000
AB provided a quote to demolish ($38,236.00) and rebuild the house as it was
($184,793.50) totaling $223,029.50.
Carpet and curtains were not included in AB‟s quote and were estimated by
FSP 3‟s assessor as $8,500, bringing the total loss to $231,329.81.
The Applicant counter offered $250,000 as full and final settlement.
FSP 3 accepted this (being $18,670.19 above the loss adjusted amount to
reinstate the property) and also paid loss of rent in the amount of $4,500.
Total settlement to the Applicant was therefore $254,500 ($94,239.98 made to
the Applicant‟s b ank as mortgage loan repayment).
FSP 3 has notified FSP 1 and FSP 2 it seeks to make recovery against them when
this dispute is finalised.
The quotes from each party vary significantly
The Applicant has presented several quotes from builders who estimate the cost to
rebuild the property including the workshop and sheds amount to over $600,000.
FSP 1 and FSP 2 do not believe the cost to rebuild the property will exceed the claim
settlement offered by FSP 3.
The following table summarises the quotes and estimates received from the parties:
Builder Demolition Construction
Case No: 415203 Determination Page 3 of 8
Builder Demolition Construction
Applicant’ s builders
SC
20.2.15
$35 - 40,000+GST $520 - $550,000+GST
Other costs: $35,000+GST
ST
2.3.15
$40 - 60,000+GST $500 - $550,000+GST
Other costs: $25 - 35,000+GST
GH
16.4.15
$526 - 576, 000
DR
11.3.15
$650,000
TH $645,000
FSP 1’s a sse ssors and builders
FSP 1‟s
assessor
18.08. 15
$46,000 + GST $249,802 including GST, demolition, allowing for asbestos
removal and 10% remote location factor, on a m 2 basis
$275,803, with inclusions as per above, on a room basis
P - 22.03.16 $38,236 $257, 308, incl GST
$375,579.60 incl GST, sheds and workshop
FSP 2’s builders
AB
23.3.16
$72,000 (as
advis ed by
Applicant but not
confirmed by AB)
$240,360.41, including GST and preliminaries, reconstruction,
paving & fencing, builder‟s margin of 10%.
This is using a local builder.
126m 2 dwelling
S
28.8.15
$32,005 Replacement cost ( 126 m 2 )
$190,022 (fence, paving and location factor of 10% an additional
$14,781) plus GST
Professional fees: $9,547 + GST
Excludes garage and sheds.
15% variance needs to be allowed.
Total replacement cost $271,980 including GST
FSP 3’s builder
AB
19.09. 14
$38,236, incl GST $184,793, including GST based on 114m 2 dwelling, without
plans. Includes builder‟s margin of 10%
Does not include engineering carpets, blinds or landscaping
A fair and reasonable cost for demolition is $45,000
The various builders above have indicated in writing that the cost of demolition to be
between approximately $38,000 and $66,000, including GST and where the removal
of asbestos has been taken into account.
Case No: 415203 Determination Page 4 of 8
The Applicant advised FOS he had spent about $45,000 on demolition and expects
to spend another $15,000 towards soil remediation and the like. However, no
evidence has been produced by the Applicant in support of this. The Applicant has
also advised he completed the works himself.
Considering all of the above, the Panel is satisfied that $45,000 (including GST) is a
fair and reasonable estimate for the cost of demolition, including for the removal of
asbestos. In reaching this estimate, the Panel notes:
FSP 2 ‟s assessor confirmed that AB‟s quote of $38,236 in respect of demolition
and rebuild to be far too low. (There is some ambiguity as to whether the
assessor was confirming the Applicant‟s concerns or simply restating them).
The assessor estimated demolition at $50,600, including GST.
S‟s estimate of $35,206 including GST is not completely clear that it includes
asbestos removal, although this can be implied given S notes the building
contained asbestos.
The Applicant‟s builders‟ estimate the costs to be between $44,000 and
$66,000, including GST.
The Applicant stated AB had advised him it would not demolish the home for
$38,236, but it would actually cost $72,000. However, this has not been
confirmed in writing to FOS.
The Panel considers the sum of $45,000 including GST to be adequate to include
any soil remediation works required to rebuild, that may be covered by the policy.
