Determination 400444
Initial denial of storm damage claim and delay in accepting liability
Summary
The estate of a landlord complained that the FSP wrongly denied a storm damage claim and delayed accepting liability. AFCA ordered payment of $101,074 for repairs, carpets, cleaning and fencing, plus $3,300 consequential loss and $1,650 non-financial loss.
The FSP is liable for repair costs the applicant incurred because its unreasonable delay in accepting liability forced it to engage a builder.
Issues
- Claim denial primary · upheld“The FSP's initial denial of the claim had no basis and it failed to consider all relevant information.”
- Delay secondary · upheld“The FSP unreasonably delayed reviewing the decision after receipt of the MC findings.”
- Repairs or contractors secondary · unclear“Make safe repairs by the FSP's repairer had not adequately performed, so the applicant had to clean and monitor the property.”
Subjects and remedies
home or building damagenatural disasterpay claimpay compensationpay non financial loss
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
Case No: 400444 Determination Page 1 of 7
Case number: 400444 2 February 2016
1 Overview
1.1 Dispute
This action is bought on behalf of the Estate of the Late ZP. Reference to the
Applicant in this matter is referenced to the Estate.
The Applicant lodged a claim on or about 30 March 2015 on the Landlord Home
Building Policy held with the Financial Service Provider (FSP). The Applicant claimed
the property had been damaged during a severe storm with resultant major structural
damage to the roof and internal damage.
The FSP initially refused payment of the Applicant’s claim on the grounds the
Applicant did not have an insurable interest and in the alternative that the damage
was not due to an insured event.
On 10 September 2015 the FSP advised that it had accepted the Applicant had an
insurable interest and offered to meet the cost of repair to the building subject to the
terms of the policy with the FSP having the right to appoint its preferred suppliers.
The Applicant maintains that it incurred the costs of repair of the building due to the
FSP’s delays and seeks payment for the cost of repair.
1.2 Issues and key findings
Is the FSP liable to meet the cost of repairs?
The FSP is liable to meet the cost of repairs reasonably incurred by the Applicant as
a result of the FSP’s delay in accepting liability in this dispute.
Is the Applicant entitled to loss of rent?
The Applicant is not entitled to payment of loss of rent as the Applicant did not have a
tenant at the time of the damage and no written tenancy agreement was in place.
Is the Applicant entitled to compensation for consequential financial loss
pursuant to paragraph 9.3 of the Terms of Reference?
The Applicant is entitled to compensation for consequential financial loss as a result
o f delays caused by the FSP’s conduct in this matter.
Compensation for consequential financial loss of $3,300 is appropriate in this matter.
Case No: 400444 Determination Page 2 of 7
Is the Applicant entitled to compensation for non-financial loss pursuant to
paragraph 9.3 of the Terms of Reference?
The Applicant is entitled to compensation for non-financial loss pursuant to
paragraph 9.3 of the Terms of Reference due to the inconvenience and time taken as
a result of the FSP’s conduct in this matter.
Compensation in the sum of $1,650 is appropriate in this matter.
1.3 Determination
This Determination is in favour of the Applicant.
The FSP is to pay the Applicant the sum of $101,074 being the cost of repairs
including replacement of the carpets and cleaning plus the sum of $4,950 being
compensation pursuant to paragraph 9.3 of the Terms of Reference for
consequential financial loss and non-financial loss.
Case No: 400444 Determination Page 3 of 7
2 Reasons for Determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues that arise from the material exchanged.
This Determination follows consideration of all of the relevant information and is
based on what is fair in all the circumstances having regard to the relevant legal
principles, terms of the policy, good industry practice including relevant codes of
practice and prior Determinations where applicable.
2.1 Is the FSP liable to meet the Applicant’s cost of repairs ?
The FSP is liable to meet the Applicant’s cost of repairs
The Applicant’s policy is an insured events policy that provides cover for damage
caused by storm. There is now no dispute that the Applicant’s property sustained
substantial damage when what was described as a mini tornado hit the area on 30
March 2015. The force of the storm caused the roof to collapse and flip in pieces.
Rafters, batons and roofing was missing.
The FSP initially rejected the Applicant’s claim and maintained that the Applicant had
no insurable interest in the property and alternatively that the damage was not due to
storm but due to wear and tear, faulty workmanship and deterioration, based on an
initial report received from its consultant.
I note that in the original Notice of Response dated 10 July 2015, the FSP maintained
its position in refusing payment of the claim. This was despite the fact the FSP had
arranged for a further inspection of the property by MC on 26 May 2015 and despite
the fact that the Applicant had provided its own building specialist report from JC
strongly criticising the earlier reports.
The FSP has advised that it had not received the report from MC at the time of the
original Notice of Response. I note however, no reference to this inspection was
made by the FSP in that response. Following receipt of the FSP’s cla im file notes, it
is apparent that the FSP had in fact closed the Applicant’s file on 16 June 2015. It is
unclear why this occurred. There is no indication in the case notes of any attempt by
the FSP to follow up a report from MC prior to the Notice of Response.
There is a note on 23 July 2015, after the Notice of Response had been provided
indicating that the FSP was awaiting an assessment from MC. It is apparent from the
file notes that the FSP was aware of MC’s view in this matter at the latest on 29 Ju ly
2015. The report provided by MC confirms the cause of damage to the Applicant’s
property was consistent with the Applicant’s explanation that the damage was due to
storm being high winds and heavy rains and as a result, the claim fell within the
terms of the policy.
