Following severe rainfall damaged the paving of a strata unit, the insurer paid part of the claim but withheld the balance until the insured obtained a hydraulic engineer's report. AFCA found the paving claim was covered and the withholding unjustified, ordering payment of the paving and leak costs, the plumbing invoices, $250 non-financial loss and interest.

No exclusion applied, and an insurer that cannot specify required rectification must pay for an expert report itself rather than hold up settlement of an accepted claim.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 399868 Determination Page 1 of 8 Case number: 399868 3 June 2016 1 Overview 1.1 Dispute There are two applicants in this dispute. The primary applicant, Mr R, owns a unit (unit 5) in a strata titled complex of six units. Mr C is the chairperson of the executive committee for the property’s owner’s corporation (and the insured party on the contract of insurance). On 15 October 2014, after a period of severe rainfall, the Mr R found that the paving in his unit’s rear courtyard was damaged. The financial services provider (FSP) paid part of the claim, but has refused to pay the balance of the claim without further information. 1.2 Issues and key findings Have the applicants established a prima facie claim under the policy? The applicants have established a prima facie claim. Has the FSP proved that an exclusion applies to decline the claim? The FSP has not established an exclusion clause applies. Has the FSP provided a valid reason why the claim should not be paid immediately? The FSP has not provided a valid reason why the claim has not been paid. Are the applicants ’ plumbing costs covered? The applicants’ plumbing costs should be met by the FSP. Is the applicant entitled to non-financial compensation? The FSP shall pay Mr R compensation of $250. 1.3 Determination This determination is in favour of the applicants. The FSP should compensate the applicants for any monies paid together with interest at the rate applicable under section 57 of the Insurance Contracts Act 1984. Case No: 399868 Determination Page 2 of 8 The FSP should arrange and pay for the costs of a hydraulic engineer’s report and determine any further liability. Case No: 399868 Determination Page 3 of 8 2 Reasons for determination 2.1 Have the applicants established a prima facie claim for cover under the policy? The FSP has agreed to pay part of the claim The FSP accepted liability for the damage to the paving and agreed to pay for the cost to remove the sand which had washed out from under the pavers into the adjoining property. However, the FSP maintains the builder of the property had deviated from the original plans for the property (particularly with respect to the capacity of the stormwater piping from the pit servicing the main driveway). It says the stormwater drainage system is inadequate for the property. It has made the claim settlement conditional on the applicants arranging for the preparation of a report on the adequacy of the stormwater drainage system for the property, by a hydraulic engineer. The a pplicants disagree with the FSP’s position with respect to the stormwater drainage system, saying the cause of the damage is primarily a leak (now fixed) located between the drainage pit servicing the rear courtyard of unit 5 and the drainage pit at the front of unit 4. The applicants seek payment by the FSP for:  the repair of the paving damage  the cost incurred for the identification and repair of the leak between the relevant drainage pits, and  the removal of the sand debris from the neighbouring property, without the need for the insured to arrange and pay fo r a hydraulic engineer’s report. The policy provides cover for accidental loss or damage There is no dispute between the parties that the damage to the unit 5 rear paving is accidental damage and that the policy responds. Accordingly, I am satisfied that the applicants have established a prima facie claim under the policy. 2.2 Has the FSP proved that an exclusion applies to decline the claim? An exclusion clause does not apply I am satisfied that the FSP is not seeking to deny liability for the damage by reli ance on any exclusion clause in the policy. Case No: 399868 Determination Page 4 of 8 2.3 Has the FSP provided a valid reason why the claim should not be paid immediately? The FSP has required the applicants to provide further information The FSP says it requires the insured to engage a hydraulic engineer to inspect the property and prepare a report on the adequacy of the stormwater system servicing the property. The FSP contends that it needs this inspection and information before settlement of the claim. The FSP obtained expert evidence The FSP relies on a report from Mr RA from [Name] Building Consultant and Engineers. Mr RA, in turn, appears to have