Home / Financial Firm (Unknown - Insurer) / Determination 412715

Determination 412715

Settlement offer and quality of storm repairs

FirmFinancial Firm (Unknown - Insurer)
Decided2016-08-23
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$97,745
Non-financial loss$3,000
Amount claimed$126,166
SourceAFCA PDF

Summary

The Applicants disputed the quality of storm repairs and the FSP's cash settlement offer for further rectification. AFCA ordered a cash settlement of $97,745.01 plus $3,000 non-financial loss compensation, with further items to be included and the settlement option reversed to the Applicants.

Because this was a second rectification under the FSP's repair guarantee, a cash settlement must be fair enough to let the Applicants complete the works, so the quotes were adjusted.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay non financial lossrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 412715 Determination Page 1 of 13 Case number: 412715 6 July 2016 1 Overview 1.1 Dispute The Applicants lodged a claim on their home building insurance policy in May 2014 after a storm caused water ingress into their home. The Financial Services Provider (FSP) accepted the claim and carried out repairs. The Applicants disputed the quality of r epairs and the FSP‟s subsequent rectification works. The FSP accepts further rectification works are required. The FSP has offered a cash settlement of $87,245.01 for the Applicants to conduct further rectification repairs and relocate to temporary accomm odation. The FSP‟s offer includes $2,000 non -financial loss compensation for stress and inconvenience. The Applicants contends the amounts offered is insufficient for the Applicants to complete the rectification works themselves with proper supervision. They were prepared to settle with the FSP for $110,000 but seek a Determination in the amount of $126,166.01 which includes $3,000 compensation. 1.2 Issues and key findings Is the FSP’s settlement offer fair in all the circumstances?  As the Applicants are now faced with another rectification by the FSP‟s contractors, it is fair in all the circumstances the choice of a settlement option in the policy is reversed.  It is for the Applicants to choose whether the FSP‟s contractors undertak e the repairs and rectification on the scopes and quotes provided (which include the lifetime guarantee on building repairs) or decide to accept a cash settlement of $97,745.01 (for the reasons detailed in this Determination).  As set out in this Determination, whichever settlement option the Applicants choose, further items, in addition to the $9 7 ,745.01, are to be included in the FSP‟s s ettlement with the Applicants.  As the scope of works by builder JL is for a complete strip out and rebuild of the affected areas of the home, and, on the material provided, addresses all the Applicants‟ concerns about the quality of the previous repairs and rectification; and as the Applicants have not provided any alternative material to establish JL‟s quotations do not represent an accurate reflection of the repair/rectification work required at the Applicants‟ home; and as the FSP‟s contractors are still prepared to carry out the work for the FSP, based on the scopes and quotations, then it is fair in all the circumstances this remains a settlement option. Case No: 412715 Determination Page 2 of 13 Is the FSP’s compensation offer fair in all the circumstances? The FSP‟s offer of $2,000 compensation for non -financial loss is not fair in all the circumstances because:  i t repeatedly failed to address the Applicants‟ stated and documented concerns about the quality of the repairs and the subsequent attempts at rectification  the time taken to resolve the matter is far greater than would be expected  t he FSP‟s handling of the claim has caused significant inconvenience to the Applicants and their family. 1.3 Determination This Determination is partly in favour of the Applicants. Should the Applicants accept this Determination, then within 14 days, it is to notify the FSP of its choice of settlement option. If the Applicants choose a cash settlement, then within seven days of notification of the Applicants‟ choice of a cash settlement, the FSP is to pay the Applicants:  $97,745.01 and  $3,000 compensation for non-financial loss. If the Applicants choose the option for the FSP‟s contractors carry out the work based on their scopes and quotations, then:  within seven days of notification of the Applicants‟ choice, the FSP is to commence arrangements for the works to be carried out  upon completion of the works, the FSP is to arrange for the repair and rectification works to be inspected and approved by a senior assessor from the FSP in the presence of the FSP‟s contractor and the Applicants . In addition, whichever settlement option the Applicants choose:  within 7 days of the Applican ts‟ acceptance of this Determination, the FSP is to obtain a q uote from the removalist (R) on the cost of the Applicants‟ contents being unpacked when they arrive at the temporary accommodation, repacked when they leave the temporary accommodation and unpa cked when the Applicants return home and a quote on the cost of the transport of the pot plants to and from the Applicants‟ temporary accommodation or another location. The revised amount is to be included in the FSP‟s settlement with the Applicants and/or the work to be done by the FSP‟s removalist at the FSP‟s expense  $300 is also to be included in the FSP‟s settlement with the Applicants for the maintenance of