The fair and reasonable cost for construction of the main building is $245,000
FSP 1 and FSP 2 do not accept the Applicant‟s quotes for rebuild which range from
$545,000 to $645,000, including GST. FSP 1 and FSP 2 consider the quotes are not
specific enough. FSP 2 states that:
SC, ST and GH‟s quotes do not provide a full scope of works and materials
DH‟s and TH‟s quotes include items not realised in the original dwelling su ch as
garage doors with automatic controller, built in robes and Italian designer
kitchen appliances and underfloor insulation.
This is supported by a statement from FSP 1‟s assessor that the home was a 3
bedroom standard weatherboard home yet the quotes obtained are based on a 5
bedroom architecturally designed home which is not like for like.
While the Applicant provided an email to FOS which set out what he says were the
instructions to his builders, there is no evidence of exactly what the builders were
quoting on. For example, DR stated:
“$650,000 will build a very nice house and depending on the size and style of home we
design it would most likely come in under $650,000.”
SC noted that its quote included a costed option for drawings that allowed for the
higher range and for architectural flair, but was subject to confirmation once the
scope was determined.
Case No: 415203 Determination Page 5 of 8
The Panel also does not accept the original quote from AB. This is beca use:
FSP 2‟s assessor appears to consider it far too low (and recommends engaging
S).
e ven FSP 3 settled on an amount higher than AB‟s quote.
the Applicant‟s statements that AB advised him it could n ot do the work for this
amount
while FSP 2 submitted that its assessor had advised the original quote from AB
was actionable, this is not consistent with the evidence of the Applicant, nor with
the significant increase in the quote provided between September 2014 and
March 2016.
This leaves the quotes from S, P and the updated quote of AB to consider. These are
to be preferred over FSP 1‟s assessor‟s estimates, given they are not actionable
quotes. The quotes are as follows:
S‟s quote on 28 August 2015 was $236,775 including GST, but excluding
quoted demolition costs of $32,005. S noted that a variance of 15% would be
acceptable for a project of this size
P‟s quote dated 22 March 2016 was $257,308 including GST but excluding
demolition (and excluding the workshop and shed)
AB‟s updated quote dated 23 March 2016 w as $240,360 including GST, but
excluding demolition.
The Applicant is critical of the three quotes. He states for example, that the 10%
remote location inclusion allowed for in S‟s quote is insufficient and 50% should be
allowed. However, the applicant has not provided any supporting evidence by way of
other builder‟s quotes that note this increased allowance. Further, AB‟s updated
quote was specifically stated to be based on a builder local to the area.
Having carefully reviewed all the above quotes, the Panel considers it is fair in all the
circumstances to allow for $245,000 including GST for the costs of rebuild (but
excluding demolition and the workshop and sheds).
FSP 1 and FSP 2 must compensate the Applicant for the difference
In February 2015, the Applicant settled with FSP 3 for the demolition and rebuild of
the property (not including the workshop and sheds) for $250,000. This compares to
the Panel‟s assessment that a fair and reasonable settleme nt approximately 15
months later is $290,000 for demolition and construction.
The Panel is of the view that this difference of 16% cannot be attributable to
inflationary building costs alone and it is fair in all the circumstances for the Applicant
to be compensated in respect of this difference. The Panel notes that AB increased
its quote by approximately 30% between 19 September 2014 (on which FSP 3‟s
settlement was based) and the quote it prepared based on a local builder in March
2016. This demonstrates that the initial quote was likely to be inadequate.
S noted that a variance of 15% could be expected with a quote of this size and it is
arguable that such a margin should be allowed for in any settlement. However, in this
instance, the Panel considers the variance risk should be borne by the Applicant.
This is because the Applicant elected to cash settle with FSP 3, in the expectation
Case No: 415203 Determination Page 6 of 8
that he could perform the work for less than the settlement he received. It is therefore
not appropriate to add 15% to t he Panel‟s estimate of $245,000 any more than it is to
reduce the amount by 15%.
The Panel‟s view is that a fair assessment of demolition and construction costs
should is $290,000 (an overall difference of $40,000 from FSP 3‟s settlement). As
this is based on current costs, it is not appropriate to make an award of interest.
The garage / workshop was not damaged by the fire
The Applicant says the garages and sheds were damaged as a result of the fire in
August 2014. The photographs taken by FSP 3 soon after the fire do not show
extensive damage to these areas. The photographs subsequently taken show
additional damage to the garage.
