Home / Financial Firm (Unknown - Insurer) / Determination 414812

Determination 414812

Cash settlement amount for storm damage to farm shed

FirmFinancial Firm (Unknown - Insurer)
Decided2016-03-04
ProductGeneral Insurance · Business / commercial
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$44,000
SourceAFCA PDF

Summary

The applicants claimed about $44,000 for storm damage to a farm shed, and the FSP offered a $6,090 cash settlement for the storm damage it accepted. AFCA found the further movement damage was caused by long-term deterioration and excluded, so the settlement was fair and no increase was ordered.

The insurer is liable only for repairing damage proximately caused by the insured storm event, and the engineer's report on long-term movement of the stumps was accepted over the applicants' unsupported evidence.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 414812 Determination Page 1 of 5 Case number: 414812 4 March 2016 1 Overview 1.1 Dispute The Applicants lodged a claim under their farm insurance policy with the Financial Services Provider (FSP) for storm damage to a three bay shed at their property. The FSP accepted liability for the damage to the western bay of the shed and the metal roof sheets on the central and eastern bays. The FSP offered to cash settle the Applicants for a total of $6,090, based on the estimated cost of repairing this damage. The Applicants are dissatisfied with the cash settlement amount. They say the entire shed has been damaged and requires rebuilding as a result of the storm, at an estimated cost of approximately $44,000 (including the cost of upgrading the power supply). 1.2 Issues and key findings Is the FSP required to increase the settlement amount? The additional damage to the shed claimed by the Applicants was not caused by the storm but by factors such as gradual deterioration and long term earth movement, which are excluded from cover under the policy. Accordingly, the FSP is not required to pay for the cost of replacing the shed. Based on the available information, the cash settlement amount offered by the FSP reflects the reasonable costs of repairing the damage caused by the storm. Accordingly the FSP is not required to increase the settlement amount. 1.3 Determination This Determination is in favour of the FSP. The FSP is not required to increase the settlement amount. Case No: 414812 Determination Page 2 of 5 2 Reasons for Determination 2.1 Is the FSP required to increase the settlement amount ? Policy provides cover for storm damage subject to exclusions The Applicants are required to establish that, on the balance of probabilities, they have suffered loss or damage which falls within the scope of cover under the policy. This is known as a prima facie claim. If the Applicants are able to establish a prima facie claim, the onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy to deny the claim. The policy provides cover for damage to t he Applicants’ property (including the three bay shed) caused by the events listed in the policy (including the insured event of “storm or water”), subject to the conditions and exclusions set out in the policy. The FSP accepts that the shed was damaged by strong winds experienced during the storm in early August 2015. On this basis, I am satisfied the Applicants have established a prima facie claim under the policy. Accordingly, the FSP bears the onus of establishing that, on the balance of probabilities, it is entitled to reduce its liability for their claim. Dispute concerns extent of damage caused by storm The FSP has accepted liability for damage to the western bay of the shed, which collapsed during the storm. The FSP offered to cash settle the Applicants for $5,590 in respect of this damage, based on the estimated cost of rebuilding this section of the shed. The FSP also offered the Applicants an additional amount of $500 for the costs of refastening metal roof sheets on the central and eastern bays of the shed which had come loos during the storm. However, the Applicants say the storm has caused additional damage to the shed, which means that it needs to be demolished and rebuilt in its entirety. The Applicants seek a cash settlement of over $44,000 based on the quotes obtained from their contractors. The FSP says it is not liable for rebuilding the shed as the additional damage was not caused by the storm in August 2015, but by factors which pre-existed the storm and are excluded under the policy (such as wear and tear, gradual deterioration and earth movement). In order to determine the extent of the FSP’s liability, it is necessary to identify the proximate cause of the dispute damage (that is, the effective, dominant or operation cause). Case No: 414812 Determination Page 3 of 5 Movement damage was caused by excluded factors The Applicants say that the strong winds experienced during the storm together with the collapse of the western bay of the shed caused the remainder of the shed to move. They say this damage is clearly evident from:  the movement of the timber post at the northern side of the shed, which supports the overhead power line between the shed and the main residence; and  the misalignment of the door