Home / Financial Firm (Unknown - Insurer) / Determination 412814

Determination 412814

Flood exclusion relied on to deny bulk of farm storm and rain claim

FirmFinancial Firm (Unknown - Insurer)
Decided2016-07-26
ProductGeneral Insurance · Business / commercial
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The FSP denied most of the applicant's farm storm claim as flood damage, which is excluded. AFCA found the damage to the water pump and machinery shed to 100mm was covered and ordered the claim reassessed, with interest if cash settled.

Flood is excluded under the policy, but stormwater runoff up to 100mm is a covered defined event, so the insurer must cover damage within that depth.

Issues

Subjects and remedies

pay interestreassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 412814 Determination Page 1 of 5 Case number: 412814 19 July 2016 1 Overview 1.1 Dispute This matter involves a claim by the applicant under his Farm Insurance policy, held with the financial service provider (FSP), following loss and damage at the farm as a result of a significant weather event. The FSP has accepted part of the applicant‟s c laim but has denied the bulk of the claim on the basis that the cause of the loss and damage to the bulk of the property was a flood which is specifically excluded from coverage under the terms and conditions of the policy. 1.2 Issues and key findings Has the FSP correctly denied the bulk of the applicant’s claim under the terms and conditions of the policy? The FSP has not correctly denied aspects of the applicant‟s claim and is required to reassess the loss and damage arising from the defined events of storm and/or rainwater. 1.3 Determination This determination is partially in favour of the applicant. The FSP is required to meet the applicant‟s claim under the terms and conditions of the policy and in accordance with the findings of this determination insofar as it relates to damage to the water pump and items within the machinery shed to a height of 100mm. The applicant is required to provide evidence of the location of items in the machinery shed to assist the FSP in its assessment. Should the FSP cash settle a ny aspect of the applicant‟s claim, the FSP is required to pay interest, in accordance with the Insurance Contacts Act 1984 (the Act) from the date of denial of the claim to the date of the cash settlement. Case No: 412814 Determination Page 2 of 5 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the material exchanged. This determination follows consideration of all of the information exchanged and is based on what is fair in the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice and where applicable, prior determinations. On 1 July 2016 the Ombudsman attended onsite where he met with the applicant and representatives of the FSP. The information obtained from the onsite attendance has been used together with all the information exchanged, in the preparation of this determination. The determination is made by a Panel consisting of the Ombudsman together with an industry representative who has had extensive experience in consumer claims and a representative who has had extensive experience with the insurance industry. 2.1 Has the FSP correctly denied the bulk of the applicant’s claim on the basis of the terms and conditions of the policy? Coverage of the policy The applicant‟s Farm Insurance Policy provides defined events coverage. This means that not all loss and damage is automatically covered but rather only loss and damage caused by the defined events which are detailed within the policy. The details of the coverage provided by the policy are contained within the Product Disclosure Statement (PDS). The PDS lists the defined events which include Storm or Rain. The PDS also contains specific exclusions which include: „ We will not pay for loss, destruction, or damage caused directly or indirectly by Flood, unless you have Optional Cover for Flood under Section 1.6 (1).‟ There is no evidence that the applicant‟s policy included the optional cover for Flood. The PDS also includes a general definition for Flood which the Panel notes has been amended. The PDS details: Word Meaning “Flood” (a) A general, temporary condition of partial or complete inundation of normally dry land areas by the overflow of water from the normal confines of any natural water course or lake (whether or not altered or modified), or of any reservoir, canal, or dam; or (b) A mud slide or mud flow which is caused or precipitated by an accumulation of water on, or under, the ground. Case No: 412814 Determination Page 3 of 5 “Rainwater” Water falling from the atmosphere in the form of rain including rainwater run off over the surface of the land or which has escaped from public roadside gutters, but not inundation of normally dry land areas by the overflow of water from - (a) the normal conf ines of any natural water course or lake whether or not altered or modified; or (b) any reservoir, canal, dam, water tank, apparatus, or pipe. The circumstances of the applicant’s loss and claim The evidence confirms that in April 2015 there was a significant weather event which caused loss and damage at the applicant‟s property. The FSP has accepted the applicant‟s claim for the costs associated with the repairing or replacing of the storm damag ed gutter of the applicant‟s domestic building. The FSP awaits the applicant‟s further instructions for this aspect of the claim to be finalised. The remainder of the applicant‟s claim relates to a bore pump, and a water pump together with damage to the machinery shed and a