Determination 412747

Denial of home claim for water-leak stump damage

FirmFinancial Firm (Unknown - Insurer)
Decided2016-07-19
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$10,469
Non-financial loss—
Amount claimed$12,409
SourceAFCA PDF

Summary

An applicant claimed under home insurance for timber stump damage linked to a mains water leak. AFCA found the leak damage covered for the western stumps only, ordered an $8,500 cash settlement plus $1,969 engineer fees, and rejected non-financial loss.

Accidental water-leak damage occurring during cover is payable, but gradual deterioration is excluded and the Wayne Tank principle did not defeat the claim for the western stumps.

Issues

Subjects and remedies

home or building damagepay claimpay compensation

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 412747 Determination Page 1 of 11 Case number: 412747 14 July 2016 1 Overview 1.1 Dispute In March 2015, the applicant lodged a claim under his home insurance policy with the financial services provider (FSP) for damage to the timber stumps at his property (and resulting movement damage). The applicant believes the damage was caused by a leaking pipe at the property which was discovered and repaired in August 2014. The FSP denied the applicant’s claim on the basis that the damage to his property was not caused by the leaking pipe and pre-existed the commencement of cover in May 2010. 1.2 Issues and key findings Is the FSP liable for the damage to the applicant’s property ? The available information establishes that the water mains leak discovered in August 2014 caused significant damage to the stumps on the western side of the applicant’s property. Accordingly, the FSP is liable for the costs of repairing that damage (and any resulting movement damage to the property). However, the FSP is not liable for the costs of restumping and relevelling the entire property, as the damage to remaining stumps was caused by gradual deterioration over time. Is the applicant entitled to any other amounts? The applicant is entitled to reimbursement of fees incurred in obtaining reports from his own engineer, as these reports have assisted in determining the FSP’s liab ility for the claim. The applicant is not entitled to compensation for non-financial loss. 1.3 Determination This determination is partly in favour of the applicant. The FSP is to pay the applicant the amount of $8,500 (in addition to the amount of $639 previously paid) in full and final settlement of his claim. The FSP is not required to pay interest on this amount. In addition, the FSP is required to reimburse the applicant for fees of $1,969 incurred in obtaining his engineer’s reports. Case No: 412747 Determination Page 2 of 11 2 Reasons for determination 2.1 Is the FSP liable for the damage to the property? Policy provides cover for accidental damage subject to exclusions The applicant is required to show that, on the balance of probabilities, he has suffered a loss caused by a risk insured against under the policy. This is known as a prima facie claim. If the applicant is able to establish a prima facie claim, then the onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to deny the claim. The applicant ’ s policy provides cover for accidental loss or damage to the property (including damage caused by liquid leaking from pipes), subject to the conditions and exclusions set out in the policy. The applicant says the damage to his property was caused by the effects of water leaking from a broken mains water pipe at the north-west corner of the property. The FSP does not dispute that a leak in the mains water pipe was identified in August 2014 (although it disputes the nature and extent of the leak). The reports prepared by the various consultants who have inspected the property confirm that a number of the timber stumps have rotted away below ground level, consistent with the effects of moisture in the surrounding soils. Level surveys carried out by the applicant’s engineer (PJ) and the FSP’s building consultant (AA) establish that the floors on the western side of the property have “dropped” significantly relative to the eastern side. The affected area (as well as at least some of the rotten stumps) is located in the general vicinity of the leaking mains water pipe. The damage to the stumps in this area was first identified in December 2013. On this basis, I am satisfied that the applica nts have established a prima facie claim for accidental damage under the policy. In these circumstances, the FSP bears the onus of establishing that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise e ntitled to deny the applicants’ claim. The FSP says it is not liable for the claimed damage because the damage was not caused by the leaking pipe discovered in August 2014, or by any other event which occurred during the period of insurance. The FSP says the damage occurred before the applicant incepted cover on 18 May 2010. Mains leak has been identified on two separate occasions A chronology of the key events which occurred prior to lodgement of the applicant’s claim is set out in section 3.2 below. Case No: 412747 Determination Page 3 of 11 As set out in the chronology, a leak in the mains water pipe at the north-west corner of the property was identified on two separate occasions – firstly, in November 2005 and then again in August 2014 (almost nine years later). The parties dispute the nature and extent of the