Home / Financial Firm (Unknown - Insurer) / Determination 404520

Determination 404520

Ongoing water entry after hail storm roof repairs; FSP liability for further damage denied

FirmFinancial Firm (Unknown - Insurer)
Decided2016-07-06
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$500
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant alleged that inadequate roof repairs after a 2010 hail storm caused ongoing water damage and sought further rectification. AFCA found most water damage was due to maintenance issues or later works, but ordered the FSP to pay $500 for unfinished veranda repainting and to re-attend to the air conditioning unit repairs.

The insurer is only liable for damage caused by the insured event or its repairers, and the applicant did not show that the later water damage was linked to the hail storm or the repairs, though outstanding minor repairs were owed.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 404520 Determination Page 1 of 7 Case number: 404520 7 June 2016 1 Overview 1.1 Dispute The applicant lodged a claim under her home insurance policy with the financial services provider (FSP) for damage to her home following a hail storm in March 2010. The FSP accepted the claim and arranged for its builder (P) to repair the home. In March 2014, the applicant notified the FSP of further water damage to her home which she considered had been caused by the poor quality of the initial repairs. The FSP accepted liability for some (but not all) of this damage and arranged for a second builder (M) to carry out further repairs. However, the applicant says the FSP has failed to fully rectify the issues with the initial repairs and her home is still suffering from ongoing water entry issues. 1.2 Issues and key findings Is the FSP required to rectify the previous repairs? The available information does not establish that the ongoing water entry issues at the applicant’s property are related t o the hail storm in 2010 or the subsequent actions of the FSP’s contractors. Accordingly, the FSP is not liable for repairing this damage under the existing claims. However, the FSP is required to attend to minor outstanding issues relating to the 2010 repairs, namely the repainting of the front veranda ceiling and the replacement of the damaged cover panels and filters for the roof-mounted air conditioning unit. 1.3 Determination This determination is substantially in favour of the FSP. The FSP is required to pay the applicant the amount of $500 in respect of the repainting of the front veranda ceiling. The FSP is also required to re-attend the property to confirm whether the repairs to the roof-mounted air conditioning unit have been carried out. The FSP is not otherwise liable for any further amounts in respect of the claims lodged by the applicant in 2010 and 2014. Case No: 404520 Determination Page 2 of 7 2 Reasons for determination 2.1 Is the FSP required to rectify the previous repairs? Dispute concerns adequacy of roof repairs The applicant says the repairs to the roof of her property carried out by the FSP’s contractors following the hail storm in March 2010 were inadequate and have resulted in ongoing water damage. In particular, the applicant says the FSP’s contractors attempted to seal the bro ken and chipped roof tiles with silicon sealant (when the tiles should have been replaced) and failed to repair all of the hail damage to the roof. During the course of this dispute, the applicant has raised concerns about water damage in a number of different areas of the property, including:  the living room ceiling;  her son’s upstairs bedroom;  the front veranda ceiling; and  the eaves lining. Accordingly, it is necessary to determine whether each of the items of damage raised by the applicant have been caused by the hail storm in March 2010 and/or the subsequent actions of the FSP’s contractors. FSP authorised rectification repairs in mid-2014 The hail storm in March 2010 caused impact damage to the applicant’s roof, as well as internal water damage to areas including the living room and one of the upstairs bedrooms. The FSP appointed a builder (P) who engaged a roofer to undertake an inspection of the roof to determine the extent of the damage to the terra cotta roofing tiles. Following this inspection, the FSP approved the replacement of 50 damaged roof tiles and the rebedding and repointing of approximately 30 metres of capping tiles. The FSP’s records indicate that the repairs were finalised and the claim closed in May 2011. The applicant says she has experienced ongoing water entry issues following completion of the repairs and has called the FSP on numerous occasions to complain. However, the FSP’s claim notes do not record any calls from the applicant between May 2011 and March 2014. The FSP’s claim notes indicate that the applicant called the FSP in early March 2014 to advise that her painter had noticed damage to an area of roof tiles towards the front of the house, as well as unrepaired damage to the roof-mounted air conditioning unit. In response to the applicant’s concerns, the FSP appointed a builder (M) to inspect the roof and identify any ongoing water entry issues. Case No: 404520 Determination Page 3 of 7 M attended the property in the company of the applicant and identified water damage to the plaster ceiling