Determination 409607

Delay in reimbursing building invoices from the home loan delayed the renovation project

FirmFinancial Firm (Unknown - Credit)
Decided2016-04-22
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicants said the FSP's slow reimbursement of building invoices from their home loan delayed their renovation and caused loss, and that staff did not highlight the 12-month interest-only period. AFCA decided in the FSP's favour and declined to consider guarantor release and credit risk, which were outside its jurisdiction.

The invoices were paid from other funds, the reimbursement delays were explicable, there was no evidence that works ceased because of payment delays, and the FSP had no duty to advise on the contractual terms.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 409607 Determination Page 1 of 7 Case number: 409607 22 April 2016 1 Overview 1.1 Dispute The Applicants had an existing home loan with another financial services provider with a debt of about $370,000. In about March 2015, they refinanced their existing loan with the Financial Services Provider (FSP) in a loan with account number ending 7062 (the Home Loan). In addition to the funds used to pay out the existing loan, the Applicants borrowed further funds of about $140,000 which they intended to be drawn down to pay for construction works to renovate an investment property (the Property). The Home Loan was secured by a mortgage over the Property and by a guarantee provided by Ms S’s parents supported by a mortgage over their property. On 26 May 2015, the FSP agreed to vary the Home Loan by increasing the amount borrowed by a further $35,400, to a credit limit of $545,400. In addition to the Home Loan, further finance was provided by the FSP by way of:  A business loan in the name of a company operated by the Applicants with account number ending 0726 (the Business Loan)  A loan account with account number ending 202248 is in names of the Applicants The Applicants say that the FSP delayed in approving drawdowns for the construction works. The Applicants claim that this delayed the completion of the project and caused them to suffer financial loss. The Applicants also say that the additional security provided by Ms S’s parents should be now be released - and that the Home Loan should have reverted to principal and interest payments after it was fully drawn down. 1.2 Issues and key findings Did the FSP delay in approving progress payments for the building works cause a delay in completing the project and causing the Applicants to suffer loss? There is insufficient information available to conclude that the building works were delayed because of the FSP’s conduct , causing the Applicants to suffer loss. However the available information does show that:  the Applicants obtained funds from other sources and paid invoices themselves  the Applicants then submitted invoices/requests for reimbursal by the FSP Case No: 409607 Determination Page 2 of 7  reimbursal was delayed for an extended period on a small number of occasions, for explicable reasons. Did any delay in the payment of the submitted invoices for reimbursal cause the Applicants to suffer loss? On three occasions, there was a significant delay between the date that the Applicants emailed invoices for reimbursal to the FSP and the FSP making payment. However in the circumstances, these delays were explicable and reasonable (and so cannot be said to have caused the Applicants financial loss). All three invoices are dated prior to the letter of offer for the Home Loan and the funding date. I am satisfied that for other invoices, where there was a more minor delay in reimbursal , that delays arose due to confusion about what invoices were for. As I have not found that the FSP acted unreasonably or made an error in reimbursing payments when it did , I cannot find that the FSP’s conduct caused the Applicants to suffer loss. Should the FSP release the guarantors’ liability under the Home Loan FOS cannot consider the Applicants’ claim that the FSP should release Ms S’s parents from their guarantee and the parents are not parties to this dispute. The parents can however, bring their own dispute to FOS regarding the guarantee. Did the FSP make an error in relation to interest only period of the Home Loan? The FSP did not breach any duty or obligation in relation to the interest only period applicable to the Home Loan.  The terms of the Home Loan clearly state that interest only payments are required for 12 months from the time the loan is fully drawn down.  The FSP was not obliged to provide advice about the effect of the contractual terms contained in the Home Loan contract. 