initial leak which was identified in November 2005. The applicant says the leak occurred when he damaged the pipe while clearing tree roots prior to constructing a new front fence. He says the leak was identified immediately and repaired by the local water authority later the same day. The FSP disputes the applicant’s account of how the leak occurred and suggests that water may have been escaping from the broken pipe for an extended period of time before the leak was discovered. The FSP’s building consultant (AA) sought further information from the local water authority about the nature of the leak identified in November 2005. However, it appears that the water authority was unable to provide any useful information. The FSP says that the applicant has provided differing versions of events to its building consultant (AA) in relation to the initial leak. However, having carefully reviewed the information provided by the applicant at various stages of the claim process, I am not satisfied that there are any material inconsistencies in his account. Accordingly, in the absence of any information contradicting the a pplicant’s account, I accept that the damage to the mains water pipe in November 2005 occurred in the manner he has described. The FSP has also suggested that the leak may have been ongoing (or have recurred in the intervening period) as a result of inadequate repairs carried out by the local water authority in 2005. However, I am not satisfied that there is sufficient information to support this. As noted above, a number of years passed following the initial repairs before the applicant again observed evidence of excessive water at the property. While it appears that the damage to the pipe identified in August 2014 was in the same part of the pipe as that repaired in November 2005, this does not of itself establish that the second leak occurred as a result of inadequate repairs to the first. In his claim form, the applicant stated that water from the broken mains pipe had been affecting the house “for what could have been over 7 years” and indicated that the current leak may have been related to the earlier repairs. However, I am not satisfi ed that the applicant’s statement was anything more than speculation based on the fact that the two leaks occurred in the same general area (which I do not consider to be at all conclusive). The applicant does not have any specific qualifications or experience which lend weight to the supposition expressed by him in his claim form (regarding both the cause of the leak and when it first occurred). Case No: 412747 Determination Page 4 of 11 For the reasons outlined above, I am satisfied that the second leak in the mains water pipe was unrelated to the earlier leak in 2005. Second leak occurred during period of cover The applicant’s policy excludes cover for loss or damage caused by any event that does not occur within the period of insurance. The FSP says it is not liable for the applicant’s claim b ecause the claimed damage was caused by an event which occurred before the commencement of cover on 18 May 2015. Accordingly, it is necessary to determine when the second mains leak (which was discovered in August 2014) actually occurred. The applicant says the presence of excessive water on the western side of the property became apparent in December 2013, when his builder (SC) attended to replace damaged weatherboard cladding to the side of the house. SC has provided a report confirming that, during the course of the repairs, the ground was noted to be wet and sodden and the perimeter stumps on the western wall were found to have rotted. At the time, SC advised that the excess water may have been caused by a high water table. Accordingly, the applicant did not take any further steps to investigate the issue. In August 2014, fencing contractors engaged to replace a storm-damaged boundary fence to the western side of the property observed excess water in holes excavated for the new fence posts. The applicant says that several weeks later he noticed a wet patch forming on the concrete path at the north-west corner of the property and undertook further investigations, leading to the discovery (and subsequent repair) of the leaking mains pipe. The applicant says he observed significant volumes of water escaping from the leaking pipe at the time of the repair. This is consistent with the observations of the FSP’s building consultant (AA), who reported that the sub -floor soils were very damp when he attended the property in March 2015. It is difficult to determine exactly when the second leak from the mains pipe commenced, given the effects of the leak were not immediately apparent as the pipe was located underground. However, I am satisfied that, on the balance of probabilities, the leak commenced after the inception of cover on 18 May 2010. As outlined above, there was no evidence of the leak until August 2013 (more than three years after the policy was incepted). Further, there is no suggestion that any excess water was observed in the western area of the property, when the applicant undertook renovations in or around 2006. Case No: 412747 Determination Page 5 of 11 While the perimeter stumps on the northern wall were replaced as part of the renovations, the remaining stumps were retained (a nd therefore can reasonably be assumed to have been in a satisfactory condition). In these circumstances, and given the absence of any evidence