Determination 414812
Cash settlement amount for storm damage to farm shed
Summary
The applicants claimed about $44,000 for storm damage to a farm shed, and the FSP offered a $6,090 cash settlement for the storm damage it accepted. AFCA found the further movement damage was caused by long-term deterioration and excluded, so the settlement was fair and no increase was ordered.
The insurer is liable only for repairing damage proximately caused by the insured storm event, and the engineer's report on long-term movement of the stumps was accepted over the applicants' unsupported evidence.
Issues
- Claim amount dispute primary · not upheld
“I am satisfied that the total cash settlement of $6,090 offered by the FSP was fair and reasonable and in accordance with the terms of the policy.”
- Claim denial secondary · not upheld
“the additional damage to the Applicants' shed was not caused by the storm in August 2015 but by gradual deterioration and movement of the timber stumps over time.”
Subjects and remedies
home or building damagenatural disasterno remedy
Text of the determination
Determination
Case No: 414812 Determination Page 1 of 5
Case number: 414812 4 March 2016
1 Overview
1.1 Dispute
The Applicants lodged a claim under their farm insurance policy with the Financial
Services Provider (FSP) for storm damage to a three bay shed at their property.
The FSP accepted liability for the damage to the western bay of the shed and the
metal roof sheets on the central and eastern bays. The FSP offered to cash settle the
Applicants for a total of $6,090, based on the estimated cost of repairing this
damage.
The Applicants are dissatisfied with the cash settlement amount. They say the entire
shed has been damaged and requires rebuilding as a result of the storm, at an
estimated cost of approximately $44,000 (including the cost of upgrading the power
supply).
1.2 Issues and key findings
Is the FSP required to increase the settlement amount?
The additional damage to the shed claimed by the Applicants was not caused by the
storm but by factors such as gradual deterioration and long term earth movement,
which are excluded from cover under the policy. Accordingly, the FSP is not required
to pay for the cost of replacing the shed.
Based on the available information, the cash settlement amount offered by the FSP
reflects the reasonable costs of repairing the damage caused by the storm.
Accordingly the FSP is not required to increase the settlement amount.
1.3 Determination
This Determination is in favour of the FSP.
The FSP is not required to increase the settlement amount.
Case No: 414812 Determination Page 2 of 5
2 Reasons for Determination
2.1 Is the FSP required to increase the settlement amount ?
Policy provides cover for storm damage subject to exclusions
The Applicants are required to establish that, on the balance of probabilities, they
have suffered loss or damage which falls within the scope of cover under the policy.
This is known as a prima facie claim.
If the Applicants are able to establish a prima facie claim, the onus shifts to the FSP
to show that, on the balance of probabilities, it is entitled to rely on an exclusion
under the policy to deny the claim.
The policy provides cover for damage to t he Applicants’ property (including the three
bay shed) caused by the events listed in the policy (including the insured event of
“storm or water”), subject to the conditions and exclusions set out in the policy.
The FSP accepts that the shed was damaged by strong winds experienced during
the storm in early August 2015.
On this basis, I am satisfied the Applicants have established a prima facie claim
under the policy. Accordingly, the FSP bears the onus of establishing that, on the
balance of probabilities, it is entitled to reduce its liability for their claim.
Dispute concerns extent of damage caused by storm
The FSP has accepted liability for damage to the western bay of the shed, which
collapsed during the storm. The FSP offered to cash settle the Applicants for $5,590
in respect of this damage, based on the estimated cost of rebuilding this section of
the shed.
The FSP also offered the Applicants an additional amount of $500 for the costs of
refastening metal roof sheets on the central and eastern bays of the shed which had
come loos during the storm.
However, the Applicants say the storm has caused additional damage to the shed,
which means that it needs to be demolished and rebuilt in its entirety. The Applicants
seek a cash settlement of over $44,000 based on the quotes obtained from their
contractors.
The FSP says it is not liable for rebuilding the shed as the additional damage was not
caused by the storm in August 2015, but by factors which pre-existed the storm and
are excluded under the policy (such as wear and tear, gradual deterioration and earth
movement).
In order to determine the extent of the FSP’s liability, it is necessary to identify the
proximate cause of the dispute damage (that is, the effective, dominant or operation
cause).
Case No: 414812 Determination Page 3 of 5
Movement damage was caused by excluded factors
The Applicants say that the strong winds experienced during the storm together with
the collapse of the western bay of the shed caused the remainder of the shed to
move. They say this damage is clearly evident from:
the movement of the timber post at the northern side of the shed, which
supports the overhead power line between the shed and the main residence;
and
the misalignment of the door to the central bay, which could not be opened as it
had dropped following the storm.