of the front veranda. M advised that this damage had been caused by rainwater entering through damaged roof tiles located beside the porch hip capping and behind the gable roof. Based on the photographs of the damaged tiles contained in M’s report, it appears likely that the damage to these tiles was overlooked by P during the course of the initial repairs. M also identified an area of broken tiles below the areas of the ridge capping which had been rebedded and repointed by P as part of the original repairs. M considered i t likely that the tiles in this area had been inadvertently damaged by foot traffic while P was carrying out these repairs. M also noted that hail damage to the cover panels and filters on the roof-mounted air conditioning unit had not been repaired as part of the original repairs. The FSP accepted liability for the repair of the damaged roof tiles identified by M and the replacement of the damaged cover panels and filters of the air conditioning unit. The FSP authorised M to carry out repairs to these items in accordance with a quotation for $4,857.38 provided in March 2014. In his report, M also identified maintenance issues with the applicant’s roof, including cracking in the lead flashing and cement bedding. M advised that these issues needed to be addressed by the applicant in order to prevent further water entry. In June 2014, the applicant’s roofer (T ) rebedded and repointed all of the roof capping, installed a whirly bird and replaced chipped tiles near the gutter line. Applicant reported further water entry issues in 2015 In March 2015, the applicant contacted the FSP to advise of ongoing leaks to t he living room and the veranda, which had caused water damage to the ceilings in these areas. The FSP arranged for its builder (M) and building consultant (S) to reinspect the property. Based on their reports, the FSP denied liability for the additional water damage on the basis that it had not been caused by the hail storm in 2010 or the subsequent actions of the FSP’s contractors. When the applicant lodged her dispute with FOS in June 2015, she advised of additional damage to her son’s bedroom on the uppe r level of the property. FSP is not liable for damage to the living room ceiling Based on the available information, I am not satisfied that the additional water damage at the applicant’s property is related to the hail storm in March 201 0 or the subseque nt repairs carried out by the FSP’s contractor. The information provided indicates that the water damage to the living room ceiling occurred between the separate inspections carried out by the FSP’s builder (M) in March 2014 and March 2015 respectively. Case No: 404520 Determination Page 4 of 7 The FSP’s claim records from March 2014 do not indicate that the applicant advised of any damage to the living room ceiling at this time, Further, M’s report dated 5 March 2014 does not refer to any such damage, despite his inspection having been carried o ut in the applicant’s presence. However, photographs included in M’s second report (following his reinspection of the property twelve months later) clearly show the water damage to the living room ceiling and the cracked tile directly above. In his report, M concluded that the damage to the roof tile above the living room had been caused by foot traffic. M’s view was confirmed by the FSP’s building consultant (S) who inspected the damage in April 2015. The applicant has not provided any independent information (for example, a report from her own roofer) which refutes the findings of the FSP’s contractors. Given the timing and location of the damage to the roof tile, I consider that, on the balance of probabilities, this damage occurred during the maintenance works carried out by the applicant’s repairer (T) in June 2014. On that basis, the FSP is not responsible for the resultant water damage to the lounge room ceiling. FSP is not liable for water damage to veranda ceiling and eaves In his March 2015 repo rt, the FSP’s builder (M) states that the damage to the ceiling of the front veranda had occurred as a result of water entry through the point of intersection between the gable roof lead flashing, the metal soaker tray and the roof tiles. M’s report includ es a close-up photograph of this area. M recommended that the lead flashing be repaired or additional flashing installed in order to prevent the backflow of water from the soaker into the ceiling cavity during periods of heavy rainfall. Based on the findin gs of M’s report (and the photographs contained therein), I am satisfied that the damage to the veranda ceiling was caused by maintenance issues, and not by the 2010 storm or the subsequent actions of the FSP’s repairers. Accordingly, the FSP is not liable for this damage. The reports provided by the FSP’s contractors (M and S) indicate that the water staining to the eaves was caused by water overflowing from the lowest point of the fascia gutters during periods of heavy rainfall, exacerbated by the accumulation of the leaf debris. M recommended that overflow holes be drilled into the gutters to allow the water to escape. As the cause of damage to the eaves is a maintenance issue, the FSP is not liable for this damage. Additional water entry issues are not related to 2010 claim In addition to the issues outlined above, the