Denial of escape-of-water earth movement damage claim

FirmFinancial Firm (Unknown - Insurer)
Decided2016-07-19
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$2,162
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

An applicant claimed for home structural damage from leaking pipes causing ground movement. AFCA upheld the denial under the earth movement exclusion but ordered the FSP to pay the $2,161.61 plumbing investigation cost under the escape of liquid benefit, with statutory interest.

The earth movement exclusion applies unless damage occurs within 72 hours of a pipe leak, and the FSP's engineer's evidence that it did not was preferred.

Issues

Subjects and remedies

home or building damagepay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 409183 Determination Page 1 of 6 Case number: 409183 10 June 2016 1 Overview 1.1 Dispute The applicant lodged a claim for damage to the structure of his house as a result of two leaks which caused earth movement. There is no dispute that most of the damage would have been caused by water escape. The FSP denied the claim on the basis the damage was caused by earth movement (which is excluded from cover) and the evidence does not support the damage occurred within 72 hours and was directly caused by the leakages (as is required by the policy to establish the exception to the earth movement exclusion). The FSP also relies on an exclusion for “cracking” damage for part of the claimed damage. The applicant disagrees and relies on the report by the FSP‟s loss assessor which says the assessor and the FSP‟s engineer believe the damage is almost instant after a water escape event, as soil and foundations are impacted by water although there may not be any evident damage within 72 hours. On the basis of this discrepancy between the FSP‟s experts, the applicant wants his claim paid. 1.2 Issues and key findings Is the FSP entitled to deny the claim? The FSP is entitled to deny the claim as the more persuasive later written evidence from the FSP‟s engineer establishes the damage was caused by earth movement but the damage did not occur within 72 hours of the pipe leaking. As the policy excludes damage in these circumstances, the FSP is entitled to deny the claim. Although cracking damage occurred, it did not occur in circumstances covered by the policy. The FSP is only liable to pay for the reasonable cost to investigate the cause of the damage. 1.3 Determination This determination is favour of the FSP. The FSP is not obliged to take any further action in relation to the claim save to pay the applicant $2,161.61 for the cost to investigate the cause of damage. If the amount has not been paid already, the FSP is also to pay statutory interest to the applicant from the date the applicant paid the investigation costs until settlement date. Case No: 409183 Determination Page 2 of 6 2 Reasons for Determination 2.1 Is the FSP entitled to deny the claim? Applicant has established a prima facie claim The applicant has the onus to establish on the balance of probabilities he has suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. The FSP‟s policy insures the applicant against accidental damage occurring during the period of insurance. The policy defines accident to mean: „ a sudden, unexpected and unintended event which: • You did not intend or expect; and • a reasonable person in Your position and with Your knowledge and experience would not have expected .‟ The material establishes in or about 14 November 2014, the applicant noticed damage to his home as a result of water leak. From the material provided, I am satisfied this damage was sudden, unexpected and unintended and occurred during the period of insurance. I am therefore satisfied the applicant has established a prima facie claim. FSP must prove policy exclusion Once so established, the onus shifts to the FSP to prove on the balance of probabilities an exclusion applies if it seeks to deny or limit its liability for the loss. In the context of this dispute, the FSP says it is not obliged to pay the claim as the policy does not cover the applicant against damage directly caused by earth movement unless the damage occurs within 72 hours of and is directly caused by water overflowing, leaking or bursting from a fixed pipe. The applicant has produced water accounts and water consumption records. They show a substantial increase in water consumption from 1 July 2014 until 6 October 2014. As a result, in November 2014, the applicant engaged a plumber who completed pressure tests. He found and rectified three different water leaks. The FSP engaged an assessor who inspected the premises on 3 December 2014. The assessor concluded, as a result of the leaking pipes, water had saturated beneath the concrete slab causing cracks in the brickwork. The FSP also engaged an engineer who inspected and photographed the premises on 21 January 2015. He concluded: „ The recent water escape and pipe failures are readily apparent. The various damages observed and described are difficult to definitely associate or dis-associate with the report of water escape, some of which appear to predate this event. The discovery and subsequent repair of the water leaks in November 2014 does not however define the commencement or duration of the leak event. Clearly, the leak may have commenced many months before its discovery. Case No: 409183 Determination Page 3 of 6 I acknowledge that at the time of its discovery the leak and associated water escape had progressively escalated to a substantial rate of discharge which made it detectable by the water authority. Exactly over what period of time the leak had continued is unknown. For that reason, we can only assume that all of the movement related damages are possibly due to ground movement which has resulted from the over wetting of the supporting ground caused by water escape. …. (various observations indicates) the leaks have been in place for weeks or months and not years.