taken the word of a former ‘ strata President ’ with respect to:  the previous stormwater overflow events at the property  what was included in the original plans for the stormwater system servicing the building  what was installed by the builder of the property, and  when the drainage pit (outside unit 4) was installed. Mr RA obtained information from another occupier of the units It is noted that although Mr RA has been strongly guided by information he says he obtained from the former ‘ strata President ’, the FSP has not provided any statement from this person as to the advice provided. I will place limited weight on such information. Further, based on any such statement or information, Mr RA maintains that the building was originally planned as including a drainage pit with 2 x 100mm PVC pipes, whereas the builder installed only 1 pipe. There are a few problems with this:  When the building was constructed (circa 1980) PVC was not the standard for stormwater piping.  Mr RA ’ s report refers to 100mm pipes, then 90mm pipes, in the original plans .  Copies of the plans to which Mr RA refers have not been provided.  Mr R contends that the pit outside unit 4 was installed in 1998 so could not have been included in the original plans for the building. Mr RA inspected the property and concluded that the main source of the water causing the damage to the pavers is the stormwater which overflowed from the unit 4 driveway pit, and entered the subfloor area of unit 5 via a manhole door adjacent to the unit 4 driveway pit. It is not clear if Mr RA observed the water overflowing from the unit 4 driveway pit into the unit 5 subfloor area, however, it seems unlikely that he did. Even after being advised of the leak between the unit 4 and unit 5 pits, Mr RA appears to have held to his view that the primary source of water which caused the damage to the paving came from the unit 4 driveway pit. I am satisfied that he is doing so mainly because of what he has been tol d by the ‘ strata President ’, which is unsubstantiated. Case No: 399868 Determination Page 5 of 8 While it appears that the unit 4 driveway pump failed on the night of the event, the applicant advises the same pump was serviced two weeks prior, and when inspected by the plumber who repaired the leak, it was operational. Although the failure of this pump is as unfortunate as it is unexplained, I am not satisfied this is an indication that the stormwater system is inadequate, as Mr RA suggests. The applicant Mr R has challenged the information Mr RA says he obtained from the former ‘ strata President ’ on a number of points. Mr R says:  The former chair of the owners corporation had a different name to that quoted by Mr RA.  The pit/pump in front of unit 4 was installed in 1998, some 18 years prior to the current event (not four years ago).  The main driveway is not only serviced by the pit/pump outside unit 4, but also by a pit which drains to the kerb.  There has only been one stormwater o verflow event affecting the front of the area in front of the property since the installation of the pit in front of unit 4, and that is the event to which this claim/dispute relates, in 2014.  There was no event in 2011, and although there was an event in 2012, it only affected the paving to the rear of unit 5 (not the driveway area at the front of the units).  As part of the claim for the 2012 event, a pit and pump was installed into the paved area of the unit 5 courtyard, as reco mmended by the FSP’s builder. The pump, which is activated by a float valve, drains this pit to the pit at the front of unit 4.  A leak developed between the unit 5 rear courtyard pit and the unit 4 pit, and this is the primary source of the water which, during the 2014 event, washed away the sand under the paving causing the claimed damage. My conclusion is that is more likely that the leak from between the pits is the main source of the water which caused the paving damage, and entered the unit 5 subfloor. Importantly, Mr RA says the stormwater system is inadequate, but requires a report by a hydraulic engineer. This suggests that he is not sure of whether the stormwater system is adequate or not. I find that if the FSP also takes this position, it should arrange and pay for such a hydraulic e ngineer’s report, not put that requirement on the insur ed applicant and hold up the settlement to Mr R until it is done. It can determine any further liability to meet the claim. The amount of rainfall It is also worth noting the relative magnitude of the rainfall on 14 October 2014. The Bureau of Meteorology records for the rainfall station (3.8km from the location of the units) show that 143 mm fell between 9am on 13 October and 9am on 14 October 2014, and this 24 hour total is about 88% of the monthly total. Further, the next four highest 24 hour totals, over the