pot plants should the Applicants not maintain the pot plants themselves . Case No: 412715 Determination Page 3 of 13 2 Reasons for Determination 2.1 Is the FSP’s settlement offer fair in all the circumstances? JL’s scope of works very detailed and comprehensive The FSP initially authorised builder J in May 2014 to undertake repair of the storm damage to the Applicants‟ building. After the Applicants complained of the poor quality of the repairs, the FSP engaged builder A to perform rectification of J‟s repair work. However, the Applicants were also dissatisfied with the work performed by A. One of the Applicants‟ key concerns was in relat ion to the timber flooring. The FSP arranged for the work to be reviewed by a flooring expert who identified a number of issues with A‟s work. The FSP‟s assessor reviewed the expert report and agreed A‟s work was not acceptable. The assessor reported the floor was to be replaced with the floorboards continuing in full under the kitchen cabinets as per the original floor. The Applicants also complained the builders left paint marks and scratches on various parts of the building, and the paint work was generally of poor quality. The Applicants outlined the issues with the repair work in several lengthy emails to the FSP over the course of the repairs and rectification. They said their house was in worse shape than when they submitted the original claim. They also contend their house has been significantly devalued as a result of substandard repairs and rectification work performed by the FSP‟s contractors. Builder A submitted a scope of works for rectification but as the parties were unable to agree, the FSP arranged for another builder, JL, to attend the site and provide a scope of works and quotation for rectification work. The scope and quotation was prepared by JL after a site visit on 10 November 2015. It includes work in the dining room, lounge/dining room, WC, kitchen, stairwell, and external deck. The quote is extremely comprehensive and detailed and addresses the Applicants‟ various concerns regarding the flooring and kitchen cabinetry. It also includes the replacement of skirting boards, window architraves and door trims with new items, as well as repainting all affected rooms. The quotation totals $64,594.71 (inclusive of GST) and a builder‟s margin of about 14%. Under paragraph 1.3, the scope of work also includes the provision of what is described as “adequate supervision for duration of works.” Upon review of JL‟s quotation, the Applicants initially submitted the quote made some “wildly unfair assumptions” such as the heavily discounted labour and material costs which are afforded to the FSP but not to the Applicants. The Applicants also contended the quotation lacked attention to many additional costs such as offsite accommodation, removal of paint contamination, and project management and oversight costs. Case No: 412715 Determination Page 4 of 13 In response, the FSP asked JL to also quote for a professional clean. JL quoted in the amount of $834.90. The FSP‟s next offer to the Applicants included the two quotes from JL, costs to remove and return contents by R ($5,515.40 including GST) and temporary accommodation ($14,300) plus $2,000 compensation for non-financial loss. The FSP offered a total of $86,743.61. Due to the non- inclusion of GST on R‟s quote, the FSP‟s offer was revised to $87,245.01. The offer was also rejected. The Applicants requested a settlement from the FSP of $110,000. Otherwise, the Applicants submit they require a Determination in the amount of $125,166.01 to allow them to complete the repairs and rectification works. The Applicants say they are seeking an amount commensurate with what it will cost them to organise the repairs, not what it will cost the FSP. The Applicants submit the FSP‟s offer is based on what the FSP can expect to pay, not what it would cost them to complete the works themselves with an on-site manager. They point out the vast majority of the rectification work is to repair the damage to their home sustained by the various contractors appointed by the FSP. In the circumstances, they contend references back to the FSP‟s policy is irrelevant. One of major sources of the Applicants‟ frustration throughout the claim was the FSP‟s apparent lack of attention to detail. At one point, the Applicants insisted on written instructions only, because they did not trust the FSP‟s representatives to accurately record information and concerns conveyed verbally. JL‟s quotes are very detailed and comprehensive. The Applicants no longer address the issue of lack of detail. In the absence of rebuttal material from the Applicants, I accept JL‟s quotations represents an accurate reflection of the repair/rectificatio n work required at the Applicants‟ home. The Applicants continue to submit the FSP‟s quotations are deficient but for the following reasons:  JL‟s quote expired on 19 January 2016  the only allowance for a full-time supervisor is for $1,540  there is no allowance for replacement of bench tops  the FSP is able to obtain a substantial discount of around 20% to 30% on materials and services, unlike the Applicants  the quote to remove and return contents was deficient  if the clean is unsuccessful, a further allowance must be allowed for the vanity in the amount of $1,700  the quotes do not contemplate cleaning the downstairs bathroom. FSP’s contractors still prepared to carry out the work based on their scopes and quotations At the request of the Service, the FSP has recently contacted both JL