Text of the determination
Determination
Case No: 414093 Determination Page 1 of 6
Case number: 414093 12 May 2 016
1 Overview
1.1 Dispute
The Applicant claims the following losses which he says resulted from the FSP’s
delay in providing him with a US$400,000 Letter of Credit (LOC):
increased interest charges on the Applicant’s overdraft account, which the
Applicant used when the LOC was not provided
loss of potential future business income as a result of the Applicant having to
postpone a business trip to Argentina.
The Case Manager provided the parties with a Recommendation on the issues in
dispute. The Recommendation was in favour of the FSP. A copy of the
Recommendation is attached to this Determination.
The Applicant rejected the Recommendation and has sent numerous emails to both
FOS and the FSP. To the extent that the emails relate to the issues the subject of the
Recommendation, the Applicant:
reiterates, without making further submissions, concerns previously raised and
considered in the Recommendation
disputes matters recorded in the FSP’s contemporaneous file notes
disputes having been told during a meeting on 6 July 2015 that the FSP was
still awaiting information in order to approve the LOC
has provided an email from his accountant in response to the Recommendation,
to the effect that the FSP was told that information requested by the FSP for
LOC approval was not available, and the FSP had neither requested interim
information nor explained why the reports were needed
says that in an email dated 26 June 2015 the FSP misrepresented to him that
the LOC would be provided by the end of June 2015, as requested.
1.2 Issues and Key findings
Were the findings of the Recommendation correct?
The findings contained in the Recommendation were correct and are adopted in this
Determination . Further submissions provided after the Recommendation have been
considered.
Case No: 414093 Determination Page 2 of 6
Do the Applicant’s further submissions change the outcome?
The matters raised by the Applicant in rejecting the Recommendation do not provide
a basis for departing from the findings made in the Recommendation. This is
because:
the Applicant has not provided any new information that changes the view
outlined in the Recommendation or that supports his claim that the matters
recorded in the FSP’s contemporaneous file notes are incorrect
there is no contemporaneous information to support what is asserted by the
Applicant’s accountant , but even if accepted, his account does not establish that
the FSP did not require further information
in the email of 26 June 2015 the FSP did not misrepresent that the LOC would
be provided by the end of June 2015 and, in any event, even if a
misrepresentation had occurred, the Applicant did not rely on it, as he had
already committed to pay the funds
it is not necessary to consider the additional complaints and issues raised by
the Applicant as these do not relate to matters the subject of the
Recommendation.
1.3 Determination
This Determination is in favour of the FSP.
I agree with the Case M anager’s reaso ns for the Recommendation and the
recommended outcome.
Case No: 414093 Determination Page 3 of 6
2 Reasons for Determination
2.1 Were the findings in the Recommendation correct?
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and pre vious FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
Recommendation. I am satisfied that the documentation I have relied on has been
provided to both parties.
I am satisfied that the Case M anager’s Recommendation contains an accurate
summary of the dispute, the issues to be determined, any applicable paragraphs of
the Terms of Reference and any relevant law.
2.2 Do the Applicant’s further submissions change the outcome ?
The documentation supports that the Applicant was aware the FSP required
further information before the LOC could be approved
In rejecting the Recommendation, the Applicant says that the matters recorded as
facts in the FSP’s contemporaneous fi le notes are untrue, and that he was not aware
the FSP required further documentation before approving the LOC.
In regard to the meeting with the FSP on 6 July 2015, the Applicant disputes that he
was told during the meeting that any requested information was still outstanding, and
that he understood that any information requested by the FSP during the meeting
was sought in relation to a pricing review that was also being completed by the FSP,
and not in connection with approval of the LOC.
However, the information provided to FOS supports the accuracy of both the FSP’s
file note of 6 July 2015, and that the FSP informed the Applicant that it required
further documentation before it would provide the LOC.
The FSP first emailed the Applicant’s accountant on 11 June 2015 and asked it t o
provide 2014 financial statements and tax returns for five different entities which were
provided. The FSP sent a further email to the accountant on 19 June 2015
requesting a copy of management accounts and data for the current financial year.
The Recommendation found that there was nothing to support that this information
was provided to the FSP.
The Applicant has provided a copy of an email from his accountant purporting to
respond to the findings in the Recommendation. The accountant states:
Later that day of Friday 19 th June 2015, MC (Accountant) spoke with FSP and informed him that
we (Accountant) did not have the above information available at that stage. It was discussed
that the current MYOB data file was not in a suitable state to just print out as interim reports. We
(Accountant ) were not requested after this comment to go ahead and prepare interims i.e. it
wasn’t stressed to us that this would be a problem that they don’t exist. It was not discussed
why this information was required. We received no further corres pondence (written or verbal)
from FSP that I am aware of or have been able to find after this conversation took place.
