Text of the determination
Determination
Case No: 414177 Determination Page 1 of 11
Case number: 414177 22 January 2016
1 Overview
1.1 Dispute
In September 2010, the Applicant lodged a claim under a residential strata title
insurance policy issued by the Financial Services Provider (FSP) after her townhouse
was damaged in a fire. During 2011, the Applicant lodged separate claims for
additional damage caused by a sewerage spill and a water leak.
The FSP accepted the Applicant’s claims and arranged to repair the property. The
initial repairs were inadequate and the FSP undertook rectification works. However,
the Applicant was dissatisfied with the quality of the building repairs and lodged a
dispute with FOS.
The Panel issued a FOS Determination (324305) in November 2014, which provided
that the FSP was to appoint a replacement builder to undertake further rectification
works, in accordance with a scope of works to be prepared by the FSP’s building
consultant (H).
The Applicant remains dissatisfied with the repairs to her townho use following this
process and says the FSP has failed to comply with the previous Determination.
1.2 Issues and key findings
Is the FSP liable for further rectification repairs?
The available information establishes that there are certain specific aspects of the
repairs carried out by the FSP’s contractors which require rectification (including the
waterproofing of the upstairs bathroom). The Applicant has also identified apparent
deficiencies in the certifications obtained by the FSP for various aspects of the works.
Given the circumstances of this dispute, it is appropriate that the FSP cash settle the
Applicant for the estimated costs of undertaking the outstanding repairs and
engaging her own contractors to inspect the works.
Is the Applicant entitled to any additional amounts?
The Applicant is entitled to reimbursement of certain costs incurred in re-letting the
property. She is also entitled to the partial reimbursement of her legal fees.
1.3 Determination
This Determination is partly in favour of the Applicant.
Case No: 414177 Determination Page 2 of 11
The FSP is to pay the Applicant the amount of $38,740 in full and final settlement of
her claim. This amount is made up of:
$5,000 for outstanding rectification repairs;
$22,640 for the repairs required as a result of the failure of the waterproofing in
the upstairs bathroom (including six weeks’ rent);
$8,000 for inspection and/or certification of the works;
$1,100 as reimbursement of re-letting fees; and
$2,000 as partial reimbursement of legal costs.
The FSP is not required to pay interest on this amount.
Case No: 414177 Determination Page 3 of 11
2 Reasons for Determination
2.1 Is the FSP liable for further rectification repairs?
Previous Determination outlined process for completing rectification repairs
As outlined above, this matter was the subject of a previous FOS Determination in
November 2014.
In that Determination, the Panel concluded that both the initial repairs and the
rectification works carried out by the FSP’s builder (B) were inadequate to r estore the
Applicant’s property to its pre -loss condition.
On this basis, the Panel determined that the FSP was required to arrange for further
rectification works to be carried out by a replacement builder, under the supervision
of the FSP’s building cons ultant (H).
The Panel considered it was appropriate for H to be appointed to manage the
finalisation of the rectification works because of his existing familiarity with the claim,
his demonstrated ability to apply an independent mind to the issues and the
Applicant’s apparent confidence in his views.
Accordingly, the Panel found that H should prepare a scope of works for the
outstanding repairs required to restore the property to its condition prior to the fire,
having regard to each of the outstanding issues raised by the Applicant in the course
of the earlier dispute. This scope of works prepared by H was to form the basis for
the rectification repairs to be carried out by the replacement builder.
The Panel noted that, as part of this process, H and/or the replacement builder
should obtain any certificates or approvals required to ensure that the completed
works complied with all applicable regulations and by-laws so that the property was
able to be reoccupied. This was a key area of concern for the Applicant during the
dispute.
Applicant remains dissatisfied with rectification works
Following the issue of the previous Determination, the FSP’s building consultant (H)
prepared a scope of works / defects list and the FSP appointed a replacement builder
(AB) to carry out the defects rectification works.
In May 2015, the FSP advised the Applicant that the rectification works had been
completed. Following a final inspection on or around 14 May 2015, H confirmed that,
in his opinion, the works had been carried out to a satisfactory standard.
However, after the Applicant inspected the property in early June 2015, she notified
the FSP that she was unhappy with several aspects of the works and considered
further rectification was required. The Applicant subsequently raised additional
concerns about the quality of the repairs.
The Applicant has also expressed concern that the certifications obtained for various
aspects of the works do not comply with the applicable statutory requirements. She is
Case No: 414177 Determination Page 4 of 11
also concerned about the manner in which the FSP and its contractors have carried
out the rectification works, which she says has caused further delays.
FSP is liable for some (but not all) additional items claimed
The Applicant has raised concerns about numerous specific aspects of the
rectification works.
The FSP has accepted that some of the additional items identified by the Applicant
may require further work, although it considers these items to be relatively minor.
