Home / Financial Firm (Unknown - Insurer) / Determination 403719

Determination 403719

Additional loss of rent declined after hail storm damage to rental property

FirmFinancial Firm (Unknown - Insurer)
Decided2016-06-14
ProductGeneral Insurance · Landlord
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A landlord claimed additional loss of rent after a hail storm damaged his rental property and the tenant did not return. AFCA found the property was unsafe during the repair period and ordered loss of rent payment with interest, but found it was safe between 11 December 2014 and 28 January 2015.

The policy covers loss of rent while the tenant cannot safely reside in the building because of the damage, and the property was unsafe during the final repairs but not in the interim period.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 403719 Determination Page 1 of 5 Case number: 403719 10 June 2016 1 Overview 1.1 Dispute The applicant lodged a claim with the financial services provider (FSP) for damage to the roof and internal ceilings of his rental property as a result of a hail storm. The FSP authorised repairs and required the tenant to vacate the property between 27 November and 10 December 2014, during the period the electricity was disconnected while the roof was repaired. The FSP accepts it is liable for loss of rent for this period only. The FSP denied the applicant‟s claim for additional loss of rent while furthe r repairs were being undertaken. 1.2 Issues and key findings Is the FSP required to pay the applicant any additional loss of rent? The FSP is required to pay the applicant for loss of rent during the period of repair, being 29 January 2015 to 13 February 2015 because:  the policy provides cover for loss of rent while the tenant cannot safely reside at the property  the replacement of the entire ceiling in the kitchen and dining room as well as removal of all contents in these rooms rendered the building unsafe during the period of repair. 1.3 Determination This determination is substantially in favour of the applicant. If it has not already done so, the FSP must compensate the applicant for loss of rent from 27 November 2014 to 10 December 2014 in accordance with the terms of the policy. No interest is payable on this amount. The FSP must also compensate the applicant for loss of rent for the period 29 January 2015 to 13 February 2015 in accordance with the terms and conditions of the policy. Interest is payable on this amount in accordance with the Insurance Contracts Act from 23 July 2015 to the date payment is made. Case No: 403719 Determination Page 2 of 5 2 Reasons for determination 2.1 Is the FSP required to pay the applicant any additional loss of rent? The a pplicant’s policy provides cover for loss of rent The applicant lodged a claim under his landlord insurance policy, which amongst other benefits, provides cover for loss of rent as follows: “When your building is insured and we accept a claim, and agree that your tenant cannot safely reside in the building becaus e of the damaged caused, we will pay the actual rent you lose while your building is being repaired or rebuilt.” The issue in dispute is whether the property was unsafe to live in once the power was reconnected on 10 December 2014 and before the repairs were complete on 13 February 2015. The tenants were required to vacate the property The FSP appointed an assessor, CA, to attend the property and determine whether the claim was one for accepting. CA found damage to the dining room, kitchen and roof, which required urgent repairs. CA noted: we have arranged for all hail damaged roof tiles to be replaced and pointing repaired as an urgent makesafe to mitigate extent of possible costs associated with loss of rent given tenant has been forced to move in to temporary accommodation due to the mains power connection be disconnected. Once roof has been repaired, electrician will be arranged to attend to re-connect primary installation and then contact [provider] for re-connection. The tenant can then move back in. [sic] The scope of works provided by CA identified that the tenants were required to move furniture and contents from the affected areas in order to provide clear access to facilitate repairs to the ceiling. The scope of works showed the entire ceiling in the kitchen and dining rooms required replacement, as well as replacing the cornices and lights. There was also some damage to the hallway noted in CA‟ s report. However, CA considered the tenants would not need to move out while the repairs were conducted. The tenants did not return after the storm The property had to be advertised as the tenants did not return after the storm. The applicant says he could not advertise the property before 6 February 2015. The a pplicant‟s real estate agent provi ded a statement in support of this. The property was unsafe during repairs The policy provides cover for loss of rent when the property is not safe to reside in. CA stated that the property could be lived in once power was reconnected. However, CA also noted that the contents of the kitchen and dining room would have to be moved while this occurred. Case No: 403719 Determination Page 3 of 5 „ Safe ‟ is defined in the Macquarie dictionary as, among other things:  free from danger or risk  involving no risk or mishap. I am not satisfied the property would have been safe to live in during the repairs given:  The ceilings needed replacing. This is necessarily hazardous for those occupying the premises at this time, including as a result of dust.  