The Applicant explained that:
„… the fire did start from the roof right side of the garage (visitor room or workshop), …
most of the damage was caused by the high water pressure of the fire brigade trying to
extinguish the fire. ‟
The Applicant also explained that there was additional soot and burnt ground near
the shed after the fire, due to burning off debris in an attemp t to minimise the costs of
demolition.
The Panel has reviewed the photographs supplied by the parties of the damage to
the sheds and garage. The Panel notes that while the garage was not damaged
externally by the fire, the Applicant‟s photos show extensiv e damage to the interior,
including to the ceiling.
However, the Applicant has not demonstrated that this damage was caused at the
time of the fire as opposed to at a later time, including when the Applicant was
burning off debris from the demolition. This is supported by comments made by FSP
2‟s assessor that due to the little damage sustained to the workshop he did not
inspect it at the time of his assessment.
Accordingly, the Applicant has not established that the damage to the workshop was
a result of the fire on 26 August 2014.
The sheds were not damaged by the fire
The FSP refers to the significant distance between the sheds and the main building
which was alight. The Panel accepts that it is unlikely the sheds would have been
damaged by the fire and as such, no allowance is made for the repair or rebuild of
the two sheds.
No determination in respect to damage to the neighbour’s property
The Applicant has claimed for damage to the neighbour‟s property. FSP 2‟s assessor
reported that the neighbour had advised the property was uninsured and requires
approximately $80,000 of repairs from the fire.
No information has been provided to support a finding that the Applicant is liable for
such damage, that a claim against the Applicant has been made by the neighbour, or
Case No: 415203 Determination Page 7 of 8
the extent of the damage. As such, the Panel is unable to make any determination in
respect of the neighbour‟s property.
Further payment is required for loss of rent
The Applicant received 30 weeks loss of rent from FSP 3, but considers he is entitled
to the balance (a further 22 weeks) considering the time it would take to rebuild the
property.
The Panel considers a rebuild within 30 weeks was somewhat optimistic, particularly
given the location of the property. The Panel notes the delay in FSP 2‟s assessment
due to the poor weather at the site. Further, given the time taken to resolve this
dispute and the outcome of this determina tion, it is fair in all the circumstances for the
balance of the loss of rent period (22 weeks) to be paid by FSP 1 and FSP 2.
Settlement costs will need to be apportioned between the three FSPs
Once the payments are made to the Applicant, the three FSP‟s will need to apportion
the costs among themselves according to their respective sums insured and policy
terms and conditions.
There has been no prejudice
FSP 1 and FSP 2 state they were prejudiced by the Applicant‟s failure to lodge a
claim with them until the Applicant realised the settlement from FSP 3 was
inadequate. This meant they did not have the opportunity to inspect the site while the
damage was still fresh and to obtain quotes at that time.
However, shortly after the fire, the Applicant notified both FSP 1 and FSP 2 of the
fire, as well as his intention of claiming against FSP 3 given it provided higher
coverage. It was open to FSP 1 and FSP 2 to make whatever arrangements they
wished to in order to protect their position at this time. The Applicant‟s actions
therefore did not prejudice either FSP 1 or FSP 2 such that they may reduce their
liability to the Applicant.
Case No: 415203 Determination Page 8 of 8
3 Supporting information
3.1 The FOS approach
The Panel has determined this dispute based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous FOS decisions.
The Panel has taken into account all the material submitted by the parties, which has
been exchanged between FSP 1, FSP 2 and the Applicant. Each party has had the
opportunity to address any issue raised by the other.
This dispute has been expedited to a Determination. No Recommendation was
issued.
3.2 Chronology
Date Event
27 February 2014 Building and content insurance taken out with the FSP 1.
17 July 2014 Building insurance taken out with FSP 2
26 August 2014 Property burnt down
28 August 2014 Applicant cancels policy with FSP 1, on basis he will lodge a
claim with FSP 3
A pplicant advised FSP 1 of fire
Applicant cancels policy with FSP 2, on basis h e will lodge a
claim with FSP 3
Applicant advised FSP 2 of fire
17 February 2015 Applicant rec eived settlement of $250, 000 from FSP 3
18 February 2015 Applicant lodged a claim with FSP 1 and FSP 2
1 June 2015 Applicant required to demolish building by emergency order
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.