of leaking prior to August 2013, I satisfied that, on the balance of probabilities, the second leak in the mains pipe occurred in the period since the inception of cover on 18 May 2010. Leaking water damaged stumps on western side The FSP says it is not liable for the claimed damage to the property because the damage to the stumps (and the resulting movement in the western part of the house) occurred as a result of the gradual deterioration of the stumps over an extended period of time. As outlined above, the various consultants appointed by the parties have confirmed that there is rotting damage and deterioration of the timber stumps at the property. To some extent, deterioration of the stumps is to be expected, given the age of the property (over 90 years old). It is usual for such properties to require restumping during their lifetime. The applicant has confirmed that the stumps in various parts of the property have been replaced at various stage, both by the previous owner of the property before the applicant purchased and as part of the renovations carried out by the applicant in 2006. However, while the consultants’ reports indicate that deterioration of the stumps was observed in various parts of the property, the perimeter stumps along the western wall of the property were noted to be in an advanced state of decay. The western side of the property was also the area where pronounced downward movement of the floors was observed, due to the timber stumps having rotted away below ground level. The applicant has provided a report from his engineer (PJ) which confirms that the advanced state of decay of the stumps on the western side corresponds to the area which would have been most affected by the water leak identified in August 2014 (given the location of the leak and the topography of the site). PJ noted that the natural slope of the site and the composition of the soil would have resulted in water from the north-west corner of the property migrating along the western side, affecting the stumps in this area. Accordingly, PJ concluded that the severe damage to the western stumps had been caused by the effects of water from the leaking pipe, given the remainder of the site conditions were relatively constant. As a civil engineer, I consider that PJ is appropriately qualified to determine the cause of the advance decay of the timber stumps. H aving carefully reviewed PJ’s report (and the various photographs provided by the parties), I consider it provides a logical and rational explanation as to how the damage occurred. Case No: 412747 Determination Page 6 of 11 While the FSP disputes PJ’s conclusions, it has not provided a report from an equivalently qualified engineer which refutes his findings. Instead, the FSP relies on a report from its building consultant (AA), who concluded that the leaking mains pipe would have had (at most) a very limited effect on the timber stumps in the vicinity of the leak. AA’s conclusion is based largely on the absence of material cracking and movement damage to the interior of the property, which he says establishes that the downwards movement of the floors in the western part of the property must have occurred before the renovations in 2006. However, the applicant’s engineer (PJ) has advised that, given the manner of construction , buildings such as the applicant’s property are able to withstand a reasonable amount of differential movement before exhibiting internal damage. PJ has also noted that internal damage may be less where differential movement has occurred gradually (for example, due to a continuing water leak), rather than suddenly (for example, when the property is restumped and/or relevelled). In these circumstances, I am not satisfied that the absence of material internal damage to the property establishes that the leaking water did not have a significant effect on the stumps at the western side of the property. Nor am I satisfied that the more extensive damage to the stumps on the western side of the property (as compared to the eastern side) can be satisfactorily explained by the differences between the site conditions on both sides, as suggested by the FSP’s building consultant (AA). For the reasons outlined above, I consider that a significant part of the damage to the stumps on the western side of the property was caused by the water mains leak discovered in August 2014. FSP is unable to rely on Wayne Tank principle The FSP says that it is entitled to rely on an established principle of insurance law known as the Wayne Tank principle, in order to deny the applicant’s claim. The effect of the Wayne Tank principle is that, where a loss is caused by two proximate causes operating in tandem and one cause is excluded while the other is not, the exclusion clause operates to allow the insurer to deny the claim in its entirety. In the present case, the FSP says the Wayne Tank principle applies because at least part of the damage to the timber stumps was caused by gradual deterioration over time (which is excluded under the policy) and not by the effects of water leaking from the mains pipe. I accept that some of the damage to the timber stumps at the property occurred as a result of gradual deterioration over time. This is apparent from the deterioration noted to timber stumps which are beyond the area affected by the water leak. However, I do not consider that the Wayne Tank principle operates in relation to the damage to