and R. Both companies are still prepared to carry out the work, based on their scopes of works and quotations. This means the FSP‟s quotations are still actionable. It also means if Case No: 412715 Determination Page 5 of 13 the FSP authorises, arranges and pays JL directly for this work, there is a lifetime guarantee on JL‟s building repairs. Fair the Applicants have the option to choose a cash settlement or repairs by the FSP’s contractors I acknowledge the policy provides it is at the FSP‟s option to decide if it will repair damage to the building or pay an insured what it would cost the FSP to repair the building. However, in this dispute, the Applicants are now faced with another rectification by the FSP‟s contractors. In these circumstances, the Applicants‟ reluctance to further engage with the FSP is understandable. Accordingly, I accept the Applicants‟ contention it is unfair to apply the policy terms. Therefore in all the circumstances, I consider it is fair the option is reversed and it is for the Applicants to choose whether they decide the FSP‟s contractors undertake the repairs and rectification on the scopes and quotes provided (which includes the lifetime guarantee on building repairs) or decide to accept a cash settlement as set out in this Determina tion. Should the Applicants decide the FSP‟s contractors undertake the repairs and rectifications, then certain further payments are to be included in the FSP‟s settlement with the Applicants as itemised in this Determination. Further, the FSP is to arrange for the repair and rectification works to be inspected and approved by a senior assessor from the FSP at the completion of the works. The inspection is to take place in the presence of the FSP‟s contractor and the Applicants. Cash settlement is $97,745.01 plus further quote required from removalist Quotes expired I acknowledge the relevant policy condition states the FSP only needs to provide a cash settlement for the amount it would cost the FSP to repair the building. But in all the circumstances of this matter, and given this is a second rectification attempt under the FSP‟s repair guarantee, I accept the Applicants‟ submission any cash settlement must be a fair amount which enables the Applicants to carry out the rectification work. If the Applicants opt to accept a cash settlement, then, as the quotes relied on by the FSP are now several months old, I am satisfied if there is to be a cash settlement it is fair in all the circumstances to allow a further allowance of $2,000 on the FSP‟s quotes. Supervision The Applicants say JL‟s quotation does not include any allowance for a full time supervisor, which they believe is necessary to ensure the work is performed satisfactorily. They say considering the previous two failed attempts at repair, which have resulted in substantial damage to their home, this is a necessary requirement and must be factored into a final settlement. In their settlement proposal, they Case No: 412715 Determination Page 6 of 13 estimated their needs in relation to a person to organise quotes and manage repairs would cost $10,500. The FSP rejects the need for full time supervision of the work, saying the quotation allows for periodic attendances to inspect the stages of work. The quotation says under 1.3 it provides “adequate supervision for duration of works.” An amount of $1,540 is allowed for site foreman/supervision. In all the circumstances, given the attempts of work done to date, and the unknown complications which may occur if repairs are undertaken by the Applicants, I am not satisfied in all the circumstances of this matter, this allowance is adequate if the Applicants arrange the repairs/rectification themselves. This is particularly so in circumstances where the Applicants are now faced with another rectification and are seeking a cash settlement so they can make their own repair arrangements. In the circumstances, I am satisfied in addition to the $1,540 allowed for supervision by JL, a cash settlement to the Applicants should include a further $3,500 for supervision of the work. Replacement of bench tops The Applicants say while an allowance has been made for reinstallation of the kitchen joinery, there is no allowance for replacement of the benchtops. They say the previous builders and the FSP‟s assessor advised the likely outcome of removing the stone bench top would be it would break and would need to be replaced. The FSP points out items 7.5 and 7.11 in JL‟s repair quotation address the issue of the supply and installation of a new benchtop. I have considered the relevant parts of the quote from JL. Both 7.5 and 7.11 address the issue. It is clear JL‟s quote includes the cost of removal and disposal of the entire kitchen. 