Home / Financial Firm (Unknown - Insurer) / Determination 403077
Determination 403077
claim_amount_dispute
Summary
The applicant disputed a $163,273 cash settlement for hail damage made worse by defective repairs and mould. AFCA found the settlement fair overall, ordered an extra $4,500 for follow-up mould testing and $3,000 for non-financial loss.
The cash settlement was a reasonable way to resolve a claim where the parties' relationship had broken down, but the FSP's deficient repairs and extended delay justified non-financial loss compensation.
Issues
- Claim amount dispute primary · not upheld“The Panel is satisfied that the cash settlement amount was fair and reasonable in the circumstances, subject to the issue discussed below.”
- Delay secondary · upheld“It has taken an excessive amount of time to resolve the applicant's claim for damage caused by the hail storm.”
- Repairs or contractors secondary · upheld“The repairs carried out by the FSP's builder were deficient and resulted in rainwater continuing to enter the property.”
Subjects and remedies
health or medicalhome or building damagenatural disasterpay claimpay non financial loss
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
Case No: 403077 Determination Page 1 of 9
Case number: 403077 23 May 2016
1 Overview
1.1 Dispute
The applicant lodged a claim under his home insurance policy with the financial
services provider (FSP) for damage to his home following a hail storm in 2011.
The FSP accepted the claim and made arrangements to repair the damage.
However, the repairs carried out by the FSP’s builder were inadequate and resulted
in further damage to the property, including mould growth.
The FSP has acknowledge d that additional repairs and remediation of the applicant’s
home and contents are required. In May 2015, the FSP cash settled the applicant for
$163,273, reflecting the estimated cost of the outstanding works plus an allowance
for temporary accommodation.
The applicant says the cash settlement paid by the FSP is not sufficient to address
all of the outstanding damage to his home and contents. He also seeks payment of
his ongoing costs for temporary accommodation and furniture rental, as well as
compensatio n for losses suffered due to the FSP’s handling of his claim.
1.2 Issues and key findings
Is the FSP required to increase the cash settlement amount?
The available information establishes that the FSP acted reasonably in determining
the cash settlement amount which is fair and reasonable overall, having regard to the
circumstances of the claim. However, the settlement amount should be increased by
$4,500 to allow for post-remediation mould testing.
Is the applicant entitled to compensation?
The applicant is entitled to compensation as he and his family have suffered stress
and inconvenience as a result of the FSP’s failure to promptly carry out the initial
repairs and take action to finalise the outstanding aspects of the claim.
1.3 Determination
This determination is partly in favour of the applicant.
Case No: 403077 Determination Page 2 of 9
The FSP is to increase the cash settlement amount of $163,273 by an additional
amount of $4,500. The FSP is to pay the applicant an additional amount of $3,000 as
compensation for non-financial loss.
Case No: 403077 Determination Page 3 of 9
2 Reasons for determination
2.1 Is the FSP required to increase the cash settlement amount?
FSP has acknowledged liability for damage arising from inadequate repairs
As outlined above, the FSP accepted the applicant’s claim for storm damage to his
home in December 2011 and arranged for the repair of the property (including the
replacement of a section of the roof).
The FSP has acknowledged that the repairs carried out by its builder (P) were
deficient and resulted in rainwater continuing to enter the property over an extended
period of time. The FSP also accepts that the ongoing entry of rainwater caused
further damage to the applicant’s home, including mould growth.
It is not clear when the mould issues with the property were first identified. However,
it appears that in mid-2013 the FSP engaged a microbiologist (Dr B) to inspect the
property and confirm whether there was a mould problem at the house and, if so,
what was causing it.
In his report of June 2013, Dr B confirmed that there was a significant mould problem
in the under floor area which was of significant concern to people entering that area.
However, Dr B found that the air within the house itself was not significantly
contaminated or hazardous to health, although there were patches of actively
growing mould in the office wardrobe and likely mould growth in some areas of the
carpet.
Dr B’s report did not clearly identify the cause of the mould issues, although he
indicated that the source of the problem was likely to be the under-floor area, as
moisture appeared to be entering the house through the timber floor and
plasterboard walls. Dr B noted that the applicant had advised him of a burst hot water
pipe which had resulted in water affecting the underfloor area.
Based on the information provided, it does not appear that the FSP identified (or
acknowledged) a possible link between the mould issues identified in June 2013 and
the repairs carried out in early 2012. It is also unclear what (if any) further action was
taken at this time.
In January 2014, the applicant obtained a report from his own microbiologist (Dr J)
which identified mould affecting various areas of the building, as well as contents
items at the property. Dr J considered that the mould issues were primarily
attributable to the inadequate roo f repairs carried out by the FSP’s contractor in
2012.
FSP cash settled claim after negotiations broke down
Following receipt of Dr J ’s initial report, the FSP installed HEPA filters at the property
in an attempt to remediate the mould issues.
Case No: 403077 Determination Page 4 of 9
However, a further report from Dr J in May 2014 concluded that the property
remained a health risk until a thorough mould assessment had been completed and
appropriate remediation measures implemented.