For example, the FSP has accepted liability for half of the cost of the additional
electrical works identified by the Applicant’s electri cian and one third of the costs of
the additional repairs identified by the Applicant’s handyman.
The FSP has also offered the Applicant an additional amount for light fittings which
she says were damaged by the FSP’s contractors during the course of the o riginal
repairs (although the value of the light fittings is disputed).
However, the FSP says that the bulk of the additional items identified by the
Applicant have already been dealt with in the course of the rectification works and/or
were not caused by the fire in 2010 or the subsequent repairs carried out by the
FSP’s contractors.
The Panel has carefully reviewed the detailed information provided by both parties in
relation to each of the individual items claimed, for the purpose of determining
whether the FSP is liable for each disputed item.
Having done so, the Panel is satisfied that the FSP should be liable for some (but not
all) of the additional items claimed.
Given the protracted nature of this dispute, the Panel considers that it is in the
interests of both parties that the outstanding issues in relation to the rectification
works be resolved by way of a cash settlement, which will enable the Applicant to
undertake the necessary works to her satisfaction.
Based on the available information, the Panel considers that it is fair in all the
circumstances that the FSP cash settle the Applicant for the amount of $5,000 in
respect of all outstanding items.
This amount does not include the additional repairs required as a result of the failure
of the waterproofing in the upstairs bathroom, which was only identified in late 2015
and is addressed separately below.
FSP is liable for repairs required due to faulty waterproofing
In November 2015, the Applicant advised of water damage to the living room ceiling
at the property due to water leaking from the upstairs bathroom.
The FSP has acknowledged that the current water leak is a direct result of the repairs
to the bathroom carried out by its contractors following the fire.
Case No: 414177 Determination Page 5 of 11
The FSP’s builder (AB) has confi rmed that water is leaking from the shower area,
due to the failure of the waterproofing membrane and the lack of sealant between the
flanges and the tiles.
The FSP’s builder has provided a quotation for $15,945.60 (including GST and a
20% margin) for the installation of replacement waterproofing and the repair of the
damage to the lounge room ceiling.
The FSP has confirmed that it is willing to arrange for its builder (AB) to undertake
the necessary repairs. However, the Applicant has expressed concern a bout AB’s
ability to carry out the repairs to an acceptable standard, given her past experience
with the FSP’s contractors and has requested a different builder.
It is clear that the relationship between the parties has deteriorated significantly
during the course of this dispute and the Applicant has lost confidence in the ability of
the FSP and its contractors (including H).
The Applicant’s existing concerns have been understandably exacerbated by the
recent discovery that the waterproofing was not carried out to an acceptable
standard.
In these circumstances, the Panel considers that the Applicant is unlikely to be
satisfied with any further works carried out by the FSP’s contractors. Accordingly,
requiring the FSP to carry out further works is only likely to prolong what has already
been a very protracted dispute.
Accordingly, the Panel considers the FSP should be required to cash settle the
Applicant for the estimated cost of the necessary repairs.
The Panel acknowledges that the quotation provided by the FSP’s builder (AB) is
likely to reflect volume-based discounts and rebates available to the FSP.
Accordingly, AB’s quotation is likely to underestimate the cost to the Applicant of
having the repairs completed by anothe r builder. In these circumstances, the Panel
considers AB’s quotation should be increased to $20,000 (that is, by approximately
20%) to ensure the settlement amount is sufficient to enable the Applicant to carry
out the necessary repairs.
The FSP’s bu ilder (AB) has estimated that the repairs will take four weeks. The FSP
has suggested that a temporary bathroom could be installed for the use of the
Applicant’s tenants during this period, so they would not be required to vacate the
property.
However, the Applicant has expressed concern that a temporary bathroom may not
be appropriate, given the tenants have a small baby.
In the circumstances, the Panel considers it is appropriate that the FSP be required
to pay the Applicant an additional amount of $2,640, representing six weeks ’ rental
payments. This will enable the Applicant to take such measures as she considers
appropriate to minimise the disruption to her tenants.
Case No: 414177 Determination Page 6 of 11
FSP is required to cash settle Applicant for certification costs
During the course of this dispute, the Applicant has consistently expressed concerns
about the certifications provided by the FSP’s contractors in relation to various
aspects of the repairs (including electrical, engineering, fire separation and
waterproofing works).
In particular, the Applicant is concerned that the electrical certifications provided by
the FSP’s contractors do not cover all of the electrical works carried out at the
property since the fire in September 2010.
The Applicant has provided copies of correspondence with the State Department of
Fair Trading which supports her position that the electrical certifications provided by
the FSP are not necessarily complete.
The Applicant has also identified a number of specific aspects in which the
certifications provided in relation to the electrical and other works do not appear to
comply with applicable legislative requirements.