7.11 allows for the supply and installation of an entire new kitchen including reconstituted stone bench tops. JL has allowed a provisional sum of $14,000 to supply and install the new kitchen. On the information provided, I am satisfied the FSP has addressed the Applicants‟ concern in relation to this item. Quote to remove and return contents The FSP obtained a quote from R dated 13 Janua ry 2016 to pack out, store and return contents to the Applicants‟ home. The quote is $5,014 plus GST ($5,515.40). The Service has confirmed R will still do the work privately for the Applicants for the amount quoted. The Applicants say the quote from R for the removal and return of their contents does not include an allowance for the actual storage of the contents; it only notes pallets are charged at $2.50 per day. They question how many pallets would be required for their contents. The Applicants also sa y the quotation from R does not allow for boxing and unpacking of their contents nor does it include storage and maintenance of their large collection of potted plants on the affected deck. Case No: 412715 Determination Page 7 of 13 Further, the Applicants contend as there have been two previous failed attempts to carry out repairs, and the vast majority of the repair work is due to the incompetence of the FSP‟s contractors, the FSP must factor in the provision of a full service. They reiterate the policy terms have no relevance as their claim is now about the poor work done by the FSP‟s contractors. The Applicants claim an additional $3,960 for pallet storage and $500 for the removal and return of pot plants. The FSP says R does not disclose its cost breakdown. It says R has allowed for the pack out, the transport of contents to the rental property, and the pack to take the contents back to the insured premises after the repairs are completed. It says the FSP will not allow to pack or unpack the contents. I note R provided the quotation after atten ding the Applicants‟ home and inspecting the contents to be transported. On this basis, I accept, R, as a professional removalist, will have included in the quotation enough capacity to cater for the contents to be transported. As the contents are to be ta ken to the Applicants‟ temporary accommodation, no storage costs need be included. However, given the Applicants have already been in temporary accommodation twice, and the further requirement for repairs is not their fault, I consider it fair for the FSP to pay for the Applicants‟ contents to be unpacked from boxes when they arrive at their temporary accommodation, repacked when they leave and unpacked from boxes when they return home. In those circumstances, I am satisfied the offer made by the FSP is adequate save for the said costs of packing/unpacking. The FSP is to ask R to quote on the cost of the Applicants‟ contents to be unpacked when they arrive at the temporary accommodation, repacked when they leave the temporary accommodation and unpacked whe n the Applicants return home. Whether the Applicants choose a cash settlement or choose JL to carry out the work, based on JL‟s scopes of works and quotations, the revised amount is to be included in the FSP‟s settlement with the Applicants. Pot plants The Applicants were concerned R‟s quote did not include storage and maintenance of the potted plants. After considerable correspondence about the pot plants, the FSP indicated it was willing to transport the pot plants to another location but no allowance wo uld be made to maintain the plants. It is not known whether the Applicants‟ temporary accommodation will accommodate the potted plants. The FSP is to ask R to quote on the cost of the transport of the pot plants to and from the Applicants‟ temporary accomm odation or another location. (In January 2016, the Applicants indicated a family member could look after the plants). The plants must be maintained during the repair period. If the Applicants‟ temporary accommodation will not accommodate the plants, then I consider it is fair in all the circumstances the maintenance cost of the plants is included in the FSP‟s settlement Case No: 412715 Determination Page 8 of 13 offer. I consider an extra $300 is a fair allowance for the maintenance of the plants should the Applicants be unable to maintain the pot plants themselves. Whether the Applicants choose a cash settlement or choose JL to carry out the work, based on JL‟s scopes of works and quotations, these revised amounts are to be included in the FSP‟s settlement with the Applicants. Vanity Unit The Appli cants were concerned the FSP‟s offer did not include the cost to replace the vanity unit (at a cost of $1,750 for the unit plus $250 plumbing) if the paint could not be removed. JL‟s cleaning quotation did not specifically address the issue. The FSP first responded by saying in the event the clean-up is unsuccessful, the FSP will allow $1,700 to replace the vanity. In a further email, the FSP said: „…as it would not be possible to remove paint from the vanity unit without causing further damage, (the FSP) will factor in the replacement cost in the final settlement.‟ If the vanity needs to be replaced, then I accept some plumbing costs may ensue. I am satisfied it is fair in all the circumstances to allow $2,000 for the vanity unit. Whether the Applicants choose a cash settlement or choose JL to carry out the work, based on JL‟s scopes of works and quotations, this amount is to be included in the FSP‟s settlement with the Applicants . Downstairs bathroom The Applicants say the cleaning quote does not co ntemplate cleaning of the downstairs bathroom. They say after the last attempted repair and the use of their facilities by tradesmen, the bathroom was left in a disgraceful state. The FSP has not addressed this issue specifically. JL‟s quote includes prof essional cleaning in the amount of $660. I accept the bathroom will require cleaning after the tradesmen vacate the insured property. However, I am satisfied an amount of $660 for cleaning costs will include the bathroom and will fairly address this concern. Offsite accommodation costs The Applicants rejected an offer from the FSP as it failed to include at least six weeks of offsite accommodation costs. Advice received from the FSP by the Service indicates the repairs would be carried out over approximately 10 weeks. The Applicants