the timber stumps at the western side of the property. Case No: 412747 Determination Page 7 of 11 The Wayne Tank principle only applies where two or more concurrent and interdependent proximate causes (that is, dominant or effective causes) operate to cause the claimed loss. In the present case, I am satisfied that the dominant or effective cause of the advanced decay to the timber stumps on the western side of the property was the effects of the water leaking from the mains pipe. Accordingly, the FSP may not rely on the Wayne Tank principle to deny the applicant’s claim . FSP is liable for part of claimed damage For the reasons outlined above, I am satisfied that the second leak in the mains water pipe occurred after the commencement of cover and caused significant damage to the timber stumps on the western side of the property. However, I consider that the less severe damage to the remainder of the stumps has occurred as a result of gradual deterioration over time. Damage caused in this manner is excluded from cover under the policy. Further, I consider it is appropriate to take into account the extent of any pre-existing damage to the stumps on the western side of the property, when considering the basis on which the applicant’s claim should be settled. The available information establishes that the rotting of the stumps below ground level caused the downwards movement of the floors in the western part of the building. Accordingly, the FSP is also liable for repairing this aspect of the damage. In its submissions, the FSP has referred to the policy exclusions for landslide, subsidence, settlement and any other form of earth movement. However, in the present case, the downward movement of the floors was due to the rotting of the timber stumps, rather than any movement of the earth itself. Accordingly, the exclusions referred to by the FSP do not apply. 2.2 How should the claim be settled? FSP is required to cash settle claim for $8,500 When the damage to the stumps on the western side of the property was first identified in December 2013, the applicant replaced some of the stumps at a cost of $1,278. The FSP has previously cash settled him for 50% of this amount on an ex gratia basis. The applicant seeks cover for the remainder of the costs incurred for the restumping carried out in December 2013, together with the estimated cost of restumping the remainder of the property, which his repairer (AR) has estimated at $11,770. The applicant also seeks cover for the cost of repairing the relatively minor internal cracking damage caused by the restumping in December 2013, together with any additional damage caused by the proposed restumping a nd relevelling of the property to address the downwards movement of the floors. Case No: 412747 Determination Page 8 of 11 For the reasons outlined above, the FSP is not liable for the cost of restumping the entire property. Accordingly, the quotation provided by AR significantly overestimates the FSP’s liability for the applicant’s claim . Given the applicant will be responsible for some of the restumping costs, the only feasible manner in which the claim can be resolved is by way of a cash settlement. Having carefully reviewed the available information, I consider the FSP should be required to cash settle the applicant for a total of $8,500 (in addition to the amount of $639 already paid) in respect of the damage to the stumps caused by the second water leak and the resulting movement damage to the property. The FSP is not liable for the costs of replacing the weatherboard cladding in November 2013, as there is insufficient information to establish that this damage was caused by the leaking mains water pipe. The report provided by the builder (SC) who carried out these repairs does not identify how the damage was caused. Nor is the FSP responsible for rectifying any issues with the ongoing ventilation of the sub-floor, which are unrelated to the damage caused by the leaking pipe. In determining the cash settlement amount, I have taken into account the passage of time. Accordingly, the FSP is not required to pay interest on this amount. Applicant is entitled to reimbursement for professional costs The applicant seeks reimbursement for fees of $1,969 incurred in obtaining initial and supplementary reports from his engineer (PJ). Under paragraph 9.4 of the FOS Terms of Reference, FOS may require a financial services provider to contribute to legal costs incurred by an applicant in the course of their dispute. It was reasonable for the applicant to engage his own engineer to dispute the findings of the FSP’s building consultant (AA) regarding the cause of damage to the timber stumps at the property. The reports prepared by PJ have been helpful in determining the extent of the FSP’s liability for the applicant’s claim . In these circumstances, the FSP is required to pay the applicant the amount of $1,969 as partial reimbursement for professional costs incurred during the course of this dispute. FOS may award compensation for non-financial loss Under the Terms of Reference, FOS may award compensation (capped at $3,000) for non-financial loss where an applicant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. However, FOS adopts a conservative approach to the award of compensation for non-financial loss and expect applicants to be moderately robust and bear the usual stress and inconvenience associated with an insurance claim. The