Case No: 414093 Determination Page 4 of 6
Other than this email, written on 20 January 2016, the Applicant has not provided any
contemporaneous information to support a finding that the FSP was informed that
information it requested from the Applicant could not be provided. The FSP officer
has said he does not know the accountant.
In any event, however, even were the accountant’s recollection to be accepted, the
fact that he indicated that information required by the FSP in support of the LOC
application could not be provided at that time does not provide a basis for concluding
that the FSP chose to proceed with the application in the absence of such
information, or that it represented to the accountant that it would do so. In fact,
subsequent discussions between the FSP and Applicant indicated that the FSP still
required further information.
An email communication between the Applicant and the FSP took place on 26 June
2015 while the Applicant was overseas. The email trail confirms that at this time the
“details” of the LOC had not been finalised with the FSP and there were a “few
things” the FSP needed to discuss with the Applicant prior to approving the LOC.
Email from Email to Email content
FSP Applicant I will discuss pricing wit h you once we have the
details of letter of credit and valuations completed.
At this stage we need to extend the facility and will
sit down with you are your venue of choice and
work through the pricing.
Applicant FSP OK but I need to act on the l/c [LOC] to ship in July
FSP Applicant There are a few things we need to discuss. I will
touch base with you early next week.
Applicant FSP Is there a problem?
FSP Applicant No
Applicant FSP Good. Talk Monday.
At this stage, considering the Applicant and the FSP had agreed to talk “early next
week”, which could mean anytime from Monday 29 June 2015, up to Wednesday 1
July 2015, it was apparent that it was unlikely that the LOC would be provided by the
“end of June” as originally requested.
The Applicant and the FSP then met on 6 July 2015 and the FSP’s contemporaneous
file notes of the same date record that the LOC was discussed during the meeting
and the Applicant was asked to provide further financial information including:
an updated list of debtors and creditors; and
management figures for nine months, or as close to 30 June as possible.
There is nothing in the available information to indicate either that the Applicant
raised an issue with this request, or provided the information sought.
Over a week later, on 14 July 2015 the Applicant emailed the FSP stating that the
LOC should have been sorted by this date. The FSP’s response was:
Case No: 414093 Determination Page 5 of 6
As previously discussed, I am working towards Friday however with the information requested
not being to hand this is taking a little more time to have approved.
The Applicant responded stating that he had missed his deadline and he was not
happy with the FSP.
If the Applicant believed he had provided all requested information, or if he was not
aware that information remained outstanding, it would have been reasonable to have
raised this in his response to the FSP at this time, but the Applicant did not do so.
This tends to support the accuracy of the FSP’s file not e of 6 July 2015, that the
Applicant was aware that the FSP required further financial information before it was
able to approve the LOC.
The email of 26 June 2015 does not represent when the LOC will be provided
The Applicant says that in the email of 26 June 2015, the FSP misrepresented to him
that the LOC would be provided by the end of June 2015. Specifically the Applicant
says that when he asked “Is there a problem?” (in relation to the LOC) the FSP
should have advised him that it was still awaiting information. Instead, the FSP
replied “no” (a copy of the full email included above). It is the Applicant’s view that
this exchange misrepresented, and assured him, that the LOC would be approved
and provided by the end of June 2015.
I agree that the FSP should have told the Applicant at that time it was still waiting for
financial information to finalise the LOC. However, in my view the email was not
misleading in the way the Applicant says for two reasons.
First, the email exchange cannot be viewed in a vacuum and must be placed in
context. Viewed objectively, while the FSP’s response confirmed that there was “ no
problem ” , this does not negate the earlier statement, a few minutes before, that there
were a few things that needed to be discussed in relation to the LOC.
On the face of it, the FSP’s email indicated that the LOC would be approved pending
the discussion of a “few things” . The email does not provide any assurance that the
LOC would be approved in any specific time frame. Further, given that it was
expressly stated that further discussion was required, the reference to there being
“no problem” cannot be read as referring to an assurance of approval but, rather,
communicated that there were no complications at that time.
Secondly, even were it accepted that he was misled by the email to believe that the
LOC would be approved, the Applicant has not shown that his loss was caused by
relying what is said to be a misrepresentation. This is because the Applicant had
already committed to paying the funds to the third party.
Despite the FSP not receiving the requested information, it ultimately approved the
LOC and sent a letter of offer to the Applicant on 15 July 2015. The Applicant did not
accept the offer.
