Home / Financial Firm (Unknown - Credit) / Determination 405848

Determination 405848

Progress payments released to builder and loan information disclosed to builder without authority

FirmFinancial Firm (Unknown - Credit)
Decided2015-12-04
ProductCredit · Other credit
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant said the FSP disclosed his loan approval to his builder and released construction progress payments without his authority. AFCA found the disclosure and payments were authorised and caused no loss, so no compensation was ordered.

The FSP was entitled to rely on the signed progress claim certificate and the complainant's phone confirmation, and it owed no fiduciary duty over the building works.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 405848 Determination Page 1 of 5 Case number: 405848 4 Dec ember 2015 1 Overview 1.1 Dispute On 20 July 2014, the FSP provided the Applicant with a loan for $472,200 (the Loan). The purpose of the Loan was to repay an existing loan which was used to purchase land, and to build a house on the land. After the Loan was approved and the construction began, the Applicant fell into dispute with his builder. The Applicant says the FSP contributed to the dispute with his builder by breaching his privacy and releasing payments to the builder when the works were not properly completed. The Case Analyst provided the parties with a Recommendation on the issues in dispute. The Recommendation was in favour of the FSP. A copy of the Recommendation is attached to this Determination. 1.2 Issues and Key findings Were the findings of the Recommendation correct? The findings contained in the Recommendation were correct and are adopted in this Determination. Further submissions provided after the Recommendation have been considered, inclusive of the Applicant‟s most recentl y supplied email records. In the Applicant‟s rejection of the Recommendation, he says that the documents he has provided show that the FSP has lied about what authority he provided for the release of his private information, as well as what authority he provided for the release of progress payments. Did the FSP breach the Applicant’s privacy? The Applicant says that he never gave the FSP authority to provide a copy of the unconditional approval letter dated 20 July 2014 (the Approval Letter) to his builder. The Applicant refers to the FSP‟s email from 28 November 2014, in which an FSP officer told him that the FSP would be breaching his privacy by sending any “funding information” to his builder. It is my view based upon the available information that the Applicant authorised the FSP to provide his builder with information about his capacity to pay for the construction of his house. The information provided by the FSP to the builder was directly relevant to the Applicant‟s capacity to pay and did not disclose otherwise irrelevant information. Case No: 405848 Determination Page 2 of 5 Did the FSP release progress payments without authority? The Applicant says the FSP was aware of his dispute with his builder, and that the builder had submitted a variation to the building permit. The Applicant says he voiced his concern to the FSP in an email dated 9 November 2014, but the FSP still proceeded to process the base stage progress payments to the builder in accordance with the signed Progress Claim Certificate. I am satisfied, based on the information presented by the parties, that the FSP did not make any comments or assertions to the Applicant to the effect that it was conducting a valuation of the construction in order to protect his interests. I accept that the Applicant interpreted the FSP‟s actions in obtaining the inspection and valuation (after he had by email raised concerns about his builder and the variations) to be for his benefit – however the materials available do not show that FSP made a representation to that effect. Rather, the FSP merely informed the Applicant that it had sent the variations and building permits through to its valuer, and had arranged an inspection and valuation. In the same correspondence, the Applicant sought advice from the FSP regarding making a complaint about his builder to the relevant building reg ulatory body and the FSP declined to provide any advice. In the context of the communications between the parties I can understand why the Applicant formed the view that he did regarding the inspection and valuation, but cannot find that the FSP was responsible for him forming that view. I accept that the FSP obtained the valuation and inspection for its own purposes only. The available information in this dispute also supports the Case Analyst‟s conclusion in the Recommendation that the Applicant authorised all progress payments that were paid. I accept however that, contrary to initial assertions, the FSP was aware that the Applicant was unhappy with his builder ‟s error regarding the footings (which the builder had agreed to address) and had requested that payments be individually cleared or checked with him prior to his pre-signed authority forms for the progress payments being relied upon to process those payments. That said, the available information in this dispute supports a conclusion - on the balance of probabilities - that on 13 November 2014, the FSP spoke to the Applicant and confirmed that he was happy for the invoice for the base stage of construction to be paid to the builder pursuant to the payment authority form (Progress Claim Certificate) that he had earlier signed. 