applicant has provided photographs of water damage to her son’s bedroom on the upper level of the property. Case No: 404520 Determination Page 5 of 7 The applicant says this area has been an ongoing problem since the 2010 hail sto rm and she has been in constant contact with the FSP about this and other issues. However, the FSP’s claim records do not include any reference to this area of damage and it does not appear have been mentioned by the applicant when she notified the FSP of additional water damage in March 2014 and March 2015. As noted above, there is no record on the claim file of any contact between May 2011 and March 2014. Further, neither M nor S mentioned damage to the upstairs bedroom following their inspection of the property in March and April 2015, despite both inspections having been undertaken in the applicant’s presence. It is relevant to note that the FSP’s records do include references to other areas of water damage (namely damage to the bathroom and the kitchen ceiling underneath) which the applicant raised with the FSP in August 2014. This damage was investigated by the FSP and determined to have been caused by water leaking from the bathroom shower, which is excluded under the policy. In the absence of any independent information confirming when the water damage to the applicant’s son’s bedroom commenced, I am not satisfied that this damage is related to the hail storm in 2010 or the subsequent repairs carried out by the FSP’s contractors. The FSP has offered to reconsider its liability for this damage, if the applicant lodges a separate claim under the policy. Available information does not establish roof repairs were inadequate The applicant says the roof repairs carried out by the FSP’s repairers (P and M) we re inadequate. She says the repairers refused to replace the damaged roof tiles and attempted to repair them with silicone only. As outlined above, following M’s inspection of the roof in March 2014, the FSP accepted liability for replacing a small area of damaged roof tiles which M considered had most likely been damaged (or missed) during the repairs carried out by the FSP’s initial builder (P). These tiles were replaced in June 2014. The applicant has provided photographs showing some cracked and chipped roof tiles. However, it is unclear when these photographs were taken and therefore when the relevant damage occurred (particularly in light of the applicant’s comments that the damage to these tiles has already been assessed by the FSP’s contractors). The applicant has been unable to obtain a report from her own repairer (T) providing any further information about the cause of damage to the tiles he replaced in June 2014. Nor has the applicant provided any other expert reports indicating that the FSP’s rep airs were inadequate. In these circumstances, and given the time which has elapsed since the hail storm in 2010, I consider that the information provided by the applicant is not sufficient to establish that the repairs carried out by the FSP’s contractors were inadequate. Case No: 404520 Determination Page 6 of 7 I note that the FSP has offered to consider its potential liability for any additional damage to the property, subject to the applicant lodging a separate claim. FSP is required to address minor issues regarding 2010 repairs As outlined above, when M inspected the property in March 2014, he advised that there was hail damage to the roof-mounted air conditioning unit which had not been repaired. This damage is apparent in the photographs included in M’s report and was included in the scope of works heh prepared at the time. However, when the FSP’s building consultant (S) attended the property in April 2015, he advised that the air conditioning unit had not been repaired. In subsequent correspondence, M confirmed that the cover panels and filters were replaced on 23 August 2014. M also advised that he had spoken to S who admitted that he did access the second storey roof to inspect the air conditioning unit. However, the FSP has not provided any information from S confirming this. Given the conflicting reports provided by M and S, I consider that the FSP should be required to re-attend the premises and confirm that the hail damage to the air conditioning unit has been rectified (and if not, to arrange for the necessary works). The available information also indicates that the repainting of the veranda ceiling (included in M’s 2014 scope of works) was never completed. The FSP says the applicant was cash settled for this payment but has been unable to provide any evidence of this (possibly because the payment was to be made directly by the relevant contractor, rather than by the FSP itself). In these circumstances, I am not satisfied that the applicant has been properly compensated for the cost of the repainting. Accordingly, the FSP should pay the applicant the amount of $500 for these works. Case No: 404520 Determination Page 7 of 7 3 Supporting information 3.1 FOS approach to this dispute FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS preliminary view and has proceeded directly to determination. This case has been decided on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues which are considered directly relevant to the outcome only.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.