Case No: 414093 Determination Page 6 of 6
3 Supporting information
FOS is not considering other complaints and issues raised by the Applicant
The Applicant has provided numerous emails including conversations between him
and the FSP which refer to other complaints and issues he has with the FSP. These
issues have not been considered as part of this FOS dispute.
From the correspondence it is not clear what specific error or errors the Applicant
alleges the FSP has made.
If the Applicant would like any new issues to be considered by FOS, he will need to
lodge a new dispute clearly detailing the specific error the FSP has made, the loss he
has incurred due to the alleged error and what he is seeking to resolve the dispute.
Recommendation
Case No: 414093 Recommendation Page 1 of 6
Case number: 414093 7 January 2016
1 Overview
1.1 Dispute
The Applicant says that the FSP delayed in providing a US$400,000 Letter of Credit
(LOC) he requested in May 2015, to be provided by the end of June 2015. The
Applicant says the FSP did not provide the LOC by the requested date which
resulted in the following losses:
the Applicant had to use an overdraft account to make the payment and in
doing so has incurred increased inte rest charges on the overdraft
the Applicant had to postpone a business trip to Argentina which resulted in the
loss of potential future business income.
The Applicant accepts that it is appropriate for him to bear the costs required to
secure the LOC, but he does not consider that he should pay the higher interest
costs incurred from using the overdraft facility.
1.2 Issues and key findings
Did the FSP unreasonably delay in providing the LOC?
The FSP did not unreasonably delay in providing the LOC to the Applicant. The FSP
requested further information from the Applicant and the Applicant’s accountant in
order to process the LOC request, but this information was not provided.
Is the Applicant entitled to compensation?
As the FSP did not unreasonably delay providing the LOC, the Applicant is not
entitled to compensation.
1.3 Recommendation
This Recommendation is in favour of the FSP. No compensation is payable to the
Applicant.
Case No: 414093 Recommendation Page 2 of 6
2 Reasons for Recommendation
2.1 Did the FSP unreasonably delay in providing the LOC ?
The Applicant requested a LOC on 28 May 2015
The Applicant initially enquired about obtaining a LOC from the FSP during a
telephone call on 28 May 2015. The FSP Representative (Mr D) arranged for a
colleague at the “trade desk” to contact the Applicant about his enquiry.
Mr D received emails from both the trade desk and the Applicant on the same day,
the email from the trade desk at 5.38pm stated that the Applicant did not wish to
proceed with the LOC.
The email from the Applicant to Mr D at 5.36pm, indicated some dissatisfaction with
his dealings with the trade desk, stating “Is that guy serious from the FX
department??????? Very strange”
The Applicant made no further requests to be contacted about the LOC at this time.
The Applicant requested a LOC on 4 June 2015
The FSP’s records indicate that during the Applicant’s annual review on 4 June 2015,
the LOC was discussed again and the FSP says that it agreed to engage its credit
department to progress with the approval. The FSP told the Applicant that it would
contact him again if it required further information to support the application.
The FSP requested further information from the Applicant
On 11 June 2015 the FSP emailed the Applicant’s accountant and requested 2014
financial statements and tax returns for five different entities. The accountant
provided this information to the FSP on the same day.
The FSP sent further emails to the Applicant and the acco untant on 19 June 2015
requesting a copy of management accounts and data for the current financial year.
The FSP says this information was not received.
The LOC was discussed during a meeting at the Applicants office on 6 July
2015
Mr D attended a meeting at the Applicants property on 6 July 2015 and the FSP has
provided a copy of Mr D’s contemporaneous diary notes, summarising the meeting.
The diary note records the following was discussed:
the FSP had questions to further understand the business prior to approving the
LOC;
the Applicant provided the FSP with details of the invoice for the LOC;
FSP requested the Applicant provide an updated list of debtors and creditors
and t the Applicant said this would be provided over the next few days;
Case No: 414093 Recommendation Page 3 of 6
FSP requested management figures for nine months, or if possible as close to
30 June as he could provide, Applicant said that the accounts would need to be
tidied but agreed to provide this by the end of the week;
FSP told the Applicant that it was unlikely the LOC would be provided by Friday
10 July 2015, but should be available by 17 July 2015; discussion took place in
which the Applicant indicated that he had cash available to cover stock
purchase but that it would be good to save the interest cost and pay for the
goods once received, that there was a 170 day delivery time.
The Applicant did not provide the requested information
Email trails (refer to Section 3.2 for further details) between the Applicant and the
FSP, following the meeting of 6 July 2015, confirm that the FSP told the Applicant
that it was still awaiting the requested information and that it was taking more time to
have the LOC approved without the requested information.