period 2012 to current, are: Case No: 399868 Determination Page 6 of 8  116mm on 8 March 2012 (this appear to be the 2012 event which resulted in previous damage to the unit 5 paving, and the installation of the pit/pump in that location)  90 mm on 21 April 2015  85mm on 22 April 2015  84mm on 29 January 2013. This confirms the a pplicant’s view that the 14 October 2014 event was extreme. I also believe that stormwater systems are only required to cope with one in 20 year events, and the 14 October 2014 event is quite possibly outside that parameter. I am satisfied that the FSP should pay for the repair of Mr R’s paving immediately. Further, if it wishes to do so, it should arrange for a hydraulic engineer to prepare a report on the drainage of the property at its expense. If the report reveals specific rectification is required, the FSP can take action based on the findings of the report. The FSP should also immediately pay for the removal of debris from the neighbouring property. If it has been removed and the costs met by the applicants, the FSP shall make payment to the applicants. Interest payable Interest should be paid on any cash settlement on the claim. If this involves reimbursement to applicant Mr R for costs incurred, interest should be paid from the time the costs were paid by the applicant. If it is for cash settlement of the damage to the paving, it should be from the date of the IDR letter on the matter (4 May 2015). 2.4 Are the applicants ’ plumbing costs covered? The policy provides a special benefit of exploratory costs and replacement of defective parts. Under this provision, the FSP will pay the reasonable exploratory costs necessarily incurred in locating the source of bursting, leaking, discharging or overflowing of tanks, apparatus or pipes used to hold or carry liquid of any kind. The applicant Mr R has provided an invoice for $181.50 from a plumber for the inspection of the stormwater system to the complex, and the preparation of a report on the findings. It is not unreasonable for the FSP to pay this amount under the exploratory costs benefit of the policy. The policy benefit provides that the FSP will also pay for reasonable costs incurred i n repairing the area of the insured property damaged by such exploratory work, and repairing or replacing the defective part or parts of such tanks, apparatus or pipes (to a limit of $1,000). I am satisfied that the FSP should pay the costs of repairing the leak in the unit 5 pit ($236.50) under this benefit. Interest should be payable from 4 May 2015 on these amounts. Case No: 399868 Determination Page 7 of 8 Compensation for non-financial loss Under the FOS Terms of Reference 9.3(b)(i) FOS can award compensation for non- financial loss. Although the applicant Mr R has not specifically claimed compensation, he has made mention of the slowness of the response by the FSP. When assessing the claim, it was not unreasonable that the FSP should investigate the circumstances of the 2012 claimed event and its relationship to the current claim. I am therefore not convinced compensation is warranted merely because of the delay while the claim was proceeding. However, the FSP’s reliance on Mr RA ’s report (based on unsupported information allegedly provided by a former ‘strata President’ ) is more difficult to justify, particular given the evidence of the leak provided by Mr R. Further, the FSP’s decision to hold up the settlement until the insured pays for a hydraulic e ngineer’s report, is unusual. I c ould accept this if it were able to identify specific rectification that was needed prior to settlement. In the current circumstances, however, where the FSP has taken a position but cannot specify the rectification that needs to take place, I am uncertain as to why the FSP would not simply pay for an expert to identify those specific rectifications. As a result of the FSP’s approach, Mr R has been putting up with damaged paving for nearly 18 months. On this basis, I determine compensation for non-financial loss of $250 if payable by the FSP. Case No: 399868 Determination Page 8 of 8 3 Supporting information 3.1 Financial Ombudsman Service (FOS) process I have decided this dispute based on what I consider is fair in all the circumstances. I have had regard to the relevant law, good industry practice, codes of practice and previous decisions of the FOS. In making this determination I have considered the entire file, including all communications with the parties not specifically referred to in these reasons. I am satisfied that the documents I have relied on i n making this decision have been exchanged between the parties. As a result, I am satisfied that the parties are aware of the issues to be considered and the submissions and evidence relevant to those issues.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.