The kitchen appliances needed relocating and it would be difficult to connect and operate these in another room in a safe environment. This conclusion is based on the original statements of works provided by CA in November 2014. However, I note from the chronology provided by the FSP that this was negotiated with the applicant and a final SOW was not provided to the applicant until 22 December 2014. I have assumed that the final SOW was at least the same, if not more extensive, than the original SOW. I have also considered the numerous references provided by the applicant regarding the requisite compliance documents required from the builder to determine the works could be conducted in a safe environment. The FSP has noted that these are generic documents and in some cases not applicable to a domestic repair. Regardless, I am satisfied that due to the nature of the work required, the property would have been unsafe while the repairs were undertaken. As a result it would have been unreasonable to require the tenant to occupy the premises during the period of the repairs, even had the tenant been willing to do so. The property was safe for a period prior to the repairs being undertaken There is no evidence that once the initial make safe work had been undertaken, but prior to the final repairs commencing, that the property was not safe to be lived in. The FSP had repaired the roof, reconnected the power and make safe provisions had occurred to the property. This is for the period 11 December 2014 to 28 January 2015. That the tenants chose not to return after the storm is a matter as between the tenants and the applicant. The FSP‟s liability is limited to when rent was not received due to the property being unsafe. The FSP is required to pay additional loss of rent The FSP has accepted that it is required to compensate the applicant for loss of rent from 27 November 2014 until 10 December 2014. In addition, the FSP must compensate the applicant for loss of rent for the period 29 January 2015 to 13 February 2015 (when the repairs were complete), in accordance with the terms and conditions of the policy. Interest is payable on this additional amount in accordance with the Insurance Contracts Act from 23 July 2015 until the date payment in made. Case No: 403719 Determination Page 4 of 5 3 Supporting information 3.1 The FOS approach I have determined this dispute based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the Recommendation was issued. There has been a full exchange of all documents relied on to make this Determination and each party has had the opportunity to address any issues raised by the other. 3.2 Policy term Term You are no t covered for Cover limit Loss of rent following damage When your building is insured and we accept a claim, and agree that your tenant cannot safely reside in the building because of the damage caused, we will pay the actual rent you lose while your building is being repaired or rebuilt. Loss of rent:  Beyond the period it should reasonably take to repair or rebuild your building;  If your building has not been tenant ed for more than 60 consecutive days immediat ely before the loss or damage; or  If you d id not have a cont ract in place at the time of the claimed event for your building to be tenant ed within the 30 days immediat ely following the date of loss or damage. The lesser of:  12 mont hs rent; or  10% of your building sum insured; or  The actual rent you lose. 3.3 Chronology The following chronology was provided by the FSP, however the supporting documents, including claim notes, were not: Record Key points 19 November 2014  Date of storm 20 November 2014  Tenant notifies real estate agent of water affecting the kitchen roof 24 November 2014  Claim lodged 27 No vember 2014  Electricity was disconnected  Tenant vacat ed property Case No: 403719 Determination Page 5 of 5 28 November 2014  FSP‟s assessor inspected the damage  Damage noted to the ceiling in the kitchen and dining room 3 December 2014  FSP approves claim 4 December 2014  Cont ract and scope of works provided to applicant 5 – 15 December 2014  Scope of works negotiated 10 December 2014  Electricity reconnected  Tenant did not return to property  FSP offered loss of rent up until this da te only 22 Decem b e r 2014  Amended scope of works provided to applicant 21 January 2015  Signed contract and scope of works received by FSP 29 January 2015  Trades appointed to repair 6 February 2015  Applicant says he was a ble to start to readvertise the property to find a new tenant from this date. 13 February 2015  Repairs completed 5 June 2015  Applicant expressed dissatisfaction with loss of rent settlement 9 Ju ne 2015  Date original tenancy was due to expire 23 July 2 01 5  IDR respons e

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.