The Applicant's storm claim was accepted, but the FSP excluded water damage to the lounge and pool room ceilings. AFCA decided in the FSP's favour, finding the water entered through defective roof sheet installation rather than a storm-made opening.

The policy excludes storm and rainwater damage caused by faulty workmanship or entry through an opening not created by the storm, and the evidence established that exclusion applied.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 400326 Determination Page 1 of 4 Case number : 400326 15 September 2015 1 Overview 1.1 Dispute The Applicant held a home building and contents insurance policy with the Financial Services Provider (FSP). A claim was lodged for damage to the insured building after a storm event. The FSP accepted the claim however has excluded cover for damage to the ceilings in the lounge room and pool room. The Applicant remains dissatisfied with the FSP’s position and is seeking for this damage to be covered under the claim. 1.2 Issues and key findings Is the FSP obliged to cover the damage to the lounge and pool room ceilings? The FSP is not obliged to cover the water ingress damage to the lounge room and pool room ceilings. The available evidence establishes, on the balance of probabilities, the water entered due to the defective installation of the roof sheets and not a storm made opening. Damage arising under these circumstances is clearly excluded from cover under the policy. 1.3 Determination This Determination is in favour of the FSP. The FSP has established, on balance, the entitlement to decline cover for the damage to the lounge room and pool room ceilings under the policy. Case No: 400326 Determination Page 2 of 4 2 Reasons for Determination 2.1 Is the FSP obliged to cover the damage to the ceilings in dispute? The damage to the lounge room and pool room ceilings is excluded from cover The policy is a defined events contract of insurance with cover subject to the specified policy limitations/exclusions. In seeking cover under the policy, the onus first rests with the Applicant to establish on the balance of probabilities that the damage claimed falls within the scope of cover available under the policy (i.e. a prima facie claim). Having considered the available information I am satisfied that the Applicant has been successful in established a prima facie claim. The onus therefore rests with the FSP to establish, on balance, an entitlement to limit cover under the claim in line with the relevant policy exclusions. Evidence establishes water ingress due to defective roof sheet installation The Applicant and the FSP have made available information to support their positions including certifications, building permits and consultant(s) reports. These reports have been referred to in more detail within Section 3 of this Determination. I have carefully considered the certificates and building permit made available by the Applicant. In considering the plumbing certificates, I note they do refer to and detail plumbing works completed at the insured property. However, these works are not relevant to the area of the roof, materials, installation or workmanship subject of this dispute. I have also considered the building occupancy permit made available by the Applicant. I note that this document does not provide any information which assists the Applicant’s position. Fur ther, it clarifies that the document is not evidence of the insured building being compliant with the relevant building legislation and regulations. The FSP has made available evidence from builders appointed to the claim. This information establishes, on balance, that the cause for the water ingress in the area of the lounge and pool rooms relates to the installation of the flat roof sheets. Evidence has also been made available to support the view the ends of these roof sheets should have been turned upwards as part of their installation. I am satisfied the available information establishes the reason for the water ingress in this area was due to the defective installation of the roof sheets as opposed to a storm created opening. The relevant policy terms are clear and specifically exclude from cover loss or damage due to storm and rainwater that arises from faulty workmanship and/or that enters the insured building through an opening not created by the storm. Accordingly, on the basis of the information made available by the parties and the relevant terms of the policy, I am satisfied the FSP has been successful in establishing an entitlement to decline cover for the lounge and pool rooms ceilings. Case No: 400326 Determination Page 3 of 4 3 Supporting information 3.1 Relevant policy wording 6. Storm and rainwater … We will NOT cover: × loss or damage caused by rain, hail or wind entering your home due to: • a design fault, structural defect or faulty workmanship • an opening that was not created by the storm 3.2 Consultants’ Evidence Record Key points Compliance Certificate (Applicant) 28 August 2009  refers to plumbing work undert aken at the insured property including:  sanitary plumbing  below ground drainage  above ground drainage  cold water plumbing  hot water plumbing  gas fitting. Compliance Certificate (Applicant) 7 September 2009  provide s date of completion for plumbing as 22 August 2009  works covered under the certificate relate to roof plumbing  the works included sup ply and installation of colourbond fascia and gutter(s), zincalume valley gutter(s) and associated flashings  date of completion is noted as 22 August 2009. ‘N’ Building Occupancy Permit (Applicant) 7 September 2009  the permit states the following: “1. This occupancy permit is not evidence that the building, part of the building or building work described above complies with the Building Act 1993 or the Building Regulations 2006.” FSP Builder’s Site Inspection Report notes  date of inspection is noted as 22 December 2014  the water ingress damage appeared to be two to four weeks old  in the consultants’ opinion the damage was due to the roof deck sheets needing to be turned up at the ends to prevent water getting in  the deck roof is flat and if there is a lot of rain the wat er flows over the end of the deck sheets and onto the plater ceiling  the report makes reference to No. DP 1.2 of the Australian Building Code Board. ‘FD’ FSP’s expert 23 December 2014  attended the insured property on 22 December 2014 to inspect and determine caus e for water ingress  in consultant’s opinion the damage was due to the roof deck sheets needing to be turned up at the ends to prevent the water getting in Case No: 400326 Determination Page 4 of 4  water has run down the wall cavity and down to the pool room and the groun d floor.