have provided no further information contending either the estimate or the amount allowed is not reasonable. If the Applicants elect to accept a cash settlement, then given the attempts of work done to date, and the unknown complications which may occur while repairs are undertaken, I am satisfied in all the circumstances of this matter, it is fair a further allowance of $5,000 is allowed. Case No: 412715 Determination Page 9 of 13 If the Applicants elect for the FSP‟s contractors to undertake the work, should the repairs take longer, the FSP is to ensure the Applicants continue to be reasonably compensated for offsite accommodation costs. FSP‟s quotes are discounted The Applicants also contend JL‟s quotations factor in a significant discount (of around 20 to 30%) available to the FSP, but not available to the Applicants. They believe this puts them at a disadvantage if a cash settlement was based on JL‟s quotation. They say as they are unable to obtain the sizeable discounts afforded to the FSP, an allowance of 20% shoul d be made to the FSP‟s quotes. In support, the Applicants have put forward a $702.02 tax invoice for the replacement and installation of their dishwasher by a plumber. They point out JL has quoted approximately $1,280+GST for the disconnection and reconnection of dishwasher, gas hotplates, the kitchen sink, a bathroom sink, and a bathroom toilet along with the relevant compliance certificates. They contend for approximately twice the price the FSP was able to obtain four additional items to be disconnected and reconnected by registered plumber with associated compliance certificates. I accept the amount quoted by JL for the installation of the various appliances and fixtures appears low, relative to the price paid by the Applicants for the installation of their dishwasher. While this could be due to a discount applied to the work by JL (as the Applicants contend), it might also be because the price the Applicants paid was not as competitive as it could have been in the circumstances. Based on the information presented, it is not possible to draw a ny conclusions in this regard. The FSP says it is entitled to rely on the policy provision which says if it agrees to settle a building claim it is entitled to pay an insured what it would cost the FSP to undertake the repairs. It also contends the Applicants have not provided any quotes to justify their position. It reiterates if the Applicants provide a quote for the cost of repairs, the FSP will take this into consideration. Having considered all the material pro vided, there is simply insufficient evidence to make any further allowances on the basis the FSP‟s quotations are discounted. The FSP has obtained comprehensive and detailed quotations to rectify or repair the damage. And the FSP‟s contractors remain willi ng to carry out the work for the FSP. Further, should the Applicants chose to allow the FSP‟s contractors to undertake the work as quoted, there is a lifetime guarantee on the work. Applicants have provided no quotations The FSP submits its offer is reasonable. It says the Applicants have not provided any quotes to justify its position. The material provided establishes in September 2015, the FSP advised if the Applicants did not wish the FSP to complete the repairs, then the FSP would consider providing a cash settlement through a repairer chosen by the Applicants. Case No: 412715 Determination Page 10 of 13 The FSP said if the Applicants wish to consider this option, then they were to provide two quotes for the repair and rectification work for the FSP to review. The Applicants contend if they were to provide alternative quotations, they would need to engage a technical projects team to identify and organise the tradespersons required to complete the work and the lifetime guarantees. They asked if the FSP was prepared to cover these costs. In response, the FSP made a proposal which ultimately resulted in JL attending the site and providing a quote. In addition, the FSP advised the Applicants it would cover the fair and reasonable costs associated with someone attending the Applicants‟ property to obtain a quote (subject to approval for reimbursement). The Applicants continued to ask if they could obtain a project manager to manage getting quotations for the repair work. In response, the FSP wrote on 7 October 2015: „ Regarding quotes, as you have agreed for (JL) to attend on-site on behalf of (the FSP), please hold off on obtaining quotes until you have reviewed the proposed scope of works that (JL) provides. If you do not believe the quote is accurate, we will address this at that point.‟ Aft er JL‟s repair quotation, and the FSP‟s offer, the Applicants further reiterated given the extent of the repair work required, they would require a project manager and team to help assemble not only the quotes but manage the work. They continue to contend it is unreasonable to expect them to organise quotes themselves without assistance from professionals. They say they have demonstrated their preparedness to do so but as the FSP has delayed proceedings for so long, it is not reasonable this is now a requirement. While I accept it can be challenging for a layperson to approach a major rebuilding project and feel confident they have captured all the necessary aspects to be included, I am satisfied the scope of works provided by JL provides a more than adequate starting point for this process to begin. I do not accept the FSP‟s advice of 7 October 2015 the Applicants should “hold off” from obtaining a