‟ When asked to comment further he described the mechanism which occurred in this instance. The leaking pipe was not in direct contact with the ground. Therefore the water had to first leak from the building cavity, then out into the surrounding ground, then penetrate the ground to impact the clay below which supported the foundations. The engineer then said: „…in his view the observe d damages would not have commenced until at least 7 days (and more likely 21 days) after the commencement of the escape. Any reaction of the clay resulting from water contact would have been a progressive process which would commence once the water had passed from the cavity, through the adjacent ground and into the clay in the supporting ground beneath the foundations.‟ The FSP relies on this statement to deny the claim because its policy excludes damage directly caused by earth movement unless the damage occurs within 72 hours of and is directly caused by the water leak. Earth movement damage did not occur within 72 hours of the pipe leaking The material provided by the parties clearly establishes there was water leaking which caused damage. The leaking water caused earth movement because of the over wetting of the supporting ground caused by the water escape. To be entitled to deny the claim, the FSP must establish the earth movement damage occurred within 72 hours of the pipe leaking. The material establishes the pipe began to leak somewhere between 1 July 2014 and 6 October 2014. Once the water began to escape, it is the engineer‟s opinion the observed damages would not have commenced until between 7 and 21 days after the commencement of the escape of the water. This is because the water had to pass through the cavity, through the adjacent ground, and into the clay in the supporting ground beneath the foundations. I am satisfied the FSP‟s engineer has the expertise to comment. In the absence of any rebuttal material from the applicant, I accept the engineer‟s opinion. In those circumstances, I am not satisfied the claimed damage to the property occurred within 72 hours of the leaking pipe. I do not accept the applicant‟s submission the claim is defeated by “fine print”. Rather, in my view, the exclusion is expressed clearly and reflects the commercial intention of the policy that cover for damage resulting from earth movement will be covered only in very limited circumstances. That is, when the cause is something Case No: 409183 Determination Page 4 of 6 sudden like an earthquake or water bursting from a fixed pipe or a leaking pipe where the resulting damage occurs within the 72 hour period specified. The applicant relies on a report written by the assessor on 4 May 2015. He writes in his opinion and the opinion of the engineer, the damages are almost instant after a water event. That is, the resultant damage did occur within 72 hours of the water leaking from the pipe. However, if this was ever the opinion of the engineer, the later written response from the engineer is clear. In his view, the observed damages would not have commenced within the 72 hour period. The policy provides cover for cracking damage but the damage must be directly caused by elements such as earthquakes, storm, impact etc . none of which are applicable to the cause of damage in this claim. Therefore I am satisfied the FSP is entitled to rely on the policy exclusion to deny the claim. FSP to pay the applicant ’s investigation costs The policy provides additional benefits when there is escape of liquid. The FSP will pay the reasonable cost to investigate the cause of the damage or likely damage. It will pay up to $2,500 for this benefit. The applicant has established he engaged a plumber to investigate the cause of damage. The plumber found three different water leaks after removing bricks. The plumber‟s invoice is $2,161.61. If not paid already, the FSP is to pay the said sum to the applicant forthwith together with statutory interest from the date the applicant paid the plumber. Case No: 409183 Determination Page 5 of 6 3 Supporting information 3.1 FOS approach As advised to the parties, FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS recommendation and has proceeded directly to determination. There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered for the purposes of this determination. This dispute has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous Financial Ombudsman Service (FOS) decisions. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues considered directly relevant to the outcome only. It is an accepted principle of general insurance law that an insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. 3.2 Relevant policy extract ‘ What You are insured against This policy insures You against Accidental damage, burglary and theft occurring during the Period of Insurance. You have insurance for: • Your Home if „Building‟ is shown on the Certificate of Insurance What is not insured This policy does not insure You against 1. Damage directly caused by: • earth movement no matter how caused, including erosion, vibration, subsidence, seepage, saturation, creeping, landslip, mudslide, collapse, shrinkage, settling, expansion or heaving, unless the damage occurs within 72 hours of, and is directly caused by: b) water overflowing, leaking or bursting from a fixed pipe or fixed system; In respect of b) above, We only pay up to $10,000 for any one claim. Case No: 409183 Determination Page 6 of 6 7. Cracking (other than Cracking of a bath tub, shower recess, wash basin, bench top, sink, toilet bowl, cistern or stove top), chipping (other than chipping of a bench top or stove top) splitting, tearing, scratching or denting, unless directly caused by fire, lightning, earthquake, Storm, explosion, burglary, theft, vandalism or impact by a vehicle or aircraft. Additional benefits Escape of liquid If liquid overflows, leaks or bursts from a fixed system at your Home during the Period of Insurance and damages or is likely to damage insured property, we pay for the reasonable cost to investigate the cause of damage or likely damage. We pay up to $2,500 for this benefit. We do not pay to repair or replace any faulty part identified by the investigation but we pay to repair any damage directly caused by the investigation. We only pay this benefit if „Building‟ is shown on the Certificate of Insurance.‟ 3.3 All other relevant material considered and relied upon  Parties‟ submissions.  Correspondence between the parties.  Insurance schedule.  Water consumption records.  Water account.  Plumber‟s invoice.  Quote from builder.  Engineer‟s report dated 26 January 2015 and email written in response to email dated 20 August 2015.  Assessor‟s reports (4).