1.3 Determination This Determination is in favour of the FSP. Case No: 409607 Determination Page 3 of 7 2 Reasons for Determination 2.1 Did the FSP delay in approving progress payments for the building works cause a delay in completing the project – so causing financial loss? The Applicants provided information setting out their claim of delay The Applicants engaged a builder to undertake construction works on the Property. The Applicants also separately acquired some of the materials and appliances directly from suppliers. For example, the Applicants sourced the windows, carpet, the kitchen and some kitchen appliances, tiles and painter themselves. The Applicants paid these suppliers directly. The Applicants would pay invoices and then have those payment amounts reimbursed by the FSP. During the course of this dispute, the Applicants were asked to provide information to support their claim that the FSP delayed the project. The Applicants provided a comprehensive table setting out their version of the chronology. The table provided details about the suppliers who were paid, the amount paid, the date of the invoice, the date the invoice was emailed to the FSP for approval, the date the invoice was paid, and the date the FSP finally reimbursed the Applicants from the Home Loan funds. I have set out a de- identified version of the Applicants’ table below. Company Amount Invoice date Emailed date Paid by Paid Date Paid by the FS P Kitchen Co $5900 18/3/2015 26/3/2015 Applicants 10/4/2015 21/5/2015 Builder $20,177.55 31/3/2015 31/3/2015 Applicants 10/4/2015 21/5/2015 Windows Co $5,000 25/3/2015 9/4/2015 Applicants 4/5/2015 21/5/2015 Oven $2,043 20/4/2015 2 2 /4/2015 Applicants 22/4/2015 21/5/2015 Tiles $902 20/4/2015 22/4/2015 Applicants 22/4/2015 21/5/2015 Builder $20,000 23/4/2015 24/4/2015 Applicants 5/5/2015 21/5/2015 Builder $4,599 23/4/2015 29/4/2015 Applicants 6/5/2015 21/5/2015 Builder $7,095 5/3/2015 18/5/2015 Applicants 5/3/2015 21/5/2015 Kitchen Co $6,000 16/6/2015 17/06/ 2015 Applicants 17/6/2015 24/6/2015 Kitchen Co $5,000 23/6/2015 24/6/2015 Applicants 9/7/2015 9/7/2015 Carpet $9,277 6/5/2015 18/7/2015 Applicants 29/7/2015 11/8/2015 Painting $2,000 1/6/2015 unknown Applicants 10/6/2015 11/8/2015 Painting $5,700 13/7/2015 22/7/2015 Applicants 28/7/2015 11/8/2015 Case No: 409607 Determination Page 4 of 7 Builder $9,500.88 15/7/2015 27/7/2015 Applicants 29/7/2015 11/8/2015 Builder $3,714.81 15/7/2015 27/7/2015 Applicants 28/7/2015 11/8/2015 The Applicants paid invoices from other funds The Applicants claim that because the FSP delayed processing drawdown payments from the Home Loan account, work was delayed because the builder and the other suppliers ceased, or delayed, work. The Applicants state that they paid all invoices using funds from sources other than from the Home Loan account. It appears that when the FSP approved drawdowns from the Account, the funds went to reimburse the Applicants for the payments (of building related invoices) they had previously made. The Applicants have stated that some costs were paid from an overdraft the FSP approved until funds from the Account were available. Some invoices were paid from these funds. Other costs were paid from funds borrowed f rom Ms S’s parents or from the Applicants’ own savings. I have been provided with numerous emails between the Applicant’s and the FSP. It is reasonably clear from these email communications that the Applicants were willingly paying for most of the invoices directly using alternative sources of funding and seeking reimbursement from the Account later. The delay must be delay in paying invoices The above table discloses several instances of delay between when the Applicants emailed the FSP with the invoice seeking a drawdown, to when the FSP approved the drawdown from the Home Loan account. However, as I have remarked above, the table discloses that the invoices were paid much earlier from the Applicants other funding sources. In some cases the invoices pre-date the letter of offer for the Home Loan, and/or the funding date for the loan. This is important. If invoices for building works and materials were paid from other sources, there would be no reason for work to cease or slow down because payments were being made. There would be no reason for building work to slow or cease. The Applicants’ information shows that there were delays in reimbursing some invoice amounts, but these were explicable The FSP’s position in relation to the dates drawdown payments were requested, and the dates payments were made differs to some extent with the Applicants’ version. However, to determine this issue I am prepared to assume the most favourable position for the Applicants and accept the information provided by the Applicants in the table above. The Applicants’ table discloses that the time between when invoices were emailed to the FSP, and the date the invoice amount was reimbursed varied. In most instances, the FSP paid two weeks or so after invoices were submitted to it by email by the Applicants, which in my view is acceptable and consistent with good industry Case No: 409607 Determination Page 5 of 7 practice. On six occasions, the FSP took longer than two or so weeks to pay. However, for the reasons given earlier in this decision, I am satisfied given the timing, nature and circumstances of these invoices - that these delays were explicable (and so cannot be said to have caused financial loss to the Applicants). It is my understanding, from reviewing the dispute file , that the Applicants are aggrieved by the standard of service and type of communication that they received from the FSP, regarding the timing of reimbursing them for invoices. There appears to have been some form asymmetry of expectations about what the FSP would and would not do - between the Applicants and the FSP. The available information in this dispute is insufficient for me to find that the FSP was responsible for the Applicants’ expectations in this regard. I note that resolving a grievance about the FSP’s standards of customer se rvice is beyond the ambit of FOS’ jurisdiction. FOS cannot review or make Determinations on matters relating to standards of customer service under our Terms of