The FSP’s building consultant (H) has confirmed that the local council confirmed it
was satisfied with the works undertaken and the certifications provided, prior to
issuing the building certificate in respect of the property.
However, the FSP has not adequately addressed the specific deficiencies identified
by the Applicant in each of the relevant certifications. The fact that the local council
may have been satisfied with the works undertaken does not overcome any lack of
compliance with applicable legislation.
Further, the fact that the waterproofing undertaken by the FSP’s contractors has
since been found to be inadequate provides some j ustification for the Applicant’s
concerns.
In the circumstances, the Panel considers that the only feasible way to address this
issue is to enable the Applicant to engage her own contractors to review the works
undertaken for the purpose of certifying that they comply with all relevant
requirements. The Applicant has confirmed that her electrician is willing to undertake
this review.
There is a lack of detailed information about the likely costs of obtaining the relevant
certifications. However, having regard to the nature and extent of the relevant
repairs, the Panel considers that an award of $8,000 is appropriate.
In determining this amount, the Panel has allowed for any minor modifications
required as a result of further issues identified in the course of the certification
process.
Applicant has not suffered any loss due to home owners warranty issues
The Applicant has expressed concern that the home owners warranty (HOW)
insurance certificates issued in relation to the works carried out by the FSP’s builders
do not comply with applicable legislative requirements.
These issues were originally raised by the FSP’s building consultant (H) prior to the
issue of the original Determination. While H subsequently confirmed that he is now
Case No: 414177 Determination Page 7 of 11
comfortable with the HOW insurance arrangements, it is not clear on what basis he
reached this view.
However, the Panel is not satisfied that the Applicant has suffered a loss as a result
of any issues with the HOW insurance. The Applicant has exercised her right to seek
rectification of the building repairs from the FSP (as the insurer which authorised the
building works) and has not sought to pursue the builder directly.
On this basis, the Panel considers the FSP is not required to compensate the
Applicant in respect of any alleged deficiencies in the HOW insurance arrangements.
Cash settlement amount represents full and final settlement
As outlined above, the Panel considers it is in the interests of both parties that the
current Determination brings finality to this dispute, given it is now over five years
since the fire at the Applicant’s property which gave rise to her original claim.
The Panel is satisfied that, during the course of this dispute, the Applicant has had
sufficient time to carefully inspect the repairs to her townhouse.
Further, during the FOS process, the Applicant has been provided with several
opportunities to provide reports from her own contractors to identify any specific
concerns with the works carried out to date. However, other than in certain limited
respects, she has failed to do so.
The Panel also notes that the Applicant has had the benefit of legal representation
during the latter part of this dispute.
As noted above, in determining each of the additional amounts to which the Applicant
is entitled, the Panel has allowed a buffer, in the event that any of the amounts
estimated are insufficient and/or to cover any other minor items which have been
omitted.
In these circumstances, the Panel considers it appropriate to emphasise that the total
amount awarded under this Determination represents the full and final settlement of
the Applicant’s claims arising out of the f ire in September 2010, the sewerage spill in
July 2011, the water leak in December 2011 and the upstairs bathroom leak in
November 2015, as well as any related repairs.
2.2 Is the Applicant entitled to any additional amounts?
Applicant is not entitled to any additional payment for loss of rent
In the previous Determination, the Panel found that the FSP should pay the Applicant
benefits for loss of rent until the rectification works were completed and the property
was re-let (subject to the Applicant showing that she had taken all reasonable action
to obtain a new tenant).
The FSP has paid the Applicant loss of rent benefits for the period to 15 June 2015,
on the basis that all works necessary to enable the property to be re-let were
completed by 5 June 2015 (at the latest).
Case No: 414177 Determination Page 8 of 11
The Applicant seeks loss of rent benefits for the additional period until the property
was re-let in mid-July 2015. She also seeks compensation for losses incurred due to
delays in the payment of loss of rent benefits by the FSP since the earlier
Determination was issued.
Having carefully reviewed the claim history, the Panel is not satisfied that the FSP
should be required to pay any additional loss of rent benefits.
While some delays have been experienced in the course of carrying out the process
outlined in the earlier Determination, the Panel is satisfied that the FSP has generally
acted in good faith to implement the Panel’ s findings as set out in the Determination.
Further, the Panel is not satisfied that the FSP is responsible for all of the delays in
implementing the Determination.
The preparation of the original scope of works was to some extent delayed by the
advent of the 2014/2015 festive season, while H’s inspection of the rectification
repairs was delayed due to pre-planned annual leave.
In addition, the Panel is not satisfied that the Applicant has necessarily taken all
reasonable steps to expedite the resolution of this matter, following the issue of the
previous Determination in November 2014.