quotation is sufficient reason for them to continue to provide no independent expert material to support their position. The FSP‟s October advice was provided because it was then seeking to obtain its own quotation which, if accepted by the Applicants, might have resolved the matter. However, once the Applicants rejected JL‟s quotation, it is reasonable to expec t them to obtain one or more alternative quotations for the work. The Applicants have not provided any alternative quotations for the work outlined in JL‟s scope of works. In the absence of any such alternative quotations, it is very difficult to conclude the JL quotation is not an accurate reflection of the scope of the work and the cost of the work save for the findings already made in this Determination. Case No: 412715 Determination Page 11 of 13 Summary In summary, I am satisfied in all the circumstances should the Applicants choose a cash se ttlement, the following is a fair cash settlement of the Applicants‟ claim ( plus compensation which is addressed below). Item Amount offered Amount determined Building repairs $64,594.71 $70,094.71 Cleaning $834.90 $834.90 Cost to remove and return contents $5,515.40 $5,515.40 (plus new quotes) Temporary accommodation $14,300 $19,300 Vanity unit $1,700 $2,000 Total $86,945.01 $97,745.01* plus items below Additional items in FSP’s settlement whichever option Applicants choose In addition, whichever option the Applicants choose:  R is to quote on the cost of the Applicants‟ contents being unpacked when they arrive at the temporary accommodation, repacked whe n they leave the temporary accommodation and unpacked when the Applicants return home. The revised amount is to be included in the FSP‟s settlement with the Applicants.  And R is also toon the cost of the transport of the pot plants to and from the Applicants‟ temporary accommodation or another location. The revised amount is to be included in the FSP‟s settlement with the Applicants .  An allowance of $300 is also to be allowed for the maintenance of the plants should the Applicants not maintain the pot plants themselves. 2.2 Is the FSP’s compensation offer fair in all the circumstances? FSP repeatedly failed to address the Applicants’ concerns A review of the information provided by both Applicants and the FSP with respect to the claim, both prior to and after the dispute was lodged with the Service, confirms the FSP either failed to attend to the Applicants‟ concerns about the repairs and the rectification works or attended to concerns but not in a timely fashion. The Applicants notified the FSP on many occasions of the details of their concerns, but unfortunately these were not properly addressed. Even after appointing a new builder (A), to rectify the issues created by J, the FSP failed to fully address the Applicants‟ concerns. Case No: 412715 Determination Page 12 of 13 Time taken to resolve the matter is greater than would be expected It is clear this claim, which was in dispute from about June 2014, has been significantly protracted. While the Applicants may have contributed to some delay (due to being unavailable while on holidays), the bulk of the time taken on the claim has resulted from the FSP‟s failure to address the Applicants‟ legitimate concerns about the quality of the repair work. FSP’s handling of claim has caused significant inconvenience The Applicants say the handling of the claim has caused them significant inconvenience, and having reviewed the material presented, I agree. The FSP has offered to pay the Applicants $2,000 compensation. The FSP acknowledges the Applicants experienced a substandard claims experience and acknowledges the repairs completed on both occasions were not completed to a satisfactory standard. Having reviewed all the material provided, I consid er the FSP‟s offer is insufficient. I am satisfied it is fair in all the circumstances the FSP pay the Applicants $3,000 for compensation for non-financial loss. Case No: 412715 Determination Page 13 of 13 3 Supporting information 3.1 FOS Approach As advised to the parties, FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. There has been a full exchange of all material information relied on for the purposes of this Determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered for the purposes of this Determination. This dispute has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. While the parties have raised numerous issues in their submissions, for the purposes of this Determination, commentary has been restricted to those issues considered directly relevant to the outcome only. Under paragraph 9.3 of its Terms of Reference, FOS may decide a Financial Services Provider compensate an Applicant for non-financial loss where an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant‟s expectation of enjoyment or peace of mind has occurred. 3.2 Relevant policy extract „(FSP‟s) Home Building Insurance offers guaranteed repair quality The quality of workmanship and the materials used in any repair or rebuilding of your home that we arrange and authorise will be guaranteed for the life of the home. ‟ 3.3 Relevant material considered and relied on  Parties‟ submissions including all material provided therewith such as loss adjustment and assessment reports, quotes, emails, photographs, lists of damage, calculations and invoices.  Correspondence between the parties.  FSP‟s policy screens, claim notes, assessment reports, repair quotes, rectification reports and scopes of work.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.