Reference. There is no information to show that delay in paying invoices caused a delay in building works The Applicants have claimed that the completion of the building works was delayed by two months because of the delay in paying invoices. However, the Applicants have provided no information to support their claim that works slowed or ceased at any stage. There is no information to suggest that work ceased because of delayed payment. In my experience, builders and tradesmen undertaking building works will complain, often bitterly, when their costs are not paid on time. The Applicants have not produced emails from the builder or other suppliers complaining about invoices not being paid, let alone formal notices issued under the building contract for late payment. For a builder to cease work is a serious step. There is often a financial cost. The building contract between the builder and the Applicants contains a right to claim liquidated damages in the event of a delay. The builder would ordinarily attempt to protect its position by sending demands or warnings well prior to the serious step of ceasing work for a period. No such communications have been provided. After considering all of the available information, in my view, there is insufficient information to conclude that any delay occurred, let alone that the delay was caused by the FSP’ s conduct. Consequently I cannot find that the FSP caused the Applicants to suffer financial loss. That is, in my view, the available information does not show that building works were delayed. It may well be that the decision of the Applicants to pay invoices themselves and then seek reimbursal may have prevented any potential delays - and may also have resulted in the project starting and finishing earlier than would have otherwise been the case. Case No: 409607 Determination Page 6 of 7 2.2 Should the FSP release the guarantors’ liability under th e Home Loan The Applicants say the FSP has sufficient security The Applicants say that the FSP has sufficient security because the value of the Property has increased. The Applicants say that the FSP ought to release Ms S’s parents from the guarantee securing the Home Loan. FOS cannot consider disputes relating to a borrower’s credit risk FOS’s Terms of Reference excludes FOS from considering disputes about a financial services provider’s assessment of the credit risk posed by a borrower or the security to be required for a loan. Accordingly, FOS is not able to consider this aspect of the Applicants’ claim. 2.3 Did the FSP make an error in relation to interest only period of the Home Loan The Applicants claim that the Home Loan should have reverted to principal and interest payments In a telephone conversation with my Case Manager, the Applicants claimed that the Home Loan should have reverted to principal and interest repayments after it had been drawn down. However this had not occurred. The Applicants’ beli ef was that this was the contractual arrangement according to the Home Loan contract. However, the Home Loan contract signed by the Applicants on 2 April 2015, states that the required repayments are interest only, and that principal and interest payments begin after 12 months from when the loan was fully drawn down. The Applicants were asked to detail their claim in light of the terms of the contract. In response the Applicants stated: “It was an oversight of ours that we didn’t see, when we read through the contract that the mortgage was interest only for 12 months from the final drawdown. However, in the same misconduct approach to initiating our mortgage, it was never highlighted to us by [the FSP’s Banker] that we would be pa ying interest only for a year after the final drawdown. We would never have agreed to this or signed the contract had we have been made aware. The FSP has not made an error The available information shows that the FSP did not make an error. The first page of the terms and conditions of the Home Loan contract details that the required repayments are interest only for a period of 12 months from when the loan is fully drawn. The Applicants do not suggest that the FSP’s staff misled them about this provision , rather, the Applicants say that the FSP’s staff did not highlight this to the Applicants. However, financial services providers do not owe fiduciary duties to their customers to advise them about the effect of the contractual provisions. It is the respo nsibility of Case No: 409607 Determination Page 7 of 7 customers entering into a contract to read and understand the provisions, or seek independent advice in relation to the effect of terms and conditions they do not understand. 3 Other issues The Applicants sought conciliation In correspondence to me, the Applicants raised concerns that their case manager had not sought to conciliate their dispute or sought an offer from the FSP to resolve their dispute. In response to that concern, enquiries were made of the FSP about participating in an Ombuds man’s conciliation conference and separately, enquiring if the FSP was interested in attempting to resolve this dispute by means other than the issue of this Determination. The FSP indicated that it did not want to participate in a conciliation or at that point in time, make a compensatory offer to resolve this dispute. I note that FOS cannot compel member financial services providers to participate in conciliation or make compensatory offers to resolve a dispute