The Applicant’s emailed responses to the FSP do not address the issue of the
missing information, rather they raise other concerns about delays in providing the
LOC.
The letter of offer for the LOC was provided by the FSP on 16 July 2015
Despite not having received all of the requested financial information from the
Applicant, the FSP provided a letter of offer for the LOC to the Applicant on 16 July
2015.
The Applicant did not accept the offer.
The Applicant has not established the date the LOC was due
Despite requests the Applicant has not confirmed the specific date he required the
LOC by. Copies of emails between the Applicant and the third party provide some
commentary about the requirement of the LOC, however they do not confirm when
the LOC was due, or when the LOC became overdue.
There are Offshore Telegraphic Transfer transac tions from the Applicant’s
overdraft account
The Applicant says that when the LOC was delayed, he used his overdraft to make
payment and seeks a refund of the interest differential.
Despite requests the Applicant has not confirmed details of the account the amount
was paid from, or highlighted the relevant payments leaving his overdraft account
with the FSP.
The Applicant’s overdraft account statements show a number of Offshore
Telegraphic Transfers (TT’s) leaving the Applicant’s account. These transaction s
total approximately AU$562,861 and are completed between 30 July 2015 and 30
September 2015.
Refer to 3.1 for further details of each transaction.
Case No: 414093 Recommendation Page 4 of 6
It is not clear if these transactions were used instead of the LOC, but if so the first of
these transactions did not take place until 30 July 2015, 14 days after the letter of
offer for the LOC was given to the Applicant by the FSP.
The Applicant has not established that the FSP made an error
The Applicant has not established that the FSP has made an error. The information
provided supports that the FSP requested further information from the Applicant and
there is no evidence to support that this information was ever provided to the FSP.
The FSP did not unreasonably delay in providing the LOC to the Applicant . The FSP
sought further information from both the Applicant and the Applicant’s accountant
however this information was not provided.
In addition, despite requests, the Applicant has not shown where he sourced the
funds from, that were used in replacement of the LOC, or the applicable interest rate
for these funds and therefore the Applicant has not established loss.
2.2 Is the Applicant entitled to compensation?
The Applicant is not entitled to compensation
As the Applicant has not established that the FSP made an error and did not
unreasonably delay in providing the Applicant with the requested LOC, the Applicant
is not entitled to be compensated.
Case No: 414093 Recommendation Page 5 of 6
3 Supporting information
3.1 Telegraphic Transfers on the Applicant’s overdraft account
The following are TT’s made from the Applicant’s overdraft account from 30 July
2015 to 30 September 2015:
Date Reference AUD Amount
31 July 2015 D805170RCV $ 63,147.48
4 August 2015 D013300RCV $ 27,551.63
17 August 2015 D976080RCV $ 91,266.49
18 August 2015 D079250RCV $ 22,635.27
25 August 2015 D666230RCV $ 27,859.24
8 September 2015 D578150RCV $ 41,388.32
21 September 2015 D578650RCV $ 94,421.29
22 September 2015 D699730RCV $ 18,311.45
30 September 2015 D287560RCV $176,280.30
Total: $562,861.47
3.2 Email trail between the Applicant and the FSP
Date Email from Email to Key note s/ Relevant comments
14 July 2015
5.50pm
FSP Applicant Refers to previous discussions, confirms FSP
working towards providing the LOC by Friday (17
July 2015) but it is taking more time to approve
without the information requested not being
provided.
16 July 2015
8.24am
Applicant FSP Applicant states he understood LOC was to be
provided by previous Friday (10 July 2015) and the
LOC was not in place and “bags were leaving first
thing tomorr ow” the bags would be removed from
the ship if he did not have the LOC or cash against
documents.
16 July 2015
9.49am
FSP Applicant FSP says they’d achieved an outcome without the
Applicant providing the requested information and
requested the Applicant t o complete the required
documents prior to issuing the LOC:
- Attached application form
- Letter of offer and guarantee to be signed – to be
Case No: 414093 Recommendation Page 6 of 6
delivered to S Branc h of FSP
- Updated copy of Applicant’s tax portal
16 July 2015
9.50am
Applicant FSP The Applicant states he has supplied the requested
information and questions whether he is a bad risk
16 July 2015 FSP Applicant FSP clarifies that it requires the appropriat e
documentation to be completed, being the letter of
offer and the guarantee and working towar ds LOC
being issued tomorrow. To have the LOC issued it
needed the application form attached to the
previous email completed and returned.