Between May 2014 and January 2015, the FSP and the applicant liaised with their
appointed experts to arrange for further mould testing at the property in order to
agree an appropriate mould remediation strategy.
The FSP agreed to fund temporary accommodation costs for the applicant and his
family, who moved out of the property due to the mould issues in early November
2014. The FSP also paid for the cost of renting replacement furniture, to address
concerns about mould contamination of the applicant’s existing furniture.
It is apparent from the information provided that there were differences between the
parties’ experts regarding the extent of mould contamination of the building and
contents, as well as the remediation strategies which should be implemented.
The parties initially worked together in good faith in an attempt to overcome these
differences and agree a way forward. However, in January 2015, these discussions
stalled, following a deterioration in the relationship between the parties.
During this period, the applicant raised concerns with the FSP about its handling of
his claim.
Following a review by its Internal Dispute Resolution (IDR) department, the FSP
decided to cash settle the applicant for a total of $163,273, in respect of all
outstanding liabilities relating to his claim (and the subsequent repairs).
The FSP prepared a deed of release in respect of the settlement, although it appears
the deed was never signed by the applicant, who was dissatisfied with the amount
offered and lodged a dispute with FOS.
FSP acted reasonably in deciding to cash settle claim
Having carefully reviewed the claim history, the Panel is satisfied that the FSP’s
approach of attempting to cash settle its outstanding liability for the claim (rather than
carry out repairs and remediation) was reasonable in the circumstances.
Despite repeated discussions over an extended period of time, the parties had been
unable to resolve their differences about the scope of the repairs and remediation
measures required. By early 2015, the relationship between the parties had
irretrievably broken down and the applicant had lost confidence in the process.
In these circumstances, the Panel considers that the only feasible manner in which
the dispute could be resolved was by way of a cash settlement.
However, in determining the amount of the cas h settlement, the FSP was required to
ensure that this amount was sufficient to allow the applicant to engage his own
contractor to repair the damage to his home and contents caused by the hail storm in
December 2011 and the subsequent repairs carried out by the FSP’s builder.
Accordingly, the Panel will now consider whether the cash settlement amount of
$163,273 paid by the FSP was fair and reasonable.
Case No: 403077 Determination Page 5 of 9
Cash settlement amount was made up of separate components
The cash settlement amount of $163,273 was made up of a number of separate
components, as set out in the following table.
Item Amount Basis for amount
Roof repairs $10,439 The estimated cost of rectifying the initial roof
repairs, based on quotation provided by the FSP’s
builder (RC) following an inspection of the property.
Floor repairs $5,850 The estimated cost of repairing water damage to
sections of the timber flooring based on a report
obtained by the FSP from a flooring specialist
identifying the damaged areas.
Replacement of
flooring
$44,490 The estimated cost of removing and replacing the
flooring in order to allow the concrete slab to dry
out , based on a quotation provided by the
applicant .
Mould remediation
of building
$26,500 The estimated cost of remediating the mould issues
with the building in accordance with the works
recommended by Dr B (which involved stripping out
the mould - affected building mat erials). This amount
was based on a desk - top estimate prepared by the
FSP’s building consultant after the FSP was unable
to gain further access to the property to enable a
quotation to be prepared.
Other repairs $19,088 The estimated cost of additional repairs incidental
to and consequent on the mould remediation and
structural repairs, based on quotations provided by
the applicant.
Mould remediation
of contents
$38,18 0 The e stimated cost of rem ediating all contents
items in mould - affected rooms (as ide ntified by Dr
B), based on a quotation provided by the FSP’s
restoration contractor (E). The FSP deducted from
E’s quotation the costs of undertaking tasks (such
as inventory and reporting) which would not be
required in the event the contractor was engage d
directly by the applicant rather than by the FSP .
Temporary
accommodation
$16,944 An a llowance for an additional six months
temporary accommodation while the repairs and
mould remediation measures were completed .
Vehicle storage $1,782 An allowance fo r alternative vehicle storage costs,
based on the estimate provided by the applicant.
Case No: 403077 Determination Page 6 of 9
The applicant has not provided details of the specific areas in which he considers the
cash settlement amount was insufficient, despite being provided with the opportunity
to do so on several occasions during the course of this dispute.
In the absence of a detailed submission from the applicant in this regard, the Panel
has reviewed the manner in which the cash settlement amount was determined, for
the purpose of considering whether it was fair and reasonable in the circumstances
Cash settlement amount was generally appropriate
As outlined above, the FSP took into account a range of information for the purpose
of determining the settlement amount, including reports and quotations provided by
the applicant himself.
The FSP also considered the numerous reports provided by the mould experts
appointed by the applicant and the FSP (Dr B and Dr J).
It appears that there were significant differences of opinion between the views
expressed by the mould experts. Among other matters, the experts appear to have
reached different conclusions about:
the degree of mould contamination present at the property;
the extent to which the mould issues were caused by the earlier storm damage
and inadequate repairs (as opposed to other factors); and
the methods which should be used to remediate the building and contents.