The delay in re-letting the property was partly due to the Applicant being unable to
inspect the property until early June 2015. Further, the Applicant was reluctant to
promptly undertake the repairs for which she had been cash settled despite the FSP
recommending that these repairs proceed in order to avoid any further delay.
In these circumstances, the Panel considers that the FSP should not be required to
pay the Applicant loss of rent benefits for any further period.
The loss of rent benefits paid by the FSP have been calculated based on rent of
$370 per week, in accordance with the previous Determination.
The Applicant has subsequently managed to lease the property for a higher rental .
However, the Panel does not consider this to be a sufficient basis for altering its
earlier findings about the rental to be used for the purpose of calculating loss of rent
benefits (which were made in the context of the broader issues considered as part of
the dispute).
Applicant is entitled to re-letting costs
As outlined in the earlier Determinat ion, the Applicant’s policy entitles her to
reimbursement of reasonable costs incurred in re-letting the property, up to a
maximum of $1,000.
The FSP has agreed to reimburse the Applicant for $1,100 of re-letting costs. For the
avoidance of doubt, this amount is inclusive of the $1,000 awarded in the earlier
Determination.
The Applicant has sought reimbursement of additional outgoings, including council
rates, utilities and strata fees.
Case No: 414177 Determination Page 9 of 11
As set out in the earlier Determination, the FSP has previously accepted that the
Applicant is entitled to the maximum amount of $1,000 payable under the policy
benefit for rates, strata fees and insurance incurred while a property is unfit to be
occupied.
Under the previous Determination, the Panel found the Applicant was also entitled to
an additional amount of $2,000, being the maximum amount available under the
policy benefit for additional utility charges incurred during the course of the earlier
repairs.
Having regard to the circumstances of this dispute, the Panel does not consider the
Applicant is entitled to any additional amounts (in addition to the $1,100 for re -letting
costs referred to above).
Applicant is entitled to partial reimbursement of legal fees
The Applicant seeks reimbursement of $11,825 for legal costs and $2,600 for
assistance provided by her taxation advisor during the course of this dispute.
Under paragraph 9.4 of the FOS Terms of Reference, FOS may require a financial
services provider to contribute to legal costs incurred by an applicant in the course of
their dispute.
However, the FOS process is designed to be accessible to applicants without legal
representation. Accordingly, FOS will not generally require a financial services
provider to contribute to an applicant’s legal costs, unless the dispute is particularly
complex or raises specific legal issues.
Further, a financial services provider will generally not be required to contribute more
than $3,000 to an applicant’s legal costs unless exceptional circumstances apply.
The Panel accepts that, in circumstances where the Applicant was concerned that
the FSP was failing to comply with the terms of the FOS Determination, it was not
unreasonable for her to seek legal representation. The Panel acknowledges that the
Applicant became frustrated by the FSP’s apparent failure to address issues which
she had raised repeatedly over the course of several years.
Having said that, the Panel does not consider that the outstanding issues in dispute
was so complex as to require the extensive involvement of a lawyer on an ongoing
basis.
For the reasons outlined above, the Panel considers that the FSP should be required
to pay the Applicant the amount of $2,000 as partial reimbursement of legal fees. The
Panel does not consider that the circumstances of the current dispute justify the
payment of any additional amount.
The Panel is not satisfied that it was necessary for the Applicant to engage a tax
advisor for the purposes of the current dispute. Accordi ngly, the FSP is not required
to reimburse the Applicant for fees paid to her tax advisor.
Case No: 414177 Determination Page 10 of 11
Applicant is not entitled to additional compensation
Under the previous Determination, the Panel awarded the Applicant the maximum
amounts payable under the FOS Terms of Reference for consequential financial and
non-financial losses suffered as a result of the manner in which the FSP handled her
claim.
Having carefully considered the manner in which the parties have acted to implement
the earlier Determination, the Panel does not consider an award of further
compensation is justified in the circumstances.
Case No: 414177 Determination Page 11 of 11
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS Recommendation. Due to the nature
of the dispute, it has been referred directly to a Panel for Determination, in line with
the Operational Guidelines to the FOS Terms of Reference. The Panel consists of an
Ombudsman and two representatives with consumer and insurance experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous Financial Ombudsman
Service (FOS) decisions.
There has been a full exchange of all material information relied on for the purposes
of this Determination and each party has had the opportunity to address any issues
raised by the other.
The Panel has reviewed and considered all of the material provided by the parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this Determination, the Panel has restricted its commentary to those issues that it
considers directly relevant to the outcome only.
During the course of this dispute, the Applicant has been assisted by her solicitor.
For the purposes of this Determination, submissions made by the Applicant’s solicitor
have been treated as having been made by the Applicant herself.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.