container and the contents therein. Within his correspondence of 8 October 2015 the applicant detailed the extent of his claim which he included as part of appendix 1. The FSP has denied the bulk of the applicant‟s claim on the basis t hat the loss and damage was caused by the excluded event of flood. The FSP has provided a report from a hydrologist to support its position. The evidence and site visit confirm that the applicant‟s property is in two halves, separated by W road. On one side of the road is the residence together with the bore pump and water pump which the applicant says were damaged in the weather event. The Panel notes the information provided by the FSP‟s hydrologist , emanating from Midland Property Management Authority, to the effect that there is an unnamed watercourse which proceeds through this area. On the other side of the road is the machinery shed, container and W Brook. Behind the home is a significant rise of some 1 kilometre from which the Panel is satisfied that a great deal of rainwater runoff would flow. The FSP says that there was a substantial volume of runoff directed to the unnamed water course which flows through the property. Whilst the FSP agrees that there was an immense amount of rainfall at or about the location of the property which would have led to stormwater runoff, it is unlikely that this stormwater runoff would have exceeded 100mm in depth and the applicant advised that the water pump is lifted above the ground o n bricks and therefore the stormwater would not have inundated the pump. However, when attending on site Case No: 412814 Determination Page 4 of 5 the Ombudsman noted that the positioning of the water pump would likely have been affected by stormwater runoff to 100mm as the pump itself was at or slightly below the level of the ground. Protection afforded by a metal cover would not have saved the pump from damage in these circumstances. On the other hand, the bore pump and the metal container which protects the electrics associated with that pump are in fact raised above ground to a level of between 600mm and 800mm. The Panel is satisfied that stormwater runoff to an extent of approximately 100mm would not have impacted the bore pump. However, the substance of the dispute between the parties is whether the water that flowed through the property causing damage could be properly categorised as stormwater runoff or whether it was water flowing through what the FSP called an unnamed watercourse. The applicant challenges this categorisation and says the a llegedly unnamed water course is really just a series of mountain gullies flowing down to flat paddocks with no confines. In this regard the Panel is satisfied that for an area to be categorised as a water course it is not necessary for water to be constantly flowing through that area. Rather the question is whether the area has defined banks or base to allow water to flow at times. At the on-site attendance, the Ombudsman noted that the area referred to by the FSP as the unnamed watercourse does have the general appearance of a gully but it is clear from the vegetation in the gully that it is an area that water would and does flow through after rainfall. Further, in the area specifically adjacent to the three dams at the property, there was at least a small line of some several metres whereby the passage of water had cut through the soil to create a wedge which would act as a stream when water was flowing. Arguably, this area had sufficiently defined base and sides that it could be considered a watercourse. However, because of what follows it is unnecessary to reach a final conclusion regarding whether the water which flowed through this area is either properly categorised as a gully or an unnamed water course. The substance of the applicant‟s claim relate s to the damage to the contents of the machinery shed and container. Having considered the exchanged evidence, the Panel is not satisfied that the flow of water, be it from stormwater runoff or via the allegedly unnamed watercourse would be sufficient to cause the extent of the damage claimed by the applicant in relation to the machinery shed and the container and the contents thereof. The evidence confirms that the container itself had shifted from its concrete base. Case No: 412814 Determination Page 5 of 5 Having considered all of the evidence, the Panel is satisfied that it is more likely than not the substance of the damage to the machinery shed and container and their contents was caused when the W Brook rose up as a result of general rainfall in the area, broke its banks and forced the water onto the applicant‟s land. The pressure of this movement of the water would have shifted the container and caused the extent of the damage to the machinery shed and its contents. Noting that the applicant‟s container was a refrigeration container, the Pa nel is not satisfied that any stormwater runoff would have been able to enter the container and it was more likely that the damage was caused when the container was shifted by the movement of W Brook. On the other hand, noting that the FSP accepts stormwater runoff to the extent of 100mm, the applicant is entitled to be covered for damage to the water pump and within the machinery shed to the level of 100mm. However, the applicant will need to provide evidence of the location of the items he says were damaged within the machinery shed. The parties are asked to work together cooperatively in this regard and should they not be able to resolve that aspect of the applicant‟s dispute then they can seek a further determination from FOS.