However, based on the information provided, the Panel is satisfied that the amounts
allowed for mould remediation were reasonable in the circumstances.
In this regard, the Panel notes that:
Dr B expressed concerns that the enzyme-based testing mechanisms used by Dr
J may result in false positives, given the enzyme was also present in skin cells
(as acknowledged by Dr J himself);
Dr J’s testing was undertaken based on a “hospital clean surface” standard rather
than the usual standard applied in the ordinary domestic environment;
both Dr B and Dr J identified other factors which may have contributed to the
mould contamination at the property, particularly given the different areas in
which mould and moisture issues were identified; and
the cash settlement amount proposed was based on stripping out the mould-
affected building materials, rather than chemically treating the affected areas.
Having carefully reviewed the available information, the Panel is satisfied that the
approach adopted by the FSP to calculate the cash settlement amount was
reasonable in the circumstances.
While there may be arguments which can be put fo rward as to the exact amount
which should have been allowed for each component, the Panel is satisfied that,
when considered in totality, the settlement amount was appropriate.
In this regard, the Panel notes that:
the amounts included for contents remediation were in addition to an earlier
payment of $20,000 (at the rate of $5,000 per person) to allow the applicant and
Case No: 403077 Determination Page 7 of 9
his family to replace clothing and other personal items while their own items were
decontaminated;
the applicant has not provided any information which shows that the additional six
months of temporary accommodation benefits included in the cash settlement
would not have allowed sufficient time for the repairs to be completed; and
the FSP has continued to fund the costs of temporary furniture rental pending the
resolution of this dispute, even though the costs of the applicant restoring his own
furniture were included in the settlement amount (and therefore rental furniture
should no longer be required).
The applicant has expressed concerns about the FSP having ceased to fund his
temporary accommodation costs following payment of the settlement amount.
However, given the settlement amount included an allowance for an additional six
months accommodation, the Panel is satisfied that, following payment of this amount,
the FSP was no longer required to fund the applicant’s ongoing temporary
accommodation costs.
For the reasons outlined above, the Panel is satisfied that the cash settlement
amount was fair and reasonable in the circumstances, subject to the issue discussed
below.
Cash settlement amount should be increased by $4,500
During the course of the dispute, the applicant requested that the cash settlement
amount be increased to allow for follow-up testing to be carried out on his home and
contents once the mould remediation measures had been completed, to confirm that
the remediation had been successful.
Given the overall circumstances of the claim, the Panel considers it is reasonable to
allow an additional amount of $4,500 for follow-up testing. The FSP is not required to
pay interest on this amount, as these costs do not appear to have been incurred by
the applicant to date.
2.2 Is the applicant entitled to compensation?
Applicant is entitled to compensation for non-financial loss
Under paragraph 9.3(b) of the Terms of Reference, FOS may award compensation
(capped at $3,000) for non-financial loss where an applicant has suffered an unusual
degree or extent of physical inconvenience, time taken to resolve the situation or
interference with their expectation of enjoyment or peace of mind.
As outlined above, it has taken an excessive amount of time to resolve the
applicant’s claim for damage caused by the hail storm. It is now over four and a half
years since the claim was first lodged.
The Panel is satisfied that the applicant and his family have suffered considerable
stress and inconvenience as a result of the initial inadequate repairs by the FSP’s
builder, as well as the extended delays in identifying the additional water damage
and mould growth.
Case No: 403077 Determination Page 8 of 9
The stress and inconvenience suffered by the applicant and his family have been
exacerbated by the fact that the applicant’s wife suffers from a health condition which
makes her particularly susceptible to mould. The family has also bee n displaced from
their home for an extended period of time.
The FSP has suggested that the applicant was responsible for some of the delays
which occurred during 2014. In particular, the FSP says it was waiting for the
applicant to provide a proposal to remediate mould in the building materials.
However, in circumstances where it was evident that the mould issues were at least
partly due to the earlier inadequate repairs carried out by the FSP, it is not clear why
the FSP did not take responsibility for addressing this issue itself.
The cash settlement paid by the FSP in May 2015 did not include any recognition of
the non-financial losses suffered by the applicant and his family as a result of the
inadequate repairs carried out by the FSP.
In these circumstances, the Panel considers that an award of compensation for non-
financial loss in the maximum amount of $3,000 is appropriate.
Case No: 403077 Determination Page 9 of 9
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a FOS Recommendation. Due to the nature
of the dispute, it has been referred directly to a Panel for Determination, in line with
the Operational Guidelines to the FOS Terms of Reference. The Panel consists of an
Ombudsman and two representatives with consumer and insurance experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous Financial Ombudsman
Service (FOS) decisions.
There has been a full exchange of all material information relied on for the purposes
of this Determination and each party has had the opportunity to address any issues
raised by the other.
The Panel has reviewed and considered all of the material provided by the parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this Determination, the Panel has restricted its commentary to those issues that it
considers directly relevant to the outcome only.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.