1.3 Determination This Determination is in favour of the FSP. I agree with the Case Analyst‟s reasons for the Recommendation and the recommended outcome. The FSP is not required to compensate the Applicant. Case No: 405848 Determination Page 3 of 5 2 Reasons for Determination 2.1 Were the findings in the Recommendation correct? I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the Recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied that the Case Analyst‟s Recommendation contains an accurate summary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. 2.2 Did the FSP breach the Applicant’s privacy? There was no breach of privacy The Applicant says he provided verbal instructions to two separate staff at the local branch of the FSP to send information about his capacity to pay to his builder. These instructions were also provided in writing in an email from 27 November 2014. The FSP responded advising it would have breached the Applicant‟s privacy if it provided in formation to his builder which was irrelevant to the Applicant‟s capacity to pay. The FSP‟s response regarding the Applicant‟s privacy had the potential to cause confusion, and could have been better worded – however it did not cause the Applicant to suffer a loss. Pursuant to the Applicant‟s instructions, the FSP supplied the builder with a copy of an „ Approval Letter ‟ which indicated that lending of $472,200 had been approved to the Applicant: This would have provided sufficient information to the builder about the Applicant‟s capacity to pay for the building works. I do not consider the contents of the Approval Letter to have disclosed information which was irrelevant to the Applicant‟s capacity to pay. Rather, the information provided was relevant for the purpose for which it was authorised to be disclosed. I am satisfied that on the facts before me, the FSP complied with its obligations under the Privacy Act 1988 and Australian Privacy Principle 6 in providing the information that it did to the builder. The Applicant did not incur any loss as a result of the disclosure Even if it were accepted that the Applicant‟s privacy was breached (which on the available information I do not accept), the information provided by the Applicant shows that his builder would have proceeded with legal proceedings to obtain the necessary information (concerning his capacity to pay) from him. This is evident from the builder‟s legal claim from 10 December 2014 in which information about the Applicant‟s capacity to pay was sought. The Applicant has not identified how he has incurred any loss as a result of the FSP providing the information to his builder. Case No: 405848 Determination Page 4 of 5 2.3 Did the FSP release progress payments without authority? The Applicant informed the FSP of a variation to the building contract In an email dated 9 November 2014, the Applicant wrote to the FSP informing it that due to an error made by his builder, a variation to the building contract had to be submitted. The variation related to the bearers used under the floor of the house. Attached to the email was an amended building permit, the builder‟s variation, a signed Progress Claim Certificate and the builder‟s claim form for the base stage progress payment. Of particular importance is the following extract from the Applicant‟s email: “However the fixing of the bearer to the stumps is still an issue which will need to be resolved before the framing progress payment is made. I have attached an amended permit for your inspection. My ongoing concern is that the house exceeds its valuation and if it fails to do so then the Builder pays the difference. However, I have no idea how this is managed by the bank, perhaps you could offer some advice?” The builder‟s variation made it clear there would be no delay in the variations being implemented and the variations would be made at no cost to the Applicant. In response, the FSP sent an email on 10 November 2014 saying it was ordering an inspection and that it had sent the variations and permits through to its valuer for the purposes of obtaining a valuation . The FSP‟s