applicant has raised a number of concerns about the manner in which the FSP handled his claim. Among other things, the applicant says the FSP: Case No: 412747 Determination Page 9 of 11  unreasonably delayed the resolution of his claim;  refused to meet with him during the internal dispute resolution process (IDR);  provided conflicting reasons for denying his claim; and  accused him of providing misleading information about the initial water leak. The applicant says the FSP’s actions inconvenienced himself and his family, and contributed to him developing a stress-related illness. Circumstances do not justify award of compensation for non-financial loss Having carefully reviewed the claim history, I am satisfied that the FSP acted reasonably promptly to determine its liability for the damage to the applicant’s property. After the applicant lodged his claim in March 2015, the FSP arranged for its loss adjuster (CL) to inspect the property. After obtaining a report from its building consultant (AA) and completing its investigations , the FSP denied the applicant’s claim in April 2015. The IDR process was completed in August 2015, after the applicant requested a review of the FSP’s decision in July 2015. For the reasons outlined above, I have determined that the FSP should be liable for some (but not all) of the damage claimed by the applicant. However, this does not of itself establish poor claim handling on the part of the FSP, such as would be sufficient to justify the award of compensation. The multiple incidents of water leaks and partial restumping at the applicant’s property made it challenging to determine the cause of the claimed damage. In these circumstances, it was not unreasonable for the FSP to rely on the advice provided by its building consultant (AA) about the cause of the damage (particularly given the applicant did not provide his own expert report until January 2016, well after the IDR process had been completed). I accept that the applicant has found the claim process stressful and consider that the FSP could have communicated with him more effectively. However, I also acknowledge that the volume of disputes managed by the FSP’s IDR departmen t makes face to face meetings with each customer impractical. As outlined above, I have taken into account the passage of time in determining the amount of the cash settlement to be paid to the applicant. In these circumstances, I do not consider the award of additional compensation is justified. Case No: 412747 Determination Page 10 of 11 3 Supporting information 3.1 FOS approach to this dispute FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS recommendation and has proceeded directly to determination. There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered for the purposes of this determination. This dispute has been decided on its merits, having regard to the rele vant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only. 3.2 Chronology of key events Date Event Approx. 1995  Applicant purchased property November 2005  Applicant identified damage to tap joint of mains water pipe during construction of new front fence. Pipe was repaired by local water authority. During 2006  Applicant had timber perimeter stumps along front (north) wall of property replaced in the course of carrying out internal renovations. 18 May 2010  Applican t incept ed home insurance policy with FSP. December 2013  During replacement of weat herboard cladding to west side of house, Applicant’s builder (SC) identified that the timber stumps along the western wall were rotten and replaced them with concrete stump s.  SC advised applicant that the water observed in the area may be due to a high water table. August 2014  During repairs to the western boundary fence, the applicant’s fencing contractors noted that the soil in the surrounding area was saturated and water was filling the excavat ed holes.  Applicant says that several weeks later, he noticed a wet patch on the concrete path at the north - west corner of the property.  A leak in the mains wat er pipe at the north - west corner of the property was subsequently identi fied and repaired by the loc al water aut hority. Feb 2015  Applicant’s builder advis ed that the west side of the house had “dropped” and suggested this may have been caused by the leaking pipe. Case No: 412747 Determination Page 11 of 11 Date Event March 2015  Applicant lodged claim with FSP for damage caused b y water leak. 3.3 Terms of policy Subject Terms Accidental damage cover What is covered Your buildings … are covered if they are destroyed, lost or damaged. We will cover your buildings … for accidental loss or accidental damage. There is some loss or damage we will only cover under specific conditions. This is accidental loss or accidental damage caused by:  Landslide or subsidence. Cover only applies where the landslide or subsidence occurs within 72 hours of , and as a direct result of, one of the following: … - Liquid that escapes from a fixed pipe or something attached to a pipe, fixed gutter, fixed tank apparatus or a drain. … What we will not pay for We will not cover your buildings and your contents for any accidental loss or accidental damage caused by:  Landslide or subsidence except as described [above];  Settling, shrinkage or any movement of earth … We will not pay for claims for loss, damage or liability arising from: …  Any event that does not occur within the period of insurance.