Landlords claimed under their building policy for storm water damage, and the insurer accepted the storm damage but cash settled at $2,344.80 net of excess instead of repairing because it would not guarantee the works. AFCA found cash settlement was permitted but increased the settlement to $3,000 net of excess, ordering a further $655.20.
The policy gives the insurer the option of paying reasonable repair cost or an equivalent cash amount, and a cash settlement should allow for contingencies where the insurer cannot guarantee repairs.
Issues
- Claim amount dispute primary · upheld
“given the FSP is not prepared to guarantee the repairs, then an allowance should be made for possible contingencies occurring.”
- Claim denial secondary · not upheld
“I am satisfied that it is fair in the circumstances that the FSP exercise its discretion to cash settle the applicants' claim.”
Subjects and remedies
home or building damagenatural disasterpay claim
Text of the determination
Determination
Case No: 414398 Determination Page 1 of 3
Case number: 414398 7 July 2016
1 Overview
1.1 Dispute
The applicants held a Landlord Building Insurance Policy with the financial service
provider (FSP). On 12 August 2014 the applicants lodged a claim for damage
sustained to the property following a storm.
Whilst accepting liability for the storm related damage, the FSP identified a number of
maintenance related issues that required rectification prior to completion of the
repairs.
After the applicants had completed the maintenance issues, the FSP authorised the
repairs. During this process the FSP identified additional damage due to unrelated
movement and defects. The FSP decided to cash settle the applicants for the cost to
repair the insured damage as it could not guarantee the quality of works due to the
unrelated damage.
The applicants dispute the FSP’s position.
1.2 Issues and key findings
Is the FSP entitled to cash settle the claim?
The FSP is entitled to cash settle the claim as the policy p rovides the FSP the option
to either pay for the reasonable cost of repair or a cash amount equivalent of what it
would reasonably cost the FSP to repair or replace the property.
Is the FSP’s offer to cash settle the claim reasonable?
The FSP has offered $2,344 to settle the claim based on an assessment provided by
its building consultant. As the consultant was not prepared to guarantee the repair
work, I believe it is fair in the circumstances that the FSP increase the settlement
offer to the sum of $3,000 net of the policy excess to allow for possible variations in
the cost of repair.
1.3 Determination
This determination is largely in favour of the FSP.
The FSP is entitled to cash settle the applicants’ claim for the sum of $3,000 net of
the policy excess of $150.
Case No: 414398 Determination Page 2 of 3
2 Reasons for determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the information obtained.
The FSP has provided detailed information including expert reports from an engineer
and building consultant in support of its position. The applicants have not provided
any information to dispute the FSP’s experts but has provided a quotation for repairs.
This determination follows consideration of all of the information exchanged and is
based on what is fair in all the circumstances, having regard to the relevant legal
principles, terms of the policy, good industry practice including codes of practice and
prior determinations where applicable.
2.1 Is the FSP entitled to cash settle the claim?
The FSP is entitled to cash settle the applicants’ claim
The FSP’s policy provides cover for a series of insured events including storm and
hail damage. There is no dispute that the applicants’ property suffered water damage
following a storm on or about 7 August 2014.
The FSP appointed PI, a building consultant to assess the damage. PI identified a
number of maintenance issues had contributed to the damage including:
gutters and valleys needed to be cleaned and maintained
ridge pointing needed to be partially re grouted over the alfresco area
gutter over bedroom 3 needed levelling or an additional overflow or downpipe
installed.
The FSP accepted liability for the water damage but denied liability with respect to
the maintenance issues as these were outside the policy coverage.
The applicants do not dispute this and agreed to complete the relevant maintenance
rectification works. There is no dispute that these works were completed by
December 2014.
Upon completion of the maintenance rectification works, the FSP appointed PI to
commence repairs. After commencing repairs, PI observed cracking to the property
that it considered were due to structural defects.
A structural engineer SE was appointed. SE considered the cracking and cornice
movement observed were due to ongoing movement of the property unrelated to the
storm event. Given the ongoing movement issues, the building consultant PI advised
they would not guarantee their workmanship if they completed the storm related
damage repairs. As a result the FSP offered to ca sh settle the applicants’ claim
based on the quote from PI.
The applicants do not dispute some cracking within the property was due to normal
household movement but maintain other cracking observed only appeared after the
storm. The applicants also believe that damage to the bulkhead was related to the
water damage caused by the storm rather than effective workmanship or shrinkage
as claimed by the FSP.
The applicants have not provided any evidence to dispute the reports provided by PI
or SE.
Case No: 414398 Determination Page 3 of 3
The available evidence supports the FSP’s finding that the cracking and damage to
the bulkheads and cornices is not storm related.
The FSP has provided evidence from its building consultant that due to the ongoing
issues with movement at the property, it could not guarantee the repair work. I accept
that the ongoing movement issues and maintenance issues need to be rectified
before this work could be guaranteed.
As there is no evidence to establish that the damage to the cornice and bulkheads
was caused by storm and as the FSP is unable to guarantee the work due to the
underlying structural issues, I am satisfied that it is fair in the circumstances that the
FSP exercise its discretion to cash settle the applicants’ claim.
2.2 Is the FSP’s offer to cash settle reasonable?
The quote provided by the FSP’s building consultant PI covers relevant plastering
and painting work to the kitchen, alfresco area and bedroom 3. The total quote is for
$2,494.80.
The FSP offered to cash settle the applicants’ claim for $2,344.80 net of the $150
policy excess.
The applicants provided a quote from M Plastering dated 30 July 2014. That quote
was for $5,185.70 but included repairing cracked and damaged roof tiles as well as
the replacement of damaged plaster ceiling sections, sanding, painting and delivery
of plaster board materials.
There is no evidence that the roof tiles were damaged or cracked during the storm
event. If this is deducted from M Plastering’s quote, the total cost of repairs would be
$3,505.70.
I have considered both quotations in forming my view in this matter.
I am concerned that the FSP offer to cash settle the claim does not take into account
possible contingencies that could arise in the repair. In my view, given the FSP is not
prepared to guarantee the repairs, then an allowance should be made for possible
contingencies occurring. When comparing the quotations in my view, it would be fair
for the FSP to cash settle this claim for the sum of $3,000 net of the policy excess.
I understand from the material exchanged that the FSP have already paid the
applicants $2,344.80. The FSP is therefore liable to pay the applicants an additional
amount of $655.20 in settlement of the claim.