response addressed the Applicant‟s concern about the valuation of the property and how this would be managed by the FSP. I am satisfied the FSP did not make any statements in its response to the Applicant that it would take steps to protect his interests . I am satisfied that the FSP obtained the inspection and valuation to protect its own interests. The FSP conducts valuations for its own credit assessment purposes In accordan ce with the FSP‟s policy on funding construction loans, a valuation is conducted at the first and final building stage. Acting in accordance with its own policy, the FSP conducted a base stage valuation of the property to ensure the construction met its credit assessment criteria. In the absence of assurances given by the FSP, the builder‟s adherence to the fixed price building contract and other building standards was the Applicant‟s responsibility. As the Case Analyst noted in the Recommendation for this dispute, the FSP did not obtain a valuation to ensure that construction was in accordance with the Applicant‟s building contract or expectations. It was the Applicant‟s responsibility to ensure that the builder was constructing his house in accordance with the building contract and plans; the FSP owed him no fiduciary duty in this regard. The Applicant authorised the release of the base stage progress payment The Applicant says he did not call the FSP on 13 November 2014 to agree to have the base claim pai d, and he believes the FSP‟s telephone log does not represent a contemporaneous note. The Applicant has not provided any information, other than his recollection, to support his claim that the telephone log is inaccurate. The Applicant has claimed that the FSP should be able to provide a recording of the call. Case No: 405848 Determination Page 5 of 5 I accept that no recording of the call exists and note that in my experience only calls to certain departments of financial service providers are recorded automatically – despite the generic warning that calls may be recorded. It is common place for calls to branch staff not to be recorded and for the existence and content of calls to those staff to only be recorded in contemporaneous system file notes by financial services providers – as is the case here. I am satisfied that based on the documents provided, the FSP‟s telephone log is the most accurate information available. It is not apparent from the available documents that the FSP has changed the telephone logs, and therefore I place more weight o n the FSP‟s telephone logs than the Applicant‟s recollections . I accept the Applicant authorised the release of the base stage progress payment by way of the Progress Claim Certificate that he signed coupled with his authorisation over the phone (on 13 November 2014) that the signed certificate could be relied upon and that he was happy for payment of the base stage of construction to proceed. I n accordance with the Applicant‟s request, the FSP did check that he was happy to make payment for the base stage of construction. That progress payment was made on 19 November 2014. Whilst confirmation that the Applicant‟s signed Progress Claim Certificate could be relied upon (to pay the builder‟s invoice) was sought by the FSP from the Applicant over the phone rather than in writing, I do not consider this to be of significance. On balance I am satisfied that the payment was authorised by the Applicant for the base stage of construction: Absent any information showing that the Applicant had revoked his authority for that payment to be made between 13 and 19 November 2014, the FSP was entitled to rely upon the Applicant‟s signed Progress Claim Certificate and phone confirmation (on 13 November 2014) from him (that payment of the invoice for the base stage of construction was authorised) – in paying the builder‟s invoice for the base stage of construction on 19 November 2014. Recommendation Case No: 405848 Recommendation Page 1 of 6 Case number : 405848 28 September 2015 3 Overview 3.1 Dispute On 20 July 2014, the FSP provided the Applicant with a loan for $472,200 (the Loan). The purpose of the Loan was to repay an existing loan which was used to purchase land, and to build a house on the land. After the Loan was approved and the construction began, the Applicant fell into dispute with his builder. The Applicant says the FSP contributed to the dispute with his builder by breaching his privacy and releasing payments to the builder when the works were not properly completed. 