Home / Financial Firm (Unknown - Insurer) / Determination 410738

Determination 410738

Claim denial under flood exclusion

FirmFinancial Firm (Unknown - Insurer)
Decided2016-07-18
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A company's commercial building was damaged by water from a creek during an April 2015 storm, and the FSP denied the claim under the flood exclusion. AFCA agreed the water was flood and the FSP could rely on the exclusion.

The water escaped from the normal confines of a natural watercourse, which falls within the policy definition of flood, so the flood exclusion applies.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 410738 Determination Page 1 of 5 Case number: 410738 18 July 2016 1 Overview 1.1 Dispute This dispute involves a claim by the applicant (the applicant in this determination is the person who controls the corporate entity in whose name the policy vests) under his Commercial Investment Insurance policy (CIP), held with the financial service provider (FSP), following damage to the applicant’s commercial investment building as a result of a severe weather event in April 2015. The FSP has denied the applicant’s claim on the basis of the policy exclusion for loss and damage caused by flood. 1.2 Issue and key findings Is the FSP entitled to rely upon the policy exclusion to deny the applicant’s claim? The FSP is entitled to rely upon the policy exclusion to deny the applicant’s claim. 1.3 Determination This determination is in favour of the FSP. The FSP is entitled to deny the applicant’s claim. Case No: 410738 Determination Page 2 of 5 2 Reasons for determination There has been a full exchange of material between the parties and eac h party has had the opportunity of addressing the issues that arise from the material exchanged. This determination follows consideration of all of the information exchanged and is based on what is fair in all the circumstances, having regard to the releva nt legal principles, terms of the policy, good industry practice and where applicable, prior determinations. On 1 July 2016 the Ombudsman attended on site where he met with the applicant and representatives of the FSP. The determination is based upon the i nformation collected during the on-site visit and all of the information exchanged during the course of the dispute. The determination is made by a Panel consisting of the Ombudsman together with a representative who has extensive experience in consumer claims and a representative who has extensive experience in the insurance industry. 2.1 Is the FSP entitled to rely upon the policy exclusion for flood to deny the applicant’s claim? Coverage of the policy The applicant’s CIP provides cover for physical loss, destruction or damage to the applicant’s property during the period of insurance. The coverage provided by the policy is detailed within the Product Disclosure Statement (PDS). The coverage provided by the policy is subject to exclusions which are also detailed within the PDS. The PDS includes: ‘Specific exclusions We will not pay you under this Section 1 for physical loss, destruction or damage caused by, or as a consequence of: … 4. Flood …’ In addition, the PDS includes: ‘General definitions These general definitions apply to all Policy sections. Some of the words and terms used in this Policy have a special meaning. When the following words or terms are used in this Policy, they have the meaning set out below. … Case No: 410738 Determination Page 3 of 5 Flood means the covering of normally dry land by water that has escaped or been released from the normal confines of:  Any lake, or any river, creek or other natural watercourse, whether or not altered or modified; or  Any reservoir, canal or dam.’ Circumstances of the applicant’s loss and claim It is not in dispute that in April 2015 there was a significant weather event in the local area which resulted in damage to the applicant’s commercial investment property. A dispute has arisen between the parties as to whe ther the cause of the damage to the property can properly be described as flood, which is excluded from cover, or alternatively storm, rainwater and rainwater runoff, which is covered under the policy. The FSP arranged for an assessor to attend on-site, who in turn engaged a consulting engineer and hydrologist, all of whom have provided reports. The applicant has engaged an engineer who has also provided a report. The Panel has been greatly assisted by the material exchanged which has included relevant photographs and videos taken during the course of the significant weather event. Having considered all of the exchanged material, the Panel is satisfied that the water which entered the car park and the building on-site was substantially water from the Two Mile Creek and the unnamed tributary of Two Mile Creek that passes beneath (C) Drive. The evidence confirms that Two Mile Creek passes underneath the (NE) Highway via culverts and then under the car park and building site via further culverts. On the basis of the evidence exchanged, the Panel is also satisfied that once the capacity of the culverts beneath the car park and building location was exceeded, the water from Two Mile Creek and the unnamed tributary inundated the site car park and flowed into the building on the site. The Panel accepts that given the slope of the NE Highway in the direction of the building site, there would have been some stormwater runoff towards the location but the Panel is satisfied that this stormwater runoff would have flowed to the area in between NE Highway and the car park and the building location. This area has been described as a basin and forms part of the Two Mile Creek as it progresses underneath the NE Highway, through the basin and then underneath the car park and building location. Through his representatives, the applicant maintains that the water within Two Mile Creek was forced on to normally dry land because its usual path was blocked by the debris in the trash rack. The Ombudsman observed and the exchanged material confirms that there is a trash rack designed to stop debris, travelling along the Two Mile Creek, from proceeding underneath the car park and building location site. Case No: 410738 Determination Page 4 of 5 The applicant says that the trash rack was blocked and despite previous complaints to the local Council, had not been cleared. The applicant says that immediately subsequent to the damage to the property, there was machinery and workers on-site clearing the debris from the trash rack. The applicant assumes that the workers and machines were engaged by the local Council. Through his representatives, the applicant maintains that the debris which had accumulated within the trash rack prevented the Two Mile Creek waters from proceeding along their normal path and were forced out of the Creek into the car park and building. Whilst the applicant maintains that complaints had been made to the Council, there is no probative evidence of the extent of the debris or blockage of the trash rack, immediately prior to the significant weather event. The Panel accepts that it may be possible that the trash rack became blocked prior to or during the course of the significant weather event as a result of the debris which was proceeding along the Two Mile Creek within the forceful water flow. However, even if it could be established that the trash rack was blocked prior to the significant weather event, the Panel is satisfied that the policy definition for ‘flood’ captures the circumstances of the applicant’s loss. The policy definition for flood, detailed above, in volves ‘… water that has escaped or been released from the normal confines of …. the natural watercourse…’ The applicant’s representatives say that the water has not escaped but rather has been forced on to dry land because its usual path was blocked. Nevertheless, although the mechanism of the escape of water may not be the same as may be experienced in other floods, the Panel is satisfied that the water still ‘escaped’ from the natural watercourse. In any event, arguably the cause of the escape could equally be attributable to the volume of water, as much as the argument that the usual path was blocked. The Panel is satisfied that the concerns held by the applicant in regard to the actions of the local Council and their failure to clear the trash rack, whilst arguably being a matter for complaint by the applicant against the Council, does not assist the applicant in his dispute regarding the coverage of the policy. The Panel is satisfied that regardless of the mechanism, water has escaped from the normal confines of Two Mile Creek and has entered the car park and building causing damage. As it is clear that the building the subject of this claim was not situated within the confines of the watercourse, this is properly characterised as flood. The Panel i s also satisfied the applicant’s policy as issued does not provide cover for flood. The Panel notes that flood cover may otherwise have been available and/or selected, however that is not a matter for this dispute or, in this instance the FSP but it may well be a matter between the applicant and his insurance broker . Case No: 410738 Determination Page 5 of 5 The result is that the FSP is entitled to deny the applicant’s claim on the basis of the exclusion for ‘flood’.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.