The engineer (CR) appointed by the FSP confirmed that there was movement
damage to the shed. However, CR concluded that this damage had not been caused
by the storm, but by the rotation of the timber stumps supporting the shed over an
extended period of time.
I am satisfied that, as an engineer, CR is appropriately qualified to determine the
cause of the movement damage to the Applicants’ shed. Having carefully reviewed
CR’s report, I consider it provides a logical and reasonable explanation as to the
cause of the damage, which is consistent with the observed facts.
In his report, CR noted that there was no evidence of recent damage to the affected
areas of the shed, such as would be expected if the movement damage had been
caused by the storm. In particular, CR noted that:
there was no evidence of any disturbance to the ground near the affected
timber stumps;
there was no sign of any recent separation of the suspended timber floor;
there were long-term deposits of windblown debris in the gaps between the
rafters and the top plate of the eastern wall; and
the nailed connections in the roof and northern elevation were still intact and
showed no signs of recent misalignment.
CR’s report contains detailed colour photographs which clearly show the rotation of
the timber stumps supporting the floor of the central bay. CR’s report also includes
photographs confirming there was no evidence of recent damage in the areas
referred to above.
The Applicants have confirmed that the shed was over 30 years old (and possibly up
to 50 years old) at the time of the storm. The photographs provided indicate that the
shed showed signs of wear and tear and deterioration prior to the storm (as may be
expected in the circumstances).
The Applicants have not provided any independent information (including a report
from an equivalently qualified expert) which refutes the findings in CR’s report.
In the absence of any such information, I am satisfied that the additional damage to
the Applicants’ shed was not caused by the storm in Aug ust 2015 but by gradual
deterioration and movement of the timber stumps over time.
Damage caused in this manner is not covered under the policy. Accordingly, the FSP
is not liable for the movement damage to the Applicants’ shed.
Case No: 414812 Determination Page 4 of 5
Settlement amount is fair and reasonable
The Applicants say the storm caused additional damage to the shed which has not
been accepted by the FSP. In particular, the Applicants say that a number of the
metal and fibreglass roof sheets were damaged during the storm, as well as a beam
along the western side of the shed.
During his inspection, the FSP’s engineer (CR) identified two metal roof sheets on
the east and west sides of the roof, which he considered may have become loose as
a result of the strong winds experienced during the s torm. The FSP has offered to
cash settle the Applicants for an amount of $500 for the cost of tightening these roof
sheets.
In his report, CR also considered the damage to the timber framing of the western
wall of the shed. However, he concluded that the damage to this area could not have
been caused by the strong winds experienced during the storm, because the nail
connections between the rafters and timber wall framing remained intact.
The Applicants also say the FSP has refused their claim for the replacement of the
shed based on CR’s comments that the shed had been constructed out of outdated
and unconventional materials.
However, notwithstanding his comments, I am satisfied that:
CR identified all of the damage to the shed he considered had been caused by
the storm in August 2015; and
the FSP determined the cash settlement amount based on the estimated cost of
repairing this damage, without any reduction to take into account the pre-
existing condition of the shed.
The Applicants have not provided any independent information to support their
position that the additional damage claimed was caused by the storm in August
2015.
Under the terms of the policy, the FSP is only liable for the cost of repairing the
damage to the shed caused by the storm (or any other event insured against under
the policy). The FSP is not liable for the cost of replacing any undamaged part of the
shed,
In these circumstances, I am satisfied that the total cash settlement of $6,090 offered
by the FSP was fair and reasonable and in accordance with the terms of the policy.
Case No: 414812 Determination Page 5 of 5
3 Supporting information
3.1 FOS approach to this dispute
FOS has considered it appropriate to expedite this dispute in accordance with the
Operational Guidelines to the FOS Terms of Reference, due to the nature of the
dispute. Accordingly, this dispute has not been the subject of a FOS Preliminary View
and has proceeded directly to Determination.
This case has been decided on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions.
There has been a full exchange of all material information relied on for the purposes
of this Determination and each party has had the opportunity to address any issues
raised by the other. All of the material provided by the parties has been reviewed and
considered.
While the parties have raised numerous issues in their submissions, for the purposes
of this Determination, commentary has been restricted to those issues which are
considered directly relevant to the outcome only.