to the central bay, which could not be opened as it had dropped following the storm. The engineer (CR) appointed by the FSP confirmed that there was movement damage to the shed. However, CR concluded that this damage had not been caused by the storm, but by the rotation of the timber stumps supporting the shed over an extended period of time. I am satisfied that, as an engineer, CR is appropriately qualified to determine the cause of the movement damage to the Applicants’ shed. Having carefully reviewed CR’s report, I consider it provides a logical and reasonable explanation as to the cause of the damage, which is consistent with the observed facts. In his report, CR noted that there was no evidence of recent damage to the affected areas of the shed, such as would be expected if the movement damage had been caused by the storm. In particular, CR noted that:  there was no evidence of any disturbance to the ground near the affected timber stumps;  there was no sign of any recent separation of the suspended timber floor;  there were long-term deposits of windblown debris in the gaps between the rafters and the top plate of the eastern wall; and  the nailed connections in the roof and northern elevation were still intact and showed no signs of recent misalignment. CR’s report contains detailed colour photographs which clearly show the rotation of the timber stumps supporting the floor of the central bay. CR’s report also includes photographs confirming there was no evidence of recent damage in the areas referred to above. The Applicants have confirmed that the shed was over 30 years old (and possibly up to 50 years old) at the time of the storm. The photographs provided indicate that the shed showed signs of wear and tear and deterioration prior to the storm (as may be expected in the circumstances). The Applicants have not provided any independent information (including a report from an equivalently qualified expert) which refutes the findings in CR’s report. In the absence of any such information, I am satisfied that the additional damage to the Applicants’ shed was not caused by the storm in Aug ust 2015 but by gradual deterioration and movement of the timber stumps over time. Damage caused in this manner is not covered under the policy. Accordingly, the FSP is not liable for the movement damage to the Applicants’ shed. Case No: 414812 Determination Page 4 of 5 Settlement amount is fair and reasonable The Applicants say the storm caused additional damage to the shed which has not been accepted by the FSP. In particular, the Applicants say that a number of the metal and fibreglass roof sheets were damaged during the storm, as well as a beam along the western side of the shed. During his inspection, the FSP’s engineer (CR) identified two metal roof sheets on the east and west sides of the roof, which he considered may have become loose as a result of the strong winds experienced during the s torm. The FSP has offered to cash settle the Applicants for an amount of $500 for the cost of tightening these roof sheets. In his report, CR also considered the damage to the timber framing of the western wall of the shed. However, he concluded that the damage to this area could not have been caused by the strong winds experienced during the storm, because the nail connections between the rafters and timber wall framing remained intact. The Applicants also say the FSP has refused their claim for the replacement of the shed based on CR’s comments that the shed had been constructed out of outdated and unconventional materials. However, notwithstanding his comments, I am satisfied that:  CR identified all of the damage to the shed he considered had been caused by the storm in August 2015; and  the FSP determined the cash settlement amount based on the estimated cost of repairing this damage, without any reduction to take into account the pre- existing condition of the shed. The Applicants have not provided any independent information to support their position that the additional damage claimed was caused by the storm in August 2015. Under the terms of the policy, the FSP is only liable for the cost of repairing the damage to the shed caused by the storm (or any other event insured against under the policy). The FSP is not liable for the cost of replacing any undamaged part of the shed, In these circumstances, I am satisfied that the total cash settlement of $6,090 offered by the FSP was fair and reasonable and in accordance with the terms of the policy. Case No: 414812 Determination Page 5 of 5 3 Supporting information 3.1 FOS approach to this dispute FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS Preliminary View and has proceeded directly to Determination. This case has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. There has been a full exchange of all material information relied on for the purposes of this Determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered. While the parties have raised numerous issues in their submissions, for the purposes of this Determination, commentary has been restricted to those issues which are considered directly relevant to the outcome only.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.