3.2 Issues and key findings Did the FSP breach the Applicant’s privacy ? The FSP did not breach the Applicant‟s privacy. The Applicant authorised the FSP to release information to his builder about his capacity to pay. The release of this information did not cause the Applicant to incur any loss. Did the FSP release progress payments without authority? The Applicant authorised the FSP to release progress payments to his builder for the construction of his house. The FSP had no obligation to ensure that the works were completed in accordance with the contract between the Applicant and his builder. Any valuation completed by the FSP was for its own purpose as lender. 3.3 Recommendation This Recommendation is in favour of the FSP. The FSP did not act inappropriately or breach an obligation owed to the Applicant. The FSP is not required to compensate the Applicant. Case No: 405848 Recommendation Page 2 of 6 4 Reasons for Recommendation 4.1 Did the FSP breach the Applicant’s privacy ? The information does not show there was a breach of privacy Under the Privacy Act 1988 and Australian Privacy Principle 6, a breach of privacy does not occur where an individual authorises the disclosure of personal information. The Applicant‟s builder asked him to show his capacity to pay for the construction works. The Applicant says he gave verbal authority to the FSP branch manager to send information to the builder. The Applicant says he did not give instructions about what specific information he authorised the bank manager to send, as he was not familiar with what was required in the situation. On 8 December 2014, the FSP branch manager sent the Applicant‟s builder a copy of the FSP‟s unconditional approval letter dated 20 July 2014 (the Approval Letter). The information sent by the bank manager was relevant to, and satisfied the q uestion of, the Applicant‟s capacity to pay, and did not disclose any other irrelevant information. The FSP has not breached the Applicant‟s privacy because he gave his consent for the FSP to provide the information to the builder. The Applicant did not suffer any loss as a result of the disclosure The FSP‟s disclosure of the Applicant‟s approved loan of $472,200 did not cause the Applicant to incur any financial loss. The builder initiated legal proceedings against the Applicant on 10 December 2014. The builder claimed the Applicant had not made a progress payment of $50,578.50 as he was required to, and had not provided evidence of his capacity to pay. The Applicant has claimed that his legal costs have been incurred as a result of the FSP‟s disclosure. However, the claim lodged by the builder is not related to the information disclosed by the FSP. If anything, the FSP‟s disclosure should have prevented the second part of the builder‟s legal claim. As a result, the FSP is not liable to compensate the Appl icant‟s legal costs for defending the builder‟s claim. 4.2 Did the FSP release progress payments without authority? The FSP does not have a legal obligation to act in the Applicant’s best interest In general, a bank or credit provider does not have a „fiduciary‟ duty or responsibility to its customer. This means that it is not obliged to advise a customer about what is in their best interest. A fiduciary responsibility arises only where the FSP provides advice or otherwise causes the customer to reasonably believe that the FSP has assumed that responsibility. When the Applicant signed the loan contract for $472,200, he agreed to be bound by the terms of the contract, including the applicable terms and conditions. The FSP‟s terms and conditions clearly disclose that it is not responsible for any aspect of the construction works, and that any valuation it obtains, is for its own purpose. The correspondence provided shows the FSP did not make any statements to the effect Case No: 405848 Recommendation Page 3 of 6 that it would conduct inspections of the bu ilding works to protect the Applicant‟s interests. The FSP conducted a valuation for its own purpose In accordance with the FSP‟s internal policy for drawing progress payments, it obtained a valuation of the construction at the base construction stage. The valuation was entirely for the FSP‟s own benefit; to ensure it had adequate security for the funds it was going to release. The FSP‟s valuation was not to ensure that the construction was in accordance with the Applicant‟s building contract, engineer‟s pl ans or that it met the standards required by the Applicant. Rather, as stated in the terms and conditions, it was the Applicant‟s responsibility to make sure the builder was constructing his house in accordance with the building contract and plans. The Applicant authorised the release of progress payments The Applicant says the FSP asked him to pre - sign “Progress Claim Certificates”, and assured him progress payments would only be released if construction works met the FSP‟s independent valuation. A timeline of the parties‟ relevant correspondence is set out at 3.2 of this Recommendation. The FSP has provided “Progress Claim Certificates” signed by the Applicant, as well as the corresponding