Despite receiving this report and being aware of the contents of this report, the FSP
did not make any reference to it until providing a second Notice of Response on 10
September 2015. This was after being made aware by the Applicant of the report
from MC. By that time, the Applicant had engaged a builder to commence repairs to
the property. It is understandable that the Applicant would do this given the likelihood
Case No: 400444 Determination Page 4 of 7
of ongoing damage. It is also understandable given the make safe repairs had not
adequately performed.
The FSP in its second Notice of Response offered to settle the Applicant’s claim by
conducting the repairs with its own preferred repairer. I accept that the policy allows
the FSP’s discretion as to whether it should chose its own repairer to conduct the
repairs or cash settle the claim. Such a discretion however needs to be used
reasonably and in accordance with the provisions of the policy.
One of the provisions of the policy is that the Applicant must do everything
reasonable to prevent further loss or damage to the property or contents. In my view,
the Applicant’s action in appointing a builder to commence repairs was caused by the
FSP’s delay and in particular its delay in acting on the report by MC. The handling of
the dispute in my view has led to an unreasonable delay.
In these circumstances, it is appropriate that the FSP meet the costs incurred by the
Applicant in repairing the building in accordance with the invoice provided of $98,100.
Further, the FSP initially denied the claim with respect to fixtures and fittings
including carpets. The FSP is to cover the cost of the carpets and internal cleaning of
$1,950 as per the quotations provided and 50% of the shared cost of the new fencing
being $1,024.
There is also a suggestion in the file that the FSP requested the Applicant to cover
the costs of the tarpaulin hire. It is unclear whether the FSP has paid those costs and
sought reimbursement from the Applicant or not. In my view, the FSP is liable for the
cost of the tarpaulin hire as these costs were incurred under the terms of the policy
and any ongoing cost i s due to the FSP’s handling of the dispute.
2.2 Is the Applicant entitled to claim for loss of rent?
The Applicant is not entitled to claim for loss of rent under the terms of the
policy
The policy provides that in order to establish a claim under the loss of rent provisions
under the policy, the Applicant must establish:
a) the tenant stopped paying the rent
b) the tenant left without notice; and
c) that they had a written rental agreement.
There is no dispute that at the time of the loss, the property was not tenanted.
Certain renovations had been performed on the property and the Applicant was in the
process of engaging an Agent to rent out the property at $550 per week.
Although there was an intention to rent the property, there was no tenant currently in
the property and no written rental agreement. There is no entitlement to payment
under the loss of rent provisions within the terms of the policy in these
circumstances.
Case No: 400444 Determination Page 5 of 7
2.3 Is the Applicant entitled to compensation for consequential financial
loss?
The Applicant is entitled to compensation for consequential financial loss due
to the claims handling by the FSP
Considerable delays occurred in the handling of the claim by the FSP. Not only did
the FSP incorrectly deny the claim and deny the Estate had an insurable interest in
the property or an entitlement under the Policy, the FSP failed to respond in a timely
manner once provided with relevant assessment reports confirming the damage was
caused by the storm event.
Due to the handling of the dispute, there were delays in the property being repaired.
The Applicant signed, on 28 March 2015, prior to the storm event, an exclusive
management agency rental agreement. The agreement authorised the agent to rent
the property for a term of 12 months at a rate of $550 per week. It is clear from the
agreement that the intention was to continue to rent the property. The delays in
having the property repaired clearly impacted on the ability of the agent to rent the
property.
In my view, the failure by the FSP to follow up the report from MC prior to providing
the initial Notice of Response and then subsequent failure to review the matter upon
receipt of the report has contributed significantly to the delay in the repair process. I
am satisfied that as a consequence of the delay, the property was rendered
untenantable for at least an additional six weeks, most likely more , than otherwise
would have been the case.
In these circumstances, I am satisfied the Applicant is entitled to consequential
financial loss pursuant to paragraph 9.3(a) of the Terms of Reference in the sum of
$3,300 being the maximum amount payable under paragraph 9.3(a).
2.4 Is the Applicant entitled to compensation for non-financial loss?
The Applicant is entitled to compensation for non-financial loss
The Applicant maintains that the FSP’s conduct in this matter has been appalling and
very stressful.
The Applicant had to continuously clean the area in the attempt to prevent additional
damage as the FSP’s repairer had not completed the entire make safe repairs
required. Cracked asbestos ceilings were still hanging in the property and it was not
until MC identified this risk and rectified it that the problems were overcome.
T he FSP’ s initial denial of the claim had no basis and would have caused
considerable stress. Further, in my view, the FSP failed to consider all relevant
information in maintaining the denial of the claim through the initial Notice of
Response and unreasonably delayed reviewing the decision after receipt of the
findings from MC. This further added to the inconvenience and stress suffered.
I am satisfied that the Applicant experienced an unusual degree of stress and delay
and loss of enjoyment of life as a result o f the FSP’s conduct. I am satisfied , in the
Case No: 400444 Determination Page 6 of 7
circumstances, that it is appropriate for the FSP to pay the sum of $1,650 by way of
compensation for non-financial loss pursuant to paragraph 9.3(b) of the Terms of
Reference.
Case No: 400444 Determination Page 7 of 7
3 Supporting information
3.1 Relevant information
Quotation from JC - $98,100.
Quotation from H Builder - $97,469.
Invoice from JC – Total $98,100.
Notice of Response from FSP 15 July 2015.
Assessment Report SR.
Certificate of Insurance 2014/15.
Policy PDS.
FSP Notice of Response received 10 September 2015.
Assessment Report OR.
Assessment Report MC.
Applicant’s submissions 19 May 2015.
Applicant’s submissions 17 August 2015.
Carpet replacement quotation – CC - $1,700.
Cleaning quotation – W&D - $250.