building invoices. Progress payments were released for the deposit, base and frame stages of the construction in accordance with the signed “Progress Claim Certificates”. The amounts released correspond with the signed building contract. The FSP‟s internal contact notes show that on 13 November 2014, after the Applicant had signed the “Progress Claim Certificate” for the base stage construction, he returned the FSP‟s telephone call and said that he was happy for the base stage payment to be released. There is no information to show that the Applicant did not authorise the progress payments released by the FSP in November and December 2014, or that he was concerned about the released payments at any stage prior to April 2015. Therefore, the FSP is not required to compensate the Applicant for the progress payments paid. A timeline of the various progress payments made is set out at 3.3 of this Recommendation Case No: 405848 Recommendation Page 4 of 6 5 Supporting information 5.1 Information relied upon for this Recommendation  The Applicant‟s and FSP‟s written submissions  The Applicant‟s signed loan contract, the loan state ments and the loan terms and conditions  Construction invoices and signed “Progress Claim Certificates”  The FSP‟s loan approval letter dated 20 July 2014  The FSP‟s internal file notes  Email correspondence between the parties  Legal claim lodged by the Applicant‟s builder  The FSP‟s internal policy for drawing progress payments 5.2 Timeline of the parties’ correspondence Date Correspondence Content 26/9/14 Applicant ‟s email Applicant says he has received an invoice from the builder for approximately $33,000 . There is a dispute with the builder about the base stage construction, which the Applicant says is incomplete. The Applicant says that whilst the FSP has asked him to pre - sign progress payments, he now revokes this and requests that all future payments a re signed by him before they are actioned. 26/9/14 FSP‟s email The FSP confirms no authorisations have been sent for the invoice as it is waiting on building permits. The FSP said it would send progress draw payments in the mail so that the Applicant can supply them directly. 13/11/14 Applicant‟s telephone call FSP says Applicant returned its call and said he is happy for it to pay the base claim. FSP notes it will need to review its valuation first. 23/4/15 FSP‟s email FSP seeking an update on the construction progress. 27/4/15 Applicant‟s email Applicant advised the build is still progressing through court. Applicant asked what the outcome of the FSP‟s valuation from November 2014 was. 27/4/15 FSP‟s email FSP advised valuation was completed on the base stage in November 2014. It also asked if the Applicant was using a new builder. 27/4/15 Applicant‟s email Applicant says subsequent inspections have shown that Case No: 405848 Recommendation Page 5 of 6 the base stage was not completed. He asked for further details about the FSP‟s valuati on to be forwarded to him. 28/4/15 FSP‟s email FSP says its inspectors only confirmed the slab was down. 10/5/15 Applicant‟s email Applicant asks the FSP to confirm that its inspectors confirmed “the 'base' was complete” . 11/5/15 FSP‟s email FSP only confirms the base was complete. 7/7/15 Applicant‟s email Applicant provides an inspection report commissioned by him. He says the base stage is far from complete and asks the FSP how it will be compensating him for its errors. 7/7/15 FSP‟s email FSP says its valuers do not confirm that council regulations are met. Its valuers merely confirm that there is a slab base on site. FSP says the Applicant signed a progress claim certificate on 18/11/14 authorising the release of the payment and therefore will not provide a refund. 5.3 Timeline of progress payments Progress payment stage Amount Invoice date Date progress claim certificate signed Date invoice paid Deposit stage $16,859.50 13/5/14 15/8/14 29/8/14 Base stage $33,719 30/10/14 2/11/14 19/11/14 Frame stage $50,578.50 21/11/14 22/11/14 24/12/14 Lock up stage $118,016.50 Has not been invoiced or paid Fixing stage $84,297.50 Has not been invoiced or paid Final stage $33,719 Has not been invoiced or paid 5.4 Extracts from the FSP’s loan terms and conditions Terms and conditions relied upon in section 2.2 of this Recommendation: “ How we provide a home loan with building loan conditions … 2.3 (h) We are not responsible for the supervision of the building or any aspect of the building work, even thoug h we may approve an alteration to or inspect the building.” and; “ 16. Security Case No: 405848 Recommendation Page 6 of 6 … 16.2 Any property valuation is for our use only. We are not responsible for any reliance on a property valuation by you or any other person.” Yours sincerely,

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.